PERHITUNGAN VOLUME

PEKERJAAN : PEMBANGUNAN RUMAH PRIBADI 1 LANTAI TYPE 55


LOKASI : BUKITTINGI
TAHUN : 2023

NO URAIAN PEKERJAAN/SKETSA PERHITUNGAN VOLUME VOLUME STN


A LANTAI I
I PEKERJAAN PENDAHULUAN
1 Pek.Pembersihan Lapangan Panjang = 14.00 m1
Lebar = 7.00 m1
Luas 14.00 x 7.00 = 98.00 m2 98.00 m2

2 Pemasangan Bowplank Panjang = 14.00 m1


Lebar = 7.00 m1
Keliling 14.00 + 7.00 + 14.00 + 7.00 = 42.00 m2 42.00 m2

II PEKERJAAN PONDASI
1 Pek. Pondasi Batu Kali
a.Pek. Galian Tanah Biasa Panjang Pondasi = 55.00 m1
Lebar = 0.80 m1
Tinggi = 0.95 m1
Volume 55.00 x 0.80 x 0.95 = 41.80 m3 41.80 m3

b. Anstampang Batu Kali


Panjang Pondasi = 55.00 m1
Lebar = 0.80 m1
Tinggi = 0.20 m1
Volume 55.00 x 0.80 x 0.20 = 8.80 m3 8.80 m3

c. Pas Pondasi Batu Kali


Panjang Pondasi = 55.00 m1
Lebar Atas = 0.22 m1
Lebar Bawah = 0.65 m1
Tinggi = 0.75 m1
Lebar rata-rata 0.22 + 0.65 / 2.00 = 0.44 m1
Volume 55.00 x 0.75 x 0.44 = 17.94 m3 17.94 m3

d. Urugan Kembali Volume Galian Dikurangi = 41.80 m3


Volume Anstampang = 8.80 m2
Volume Pondasi Batu Kali = 17.94 m2
Volume Sloof 0.15 x 0.20 x 55.00 = 1.65 m3
Volume Bersih 41.80 - 8.80 + 17.94 + 1.65 = 52.59 m3 52.59 m3

III Pekerjaan Beton Bertulang


1 Pekerjaan Sloof Uk.15/20 cm (S2)
a. Pekerjaan Beton K.250 Panjang = 55.00 m1
Lebar = 0.15 m1
Tinggi = 0.20 m1
Volume 55.00 x 0.15 x 0.20 = 1.65 m3 1.65 m3

b. Pekerjaan Pembesiaan Besi Pokok


Jumlah Batang = 18.33 m1
Berat Besi Æ12/M = 0.89 kg
Banyak/Titik = 4.00 Bh
Panjang/M' 4.00 x 55.00 = 220.00 m'
Banyak Titik = 1.00 Unit
Volume 18.33 x 0.89 x 4.00 x 1.00 = 65.10 kg 65.10 kg

Besi Begol
Panjang = 0.64 m1
Berat Besi Æ8/M = 0.39 kg
Banyak/Titik = 441.00 Bh
Banyak Titik = 1.00 Unit
Volume 0.64 x 0.39 x 441.00 x 1.00 = 111.36 kg

Jumlah Pembesian 65.10 + 111.36 = 176.46 kg 176.46 kg

c. Pekerjaan Bekisting Sloof Panjang = 55.00 m1


Tinggi = 0.40 m1
Banyak = 1.00 Titik
Volume 55.00 x 0.40 x 1.00 = 22.00 m2 22.00 m2

2 Pekerjaan Kolom Teras Uk. 12/15(K1)


a. Pekerjaan Beton K.250 Panjang = 2.50 m1
Lebar = 0.12 m1
Tinggi = 0.15 m1
Banyak = 2 Titik
Volume 2.50 x 0.12 x 0.15 x 2.00 = 0.09 m3 0.09 m3

b. Pekerjaan Pembesiaan Besi Pokok


Tinggi = 3.50 m1
Berat Besi D 13/M = 1.04 kg
Banyak/Titik = 4.00 Bh
3.50 x 4.00 = 14.00 m'
14.00 x 2 = 28 m'
Panjang Besi/12 28.00 / 12.00 = 2.33 btng
Berat Besi Tul.Utama 2.33 x 1.04 = 2.43 kg

