Newmarket Viaduct Deconstruction

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

SE17 paper_Newmarket Viaduct deconstr_Layout 3 02/09/2011 11:21 Page 32

Paper
Newmarket Viaduct deconstruction
Jon Varndell, BEng (Hons), CEng, MICE Introduction
Design Manager – NGA Newmarket Alliance, URS – Principal Engineer The Newmarket Viaduct was constructed in the 1960s and forms
a vital link in Auckland’s motorway network. The dual three lane
Peter Lipscombe, NZCE, BE (Hons), PhD, MIPENZ, CPEng viaduct now carries over 160 000 vehicles per day and is part of
Structure Design Manager – NGA Newmarket Alliance, URS – Principal Engineer the busiest section of road in New Zealand. The viaduct is 690m
long and comprises 16 spans up to 23m high passing over a busy
Ian Billings, BE (Hons), FIPENZ, CPEng
urban retail area and the North Auckland Railway line (Fig 1).
Senior Bridge Advisor – NGA Newmarket Alliance, Beca – Technical Director
The viaduct consists of two post-tensioned, cast in-situ box
Keywords: Newmarket Viaduct, Auckland, New Zealand, Viaducts, Replacing, Motorways,Temporary works,
girders transversely connected at each pier. Constructed by the
Segments, Strengthening, Risk management
balanced cantilever method, it was one of the earliest bridges built
Received: 03/11: Modified: 04/11; Accepted: 05/11
using this method in New Zealand. Deficiencies in the design,
© Jon Varndell, Peter Lipscombe & Ian Billings related to differential temperature effects, were identified during
construction when large (up to 4mm wide) cracks were observed
in the soffit slab. Mitigation measures were put in place and
Synopsis subsequent research carried out on the viaduct was also used for
The Newmarket Viaduct was completed in 1966 and has played a the development of the differential temperature design rules for
vital role in the Auckland motorway network for the last 45 years. bridges.
The viaduct carries more than 160 000 vehicles per day over The combined effects of substantial traffic volume growth and
several key arterial roads and the North Auckland railway line. the vital role the viaduct plays in the security of the motorway
The structure comprises two parallel, balanced cantilever bridges network, led to the decision for the viaduct to be replaced. The
connected at each pier with a post-tensioned portal frame. new viaduct will provide additional lanes and improved seismic
Increased traffic volumes and the limitations of the live load, resistance, edge protection and vehicle load capacity. The key
differential temperature and seismic performance of the structure challenge was that the old viaduct had to be deconstructed and
created the need to replace the old six lane viaduct. This paper replaced with no impact on the peak motorway traffic capacity
describes how the viaduct is being replaced in stages while throughout construction.
keeping the motorway operational throughout. Implemented under The essential link between the design and construction/
an alliance framework, the benefits of the integrated client, design deconstruction methodology, coupled with the uncertainties about
and construction team are discussed. The complex and the old viaduct, and the management of significant risks, resulted
unprecedented challenges of deconstructing this post tensioned in the project being implemented as an alliance; a virtual
viaduct in stages whilst it remains in service are described in detail. organisation comprising the owner (the NZ Transport Agency)
three contractors and four design firms.
This paper describes the project’s unprecedented challenges
and methods used to deconstruct the old viaduct while keeping
the motorway fully operational, and summarises the key mitigation
measures put in place to manage the risks.

Staging of the works


The project involves an on-line replacement of the old viaduct; with
the centre line of the viaduct being shifted by just 13m to the east.
This was to avoid major motorway realignment and land purchase,
and minimise disruption to the community. A detailed staging
scheme was developed to enable the motorway to remain in full
service throughout the project. The 4 key construction stages are
illustrated in Fig.2.
The extremely tight clearances to the motorway traffic,
combined with the height of the viaduct above ground level,
required meticulous planning of each construction and
deconstruction activity.
1 Aerial photograph taken in December 2010 showing the old
southbound viaduct at commencement of deconstruction

1 2 3 4
2 Key construction stages
Stage 1 – Construct the new southbound viaduct, parallel to, and slightly overlapping with, the old southbound viaduct
Stage 2 – Commission the new southbound viaduct and then deconstruct the old southbound structure
Stage 3 – Construct the new northbound viaduct in the gap left by the deconstruction
Stage 4 – Commission the new northbound viaduct and then deconstruct the old northbound structure

