Professional Documents
Culture Documents
Handling Systems: Simulation
Handling Systems: Simulation
Handling Systems: Simulation
183
only. All the rest of the mining sections make use of Figure 1. Conveyors C13 and C14 can feed main
14.5-ton cars. The mine logged the number of tips bunkers on an alternative basis; however, conveyor
into each feeder-breaker, and the numbers were then C13 feeds primarily bunker 1, and conveyor C14
converted into average feed rates of the relevant feeds bunker 2.
feeding conveyors. However, for conveyors A14 and The current flow rate of conveyor belts C08 / 07,
A18, instead of flow rates, discrete feed of parcels C06/05 and D02/01 is monitored by belt weighers.
equivalent to the load of the shuttle cars was applied The problems at this mine were caused by a lack of
with the actual inter-arrival time. control over mining sections operation and over
There are in total seven bunkers in the system, each discharge rates from the surge bunkers on the trunk
with a 1,000-ton capacity. Five of them-numbered 3 belts. This resulted in overflow of the bunkers and
to 7 and later referred to as &dquo;surge bunkers&dquo;-receive the trunk belts. Every time a trunk belt was over-
the material from the feeding conveyors. The other loaded, a stoppage of about six hours was required
two bunkers-numbers 1 and 2, which will be called for cleaning. If a surge bunker overflowed, the
&dquo;main bunkers&dquo;-are fed by the trunk conveyors (see corresponding mining sections had to be shut down.
Figure 1). The loss of production due to breakdowns of the
Each of the bunkers is provided with four vibrating equipment and overflow of conveyor belts was 40%.
feeders, two for each trunk conveyor. The vibrating The objective of the simulation project was to
feeders each have a 600 t/h capacity. The rate of develop and verify a process control algorithm with a
discharge can be controlled in steps of 200 t/h; i.e., simulation model to:
the discharge rate from a vibrating feeder onto a Avoid overflow of the surge bunkers, and
(1)
trunk conveyor belt can be 0, 200, 400 or 600 t/h.
(2) Eliminate excessive feed of the trunk conveyor
Each of the four vibrating feeders can be controlled
belts to minimise the probability of blockages.
individually.
The level of material in the bunkers is monitored.
There are two identical trunk conveyor lines in use, 2.2. Simulation Approach and Assumptions
each consisting of four conveyors rated at 2,500 t/h. In a discussion with the mine, it was decided that in
Material is transferred from one conveyor belt to the view of the inertia of the vibrating feeders, control
other to make up a continuous line, as shown in actions to reduce or increase the discharge rate
184
would begin within a period of 10 minutes. The with the conclusion of the paper, &dquo;Simulation Model-
current discharge rate of a vibrating feeder was ling of Bulk Conveying Systems&dquo; [6].
sampled from a random distribution, and no har- Due to the fact that in a simulation model a con-
monic profile could be assigned to it. However, the veyor may only be loaded at the rear, the actual
control step excitation had a longer period than the conveyor belts had to be divided into segments
transport delay of a trunk belt; therefore, a continu- between the feed points, consecutively linked to-
ous simulation approach was applied in accordance gether (see Figure 2).
185
The actual discharge rate from a vibrating feeder The maximum theoretical feed rate of a trunk
was simulated as a distribution to take into account conveyor line was assumed to be 50 tons per minute
the effect of dispersion of the particle size. The profile (t/m), or 3,000 t/h, to allow for detection of the
of the distribution, which is shown in Figure 3, was overload of a conveyor belt. It was assumed that a
based primarily on the operation experience of the conveyor would be blocked any time the current flow
mine personnel. rate exceeded some pre-set value defined by the user.
Four vibrating feeders physically installed beneath The average downtime period to clean the belt and
each bunker were simulated as two outputs, each remove spillage was set at six hours.
responsible for equivalent discharge of material from In addition to overloads of the conveyor trunk
the bunker onto one of the two trunk conveyor belts. belts, mechanical breakdowns were also introduced
186
187
188
specifically taking into account the natural decline in and the discharge rate onto the trunk conveyor
production at the end of the day shift when all the belts for an underground mine. The control
bunkers were being emptied to the lowest permis- objectives were to prevent the overflow of the
sible level. Then the control algorithm maintained the bunkers, eliminate blockages of the trunk belts
delivery of the trunk conveyor line at a rate very due to overload and maintain smooth, uninter-
close to the target of ±31 t/m. rupted operation.
The effect of the breakdown of conveyor D01, the
(2) The efficiency of the control algorithm was
last one in the line, on delivery performance was verified with the simulation model, and the
much heavier as the entire line became blocked. results of experimentation with the model
However, once the healthy status of the conveyor
_
was restored, the delivery was step-by-step brought rithm were achieved.
to the target level.
