Gramzow phase two

03.04.2023 created with QuickPlan for macOS

Jakub Sehnal
Mar 2023 Apr 2023
WBS Task Start Finish Duration
30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22
30. 3. 2023 22. 4. 2023 24

1 Lot 4 - 474 total tables 30. 3. 2023 22. 4. 2023 24 Lot 4 - 474 total tables

1.1 DC cable pull to structures 30. 3. 2023 6. 4. 2023 8 DC cable pull to structures

1.2 Modules interconnection 4. 4. 2023 11. 4. 2023 8 Modules interconnection

1.3 MC4 connectors to the end of the strings 7. 4. 2023 14. 4. 2023 8 MC4 connectors to the end of the strings

1.4 ISO test (FLUKE) includes snagging 13. 4. 2023 19. 4. 2023 7 ISO test (FLUKE) includes snagging

1.5 DC performance test (BENNING/SUNPRO) 18. 4. 2023 19. 4. 2023 2 DC performance test (BENNING/SUNPRO)

1.6 Binding the DC cables 17. 4. 2023 19. 4. 2023 3 Binding the DC cables

1.7 DC to inverters 19. 4. 2023 22. 4. 2023 4 DC to inverters

1.8 LV to inverters 3. 4. 2023 9. 4. 2023 7 LV to inverters

1.9 Table assembly 30. 3. 2023 6. 4. 2023 8 Table assembly

1.10 Modules installation 30. 3. 2023 10. 4. 2023 12 Modules installation

1.11 Earthing bridges 4. 4. 2023 7. 4. 2023 4 Earthing bridges

1.12 UV protection between the tables 12. 4. 2023 17. 4. 2023 6 UV protection between the tables

2 Lot 5 - 18 tables total 3. 4. 2023 18. 4. 2023 16 Lot 5 - 18 tables total

2.1 pumping the water, sand to the bed 5. 4. 2023 5. 4. 2023 1 pumping the water, sand to the bed

2.2 LV cable pull 5. 4. 2023 5. 4. 2023 1 LV cable pull

2.3 Conduits between the rows for DC 5. 4. 2023 5. 4. 2023 1 Conduits between the rows for DC

2.4 Backfill, earthing, achtung tape 5. 4. 2023 5. 4. 2023 1 Backfill, earthing, achtung tape

2.5 Table assembly 3. 4. 2023 4. 4. 2023 2 Table assembly

2.6 DC cable pull 5. 4. 2023 7. 4. 2023 3 DC cable pull

2.7 Inverter fix 5. 4. 2023 5. 4. 2023 1 Inverter fix

2.8 Modules installation 8. 4. 2023 10. 4. 2023 3 Modules installation

2.9 Modules interconnection 11. 4. 2023 11. 4. 2023 1 Modules interconnection

2.10 MC4 connectors to the end of the strings 11. 4. 2023 11. 4. 2023 1 MC4 connectors to the end of the strings

2.11 ISO test (FLUKE) includes snagging 12. 4. 2023 12. 4. 2023 1 ISO test (FLUKE) includes snagging

2.12 DC performance test (BENNING/SUNPRO) 13. 4. 2023 13. 4. 2023 1 DC performance test (BENNING/SUNPRO)

2.13 Binding the DC strings 13. 4. 2023 13. 4. 2023 1 Binding the DC strings

2.14 DC to inverter connection 14. 4. 2023 14. 4. 2023 1 DC to inverter connection

2.15 LV to inverter 10. 4. 2023 10. 4. 2023 1 LV to inverter

2.16 Earthing bridges 8. 4. 2023 8. 4. 2023 1 Earthing bridges

2.17 UV protection between the tables 18. 4. 2023 18. 4. 2023 1 UV protection between the tables

3 LOT 2 - 177 tables total 31. 3. 2023 21. 4. 2023 22 LOT 2 - 177 tables total

3.1 Modules interconnection 3. 4. 2023 8. 4. 2023 6 Modules interconnection

3.2 MC4 connectors to the end of the strings 5. 4. 2023 6. 4. 2023 2 MC4 connectors to the end of the strings

3.3 ISO test (FLUKE) includes snagging 10. 4. 2023 12. 4. 2023 3 ISO test (FLUKE) includes snagging

3.4 DC performance test (BENNING/SUNPRO) 12. 4. 2023 12. 4. 2023 1 DC performance test (BENNING/SUNPRO)

3.5 DC strings binding to the structures 11. 4. 2023 12. 4. 2023 2 DC strings binding to the structures

3.6 DC to the inverters 13. 4. 2023 14. 4. 2023 2 DC to the inverters

3.7 LV to the inverters 31. 3. 2023 31. 3. 2023 1 LV to the inverters

3.8 Earthing bridges 10. 4. 2023 11. 4. 2023 2 Earthing bridges

3.9 UV protection between the tables 19. 4. 2023 21. 4. 2023 3 UV protection between the tables