32 The Structural Engineer 89 (17) 6 September 2011


SE17 paper_Newmarket Viaduct deconstr_Layout 3 02/09/2011 11:21 Page 33

Soon after opening, gaps up to 4mm wide were observed in the


bottom slab at a number of transverse joints and cracking was
evident at other locations in the box webs and transverse pier
diaphragms. The subsequent major investigation identified that the
design standards of the time did not adequately address
differential temperature effects, which were subsequently found to
be significant. There was insufficient reserve of prestress to absorb
the differential temperature effects.
The bridge was closed to heavy vehicles until substantial
longitudinal external post-tensioning was installed inside the box
3 The old viaduct – 690m long structure comprised 16 spans ranging girders (in the form of Macalloy bars) to strengthen the structure.
from 33.5m to 61m The differential temperature gradient was also reduced by the use
of a light-coloured dacite chip in the bridge surfacing; reducing the
gradient by 5.5°C. These measures were completed by the late
The old viaduct description 1960s and proved to be reasonably successful although ongoing
The old viaduct consisted of two parallel post-tensioned concrete problems were experienced with some of the deck slab transverse
box girder structures; each carrying three lanes of motorway traffic joints ‘working’ under wheel loads and cracks opening by up to
at a height above ground level varying from 8m to 23m. The 690m 0.3mm in the bottom slab.
long structure comprised 16 spans ranging from 33.5m to 61m as In 2002 an investigation was commissioned into widening the
indicated in Fig 3. viaduct and bringing it up to current standards. Extensive
The site geology is complex and variable. Most of the viaduct inspection and assessment studies were conducted and a number
was founded on one of two basaltic lava flows that originated from of deficiencies identified. These included substandard edge
volcanic cones on each side of the valley the viaduct crosses. The barriers, limited traffic load capacity, due to the thin deck slabs,
two flows do not quite meet and thus three piers between the lava and seismic vulnerabilities in the piercaps and movement joints
flows were supported on piled foundations, which extended down that could lead to potential collapse of part or the entire viaduct
to the Waitemata sandstone. Extensive sand/cement grouting, during a relatively low return period (200 year) seismic event. A
applied under pressure, was undertaken to fill fractures in the widening and strengthening design was developed but it indicated
basalt for the shallow pad foundations. this would be costly and that risks inherent in the lightly reinforced
Each box girder was supported on a single, reinforced, hollow and poorly detailed structure would remain. In early 2006 the New
box column, founded on spread footings or piled foundations. Zealand Transport Agency made the decision to replace the
Each column had a pin connection at the base formed using a viaduct rather than widen and strengthen it.
0.9m × 0.4m × 0.3m concrete block set into both the pad/pile cap
and the pier base. A transverse, post-tensioned pier cap Deconstruction philosophy
diaphragm beam between the tops of each column pair, linked the The deconstruction philosophy was specifically developed to
north and southbound bridges to form a pin base portal in the address the huge challenges presented by the site constraints so
transverse direction (see Fig 4). that the viaduct could be deconstructed safely in a controlled
The twin cell box girders were continuous in the longitudinal manner.
direction between the bridge’s six movement joints. These were The old viaduct, with its pinned base piers, firstly had to be
provided with longitudinally guided ‘Radialube’ (sliding plate) stabilised before it could be separated longitudinally into two
bearings. The longitudinal cantilever and continuity post-tensioning halves. The temporary works required to secure the longitudinal
tendons were located within the three webs of each box girder. and transverse stability of the viaduct, after cutting the post-
Transverse prestressing was also used in the box girder top and tensioned pier cap beams that connected the two halves, were
bottom flanges to reduce their thickness. extensive. As the northbound viaduct continued to carry traffic for
The viaduct was designed by the Ministry of Works between a year after being cut free, the design of the temporary works was
1962 and 1963, and construction was completed in 1966. As was treated with the same rigour and authorisation process as would
the practice at the time, no explicit allowance was incorporated in be applied to permanent works.
the design for differential temperature effects. Once the pier caps had been cut and the viaducts separated
The box girders were constructed in 3m long segments with no into two structures, stabilised by the temporary works, the first
reinforcement steel across the transverse joints between viaduct was deconstructed using the reverse balanced cantilever
segments. In addition, the boxes were lightly reinforced and had method. This involved deconstructing the viaduct in the opposite
thin flanges, with a 150mm deck slab and 125mm bottom slab sequence to which it had been constructed. Firstly, the mid-span
(see Fig 5). The thin deck slab limited the traffic load carrying closure segment was removed to create a free balanced cantilever.
capacity of the viaduct. Then segments were removed, one at a time from both ends of