The comparative statistics on the performance of
the system in two scenarios is summarised in Table 2. Table 2. Effects of breakdowns -
189
PLC-based process control system installed on new mine or, alternatively, the capacity of the
the mine after completion of this study. Accord- existing stockyard may be adjusted accordingly.
ing to feedback from the operators, the surge It is supposed that material from the new mine will
bunkers have been running at ±60-70% average be predominantly supplied to plant 2, while plant 1
level and no overloads of the trunk belts have will consume material mainly from the existing mine.
occurred. However, the old mine must be able to feed material
(4) The problem identified at that stage was insuffi- to plant 2 if required; it is considered higher priority
cient throughput of the mining sections resulting due to the absence of any entry buffer, and once a
in the average delivery rate of the system at stockpile is exhausted, the plant will be idling.
±60% of its design capacity. The objectives of the simulation study were there-
fore as follows:
(1) Size the new surge bunker 2, taking into account
3. Case Study: Sizing Bulk Handling the feed of the new incline conveyor C5 deliver-
Equipment ing material from six to 16 underground mining
3.1. Introduction to and Objective of the Simulation Study sections to be quantified;
An existing Mine 1 mines material, which is con- (2) Configure and size the stockyard to accommo-
veyed into bunker 1, then via conveyors Cl and C2 date material coming from the existing Cl and
into an existing stockyard 1, comprising 2 x 20,000 t the new overland conveyors, and to provide
stockpiles (see Figure 10). From the stockyard, feed into material processing plants 1 and 2 as
material is reclaimed and conveyed via conveyor C3
into an 8,000-ton silo, feeding material to processing
uninterruptible as possible at required rates of
1,200 and 2,000 t/h, respectively. Configuration
plants 1 and 2 via conveyor C4, link 2. of the stockyard entails investigation of the
The expansion plans of the mine involve establish-
ment of a new underground operation (Mine 2),
sufficiency of the existing capacity and a defini-
tion of the new required capacity if that becomes
deploying six to 16 mining sections that will feed the necessary. ,
,
190
the operation of the new overland conveyor system was updated every time it registered a higher level of
and the existing facilities. material in the bunker. The following considerations
The mining operation was simulated as some were taken into account to size the new surge bun-
191
The capacity of the existing stockyard should The existing mining operation delivers material to
maintain the maximum utilisation of the reclaimer the Cl conveyor at a rather stable rate provided by
and the reclaim conveyor; i.e., the reclaimer must the belt weigher and surge bunker 1 feeding up the
always have some material in one of the two stock- conveyor to maintain a 1,400- to 1,500-t/h feed. The
piles to reclaim. Therefore, the definition of the feed rate of conveyor Cl was therefore assumed to be
a uniform distribution with a minimum of 23.5 and
required size of the stockyard was based on the
minimisation of the idling time of the reclaimer- maximum 25.0 t/m (average 1,455 t/h).
conveyor combination. The feed of a new mining section was described as
Three scenarios were simulated after discussions of a square negative parabola with a maximum in the
the model with the mine and are shown in Table 3. middle of a shift and zero production at the begin-
Scenario 3 was considered specifically to deal with ning and at the end of the shift. The average feed of a
interruptions of the feed into plant 1. In that event, it section over a one-shift period was assumed at ±220
was suggested to shut down Cl and route to Plant 1 t/h, as per a similar operation in one of the operating
material coming from C6 via link 3, C2 and link 1, underground mines.
because Plant 1 was highly prioritised.
192
Conveyor C5 conveys material into the new surge As in theprevious case study, a full calendar year
bunker 2, feeding the new overland conveyor at the operation according to the actual mine work schedule
controlled average rate of 3,000 t/h. was simulated.
Reclaim rates from the stockpiles and discharge
rates from the surge bunkers were sampled from a 3.3. Discussionof Simulation Results
normal distribution with mean values as per the The level monitor in bunker 2 registered ±4,900 t
relevant parameters of Table 3. maximum volume of material; therefore, it was
Stacking and reclaiming took place on the alterna- decided to retain the size of the bunker at 5,000 tons
tive basis with reclaiming as first priority (a stacker with a maximum of 11 underground sections concur-
could not interrupt a reclaimer; however, once rently mining material.
reclaiming was finished, the stacking had to be The simulation report on production of material is
stopped and the reclaimer moved to the other presented in Table 5.
