Professional Documents
Culture Documents
Economic Analysis of Energy Saving Investments
Economic Analysis of Energy Saving Investments
Investments 19
19.1 Introduction
The payback period is the time required to recover the capital investment
from net cash flow.
The two terms of the payback ratio can be either before or after taxes depending
on the requirements of the investor.
If the salvage cost, that is, the residual value of the equipment at the end of its
useful life, is deducted from the initial capital cost, a payback with salvage is
calculated. Of course, it is shorter than the payback without salvage as defined
above.
The payback method does not consider the savings after the payback years; thus
it penalizes projects that have a long potential life in comparison with those that
offer high savings for a short period.
The payback method does not consider energy-pricing variation or the time
value of the money.
Nevertheless, the payback method is very simple and it can serve as a yardstick
to compare possible investments.
These methods are based on the conversion of investment and annual cash flow at
various times to their equivalent present values and vice versa. The real interest or
discount rate (r), that is, the nominal discount rate less the inflation rate, and the
number of years (n) of the evaluation period have to be considered.
Several factors are used to accomplish these conversions:
• Future worth factor:
This converts a single present amount (at year zero) to an amount at a future
point in time:
FWF ¼ (1 + r)n.
• Present worth factor:
This converts a future amount to an amount today (at year zero):
1
PWF ¼
ð1 þ r Þn
19.3 Methods Using Life Cycle Costing 303
The net present worth of a project is defined as the difference between the
present worth of the total project revenues (energy cost saving + other
cost savings additional operating costs) and the present capital cost of
the project:
X
n
1
PW ¼ j C pel Qel þ C p Qth C pa Q a Ip
ð1 þ r Þj j th j j
1
where Cp ¼ present monetary value (at year zero) of each unit of revenue (Cpel:
value of unit of electrical energy saving; Cpth : value of unit of thermal energy
saving; Cpa: value of unit of additional saving or cost of materials and working
hours), and Qj ¼ annual revenues in physical units (Qelj : amount of electric energy
saving; Qthj : amount of thermal energy saving; Qaj : amount of additional or saved
materials and working hours, etc.). It is usually assumed that they become effective
in year 1 ( j ¼ 1); Ip ¼ present investment at year zero. If the investment has been
made in different years, the present investment can be calculated by using the PWF
factor:
X
n
Ij
¼ Io þ j
1 ð1 þ r Þj
Xn
1
PW ¼ Cpel Qel þ Cpth Qth Cpa Qa j I
1 ð 1 þ i Þj
¼ Cpel Qel þ Cpth Qth Cpa Qa PAF I ¼ NACF PAF I
where Qel, Qth, and Qa ¼ annual amount of revenues in physical units assumed
constant throughout the life of the investment. They start to become effective in
year 1; n ¼ years of investment life, i ¼ r + f f* (i ¼ r, if f ¼ f*), and I ¼ total
investment concentrated in the year zero (see Payback):
X
n
1
j ¼ Present annuity factor ðPAFÞ
1 ð1 þ iÞj
If PW is greater than zero, the project is valid since the revenues are
enough to pay the interest and to recover the initial capital cost
before the end of the life of the investment. If PW equals zero, the
balance occurs at the end of the life, but the investment is scarcely
attractive. PW less than zero means that the project is a bad one.
Projects can conveniently be compared by taking as a parameter the
ratio between the present worth of the project and the related investment
(PW/I).
19.4 Case Studies 305
Factors such as PWF and PFA can be evaluated either by using tables (see
Tables 19.1 and 19.2) or by calculation on personal computers, with any software
available.
Table 19.3 shows an example of PW calculation by using both the general and
the simplified expressions.
IRR is the internal interest rate that reduces to zero the present worth of
the project at the end of the life of the project (n years).
This parameter, named IRR, can easily be compared with the company interest
rate to evaluate the merit of the project. The calculation of IRR requires an iterative
approach: selecting different values of the parameter i) and calculating the PW,
generally using the basic expression.
Several examples discussed from the technical point of view in the previous
chapters are here examined to evaluate the economic validity of the correlated
investment from the cost energy-saving angle.
The basic methods reported in Sects. 19.2 and 19.3 are used and the results for all
the case studies examined throughout the book are shown in Table 19.4.
To facilitate the understanding the table provides example values for the energy
costs and for the investment. Notice that the ratio between electric and thermal
energy costs, which is introduced as an example, has a general validity because this
ratio is roughly the same for many countries. The cost of unit of energy (MWh for
electric energy, TOE for thermal energy) is expressed as kU/MWh or kU/TOE
where U can be any currency; a reference cost of 0.1 kU/MWh and 0.16 kU/TOE of
thermal energy is assumed.
For each case, Table 19.4 shows the annual energy saving, both electrical and
thermal, and the corresponding cost saving. Expected investment life is also
introduced; investment I is expressed in kU units.
The different kinds of investment are compared by using payback and IRR
parameters.
Notice that only energy cost and saving have been considered; for a more
detailed analysis, additional costs and savings (working hours, maintenance,
306 19 Economic Analysis of Energy-Saving Investments
X
n
Table 19.2 Present annuity factor values PAF ¼ jð1þi
1
Þj
1
replacement of components during the investment life, etc.), which often markedly
affect the economic evaluation, must be taken into account.
The same approach can be followed for any other energy-saving investment in
process and facility plants, as it is quite a good way to correlate and to compare
different investments inside a factory.
Table 19.4 Examples of case studies
19.4
Economic evaluation
Annual energy saving Annual cost saving Investment life Investment parameters
Qel Qth Cpel Qel Cpth Qth PAYBACK IRR
Description of case studies Section MWh/year TOE/year kU/year Year kU Year %
Case Studies
Economic evaluation
Annual energy saving Annual cost saving Investment life Investment parameters
Qel Qth Cpel Qel Cpth Qth PAYBACK IRR
Description of case studies Section MWh/year TOE/year kU/year Year kU Year %
Refrigeration plant 12.10
Replacement of absorption system 1,140 902.0 114.0 144.3 10 305 10.06 -
Heat recovery 0.0 80.7 0.0 12.9 10 20 1.55 64.00
HVAC 13.7
Recovery from exhaust air 21.7 422 2.2 67.5 10 600 9.2 1.5
Computer control 240.0 90.0 24.0 14.4 8 200 5.2 11
Lighting 14.6
Replacement of fluorescent with HF 249.3 0.0 24.9 0.0 8 160 6.4 5.1
19