4 Old viaduct cross section 5 Old viaduct box girder during construction (circa 1965)

The Structural Engineer 89 (17) 6 September 2011 33


SE17 paper_Newmarket Viaduct deconstr_Layout 3 02/09/2011 11:21 Page 34

6 New southbound viaduct next to the old viaduct, showing transverse 7 Longitudinal props and shield beam
stabilisation

the cantilevers using a 140m long, 810t, overhead gantry that was – traffic live load.
also used for the new viaduct construction. The deconstruction
progressed back to the pier table, at which point the pier table and The Ultimate Limit State load combinations considered were
pier column were demolished either by hydraulic crushers attached consistent with those derived from the Bridge Manual2 and
to a hydraulic excavator on the ground or cut into small sections AASHTO.
and removed by crane. The viaduct was thus dismantled in the In general, checks on section capacity were undertaken at the
reverse sequence to which it had been built, however, a key Ultimate Limit State only. Serviceability Limit State capacity checks
difference was that the prestressing tendons could not be were undertaken in a few cases but only to determine suitable
progressively destressed because they had been grouted at the limits for alert/alarm values used in monitoring the works. When
time of the original construction. The inability to destress the analysis showed that elements of the viaduct were overstressed,
tendons resulted in a stress distribution within the partially the deconstruction methodology was revised to try and reduce the
deconstructed works quite different from that experienced during loads. If this was not possible, then strengthening was designed.
the original construction. Analysis and control of these built-up Capacity checks were made on the assumption that the tendons
stresses is discussed in the next section. were either fully bonded (as intended in the original construction) or
unbonded (as might happen with poor grouting practice). In cases
Deconstruction analysis where tendon grouting was critical, the more adverse condition
A stage-by-stage deconstruction analysis was undertaken to was assumed to exist unless intrusive investigation was
calculate the expected forces in the viaduct at each stage of the undertaken to prove the quality of the grout.
deconstruction process. This included modelling the reactions
from the 810t overhead gantry used for the deconstruction Temporary works
process, in its various configurations. The gantry was supported Pier brackets
directly over the piers and therefore did not impart loads into the As previously noted, deconstruction required cutting the portal
superstructure. However, the effects of the gantry weight on the frames that supported both superstructures at every pier location
foundations and temporary works were significantly larger than any (see Fig 6). This required cutting the piercap beam and severing
previously applied loads to the structure, requiring strengthening of the post tensioning (comprising six tendons, each with 12 × 0.5in.
some of the foundations. The effects of wind and seismic loads strands) thus compromising the transverse stability of the structure
from the gantry were also very significant and had to be modelled and the support of the outer webs of the box girders.
for each stage of the deconstruction. While properly grouted tendons do re-anchor and therefore not
Analysis of the deconstruction sequence was performed using all of the strength is lost it was considered this should not be relied
three separate computer models and the results combined using a upon for the fundamental vertical support of the box girder webs –
suite of spreadsheets. The first of the models was a 2-D time- structural steel pier brackets were installed to support the load
dependant model that calculated the stress state in the viaduct (see Fig 6). In addition to supporting vertical loads, the pier
allowing for prestressing, creep, shrinkage and dead load effects. brackets also provided anchorage for the gantry holding down
This model was developed after an extensive assessment of the bars and connection points for the transverse props. The brackets,
original structure data (including interviewing members of the each weighing 7t, supported a load of up to 620t. They were
original construction teams). The second model was a 2-D beam clamped to the pier with sufficient force to resist the load by
element model used to calculate wind, seismic and gantry load friction. Friction was enhanced by roughening the surface of the
effects on the viaduct and temporary works. The third model was a concrete column, using weld beads on the steel contact plate, and
grillage model used to assess segment removal and live load 60MPa low-shrinkage grout between the two surfaces. Scaled
actions on the superstructure. trials were undertaken to verify the friction force that could be
The primary load cases considered in the deconstruction were resisted. The coefficient of friction used in design was 0.91, this is
basically the same as those that would be considered for the lower bound residual value after 2mm slip from a series of 16
construction of a new viaduct. tests.
The primary loadings included: At some highly loaded piers a reinforced concrete corbel was
– dead load (including the gantry weight); also added beneath the pier bracket.
– specialist construction equipment (e.g. diamond wire cutters);
– construction live load (typically 0.5kPa); Transverse stabilisation
– accidental release of a segment (derived from AASHTO1); Transverse stability of the cut portal frame was maintained by
– in-service wind loads (based on 15m/s wind speed); transverse props. These comprised twin 762mm OD × 6.4mm WT
– out-of-service wind loads (1000 year return period); tubes diagonally propping the northbound viaduct and a 457mm
– earthquake loads (500 year return period); OD × 12.7mm WT tube supporting the southbound. This
– temperature effects; configuration allowed the southbound viaduct to be deconstructed

