Shubham Pandey QSE Final
Shubham Pandey QSE Final
Earthwork in excavation of
1
foundation of trench
2 Earthwork in filling Earthwork Filling in Foundation Trench 0.2 * Volume of earthwork excavation
b Under Floor
(i) Officer Cabin 1 4 3 0.1 12 m^3
(ii) Attatched Toilet 1 3 2 0.1 6 m^3
(iii) Wating Room 1 10.375 3.975 0.1 41.240625 m^3
(iv) Recption 1 2.3 2 0.1 4.6 m^3
(v) Multipurpose Room 1 4 3.125 0.1 12.5 m^3
(vi) Stair Block 1 4.4 2.2 0.1 9.68 m^3
(vii) Office Space 1 7.187 4.087 0.1 29.373269 m^3
(viii) Toilet 2 3 2 0.1 12 m^3
b Under Floors
(i) Officer Cabin 1 4 3 0.2 2.4 m^3
(ii) Attatched Toilet 1 3 2 0.2 1.2 m^3
(iii) Wating Room 1 10.375 3.975 0.2 8.248125 m^3
(iv) Recption 1 2.3 2 0.2 0.92 m^3
(v) Multipurpose Room 1 4 3.125 0.2 2.5 m^3
(vi) Stair Block 1 4.4 2.2 0.2 1.936 m^3
(vii) Office Space 1 7.187 4.087 0.2 5.8746538 m^3
(viii) Toilet 2 3 2 0.2 2.4 m^3
1
Shubham Pandey 002110401188
Less For
a. Doors
(i) Door2 4 1.2 0.125 2.1 1.26 m^3
(ii) Door3 3 0.9 0.125 2.1 0.70875 m^3
b. Lintel 1 27.705 0.125 0.15 0.51946875 m^3
Total= 10.34517969 m^3
A Column foundation
2
Shubham Pandey 002110401188
C staircase
(i) First flight
a. Waist slab 1 3 1.2 0.15 0.54 m^3
b. mid landing 1 1.5 2.5 0.15 0.5625 m^3
D Slab
Less for
stair hall 1 5.975 2.875 0.125 2.147265625 m^3
Total= 28.32975 m^3
E RCC lintel
(i) Main wall 1 55.35 0.25 0.15 2.075625 m^3
(ii) partition wall 1 29.112 0.125 0.15 0.54585 m^3
F RCC chajja
Over window depth of chajja= 0.1 0.05 /2 0.075
Length of chajja for W1 1.5 0.1 2
m^3
(i) W1 2 1.7 0.45 0.075 0.11475 1.7m
Length of chajja for W2 1.2 0.1 2
m^3
(ii) W2 4 1.4 0.45 0.075 0.189 1.4m
Length of chajja for W3 0.8 0.1 2
m^3
(iii) W3 3 1 0.45 0.075 0.10125 1.0m
(iv) Roof door 1 1.5 0.45 0.0506 0.034155 m^3
Total= 31.39038 m^3
a column foundation
3
Shubham Pandey 002110401188
c Slab
(i) Total roof slab 1 144.022 m^2
(ii) Stair room roof 1 6.1 3 18.3 m^2
Less for
(i) stair hall 1 5.975 2.875 17.178125 m^2
(ii) main wall 1 55.35 0.25 13.8375 m^2
(iii) partition wall 1 29.112 0.125 3.639 m^2
Total= 34.654625 m^2
shuttering for main wall
e foundation
for outside there is no joints,so the
out side length is equal to the
uncorrected length of main wall=
(i) Outside for PCC 1 55.35 0.2 11.07 m^2 55.35
for inside,it is equal to the corrected
(ii) Inside for PCC 1 47.238 0.2 9.4476 m^2 length 45.238m
4
Shubham Pandey 002110401188
(i) Main wall (side shuttering) 2 55.35 0.15 16.605 m^2 Length are same as DPC calculation
(ii) Partition wall (side shuttering) 2 29.112 0.15 8.7336 m^2
Bottom shuttering for small
(iii) openings
5
Shubham Pandey 002110401188
6
Shubham Pandey 002110401188
COST Calculation
Sl No. Description Quantity Unit Rate [in Rupees] Unit Amount[in Rupees]
Earthwork in excavation of
1 foundation trench in all sorts of 76.255 m^3 12325 Rs/ 100 m3 9398.42875
soil Depth not exceeding 1.5 m]