DETAILED SCOPE OF SUPPLY

Internal pipeline cleaning and coating (MSP5-MSP10)

No. Description Responsibility Remarks


1 Project Preparation, Insurance, Safety Vendor
2 Mob/Demob, Visa, Work permits Vendor
3 Chemicals & Painting materials Vendor
4 Speciality equipment & Pigs Vendor
Equipment (Compressors, air dryers, See attached list for equipment at both
5 Vendor
etc.) ends
6 Labour Vendor
Transportation costs from vendor's
7 Vendor
locations to VSP port.
Piping specification will be the same as
8 Temporary spools (~ 12m) VSP
the main pipeline
150m3 can be injection water, 50m3
9 Fresh water (200m3) VSP
potable water
10 Diesel for equipment VSP 60÷80m3
11 Seperation of effluent Vendor
12 Neutralization of spent acid Vendor
13 Disposal of effluent VSP
Tanks and space (or access) for water,
14 VSP 200÷250 m3
effluent, and diesel
Offshore transportation, accomodation &
15 VSP
meals.
16 Support vessels VSP