34 The Structural Engineer 89 (17) 6 September 2011


SE17 paper_Newmarket Viaduct deconstr_Layout 3 02/09/2011 11:22 Page 35

gantry and probably the adjacent viaducts. For the longitudinal


props a shield beam (see Fig 7) was designed to protect the props
by absorbing energy from accidental release of a box girder
segment above. The shield beam was supported by the vertical
props located approximately 9m from the pier. The vertical props
acted in both tension and compression. While supporting the
shield beam, these primarily resisted the out-of-balance load
effects from removal of box girder segments No. 4 to 8. The pier
itself was strong enough to resist the out-of-balance actions during
removal of box girder segments No.1 to 3.
The four main elements of the temporary works described
previously are shown in Fig 8. These totalled 55t of steelwork at
each pier. Where possible, the temporary works were re-used
along the viaduct as deconstruction progressed. In this way only
six full sets were required for deconstruction of 28 piers.

8 Temporary steelwork required for pier stability during deconstruction Deconstruction methodology
The typical deconstruction sequence involved removal of the
midspan closure segments, followed by successive removal of the
cantilever segments.
to foundation level prior to deconstructing the northbound.
Midspan closure segment removal
Longitudinal stabilisation Removal of the closure segment at the mid-span location involved
Similar to the transverse direction, longitudinal props were required changing the structural system from a continuous structure, with
in the longitudinal direction to maintain stability when the mid-span its locked-in forces, to a statically determinate one. In the process
closure segments were removed (see Fig 7). The longitudinal props of making the first cut, bending moment and shear was released
comprised 610mm OD × 9.5mm WT steel tubes connected at the and redistributed into the newly created free cantilever. There were
upper end to the pier column, and at the lower end to a specially significant locked in forces from the original construction together
constructed reinforced concrete foundation. The foundations with prestress losses, creep and shrinkage that had occurred since
required four, 90t ground anchors to provide the necessary uplift that time. These locked-in forces had to be released in a controlled
resistance when the prop went into tension. manner to avoid a dynamic load release. This was achieved by
Protection of the longitudinal and transverse props from damage staged cutting and hydraulic jack unloading to decompress the
was a paramount consideration since loss of these had the locked-in forces. Figs 9.1 to 9.4 show the procedure in more
potential to destabilise the pier with consequential loss of the pier, detail. Fig 10 shows the closure segment removal system in use,

9.1 9.2

9.3 9.4

Fig 9.1 A 200mm diameter hole (300mm deep) was cored in the top of each web and a jack was installed in the hole. The jacks
were pressurised to a force equivalent to the estimated force in the top flange of the box girder. A steel beam was
prestressed to the deck above each of the three webs to control any shear movement between the cantilever tips
Fig 9.2 The bottom slab of the box girder was cut, followed by the top slab. The diamond wire saw used for cutting made an 11mm
wide cut; wide enough to release the locked-in displacements in subsequent stages. Each web was then cut from the
bottom of the box girder up to the continuity tendons and from just above the continuity tendons up to the underside of the
jacks. At this point the bending moment across the cut line was carried by a couple between the jacks and the continuity
tendons, and the shear was carried by the small remaining area of concrete surrounding the continuity tendons
Fig 9.3 The horizontal jacks in the top of the webs were slowly and uniformly unloaded to release the bending moment in the
section. The midspan deflected downwards as forces redistributed. This displacement was typically 25mm. The jacks under
the steel beams were preloaded to a force equivalent to the estimated shear across the cut line. Then the continuity
tendons were cut; outer webs first, followed by the central web. The jacks under the steel beams were slowly and uniformly
unloaded to release the shear force across the cut line
Fig 9.4 A second cut was made to isolate the closure segment. The closure segment was then lowered to the ground on strand
jacks. In a few locations it was removed by crane or gantry where the ground underneath was not suitable

