Republic of the Philippines

Laguna State Polytechnic University


Province of Laguna

College of Computer Studies


Seatwork 4

NAME: MYCELL S. TENA SCORE: ____/35


SECTION: BSIT- 3C SMP DATE SUBMITTED:3/26/23

Directions:
✓ Answer the following question below:
✓ You can only take this seatwork once. So, make sure you don’t miss anything before you submitting
it.

Project Management Tools

1. With the given table below, solve for the following:

Expected Duration (week)


ACTIVITY PREDECESSOR Most
Optimistic Likely Pessimistic
A - 2 4 9
B A 5 8 14
C B 4 10 13
D B 4 7 10
E C 11 14 20
F D 9 13 16
G E,F 2 4 6

a. Construct a project network (5 points)

b. Complete the table and find the expected/mean duration and variance of each activity (5 points)
[ITEL305– SIA2]
Seatwork 3 Page 1 of 4
Republic of the Philippines
Laguna State Polytechnic University
Province of Laguna

Expected Duration (week)

ACTIVITY PREDECESSOR Mean


Pessimistic Most Likely Optimistic Variance
Duration

A - 2 4 9 4.5 1.36

B A 5 8 14 8.5 2.25

C B 4 10 13 9.5 2.25

D B 4 7 10 7 1.00

E C 11 14 20 14.5 2.25

F D 9 13 16 12.83 1.36

G E,F 2 4 6 4 0.44

c. Perform forward and backward passes for this network (5 points)

d. Find the Critical Path and Expected Project Completion Time (5 points)

[ITEL305– SIA2]
Seatwork 3 Page 2 of 4
Republic of the Philippines
Laguna State Polytechnic University
Province of Laguna

CPM Activity Mean Duration Variance


4.5 1.36
A
8.5 2.25
sigma2 = 8.55 B
sigma = √8.55 9.5 2.25
C
=2.92 weeks 14.5 2.25
E
4 0.44
G
41 weeks 8.55

e. Create a GANTT Chart for this table and use the Mean duration for your timeline (5 points)

[ITEL305– SIA2]
Seatwork 3 Page 3 of 4
Republic of the Philippines
Laguna State Polytechnic University
Province of Laguna

2. Assuming that the Critical Path is ACEGH, complete the table below. Find the mean duration and variance. (5
pts)

Duration (week) Mean


Activity Variance
O M P Duration
A 1 2 3 2 0.11
B 2 3 4 3 0.11
C 1 2 3 2 0.11
D 2 4 6 4 0.44
E 1 4 7 4 1.00
F 1 2 9 3 1.78
G 3 4 11 5 1.78
H 1 2 3 2 0.11

Mean Duration Variance


CPM Activity
sigma2 = 3.11 2 0.11
A
sigma = √3.11 2 0.11
C
=1.76 weeks
4 1.00
E
5 1.78
G
2 0.11
H
15 weeks 3.11

3. What is the probability of the project time completion within 16 weeks (use a standard normal distribution
table)? (5 pts)

Probability = [ x-µ σ ≤ 16-15 1.76]


=p [z ≤ 0.56]
= 0.05 and 0.06 is 0.7123 or 71.23 completion probability in 16 weeks.

[ITEL305– SIA2]
Seatwork 3 Page 4 of 4