Activity

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 3

DATE SEPTEMBER

ITEMS COST %Wt DURATION 10 20 30


MOBILIZATION 30000 1.81% 3
LAYOUT 20000 1.20% 1
EXCAVATION 50000 3.01% 10
FALSEWORK 160000 9.64% 96
COLUMN FOOTING 50000 3.01% 12
GROUND FLOOR COLUMN 40000 2.41% 8
BACKFILLING 30000 1.81% 5
2ND FLOOR SLAB 60000 3.61% 8
2ND FLOOR BEAM 50000 3.01% 7
WALL FOOTING 45000 2.71% 5
1ST FLOOR WALL 80000 4.82% 10
STAIR 1 20000 1.20% 5
GROUND FLOOR SLAB 75000 4.52% 7
2ND FLOOR COLUMN 40000 2.41% 8
1ST FLOOR ELECTRICAL WORKS 40000 2.41% 5
1ST FLOOR PLUMBING WORKS 35000 2.11% 5
ROOF SLAB 70000 4.22% 5
ROOF BEAM 35000 2.11% 4
2ND FLOOR WALL 95000 5.72% 10
STAIRS 2 20000 1.20% 5
2ND FLOOR PLUMBING WORKS 40000 2.41% 8
2ND FLOOR ELECTRICAL WORKS 35000 2.11% 5
DOORS & WINDOWS 130000 7.83% 5
PLASTERING WORKS 130000 7.83% 15
TILE WORKS 150000 9.04% 8
PAINTING 90000 5.42% 10
DEMOBILIZATION 40000 2.41% 5

TOTAL 1660000 100.00% 135

LEGEND:
CRITICAL ACTIVITIES
NON CRITICAL ACTIVITIES
FLOAT
OCTOBER NOVEMBER DECEMBER
40 50 60 70 80 90 100
JANUARY FEBRUARY
110 120 130 140