The Structural Engineer 89 (17) 6 September 2011 35


SE17 paper_Newmarket Viaduct deconstr_Layout 3 02/09/2011 11:23 Page 36

10 Closure segment being lowered to the ground on strand jacks 12 Box girder segment fitted with delamination restraints around the top
web/flange junction

11 Gantry typically used to deconstruct the free cantilevers

with the closure segment being lowered to the ground. support leg.
The magnitude of the locked-in forces was estimated to be quite A primary advantage of using the overhead gantry was that it
large with a significant degree of uncertainty. Furthermore simplified segment removal in areas where access from the ground
temperature difference between the top and bottom flanges was difficult. Segments could be lowered to the ground at places
produced very large bending moments in the box girder that that suited site constraints. Typically, each segment was lowered
changed throughout the day. To manage these effects the critical on to a waiting transporter and carted away for recycling, at a site
activities involved with releasing the locked-in forces were remote from the viaduct. Scrap steel was sold to a local steel mill
undertaken when the temperature difference between the top and and the recovered aggregate is destined for use on an upcoming
bottom flanges was less than 2°C. This typically meant the works Transport Agency project.
were undertaken between midnight and 9.00am.
Strengthening works
Cantilever segments removal Parts of the viaduct had to be strengthened so that it could be
Removal of segments from each cantilever was undertaken with deconstructed safely. This ironic situation arose for three reasons:
the overhead gantry. To minimise the dynamic effects that would firstly to compensate for defects in the original box girder; secondly
result from a sudden release of forces, the hanger bars between to compensate for the weight of the gantry; and thirdly because of
the gantry and the segment were pre-stressed with a force the build up of stresses that could not be released due to the cut
equivalent to the weight of the segment prior to cutting. The tendons redeveloping their bond. These elements are discussed
specified cut sequence was: outer webs then central web – from below.
the bottom up.
To minimise the out-of-balance effects, the segment on the Additional post-tensioning
opposing free cantilever was also stressed up to the gantry in Additional external post-tensioning had to be installed to ensure
preparation for its removal. segments joints remained closed at the quarter span points of the
In the process of cutting along the segment construction joint, spans adjacent to intermediate deck joints. There were six
there was a risk of disrupting the cantilever anchorage in the locations where this was required. Analysis showed that
segment adjacent to the construction joint. If the anchor head had excessively large cracks would have opened at these locations
been damaged, and if the cantilever tendon was poorly grouted, and as a result the shear capacity could have been compromised
the segment adjacent to the one being removed could have been if the external post-tensioning was not installed.
accidentally released. To mitigate this risk, the segment adjacent to
the one being cut was also suspended passively from the gantry Substructure strengthening
on hangers. The load path down the columns and into the foundations passed
Fig 11 shows how the gantry was typically used to deconstruct through the high strength (55MPa) concrete hinge block (plan
the free cantilevers. This method was used to deconstruct down to dimensions 916 × 406mm) at the base of every column. Around
the ±1 segments. Due to the very short pier table, and the large the hinge block there was a 25mm gap to ensure the connection
reaction force from the gantry on the pier table, it was necessary to behaved as a true hinge. At 810t the heavy gantry introduced
leave the ±1 segments on the pier while the gantry launched loads into the substructure up to 40% larger than they had
forward to the next pier. The ±1 segments were then removed with previously experienced with traffic loads. There was concern that
the rear of the gantry while it was supported on the lighter rear the lightly reinforced pad foundations may fail in a brittle manner

