SCHEDULE "B"

ATTACHMENT II

CRITICAL MILESTONE DATES

1. Milestone Dates

The following constitutes the Critical Milestone Dates, as referenced in


Paragraph 1.5 of Schedule “B”.

No. of Calendar Days


From Notice to
Milestone Events
Proceed or Specific
Dates
Design And Procurement
1.1 Establish Design Site Office and Facilities 14
1.2 Detail Design Kick-off Meeting 14
1.3 Provide Document Control Index (DCI) 20
1.4 Complete 30% Design and Detailed Engineering 90
Complete Issued For Construction Drawings for
1.5 120
Civil Works
1.6 Complete the Alignment Sheet and Right of Way 150
Construction.
1.7 Complete P.O. Placement for all Major Materials 150
(MOV, GOV, Scraper Trap, Hot Tap Machines &
Fittings and RTU’s)
1.8 Complete 60% Detailed Engineering Design 210
1.9 Complete 90% Detailed Engineering Design 240
1.10 Complete P.O. Placement for all Other Materials 240
1.11 Complete Issued For Construction (IFC)
Drawings 270
Construction
1.12 Construction Kick-Off Meeting
120
1.13 Complete Construction of Temporary Facilities,
Site Office and Satellite Office 210
1.14 Complete Mobilization 230
Saudi Aramco: Company General Use
B-II-1
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 09/13
SCHEDULE “B”, ATTACHMENT II CONTRACT NO. 66000XXXXX

1.15 Complete Construction of Main Pipeline 715


1.16 Complete Hydrotest of the Mainline Pipeline 810
1.17 Complete Construction of Scraper Launcher and
Receiver Area
840
1.18 Complete Chemical Cleaning and Caliper Run 870
1.19 Complete Construction of Valve Stations
including valves installation, Metering & Filtration
900
1.20 Complete Pre-commissioning, and achieve
PMCC 30th April, 2018
1.21 Complete Final MCC 31st May, 2018
1.22 Complete As-Built Drawings, Project record
books 31st July, 2018
1.23 Close all Exception Items 31st July, 2018
1.24 Complete Demobilization 31st July, 2018
1.25 Project Close Out 31st July, 2018

2.0 DEFINITION OF CRITICAL MILESTONE DATES

CONTRACTOR shall complete all required activities for the milestones, including
the following:

2.1 Complete Design Office mobilization

Offices dedicated for SAUDI ARAMCO and CONTRACTOR personnel


assigned to the project shall be available for occupancy and fully furnished
and equipped in accordance with Attachment IV to Schedule “B”.

2.2 Award all major equipment POs

The POs for all major equipment shall be placed with the Vendors by the
Milestone Date.

2.3 Complete 30% or 60% design review meeting

HAZOP has been completed, and all process flow diagrams, material
balances and piping and instrument diagrams are frozen. All plot plans,
piping plans technical studies, technical data sheets, master equipment
list and first takeoff of materials issued. Any other engineering documents
Saudi Aramco: Company General Use
B-II-2
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 09/13
SCHEDULE “B”, ATTACHMENT II CONTRACT NO. 66000XXXXX

and drawings deemed necessary to illustrate the degree of completion


and accuracy commensurate with the progress at 30% or 60% are
complete.

2.4 Award all POs

The POs for all bulk materials shall be placed with the Vendors by the
Milestone Date.

2.5 Complete 90% design review meeting

Review of all plot plans; piping layouts; electrical single line diagrams;
ETAP (Electrical Transient Analysis Program) studies; relief and technical
studies; electrical, instrument, mechanical equipment data sheets;
constructability study reports; piping isometrics, any documents and
drawings deemed necessary by SAUDI ARAMCO to illustrate the degree
of completion and accuracy commensurate with the progress, to confirm
that 100% of the design contractors WORK is complete, but pending
SAUDI ARAMCO comments to complete the WORK.

2.6 Issue all IFC drawings & documents

Issue all plot plans; piping layouts; electrical single line diagrams; ETAP
studies; relief and any technical studies; electrical, instrument, mechanical
equipment data sheets; constructability study reports; piping isometrics,
any documents and drawings deemed required for the design package by
SAUDI ARAMCO, such that they are 100% complete, and all key
documents, and those deemed necessary, have been approved by SAUDI
ARAMCO.

2.7 Completion of demolition of any existing equipment and piping

CONTRACTOR shall demolish all redundant equipment, auxiliary


systems, and utilities and associated foundations upon Commissioning of
the New System.

2.8 Final Mechanical Completion

The final and all partial Mechanical Completion certificates have been
signed by all required SAUDI ARAMCO Departments.

Saudi Aramco: Company General Use


B-II-3
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 09/13
SCHEDULE “B”, ATTACHMENT II CONTRACT NO. 66000XXXXX

2.9 Project record books

Provide the project record books referenced in the Job Specification


before Final Mechanical Completion to support the Commissioning
activities.

2.10 Project Completion and Demobilization

The FACILITIES are commissioned by SAUDI ARAMCO with


Commissioning assistance provided by CONTRACTOR The FACILITY is
“On-stream”, and all performance items have been corrected, all
demolition completed and the temporary facilities have been removed.

END OF ATTACHMENT II TO SCHEDULE “B”