SCHEDULE "B"
ATTACHMENT II
1. Milestone Dates
CONTRACTOR shall complete all required activities for the milestones, including
the following:
The POs for all major equipment shall be placed with the Vendors by the
Milestone Date.
HAZOP has been completed, and all process flow diagrams, material
balances and piping and instrument diagrams are frozen. All plot plans,
piping plans technical studies, technical data sheets, master equipment
list and first takeoff of materials issued. Any other engineering documents
Saudi Aramco: Company General Use
B-II-2
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 09/13
SCHEDULE “B”, ATTACHMENT II CONTRACT NO. 66000XXXXX
The POs for all bulk materials shall be placed with the Vendors by the
Milestone Date.
Review of all plot plans; piping layouts; electrical single line diagrams;
ETAP (Electrical Transient Analysis Program) studies; relief and technical
studies; electrical, instrument, mechanical equipment data sheets;
constructability study reports; piping isometrics, any documents and
drawings deemed necessary by SAUDI ARAMCO to illustrate the degree
of completion and accuracy commensurate with the progress, to confirm
that 100% of the design contractors WORK is complete, but pending
SAUDI ARAMCO comments to complete the WORK.
Issue all plot plans; piping layouts; electrical single line diagrams; ETAP
studies; relief and any technical studies; electrical, instrument, mechanical
equipment data sheets; constructability study reports; piping isometrics,
any documents and drawings deemed required for the design package by
SAUDI ARAMCO, such that they are 100% complete, and all key
documents, and those deemed necessary, have been approved by SAUDI
ARAMCO.
The final and all partial Mechanical Completion certificates have been
signed by all required SAUDI ARAMCO Departments.