SCOPE OF WORK AND SUPPLY

Item no Description Scope of work and supply Remarks

Install/Works Material/Equipment Supply


PGP BASF PGP BASF
1 Preparation
1.1 Measurement x x
1.2 Mobilisation materials ,toools ,Equipment and manpower x x
1.3 Temporary Facilities,site office and work shop x x
2 Engineering Work
2.1 Sub Project Document x x
2.2 Sub HSE Document x x
2.3 Sub Drawing for Contruction x x
2.4 Sub Material Approval x x
3 Construction Work
III. A CIVIL WORKS
- PILLING WORKS x x
- EXCAVATION SOIL x x
- LEAN CONCRETE x x
- ROUND BAR x x
- FORMWORK x x
- CONCRETE x x
III. B STRUCTURE WORKS
- FABRICATION x x
- INSTALLATION x x
- LIFTING MATERIAL x x
4 Project Closing Report & As Built Drawing x x
5 Demobilization x x