FEBRICATION DEPTT.

SERVICE CONTRACT PROPOSAL


Job No:
Job Name: Flooring work & Tiles work
Scope Of Work: CIVIL
Area Of Work: Rolling mill plant 02
Drawing No / B.M.No: N/R Labour Rate Job / MJO Rate : MJO
Start date: Completion Date:
Cost Code: Vendor Name: PRAVEEN CONS.
Budget: Vendor Code: 1007296
Available Balance Budget:

Rolling Mill Rolling Mill


Description Rate TOTAL Amount
S.No. Item Code Unit PT#2 (Tiles PT#2 (Tiles
(in Rs. ) QTY. (in Rs)
work) 1st work) 2nd

DEMOLISH: STRUCTURE;TYP:DISMANTLE;SCOPE:BREAKING OLD RCC FLOOR FOUNDATION, DETAIL:BREAKING RCC


1 721415100025 Cum 645.12 26.10 0.68 26.775 ₹ 17,273.09
THICKNESS (100-150 MM) WITHOUT MATERIAL, TLS PRVD BY:SUPPLIER, MTRL PRVD BY:HIL, RATE TYP:STANDARD

CONSTRUCT: STRUCTURE;TYP:STEEL TOR BAR FOR RCC;SCOPE:SUPPLYING CUTTING, BENDING,


2 721211010072 BINDING AND PLACING REINFORCEMENT STEEL BARS IN BELOW AND UPTO PLINTH LEVEL FOR RCC Ton - 1.10 0.04 1.14 -
STRUCTURE MANUFACTURED FROM SAIL, TATA, RINL, JINDAL IN ALL TYPE OF STRUCTURE

PROVIDE: CONCRETE WORK;TYP:RCC;SCOPE:MIXING AND PLACING IN FOUNDATION UPTO PLITH LEVEL, GR:M30, RATE
3 721519050347 cum - 26.10 0.68 26.775 -
TYP:STANDARD, TLS PRVD BY:HIL, MTRL PRVD BY:HIL

LAY: TILE; TYPE: MOSAIC AND GLAZED TILE; SCOPE: FIXING OF TILE, DIMENSIONS: THK 19, MATERIAL: CERAMIC,
4 721525000110 TRANSPORTATION ARRANGEMENT: HINDALCO, TOOLS PROVIDED BY: HINDALCO, MATERIAL PROVIDED BY: HINDALCO, Sq m 395.89 174.00 4.50 178.50 ₹ 70,666.37
ADDITIONAL INFORMATION: MOSAIC AND GLAZED TITLES WORK:/ FIXING OF SPARTEKTILES.'*'

PROVIDE: EARTH WORK; TYPE: EARTH WORK; SCOPE: BANKING EXCAVATED EARTH IN LAYERS NOT EXCEEDING 20 CM
IN DEPTH, BREAKING CLODS, WATERING, ROLLING EACH LAYER WITH ½ TON ROLLER AND ROLLING EVERY 3RD AND
TOP-MOST LAYER WITH POWER ROLLER OF MINIMUM 8 TONNES A & DRESSING UP, IN EMBANKMENTS FOR ROADS,
FLOOD BANKS, MARGINAL BANKS, AND GUIDE BANKS ETC., LEAD UPTO 50 M AND LIFT UPTO 1.5 M (POWER/ROAD
5 811015220023 CU MTR 34.16 _ 44.6 ₹ 1,523.63
ROLLER WILL BE PROVIDED BY HIL) : FOR ALL KIND OF SOIL, HOWEVER SPECIAL TOOLS SUCH AS CRANE, SCAFFOLD,
WILL BE PROVIDED BY HIL, RATES ARE INCL. OF CONTRACTOR PROFIT, TOOLS, OH'S, SAFETY PPE'S, & STATUTORY
REQ'S, TRANSPORTATION ARRANGEMENT: HIL, TOOLS PROVIDED BY: SUPPLIER, MATERIAL PROVIDED BY: HIL,
ADDITIONAL INFORMATION: ALL KIND OF SOIL, APPLICABLE STANDARD: HIL

PROVIDE: TRANSPORTATION SERVICE;TYP:SOIL AND LOOSE BOULDER;CARGO SIZE:8FT, MODE OF TRANSPORT:BY


6 781000000544 ROAD, DESTINATION:INSIDE PLANT TO TIKIRI, WEIGHT/VOLUME:12M3, CARGO TYPE:TIPPER, RATE TYP:NEGOTIATED, CU MTR 79.06 26.1 0.68 26.78 ₹ 2,117.20
ADDITIONAL INFORMATION:EXCAVATION OF LOOSE

AMOUNT ₹ 91,580.28

SITE INCHARGE PROPOSED BY APPROVED BY