stockpile). A change-over time of 45 minutes was The best production figure is obtained for the
allowed for stacker and reclaimer motion and setup. existing stockyard with 2 x 40,000-ton stockpiles (see
No simulation of plants 1 and 2 was required; scenario 1 in Table 3).
however, defining the effects of the breakdowns and Performance of the system in scenario 1 (with 2 x
maintenance stoppages on the throughput of the 20,000 t stockpiles) and in scenario 2 is similar.
plants was delegated to conveyors C4 and C9 feeding Although intuitively one would think that the
the plants.
throughput capacity of a stockyard with 2 x 20,000 t
Failures of both the mine and the plant were and 2 x 25,000 t stockpiles would be better than for
assumed to occur on a weekly basis. The MTBF was the 2 x 20,000 t stockpiles, it is necessary, however, to
simulated by the negative exponential distribution,
keep in mind that the loss in the throughput of a
and the MTTR by the Gamma distribution to obtain
system with one stacker and one reclaimer will be
the above availability as per standard statistical smaller than that of the system with two stackers and
methods (see Table 4). two reclaimers due to the time spent on changing
Further research on the availability effect was over. Another fact is that the shorter the average
undertaken with respect to the key equipment in the change-over time of stackers/reclaimers, the better
stockyard-namely, stackers, reclaimers with associ- the utilisation of the new incline conveyor C5 will be.
ated conveyors, and the new overland conveyor. The A further decrease in material production in sce-
98% availability of that equipment was assumed and nario 3 is explained by the fact of shutting down
calculated exactly in the same way as for the above conveyor Cl and re-routing material coming from the
equipment.
194
new overland conveyor C6 directly to the transfer could be the size of the new stockpiles, which caused
tower while there was no feed into plant 1. When Cl the stacker and reclaimer to move more frequently
was stopped, it didn’t deliver any material into the than in the existing stockyard (compare 16.7 hours
system, which contributed to the loss in production. required to reclaim the full old stockyard to 12.5
Performance parameters of conveyors are broken hours to reclaim the full new one).
down in Table 6. The overall best utilisation of In scenario 3 the situation reversed: conveyor C4
conveyors was observed for scenario 1 with 2 x performed better than C9 due to the preferential feed
40,000 t stockpiles, which fully correlates with the of the former (remember, the control algorithm had
results of material production. an objective to maintain uninterrupted feed to
The utilisation of conveyor C8 in scenario 2 is rather plant 1).
worse than that of C3. This indicates that the opera- Parameters of the stockpiles and bunkers are
tion of the new stacker and reclaimer was less summarised in Table 7.
efficient that of the existing ones. The reason for that
195
As a result of simulating experimentation, the , Systems." SIMULATION, vol. 70, no. 2, pp 90-103, February
1998.
following conclusions can be made:
(1) The absolute maximum number of underground
sections that can mine and feed material into the
ALEXANDER A. LEBEDEV
new surge bunker concurrently is 11, with the
received MSc (Cum Laude) and
capacity of the new incline conveyor of 3,600 PhD degrees in metallurgical
t/h. engineering from the Moscow
(2) The new surge bunker sized at 5,000 t will be Institute of Steel and Alloys in
able to accommodate the irregularity of the feed 1982 and 1987, respectively. He
coming from the underground mining opera- specialised in thermal physics and
tion. process control and
instrumentation. Before he
(3) A capacity of the new overland conveyor of relocated to South Africa, his
amount of
3,000 t will suffice to deliver the scientific interests concentrated on
material required for the plants and to balance application of computer modelling
the feed coming into the surge bunker with the to heat transfer and process
above two recommendations followed. control. He is currently employed as a senior consultant
with Xcel Engineering and Management, a South African
(4) The existing stockyard at its current capacity of industrial engineering consulting firm, and is actively
two stockpiles of 20,000 t each will maintain the involved in systems engineering and simulation modelling
annual production of material exceeding 18 of large industrial systems. He is a registered Professional
million tons and sufficient throughput of the
Engineer.
material plants at 100% availability of equip-
ment if the capacity of the existing stacker can be
upgraded to 4,500 t/h and of the reclaimer to PHILLIP STAPLES graduated
3,200 t/h. with a BSc degree in Mechanical
(5) The stockyard with two new stockpiles of Engineering from the University
25,000 t each, a new stacker of 3,000 t/h, a new College, Swansea, United
reclaimer of 2,000 t/h and associated conveyors Kingdom. For the past 22 years,
he has been working in South
! will also provide the production of material of Africadesigning high-tech
more than 18 million tons per annum and a
conveying systems and stacker
sufficient feed through the plants with no reclaimers for the coal and base
breakdowns in the system. metal industries. He operates as a
196