VOLUME
VOLUME
II PEKERJAAN PONDASI
1 Pek. Pondasi Batu Kali
a.Pek. Galian Tanah Biasa Panjang Pondasi = 55.00 m1
Lebar = 0.80 m1
Tinggi = 0.95 m1
Volume 55.00 x 0.80 x 0.95 = 41.80 m3 41.80 m3
Besi Begol
Panjang = 0.64 m1
Berat Besi Æ8/M = 0.39 kg
Banyak/Titik = 441.00 Bh
Banyak Titik = 1.00 Unit
Volume 0.64 x 0.39 x 441.00 x 1.00 = 111.36 kg
Besi Begol
Panjang = 0.32 m1
2.50 / 0.15 = 16.67 bh
Panjang Besi Dari 1 kolom 0.32 x 16.67 = 5.33 m'
Berat Besi Æ8/M 0.39 x 5.33 = 2.10 kg
2.10 x 1.00
Besi Begol
` Panjang = 0.38 m1
3.30 / 0.15 = 22.00 bh
Panjang Besi Dari 1 kolom 0.38 x 22.00 = 8.36 m'
Berat Besi Æ8/M 5.33 x 8.36 = 44.59 kg
44.59 x 1.00
dinding 2
tinggi = 3.30 m
panjang = 1.50 m
banyak = 4.00 unit
volume 3.30 x 1.50 x 4 = 19.80 m
dinding 3
tinggi = 3.30 m
panjang = 2.50 m
banyak = 1.00 unit
volume 3.30 x 2.50 x 1 = 8.25 m
dinding 4
tinggi = 3.30 m
panjang = 3.50 m
banyak = 1.00 unit
volume 3.30 x 3.50 x 1 = 11.55 m
3 Pekerjaan Acian
luas acian = Luas plasteran
= 177.64 m2 177.64 m2
J2
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m
J3
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m
J4
Jumlah Unit = 1.00 unit
Dimensi kayu kozen = 0.05 m
= 0.15 m
P1
Jumlah Unit = 1.00
jumlah dalam 1 unit = 1.00
Lebar pintu = 0.80 + 0.90 + 0.90 = 2.60
Tinggi pintu = 2.00
Luas = 5.20
P2
Jumlah Unit = 1.00
jumlah dalam 1 unit = 1.00
Lebar pintu = 0.75 + 0.80 + 0.80 = 2.35
Tinggi pintu = 2.00
Luas = 4.70
P3
Jumlah Unit = 1.00
jumlah dalam 1 unit = 2.00
Lebar pintu = 0.70 + 0.60 + 0.60 = 1.90
Tinggi pintu = 2.00
Luas = 7.60
J3
Jumlah Unit = 2.00
jumlah dalam 1 unit = 3.00
Lebar = 0.55 + 0.60 + 0.60 = 1.75
Tinggi = 0.50
Luas = 5.25
3 Jendela kaca
Jendela 1
Jumlah unit = 2 Unit
jumlah dalam 1 unit = 1 bh
Lebar jendela = 0.40 m
Tinggi jendela = 1.55 m
Luas = 2 x 1 x 0.40 x 1.55 =
= 1.24
NO URAIAN PEKERJAAN/SKETSA PERHITUNGAN VOLUME VOLUME STN
Jendela 2
Jumlah unit = 3 Unit
jumlah dalam 1 unit = 2 bh
Lebar jendela = 0.40 m
Tinggi jendela = 1.34 m
Luas = 3 x 2 x 0.40 x 1.34 =
= 3.22
Jendela 3
Jumlah unit = 2 Unit
jumlah dalam 1 unit = 3 bh
Lebar jendela = 0.75 m
Tinggi jendela = 1.75 m
Luas = 2 x 3 x 0.75 x 1.75 =
= 7.88
12.33
VI Pekerjaan lantai
1 Pekerjaan Urungan Pasir Kamar Tidur 1
Panjang = 3.00 m1
Lebar = 3.00 m1
Tinggi = 0.03 m1
Banyak = 1 Unit
Volume 3.00 x 3.00 x 0.03 x 1.00 = 0.27 m3
Kamar Tidur 2
Panjang = 3.00 m1
Lebar = 3.00 m1
Tinggi = 0.03 m1
Banyak = 1 Unit
Volume 3.00 x 3.00 x 0.03 `x 1.00 = 0.27 m3
Km/Wc
Panjang = 1.86 m1
Lebar = 1.80 m1
Tinggi = 0.03 m1
Banyak = 1.00 Unit
Volume 1.86 x 1.80 x 0.03 x 1.00 = 0.10 m3
Teras
Panjang = 2.50 m1
Lebar = 2.00 m1
Tinggi = 0.03 m1
Banyak = 1.00 Unit
Volume 2.50 x 2.00 x 0.03 x 1.00 = 0.15 m3
2 Pekerjaan Beton Tumbuk K. 250 Luas Urugan Pasir 5.63 / 0.03 = 187.76 m2
Tinggi Beton Tumbuk = 0.07 m1
Volume 187.76 x 0.07 = 13.14 m3 13.14 m3
Panjang = 0.80 m1
Banyak = 1.00 Unit
Volume 0.80 x 1.00 = 0.80 m1
Panjang = 0.70 m1
Banyak = 1.00 Unit
Volume 0.70 x 1.00 = 0.70 m1
Km/Wc
Panjang = 1.86 m1
Lebar = 1.80 m1
Banyak = 1.00 Unit
Volume 1.86 x 1.80 x 1.00 = 3.35 m2
Teras
Panjang = 2.50 m1
Lebar = 1.00 m1
Banyak = 1.00 Unit
Volume 2.50 x 1.00 x 1.00 = 2.50 m2
IX Pekerjaan Pengecatan
1 Pekerjaan Pengecatan tembok dengan Cat Air Volume Acian = 177.64 m2 177.64 m2
2 Pekerjaan Cat Plafond Dengan Cat Air Jumlah Plafond = 46.85 m2 46.85 m2
X PEKERJAAN ATAP
1 Pekerjaan atap Genteng Luas 1 p x l = 5.20 x 2.20 = 11.44
Luas 2 p x l = 7 x 4.60 = 29.90
Luas 3 p x l = 5.30 x 4.60 24.38
Luas 4 p x l 4.90 x 4.00 = 19.60
85.32