Besi Begol
Panjang = 0.32 m1
2.50 / 0.15 = 16.67 bh
Panjang Besi Dari 1 kolom 0.32 x 16.67 = 5.33 m'
Berat Besi Æ8/M 0.39 x 5.33 = 2.10 kg
2.10 x 1.00

Jumlah Pembesian 2.43 + 2.10 = 4.53 kg 4.53 kg

c. Pekerjaan Bekisting Kolom Panjang = 2.50 m1


Lebar = 0.54 m1
Banyak = 1.00 Titik
Volume 2.50 x 0.54 x 1.00 = 1.35 m2 1.35 m2
NO URAIAN PEKERJAAN/SKETSA PERHITUNGAN VOLUME VOLUME STN

3 Pekerjaan Kolom Uk. 15/15 (K2)


a. Pekerjaan Beton K.250
Panjang = 3.30 m1
Lebar = 0.15 m1
Tinggi = 0.15 m1
Banyak = 14 Titik
Volume 3.30 x 0.15 x 0.15 x 14.00 = 1.04 m3 1.04 m3
b. Pekerjaan Pembesiaan
Besi Pokok
Tinggi = 3.50 m1
Berat Besi D 13/M = 1.04 kg
Banyak/Titik = 4.00 Bh
3.50 x 4.00 = 14.00 m'
14.00 x 14 = 196 m'
Panjang Besi/12 196.00 / 12.00 = 16.33 btng
Berat Besi Tul.Utama 16.33 x 1.04 = 16.99 kg

Besi Begol
` Panjang = 0.38 m1
3.30 / 0.15 = 22.00 bh
Panjang Besi Dari 1 kolom 0.38 x 22.00 = 8.36 m'
Berat Besi Æ8/M 5.33 x 8.36 = 44.59 kg
44.59 x 1.00

Jumlah Pembesian 16.99 + 44.59 = 61.57 kg 61.57 kg

c. Pekerjaan Bekisting Praktis Panjang = 0.15 m1


Lebar = 0.50 m1
Banyak = 22.00 Titik
Volume 0.15 x 0.50 x 22.00 = 1.63 m2 1.63 m2
IV PEKERJAAN DINDING
1 Pekerjaan Pas. Batu Bata Tebal 1/2 Bata, spesi 1Pc:2Ps Luas pas. Batu bata
dinding 1
tinggi = 3.30 m
panjang = 3.00 m
banyak = 8.00 unit
volume 3.30 x 3.00 x 8 = 79.20 m

dinding 2
tinggi = 3.30 m
panjang = 1.50 m
banyak = 4.00 unit
volume 3.30 x 1.50 x 4 = 19.80 m

dinding 3
tinggi = 3.30 m
panjang = 2.50 m
banyak = 1.00 unit
volume 3.30 x 2.50 x 1 = 8.25 m

dinding 4
tinggi = 3.30 m
panjang = 3.50 m
banyak = 1.00 unit
volume 3.30 x 3.50 x 1 = 11.55 m

jumlah = 118.80 m2 118.80 m2

luas pas. Kozen

kozen P1 0.90 x 2.00 x 1 = 1.80


kozen P2 0.80 x 2.00 x 1 = 1.60
kozen P3 0.75 x 2.00 x 1 = 1.50
kozen P4 0.70 x 2.00 x 1 = 1.40
kozen J1 0.28 x 1.33 x 1.00 = 0.37
kozen J2 0.76 x 1.22 x 1.00 = 0.93
kozen J3 1.26 x 0.28 x 3.00 = 1.06
kozen J4 0.56 x 1.75 x 3.00 = 2.94
luas bersih pas. Dinding Bata
= 118.80 - 0.37 = 118.43 m2
2 pekerjaan plasteran Spesi 1PC:4 Ps tebal 20mm
luas plasteran = 1.50 x Luas penampang dinding bata
= 1.50 x 118.43 = 177.64 m2 177.64 m2

