Introduction
Amtrak
Arcadis Gen
Create a more sustainable and resilient society, deploying technology and solutions across the asset lifecycle
Leadership
Serbia 65 RoW 4
Arcadis Gen – Product lines
User Base (now): 200 User Base (this phase) :350 User-base (this phase: 250
Final User base: 200 Final User base: c2000 Final User base: c2000
Products
Hosting
Services Support
Configuration
Reporting
Industry
Processes Solution Analytics
Model
Integrations Visualisation
Data Consulting
Programme Products
Delivery
© Arcadis Gen US Inc.. All rights reserved. Commercial in confidence.
Enterprise Asset Management System
What does it do?
Capability Overview
Asset Lifecycle Asset Onboarding, registration, updates, moves & decommissioning
Maintenance Regime Management Proactive backlog creation: Inspection & Maintenance regimes
Fault & Incident Reporting Reactive work assignment & backlog management
Work Management & Execution Internal & 3rd party work assignment & control
Planning Scheduling & Compliance Scoping & scheduling of proactive & reactive work backlogs
Person & Work Group Management Labour records, qualifications, crews, rosters & organisations
Stock Logistics & Procurement Stores, spares & materials management & assignment
Amtrak
Impacted Physical Assets Asset Management Drives Outcomes That Support:
Right Of Way, Signals & Communications:
✓ Develop and execute FAST Service and Asset Line plans
✓ Advance full implementation of PRIIA / FAST requirements for NEC Operations and Infrastructure (Section 212)
✓ Implement PTC or achieve PTC-levels of safety across Amtrak’s network and deploy new technology to strengthen
safety performance
✓ On-time, within scope and on budget delivery the Annual Engineering Capital Plan as approved by the Board of
Right of Way Signals & Comm. Directors and aligned with NEC Plan
Key Engineering Safety & Security Areas
Locomotives & Passenger Car:
✓ Achieve Acela21 goals on budget, scope and schedule
✓ Advance full implementation of PRIIA / FAST requirements for State Supported Routes (Section 209)
Commercial in confidence.
EAM2.0 Phase 2
Values
• Phase 2: $37m
Durations
• Program: 21 months
• Requirements (to fix scope within
budget): 6 months
Scope
Complete Engineering functional build
(all divisions)
Deployment: Mid-Atlantic >
Philadelphia
• Engineering Track:
• Engineering Bridges & Buildings:
• Engineering Communications &
Signals:
• Engineering Electrical Traction:
• Mechanical ALC-42 Fleet:
© Arcadis Gen US Inc.. All rights reserved. Commercial in confidence.
Summary / Close
Open Data Engineering Roles Role Type Workstream Loc Target Priority
ETL Data Migration Engineer (*2) Data tooling & pipeline design T&IT U.S. May *
Data Engineer (*2) Data manipulation & migration expert IMCS U.S. April *
Data Engineer Data manipulation & migration expert ALC42 TBC June
Open Funct. EAM Consulting Role Type Workstream Loc Target Priority
Roles
GIS Consultant GIS Professional – data & requirements All U.S. Mar
Financial SME EAM Professional – Oracle & Asset Hierarchy All U.S. Feb *
Structures SME for BB EAM Professional – Bridges & Structures IMCS U.S. April *
Scrum Master Agile Scrum Master All U.S. May
MLR L&D Trainer Professional Trainer (EAM Core) IMCS U.S. June
MLR L&D Trainer Professional Trainer (EAM Core) ALC42 U.S. June
PMA Project Management Assistant PMO / All TBC April
Potential Funct. EAM Consulting Role Type Workstream Loc Target Priority
Roles
Ops Desk workstream lead EAM Professional – Rail ops fault reporting & IMCS U.S. TBC
management
Ops Desk workstream support EAM Support (facilitation, stakeholder mgmt.) IMCS U.S. TBC
Useful Contacts at Gen
Amtrak Project & Resourcing