BUILDING WORKS

Item Description Qty

Work Package 1 | MEASURED WORKS - LABOUR CHARGES

SUMMARY

1.1 SUBSTRUCTURE

1.2 WALLING AND FRAMES

1.3 METAL WORK

1.4 FINISHING AND DECORATION

TOTAL Work Package 1 | MEASURED WORKS - LABOUR


CHARGES

1.1 SUBSTRUCTURE (FOUNDATION)

Excavation & Earthworks


Site Clearance m2 3,363
Trench Excavation m3 240
Excavation of pit m3 138
Backfilling m3 187
Damp Proof Course m 232
Soil Sterilization m 232

Concrete Works
50 mm blinding m2 160
Concrete to trench m3 48
Concrete to Column Bases m3 23
Concrete Footing m3 10
Starter Columns m3 1

Formworks
Sides of strip foundation m2 116
Sides of strip column bases m2 78
Sides of starter column m2 78
Sides of ground beams m2 139

Reinforcements
12mm bars kg 1,648
Steel ups kg 1,263
Blockwork
foundation wall; 230mm thick wall m2 255

Plinth Finishes
Rendering,Externally m2 104
Three coats weather guard paints m2 104

TOTAL 1.1 SUBSTRUCTURE (FOUNDATION)


1.2 WALLING AND FRAMES

Blockwork
superstructure wall; 230mm thick wall m2 230

Concrete Works
Columns m3 15

Formworks
Sides of columns m2 171

Reinforcements
16mm bars kg 3,119

8mm steel up for column &beam kg 876.81

TOTAL 1.2 WALLING AND FRAMES


1.3 METAL GATE

5600x2100mm mild steel sliding gate No 1


3000 X850 grills made up with square pipes No 75

TOTAL 1.3 METAL GATE


1.4 FINISHING AND DECORATION

WALL FINISHING

Plastering
Plaster to walls; internally m2 256
Plaster to walls; externally m2 256

Painting
Paint to walls; internally m2 256
Paint to walls;Externally m2 256

CAPING,BEAM &COLUMN FINISHING

Plastering

Plaster to 50mm thick caping m2 18


Plaster to 150mm thick reinforced concrete beam m2 70
Plaster to reinforced concrete column m2 102

Painting

Painting to 50 mm thick caping m2 18


Painting to concrete beam m2 70
Painting to concrete column m2 102

TOTAL 1.4 FINISHING AND DECORATION


Rate Amount
TZS TZS

19,939,191.96

3,821,197.67

3,840,000.00

10,171,097.50

37,771,487.13

500.00 1,681,641.60
4,000.00 960,273.00
4,000.00 550,800.00
500.00 93,534.13
250.00 57,987.50
250.00 57,987.50

50,000.00 8,002,275.00
50,000.00 2,400,682.50
50,000.00 1,164,000.00
50,000.00 477,480.00
50,000.00 51,975.00

5,000.00 579,875.00
5,000.00 391,600.00
5,000.00 391,600.00
5,000.00 695,850.00

350.00 576,770.21
350.00 442,154.27

3,500.00 893,007.50

2,500.00 260,943.75
2,000.00 208,755.00

19,939,191.96

3,500.00 804,405.00

50,000.00 762,300.00

5,000.00 856,125.00

350.00 1,091,483.75

350.00 306,883.92

3,821,197.67

1,140,000.00 1,140,000.00
36,000.00 2,700,000.00

3,840,000.00

7,500.00 1,921,950.00
7,500.00 1,921,950.00

7,000.00 1,793,820.00
7,000.00 1,793,820.00

7,500.00 132,825.00
7,500.00 521,887.50
7,500.00 762,300.00

7,000.00 123,970.00
7,000.00 487,095.00
7,000.00 711,480.00

10,171,097.50
Item Description No. Length

SITE PREPARATIONS AND EXCAVATIONS

1 Preparation of areas to receive new works 1 59.38

2 Excavate trenches for fdns


1 59.38
1 56.64
1 59.31
1 34.33
1 22.29

3 Excavate pits for column bases (0<=d<=1500mm) 74 1.2

3 1

4 Backfilling

4 DPC 231.95

5 Soil sterilization to one side of outer fdn wall 231.95

CONCRETE WORKS

6 50mm blinding concrete to trench 1 231.95

7 Concrete to trench-C20 1 59.38


1 56.64
1 59.31
1 34.33
1 22.29

7 Concrete to Column bases -C30

F1&C1 3 1.2
F2 &C2 74 1

8 Concrete footing /Concrete to ground beam -C30 1 207.6

9 Starter Columns

F1&C1 3 0.3
F2&C2 74 0.3

BLOCKWORK

10 Foundation walling, 230mm thick 1 231.95

FORMWORK

11 To sides of strip fdns 2 231.95

12 to sides of column bases

F1 &C1 3 1.2
F2&C2 74 1

13 to sides of starter columns


F1 &C1 3 1.2
F2&C2 74 1

14 To sides of ground beams 2 231.95

Reinforcement
15 12mm Bars; high yield steel; cold worked; B.S. 4461

Foundation strip 1 927.88


Ground beams 1 927.88

16 Steel ups

a Foundation strip 773.17 0.92


b Ground beams 773.17 0.92

21 Plinth finishing

Render; cement and sand (1:4); wood floated;


