Professional Documents
Culture Documents
Ias 37
Ias 37
Ias 37
Onerous contracts
IAS 37 defines an onerous contract as one in which unavoidable costs of completing the
contract exceed the benefits expected to be received under it (IAS 37: para. 10).
Unavoidable costs of meeting an obligation are the lower of:
◦ Cost of fulfilling the contract
◦ Penalties from failure to fulfil the contract
An example may be a fixed price supply contract related to a particular product that, due to
inflation, now costs more to manufacture than the fixed sale price agreed in the contract. If
an entity has a contract that is onerous, the present obligation under the contract must be
recognised and measured as a provision (IAS 37: para. 66).
Specific types of provision
Future repairs to assets
Some assets need to be repaired or to have parts replaced every few years. For example, an
airline may be required by law to overhaul all its aircraft every three years.
Provisions cannot normally be recognised for the cost of future repairs or replacement parts.
This is because there is no current obligation to incur the expense – even if the future
expenditure is required by law, the entity could avoid it by selling the asset.
Example
Danboy is a company that owns several shops and which has a year end of 31 December
20X1.
One of the shops is loss-making. At 31 December 20X1, Danboy forecasts that this shop will
make a loss of $50,000 in the year ended 31 December 20X2.
As at 31 December 20X1, one of the shop buildings requires repair. The cost has been reliably
estimated at the reporting date at $10,000. The repair is made in the following accounting
period at a cost $12,000.
Required:
◦ Discuss the accounting treatment of the above in the financial statements for the year ended 31
December 20X1.
Solution
IAS 37 states that no provision should be made for future operating losses. Therefore, no
provision should be made for the $50,000 forecast losses.
No provision should be made for future repairs despite it being probable and capable of
being reliably measured. This is because there is no obligation at the year end. The repairs
expenditure of $12,000 is expensed to profit or loss as it is incurred.
Example
Under new legislation, an entity is required to fit smoke filters to its factories by 31
December 20X7. At the reporting date of 30 June 20X7, the entity has not fitted the smoke
filters.
Required:
◦ Should a provision be made at the reporting date for the estimated cost of fitting the filters?
Solution
No provision should be made for this future expenditure despite it being probable and
capable of being reliably measured. There has been no obligating past event (the fitting of
the filters).
Environmental provisions
Environmental provisions are often referred to as clean-up costs because they usually relate
to the cost of decontaminating and restoring an industrial site after production has ceased.
A provision is recognised if a past event has created an obligation to repair environmental
damage:
◦ A provision can only be set up to rectify environmental damage that has already
happened. There is no obligation to restore future environmental damage because the
entity could cease its operations.
◦ Merely causing damage or intending to clean-up a site does not create an obligation.
➢An entity may have a constructive obligation to repair environmental damage if it
publicises policies that include environmental awareness or explicitly undertakes to
clean up the damage caused by its operations
Environmental provisions
The full cost of an environmental provision should be recognised as soon as the obligation
arises.
◦ The effect of the time value of money is usually material. Therefore, an environmental
provision is normally discounted to its present value.
◦ If the expenditure results in future economic benefits then an equivalent asset can be
recognised. This is depreciated over its useful life, which is the same as the ‘life’ of the
provision.
Example
a) An entity has a policy of only carrying out work to rectify damage caused to the
environment when it is required to do so by local law. For several years the entity has
been operating an overseas oil rig which causes environmental damage. The country in
which the oil rig is located has not had legislation in place that required this damage to
be rectified.
A new government has recently been elected in the country. At the reporting date, it is
virtually certain that legislation will be enacted that will require damage rectification.
This legislation will have retrospective effect.
b) Under a licence granted by a local government, an entity has constructed a rock-crushing
plant to process material mined from the surrounding area. Mining activities have
already started. Under the terms of the licence, the entity must remove the rock-
crushing plant when mining activities have been completed and must landscape the
mined area, so as to create a national park.
Required:
◦ For each of the situations, explain whether a provision should be recognised.
Solution
For each situation, ask two questions.
a) Is there a present obligation as the result of a past event?
b) Is an outflow of economic benefits probable as a result?
A provision should be recognised if the answer to both questions is yes. In the absence of
information to the contrary, it is assumed that any future costs can be estimated reliably.
a) Present obligation? Yes. Because the new legislation with retrospective effect is virtually
certain to be enacted, the damage caused by the oil rig is the past event that gives rise to a
present obligation.
◦ Outflow of economic benefits probable? Yes.
◦ Conclusion – Recognise a provision.
b) Present obligation? Yes. There is a legal obligation under the licence to remove the rock-
crushing plant and to make good damage caused by the mining activities to date (but not any
that may be caused by these activities in the future, because mining activities could be
stopped and no such damage caused).
◦ Outflow of economic benefits probable? Yes.
◦ Conclusion – Recognise a provision for the best estimate of the eventual costs of rectifying the damage
caused up to the reporting date.
Example
On 1 January 20X6, Scrubber spent $5m on erecting infrastructure and machinery near to an
area of natural beauty. These assets will be used over the next three years. Scrubber is well-
known for its environmentally friendly behaviour and is therefore expected to restore the
site after its use.
The estimated cost of removing these assets and cleaning up the area on 1 January 20X9 is
$3m.
The pre-tax, risk-specific discount rate is 10%. Scrubber has a reporting date of 31 December.
Required:
◦ Explain how the above should be treated in the financial statements of Scrubber.
