Daily Report LP Gas Compressor B - 10000 Hrs Pm-17
Daily Report LP Gas Compressor B - 10000 Hrs Pm-17
07:00-09:00 WIB 2. Install Blind Flange for Jacket Water Compressor Bravo Continue Sefriyandri (Mechanic)
09:30-12:00 WIB Install Blind Flange for Jacket Water Compressor Bravo Continue
3. Dismantle Cover Valve & Valve Suction Outer End dan Frame End Stage 1
13:00-17:30 WIB Continue
Drain Oil Compressor
Total % working 5%
Documentation
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Dismantle valve discharge st 2 Compressor Bravo Finish Sefriyandri (Mechanic)
Total % working 8%
Documentation
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Cleaning piston and rod piston, cleaning chair valve Continue Sefriyandri (Mechanic)
09:30-12:00 WIB 3. Measurement clearance groove piston to ring compressor and ring rider Finish
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Cleaning cover valve suction and discharge Continue Sefriyandri (Mechanic)
09:30-12:00 WIB 3. Cleaning and measurement clearance and dimensions packing gas Finish
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Install ring rider and ring piston to piston continue Continue Sefriyandri (Mechanic)
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Dismantle cover head cylinder stage 2 Finish Sefriyandri (Mechanic)
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Dismantle and replace stud bolt cover head cylinder stage 2 Finish Sefriyandri (Mechanic)
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Install packing rod gas stage 2 to cylinder Finish Sefriyandri (Mechanic)
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Install valve discharge new stage 2 frame end and outer end Finish Sefriyandri (Mechanic)
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
07:00-09:00 WIB 2. Install and cleaning crankcase compressor Finish Sefriyandri (Mechanic)
09:30-11:00 WIB 3. Replace and install thrust bearing and main bearing Finish
11.00-12:00 WIB 4. Install connecting rod and bearing conrod Finish
12:00-13:00 WIB Lunch
13:00-18:30 WIB 5. Install oil scraper compressor stage 1 Finish
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
09:30-12:00 WIB 3. Dismantle blind flange for cooling system packing rod and engine jacket water Finish
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
09:30-12:00 WIB 3. De-spading line bottle suction and discharge stage 2 Finish
12:00-13:00 WIB Lunch
13:00-16:00 WIB 5. Filled lube oil completed Finish
16:00-18:00 WIB 6. Housekeeping Finish
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
09:30-12:00 WIB 3. Repair condensate pump with maintenance AGN Crew Finish
12:00-13:00 WIB Lunch
13:00-16:00 WIB 5. Start up compressor B Finish
16:00-16:30 WIB 6. Continue monitoring compressor B Finish
Status of Jobs :
Tools Used :
W/
IN √ WAITING COMPLETED √
P
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
IN √ WAITING COMPLETED √
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :
Status of Jobs :
Tools Used :
IN √ WAITING COMPLETED √
PROGRESS PART
(Handtools mechanic)
Next Plan :
Measurement results :
Material Used :