external to:-

a Walls 1 231.95

Three coats weatherguard paints to:-

b Walls 1 231.95
Breadth Height Quantity Unit

56.64 3363.28 M2

0.69 1.5 61.4583 M3


0.69 1.5 58.6224 M3
0.69 1.5 61.38585 M3
0.69 1.5 35.53155 M3
0.69 1.5 23.07015 M3

TOTAL 240.06825 M3

1 1.50 133.20 M3

1 1.50 4.50 M3

TOTAL 137.70 M3

187.06825 M3

231.95 M

231.95 M

0.69 160.05 M2

0.69 0.30 12.29 M3


0.69 0.30 11.72 M3
0.69 0.30 12.28 M3
0.69 0.30 7.11 M3
0.69 0.30 4.61 M3

48.01 M3

1 0.30 1.08 M3
1 0.30 22.20 M3

23.28 M3

0.23 0.20 9.55 M3

0.3 0.15 0.04 M3


0.3 0.15 1.00 M3

1.04 M3

1.10 255.15 M2

0.25 115.98 M2

1.2 4.32 M2
1 74.00 M2

TOTAL 78.32 M2
1.2 4.32 M2
1 74.00 M2

TOTAL 78.32 M2

0.3 139.17 M2

0.888 823.95744 Kg
0.888 823.95744 Kg

1647.91488 Kg

0.888 631.6489632 Kg
0.888 631.6489632 Kg
1263.2979264 Kg

0.45 104.3775 M2

0.45 104.3775 M2
Remark

Detail Measurement has been attached separate


No Description No Length

FRAME

CONCRETE WORK

1 Columns

F1 &C1 3 0.3
F2&C2 74 0.3

2 Beam 231.95

FORMWORK

3 To side of column 77 4.4

4 To side of Beam 2 231.95

REINFORCEMENT

16 mm Bars; high yield steel; cold worked; B.S. 4461 in column

5 Column 77 13.6

6 Beam 1 927.8

STEEL UP

7 Steel up for column 320 0.92

8 Steel up for beam 770 0.9


Breadth Height Quantity Unit Remark/Clarification

0.3 2.20 0.59


0.3 2.20 14.65

TOTAL 15.25 M3

0.3 0.15 10.44 M3

0.30 101.64 M2

0.15 69.59 M2

TOTAL 171.23 M2

1.579 1653.5288 kg

1.579 1464.9962 kg

TOTAL 3118.525 M2

0.888 261.4272 kg

0.888 615.384 Kg

TOTAL 876.8112 Kg
No Description No. Length Breadth Height

WALLING BLOCKS

Area 1 231.95 1.2

DDT

Column -77 0.3 0.3 2.1

TOTAL WALL BLOCK


Quantity Unit Remark /Clarification

278.34 m2

-48.51 m2

229.83 M2
No Description No.

METAL GATE

a 5600x2100mm mild steel sliding gate with it full accessories 1

METAL GRILLS

b 3000 X850mm grills made up with 16mm square pipes 75


Length Breadth Height Quantity Unit Remark/Clarification

1 No

75 No
No Description

FINISHING AND DECORATION

WALL FINISHING

a Steel trowelled plastered surfaces

Internally
Externally

b Painting to plastered wall surface

Internally
Externally

CAPING , BEAM AND COLUMN FINISHING

a Plastering to 50 mm thick caping

b Plastering to 150mm thick reinforced concrete beam

c Plastering to reinforced concrete column

d Painting to 50 mm thick caping

e Painting to concrete beam

f Painting to concrete column


No. Length Breadth Height Quantity Unit

213.55 1.2 256.26 M2


213.55 1.2 256.26 M2

213.55 1.2 256.26 M2


213.55 1.2 256.26 M2

77 0.46 0.5 17.71 M2

2 231.95 0.15 69.585 M2

77 4.4 0.3 101.64 M2

77 0.46 0.5 17.71 M2

2 231.95 0.15 69.585 M2

77 4.4 0.3 101.64 M2