3 Pekerjaan Acian
luas acian = Luas plasteran
= 177.64 m2 177.64 m2

V PEKERJAAN KOZEN PINTU, JENDELA


1 Pck. Kozen Pintu. Jendela
P1
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 0.90 m
Arah vertikal = 2.00 + 2.00 = 4.00
total = 0.90 + 4.00 = 4.90
Volume = 1.00 x 0.05 x 0.15 x 4.90
= 0.04 0.04
P2
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 0.80 m
Arah vertikal = 2.00 + 2.00 = 4.00
total = 0.80 + 4.00 = 4.80
Volume = 1.00 x 0.05 x 0.15 x 4.80
= 0.04
P3
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 0.75 m
NO URAIAN PEKERJAAN/SKETSA PERHITUNGAN VOLUME VOLUME STN
Arah vertikal = 2.00 + 2.00 = 4.00
total = 0.75 + 4.00 = 4.75
Volume = 1.00 x 0.05 x 0.15 x 4.75
= 0.04
P4
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 0.70 m
Arah vertikal = 2.00 + 2.00 = 4.00
total = 0.70 + 4.00 = 4.70
Volume = 1.00 x 0.05 x 0.15 x 4.70
= 0.04 m
J1
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 0.28 m
Arah vertikal = 1.33 + 1.33 = 2.66
total = 0.28 + 2.66 = 2.94
Volume = 1.00 x 0.05 x 0.15 x 2.94
= 0.02 m

J2
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 0.76 m
Arah vertikal = 1.22 + 1.22 = 2.44
total = 0.76 + 2.44 = 3.20
Volume = 1.00 x 0.05 x 0.15 x 3.20
= 0.02 m

J3
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 1.26 m
Arah vertikal = 0.28 + 0.28 = 0.56
total = 1.26 + 0.56 = 1.82
Volume = 1.00 x 0.05 x 0.15 x 1.82
= 0.01 m

J4
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m

Panjang kayu kozen


Arah horizontal = 0.56 m
Arah vertikal = 1.75 + 1.75 = 3.50
total = 0.56 + 3.50 = 4.06
Volume = 1.00 x 0.05 x 0.15 x 4.06
= 0.03 m
0.09
total Volume kozen
volume = 0.17 m2 0.17 m2
2 Pekerjaan Pintu Panel
PJ1
Jumlah Unit = 1.00
jumlah dalam 1 unit = 1.00
Lebar pintu = 0.90 + 0.60 + 0.60 = 2.10
Tinggi pintu = 2.00
Luas = 4.20

P1
Jumlah Unit = 1.00
jumlah dalam 1 unit = 1.00
Lebar pintu = 0.80 + 0.90 + 0.90 = 2.60
Tinggi pintu = 2.00
Luas = 5.20

P2
Jumlah Unit = 1.00
jumlah dalam 1 unit = 1.00
Lebar pintu = 0.75 + 0.80 + 0.80 = 2.35
Tinggi pintu = 2.00
Luas = 4.70

P3
Jumlah Unit = 1.00
jumlah dalam 1 unit = 2.00
Lebar pintu = 0.70 + 0.60 + 0.60 = 1.90
Tinggi pintu = 2.00
Luas = 7.60