36 The Structural Engineer 89 (17) 6 September 2011


SE17 paper_Newmarket Viaduct deconstr_Layout 3 02/09/2011 11:23 Page 37

under these loads. To reduce this risk and achieve a better load properties. The daily and long term movement of the viaduct
distribution across the foundation, the 25mm gap surrounding the superstructure, expansion joints and piers was monitored using
hinge was grouted with cement grout resulting in a continuous surveying prisms mounted on the structure with a total station
connection. For the piers with piles, the additional bending collecting data automatically over a 24h period. The results were
moment introduced by the continuity would have overstressed the then back-analysed to confirm the findings from the structural
foundations and the gap was grouted only over part of the column analysis.
footprint to minimise moment transfer.
Even with these measures, the piers either side of Broadway Existing post-tensioning
(the longest span) required the foundation pads to be strengthened Three critical aspects of the post-tensioning had to be verified;
to safely carry the gantry loads. This was achieved with a their precise location, competency of grouting and strand
composite concrete overlay, 800mm deep, over the original pad condition. Ground penetrating radar surveys were used to initially
foundation. identify the tendon locations. These were confirmed at key
locations by drilling 25mm diameter holes to expose the tendon
Strengthening to resist excessive prestress ducts. The duct sheath and grouting were removed using a hand
As segments were successively removed from the free cantilever, chisel to expose the tendon strands and an endoscope was used
stresses built up in the remaining structure. This was because the to inspect and record the grout and tendon condition. The tendons
post-tensioned tendons (cantilever tendons and continuity were generally found to be in very good condition and well
tendons) that originally supported the whole superstructure could grouted. It was particularly important not to cut through the
not be progressively destressed as parts of the superstructure cantilever tendon anchorages either side of the closure segments
were removed. Left unchecked, this could have resulted in a and in these cases separate enlarged intrusions were made to
longitudinal shear failure between the web and the deck slab of the expose the anchor heads.
box girder and delamination of the group of cantilever tendons at
the top of the web. Both scenarios had the potential for an
uncontrolled collapse of the superstructure during deconstruction. Ground conditions
The solution adopted comprised the installation of continuous There was a real risk of pier settlement during the deconstruction
concrete strips over and under the web-deck junction. These were due to:
then prestressed to the box girder, both vertically through the deck – the use of the gantry resulted in the maximum pier load being up
and horizontally through the webs (Fig 12). The concrete strips to 40% greater than the viaduct had experienced in its 45 year
generally extended over the first one to three segments each side history;
of a pier and ensured the superstructure remained stable should – the underlying basalt had required extensive grouting during the
shear failure occur. They also effectively confined the grouped original construction to make it perform as a massive block. To
tendons and prevented delamination failure. mitigate this risk the ground conditions were investigated with
extensive drilling and the critical pier foundations were proof
Risk management loaded in advance by stressing of the deconstruction ground
Effective risk management was a critical factor in the successful anchors (by up to 800t) to represent the loading from the gantry.
deconstruction of the viaduct. A comprehensive risk management A fundamental change was also made to the deconstruction
system based on the proprietary Active Risk Management system, sequence and gantry operation to reduce the maximum load on
was used to identify, assess, control and monitor risk. Initially the the piers.
system was used to establish a risk contingency sum for
incorporation into the target outturn cost. During the detailed Trials to validate critical deconstruction activities
design and construction phase more detail was added, particularly Validation trials were carried out for critical elements that were
as new information came to light. Detailed response (mitigation) either unprecedented or where the consequences of failure were
plans were developed and assigned to appropriate single owners significant. Testing of scaled down pier bracket/pier interface pads
throughout the alliance team. Over 80 risks were identified and confirmed the design friction parameters and factor of safety. The
300 response plans developed. This is where the ‘active’ nature of first midspan cut and segment removal were reprogrammed to the
the system came to the fore; as owners were automatically sent southern end of the viaduct – where the viaduct was closest to the
reminders to close out their risk mitigations on time. ground – with temporary back-up propping located under the cut
A project review panel was established to review and challenge location to confirm the performance of the cutting method. This
the robustness of the project team’s identification and mitigation of initial trial also included testing of the delamination restraints to
risk. The panel comprised senior managers from the alliance confirm their effectiveness.
participants who were not directly involved in the delivery of the
project. The panel visited the project every 3 months. Temporary works performance
The key risks and mitigation measures addressed for the A rigorous programme of monitoring was employed to check the
deconstruction are summarised below. forces and performance of the temporary works. Strain gauges
measured the forces in the longitudinal, diagonal and vertical
Existing structure condition props. The ground anchors were re-stressed to compensate for
It was essential for the existing condition of the viaduct to be foundation settlements and the jacks on the pier brackets were
understood sufficiently so that the assumptions made in the checked regularly to verify that they retained the specified force.
deconstruction analysis and temporary works design were based
on an acceptable level of residual risk. Vehicle impact with partially deconstructed viaduct or gantry
The extreme threat for the deconstruction was the risk of a major
As-constructed details vehicle impact with either the partially deconstructed works or the
A detailed review was carried out of previous papers written about gantry. Speed restrictions, backed up by speed monitoring,
the viaduct3, inspection records and structural assessment enforcement cameras and extensive communications, were
reviews. A full set of as-built drawings (in Imperial units) was employed to reduce traffic speeds from the original 100kph to
obtained and the information, including the individual tendon 70kph. Test Level 4 (TL4) barriers were installed to provide a high
profiles, was digitised into a 3D CAD model. Contact was made level of containment. The maximum risk exposure occurred once a
with the original Resident Engineer and Construction Manager, midspan cut had been made and the full balanced cantilever could
with both interviewed to gain a better understanding of issues that be impacted at its tip. To mitigate this risk the cantilever was tied
occurred during the viaduct’s design and construction. back to the new viaduct box using unstressed prestressing
On-site checks were undertaken to confirm the dimension of key strands.
elements and cores were taken to test concrete and reinforcement