Solution
Scrubber has a constructive obligation to restore
the area to its original condition as a result of a past
event (erecting the infrastructure). Therefore, it
should recognise a provision at 1 January 20X6. The
best estimate of the expenditure is $3m, but this
must be discounted to its present value of
$2,253,000 ($3m × 0.751). Movement on provision 20X6 20X7 20X8 20X9
Scrubber could not carry out its operations without Opening balance 2,253 2,478 2,727 3,000
incurring the clean-up costs. This means that Finance cost at 10% 225 249 273 -
incurring the costs gives it access to future
economic benefits. The estimated clean-up costs Utilisation - - - (3000)
are therefore included in the cost of the property,
plant and equipment (PPE): Closing balance 2,478 2,727 3,000 -
Dr PPE $2,253,000
Cr Provisions $2,253,000
Each year, the discount unwinds and the provision
increases. The unwinding of the discount is charged
to the statement of profit or loss as a finance cost.
Solution Continued
Initial cost of PPE $000
Cash paid 1 January 20X6 5,000
PV of clean-up costs 2,253
Total 7,253
Where the restructuring involves the sale of an operation, no obligation arises until the entity
has entered into a binding sale agreement.
Restructuring costs
A restructuring provision includes only the direct expenditures arising from the restructuring,
which are those that are both (IAS 37: para. 80):
a) Necessarily entailed by the restructuring; and
b) Not associated with the ongoing activities of the entity.
The amount recognised should be the best estimate of the expenditure required and it
should take into account expected future events. This means that expenses should be
measured at their actual cost, where this is known, even if this was only discovered after the
reporting date (this is an adjusting event after the reporting period per IAS 10).
Example
Trailer, a public limited company, operates in the manufacturing sector. During the year
ended 31 May 20X5, Trailer announced two major restructuring plans. The first plan is to
reduce its capacity by the closure of some of its smaller factories, which have already been
identified. This will lead to the redundancy of 500 employees, who have all individually been
selected and communicated with. The costs of this plan are $9 million in redundancy costs,
$4 million in retraining costs and $5 million in lease termination costs. The second plan is to
re-organise the finance and information technology department over a one-year period but
it does not commence for two years. The plan results in 20% of finance staff losing their jobs
during the restructuring. The costs of this plan are $10 million in redundancy costs, $6 million
in retraining costs and $7 million in equipment lease termination costs.
Required
◦ Discuss the treatment of each of the above restructuring plans in the financial statements of Trailer
for the year ended 31 May 20X5.
Solution
Plan 1:
A provision for restructuring should be recognised in respect of the closure of the factories in
accordance with IAS 37 Provisions, Contingent Liabilities and Contingent Assets. The plan has
been communicated to the relevant employees (those who will be made redundant) and
factories have already been identified. A provision should only be recognised for directly
attributable costs that will not benefit ongoing activities of the entity. Thus, a provision should be
recognised for the redundancy costs and the lease termination costs, but none for the retraining
costs:
$m
Redundancy costs 9
Retraining -
Lease termination costs 5
Liability 14
$m
Provision for dismantling and restoration costs b/d 2.145
Interest ($2.145m x 8%) 0.172
New provision for restoration costs at year end prices ($500,000 x 1/1.08 ^19) 0.116
Provision for dismantling and restoration costs c/d at 31 December 20X4 2.433
The overall charge to profit or loss for the year is:
Depreciation 2.607
New provision for restoration costs 0.116
Finance costs 0.172
Provision for dismantling and restoration costs c/d at 31 December 20X4 2.895
Example
On 15 January 20X5, the Board of Directors of Shane voted to proceed with two
reorganisation schemes involving the closure of two factories. Shane’s reporting date is 31
March, and the financial statements will be authorised for issue on 30 June.
Scheme 1
◦ The closure costs will amount to $125,000. The closure will be announced in June, and will
commence in August.
Scheme 2
◦ The costs will amount to $45,000 (after crediting $105,000 profit on disposal of certain machines).
The closure will take place in July, but redundancy negotiations began with the staff in March.
Required:
◦ For each of the two schemes discuss whether a provision should be recognised and, if so, at what
amount.
Solution
Scheme 1
◦ The obligating event is the announcement of the plan, which occurs in June. This is after the year-
end, so there can be no provision. However, the announcement in June should be disclosed as a
non-adjusting event after the reporting date.
Scheme 2
◦ Although the closure will not begin until July, the employees will have had a valid expectation that
it would happen when the redundancy negotiations began in March. Therefore, a provision should
be recognised. The provision will be for $150,000 because the expected profit on disposal cannot
be netted off against the expected costs.
Example
On 30 June 20X2, the directors of Delta decided to close down a division. This decision was
announced to the employees affected on 15 July 20X2 and the actual closure occurred on
31 August 20X2, prior to the 20X2 financial statements being authorised for issue on 15
September.
Expenses and other items connected with the closure were as follows:
$m
Redundancy costs (estimated) 22
Staff retraining (actual) 10
Operating loss for the 2 months to 31 August 20X2 (estimated at 30 June) 12
Profit on sale of property 5
The actual redundancy costs were $20 million and the actual operating loss for the two
months to 31 August 20X2, was $15 million.
Required:
◦ What is the amount of the restructuring provision to be recognised in the financial statements of
Delta plc for the year ended 31 July 20X2?
Solution
The only item which can be included in the provision is the redundancy costs, measured at
their actual amount of $20 million.
IAS 37 prohibits the recognition of future operating losses, staff retraining and profits on
disposals of assets.
Contingent liabilities
A contingent liability is defined by IAS 37 as:
◦ a possible obligation that arises from past events and whose existence will be confirmed by the
outcome of uncertain future events which are outside of the control of the entity, or
◦ a present obligation that arises from past events, but does not meet the criteria for recognition as
a provision. This is either because an outflow of economic benefits is not probable or (more rarely)
because it is not possible to make a reliable estimate of the obligation.