Maintenance Multicor S80 Dismantling


1. Preparing .
• Shut Power Off.
• Cleaning area.
• Dismantling Cable at Electronic Disocont Tersus :
LoadCell.

Speed sensor.

Lock For Loadcell Before Take Out the Mechanic.

2. Take Out Complete Component using Crane

we make processes work


Grand Slipi Tower, Lt. 38 Unit I / Jl. S. Parman Kav. 22 - 24
Jakarta Barat 11480 / Indonesia
Tel. : +62.21 - 290 22335 / 36
Tel. : +62.21 - 290 21937 / 38
Fax : +62.21 - 290 22062
www.schenckprocess.com P.T. Schenck Process Indonesia

2. Remove Cover One Side and Open bolt.

3. Remove Loadcell Measuring Device Frame

we make processes work


Grand Slipi Tower, Lt. 38 Unit I / Jl. S. Parman Kav. 22 - 24
Jakarta Barat 11480 / Indonesia
Tel. : +62.21 - 290 22335 / 36
Tel. : +62.21 - 290 21937 / 38
Fax : +62.21 - 290 22062
www.schenckprocess.com P.T. Schenck Process Indonesia

4. Open the 4 Nut and remove the Motor

5. Open the 5 nut of the Measuring Wheel, Open the Snap Ring.

6. Open the universal clamping of the Flexible Connection Silicone.


Lift Up the arm frame Measuring shaft.

we make processes work


Grand Slipi Tower, Lt. 38 Unit I / Jl. S. Parman Kav. 22 - 24
Jakarta Barat 11480 / Indonesia
Tel. : +62.21 - 290 22335 / 36
Tel. : +62.21 - 290 21937 / 38
Fax : +62.21 - 290 22062
www.schenckprocess.com P.T. Schenck Process Indonesia

7. Open the nut, Lift Up the base plate.

8. Shaft for the Measuring Wheel

9. Open Rubber Coupling ( Blue Arrow )


Open Long Nut ( Red Cycle )

we make processes work


Grand Slipi Tower, Lt. 38 Unit I / Jl. S. Parman Kav. 22 - 24
Jakarta Barat 11480 / Indonesia
Tel. : +62.21 - 290 22335 / 36
Tel. : +62.21 - 290 21937 / 38
Fax : +62.21 - 290 22062
www.schenckprocess.com P.T. Schenck Process Indonesia

10. Open the Coupling ( Red Color )

11. Open Tree Snap Ring ( Red Arrow )


Open Pin Bolt ( Blue Cycle )

12. Take Out Measuring shaft Rotor from Measuring Shaft Housing.

we make processes work


Grand Slipi Tower, Lt. 38 Unit I / Jl. S. Parman Kav. 22 - 24
Jakarta Barat 11480 / Indonesia
Tel. : +62.21 - 290 22335 / 36
Tel. : +62.21 - 290 21937 / 38
Fax : +62.21 - 290 22062
www.schenckprocess.com P.T. Schenck Process Indonesia

13. Open shaft sealing ring and Inner Bearing.

14. Stationary Outer housing.


Open the Snap Ring and the nipple bolt. Open the cover.

15. Open sealing and inner bearing.

we make processes work


Grand Slipi Tower, Lt. 38 Unit I / Jl. S. Parman Kav. 22 - 24
Jakarta Barat 11480 / Indonesia
Tel. : +62.21 - 290 22335 / 36
Tel. : +62.21 - 290 21937 / 38
Fax : +62.21 - 290 22062
www.schenckprocess.com P.T. Schenck Process Indonesia

16. Installing all after finish Change the parts.