J3
Jumlah Unit = 2.00
jumlah dalam 1 unit = 3.00
Lebar = 0.55 + 0.60 + 0.60 = 1.75
Tinggi = 0.50
Luas = 5.25
3 Jendela kaca
Jendela 1
Jumlah unit = 2 Unit
jumlah dalam 1 unit = 1 bh
Lebar jendela = 0.40 m
Tinggi jendela = 1.55 m
Luas = 2 x 1 x 0.40 x 1.55 =
= 1.24
NO URAIAN PEKERJAAN/SKETSA PERHITUNGAN VOLUME VOLUME STN
Jendela 2
Jumlah unit = 3 Unit
jumlah dalam 1 unit = 2 bh
Lebar jendela = 0.40 m
Tinggi jendela = 1.34 m
Luas = 3 x 2 x 0.40 x 1.34 =
= 3.22
Jendela 3
Jumlah unit = 2 Unit
jumlah dalam 1 unit = 3 bh
Lebar jendela = 0.75 m
Tinggi jendela = 1.75 m
Luas = 2 x 3 x 0.75 x 1.75 =
= 7.88
12.33

Total Luas Pintu = 1.24 + 7.88


Luas = 9.12 9.12

4 Pas. Kunci tanam Merk SES (setara) 2 slaag


Jumlah unit = 1 Unit
jumlah dalam 1 unit = 1 bh
Volume = 1 x 1 = 1 m2 1.00 m2

5 Pas. Engsel Pintu Jumlah unit = 1 Unit


jumlah dalam 1 unit = 3 bh
Volume = 1 x 3 = 3 m2 3.00 m2

6 Pas. Engsel jendela Jumlah unit = 1 Unit


jumlah dalam 1 unit = 3 bh
Volume = 1 x 3 = 3 m2 3.00 m2

7 Pas. Grendel jendela Jumlah unit = 7 Unit


jumlah dalam 1 unit = 2 bh
Volume = 7 x 2 = 14 m2 14.00 m2

8 Pas. Kait angin jendela Jumlah unit = 7 Unit


jumlah dalam 1 unit = 2 bh
Volume = 7 x 2 = 14 m2 14.00 m2

9 Pas. Tangan-tangan jendela Jumlah unit = 7 Unit


jumlah dalam 1 unit = 1 bh
Volume = 7 x 1 = 7 m2 7.00 m2

VI Pekerjaan lantai
1 Pekerjaan Urungan Pasir Kamar Tidur 1
Panjang = 3.00 m1
Lebar = 3.00 m1
Tinggi = 0.03 m1
Banyak = 1 Unit
Volume 3.00 x 3.00 x 0.03 x 1.00 = 0.27 m3

Kamar Tidur 2
Panjang = 3.00 m1
Lebar = 3.00 m1
Tinggi = 0.03 m1
Banyak = 1 Unit
Volume 3.00 x 3.00 x 0.03 `x 1.00 = 0.27 m3

Ruang Dapur & Ruang Makan


Panjang = 2.50 m1
Lebar = 1.50 m1
Tinggi = 0.03 m1
Banyak = 1 Unit
Volume 2.50 x 1.50 x 0.03 x 1.00 = 0.11 m3

Ruang Tamu& keluarga


Panjang = 2.50 m1
Lebar = 2.00 m1
Tinggi = 1.00 m1
Banyak = 1.00 Unit
Volume 2.50 x 2.00 x 1.00 x 1.00 = 5.00 m3

Km/Wc
Panjang = 1.86 m1
Lebar = 1.80 m1
Tinggi = 0.03 m1
Banyak = 1.00 Unit
Volume 1.86 x 1.80 x 0.03 x 1.00 = 0.10 m3

Teras
Panjang = 2.50 m1
Lebar = 2.00 m1
Tinggi = 0.03 m1
Banyak = 1.00 Unit
Volume 2.50 x 2.00 x 0.03 x 1.00 = 0.15 m3

Volume Total = 5.63 m3 5.63 m3

2 Pekerjaan Beton Tumbuk K. 250 Luas Urugan Pasir 5.63 / 0.03 = 187.76 m2
Tinggi Beton Tumbuk = 0.07 m1
Volume 187.76 x 0.07 = 13.14 m3 13.14 m3