The Structural Engineer 89 (17) 6 September 2011 37


SE17 paper_Newmarket Viaduct deconstr_Layout 3 02/09/2011 11:23 Page 38

Deconstruction process control


The analysis and design for the deconstruction was very
prescriptive. Each step of the deconstruction process had to be
carried out strictly in accordance with the plan so that the
assumptions made in the design were complied with. A detailed Eurocode Manuals
deconstruction specification and staging drawings clearly defined
the process. The specification included the detailed monitoring
requirements such as, prop forces, superstructure deflections,
available to buy
differential temperature, and crack width measurement. Alert and
alarm values were specified for each monitoring metric and at each
stage of the deconstruction.
Integration of the design and deconstruction teams in one
project office was a key factor in ensuring the requirements were
translated into workable method statements. An overarching
process control plan, with strict hold points and sign-off protocols,
was used to control the progress of each step of the
deconstruction. This combination of an integrated team and strict
adherence to the deconstruction plan ensured the inherent risks
were managed effectively.

Acknowledgments
The authors wish to acknowledge support and contribution of the
New Zealand Transport Agency in the success of this project, as
well as the project participants – Leighton, Fulton Hogan, VSL,
URS, Beca, Tonkin & Taylor and Boffa Miskell.

References
1 American Association of State Highway and Transportation Officials LRFD
Bridge Design Specifications, 4th edition 2007
2 Transit New Zealand Bridge Manual, 2nd edition with amendments up to Please visit http://shop.istructe.org or
and including June 2005. Published by New Zealand Transport Agency
call 020 7235 4535 to purchase your
3 Built, J. W., Smith, A. W., McKinnell, P. B.: ‘The Newmarket Viaduct’; New
ow
Zealand Engineering; 20/12, December 1965, p493-511
copy now!
y n
Bu

A short guide to embodied


carbon in building structures
Climate change is widely accepted as one of the greatest
challenges facing the world today. Since the signing of the
Kyoto Protocol in 1997, governments and world leaders
have committed to reducing the output of carbon dioxide
and greenhouse gases in massive amounts, having a
profound effect on most industries and in the development
of technology to meet this aim.

A short guide to Embodied Carbon in Building Structures


provides essential guidance to structural engineers about
how they can reduce the carbon footprint of structures,
Member’s price: £10 focusing mainly on embodied energy and carbon associated
Non-members price: £25 directly with the structure.

Please visit http://shop.istructe.org/or tel: +44(0)20 7235 4535 to purchase your copy now!
Registered Charity with the Charity Commission for England and Wales No. 233392 and in Scotland No. SC038263

38 The Structural Engineer 89 (17) 6 September 2011

You might also like