3 Pekerjaan Lantai Keramik Uk. 30x30 cm


Kamar Tidur
Panjang , = 3.00 m1
Lebar = 3.85 m1
Banyak = 2.00 Unit
Volume 3.00 x 3.85 x 2.00 = 23.10 m2 23.10 m2

Ruang Tamu & Keuarga


Panjang = 2.50 m1
Lebar = 2.00 m1
Banyak = 1.00 Unit
Volume 2.50 x 2.00 x 1.00 = 5.00 m2 5.00 m2

Ruang Makan & dapur


Panjang = 2.50 m1
NO URAIAN PEKERJAAN/SKETSA PERHITUNGAN VOLUME VOLUME STN
Lebar = 1.50 m1
Banyak = 1.00 Unit
Volume 2.50 x 1.50 x 1.00 = 3.75 m2

Jumlah Volume = 31.85 m3 31.85 m3

4 Pekerjaan Keramik Lantai 25x25


Km/Wc 1
Panjang = 1.35 m1
Lebar = 1.35 m1
Banyak = 1.00 Unit
Volume 1.35 x 1.35 x 1.00 = 1.82 m2

Jumlah Volume = 1.82 m2 1.82 m2

5 Pekerjaan Pasangan Bon-Bon Keramik


Panjang = 1.20 m1
Banyak = 1.00 Unit
Volume 1.20 x 1.00 = 1.20 m1

Panjang = 0.80 m1
Banyak = 1.00 Unit
Volume 0.80 x 1.00 = 0.80 m1

Panjang = 0.70 m1
Banyak = 1.00 Unit
Volume 0.70 x 1.00 = 0.70 m1

volume total = 2.70 m1 2.70 m1

VII Pekerjaan Plafond


1 Pekerjaan Rangka Plafond gupsum Kamar Tidur
Panjang , = 3.00 m1
Lebar = 3.00 m1
Banyak = 2.00 Unit
Volume 3.00 x 3.00 x 2.00 = 18.00 m2

Ruang Tamu & Keluarga


Panjang = 4.50 m1
Lebar = 4.00 m1
Banyak = 1.00 Unit
Volume 4.50 x 4.00 x 1.00 = 18.00 m2

Ruang Makan & Dapur


Panjang = 2.50 m1
Lebar = 2.00 m1
Banyak = 1.00 Unit
Volume 2.50 x 2.00 x 1.00 = 5.00 m2

Km/Wc
Panjang = 1.86 m1
Lebar = 1.80 m1
Banyak = 1.00 Unit
Volume 1.86 x 1.80 x 1.00 = 3.35 m2

Teras
Panjang = 2.50 m1
Lebar = 1.00 m1
Banyak = 1.00 Unit
Volume 2.50 x 1.00 x 1.00 = 2.50 m2

Volume Total = 46.85 m2 46.85 m2

2 Pekerjaan List Profil Kayu Panjang Total = 35.60 m1 35.60 m1

VIII Pekerjaan Elektrikal


1 Pasangan Instalasi Stop Kontak Lampu 2x2,5 NYM Komplit = 6.00 unit
2 Pasangan Bola Lampu Philips Plafond 11 Watt = 4.00 unit
3 Pasangan Bola Lampu Philips Plafond 16 Watt = 2.00 unit
4 Pasangan Bola Lampu Philips 5 Watt = 4.00 unit
5 Pasangan 16 A MCB = 2.00 unit
6 Lampu Hias Gantung = 1.00 unit

IX Pekerjaan Pengecatan
1 Pekerjaan Pengecatan tembok dengan Cat Air Volume Acian = 177.64 m2 177.64 m2

2 Pekerjaan Cat Plafond Dengan Cat Air Jumlah Plafond = 46.85 m2 46.85 m2

X PEKERJAAN ATAP
1 Pekerjaan atap Genteng Luas 1 p x l = 5.20 x 2.20 = 11.44
Luas 2 p x l = 7 x 4.60 = 29.90
Luas 3 p x l = 5.30 x 4.60 24.38
Luas 4 p x l 4.90 x 4.00 = 19.60

85.32