Savvas Partition Cost
5 Electrical works
Supply and fix air con points per office ( include 2.5 - 3 nos
a cable, conduit runing from main board Nos 18 SCR 1,150.00
Supply and fix LED tube light- each light got switch and
b supply cable run from main board Nos 24 SCR 1,100.00
Supply and fix Double socket main 2.5 - 3 code cable run
c through all offices from main board from ceilling Nos 36 SCR 1,150.00
Supply and fix Data and telephone point 2 single box with all
d conduite run through partition Nos 18 SCR 800.00
Supply and install to upgrade main DB board relevent to
e different offices Nos 1 SCR 10,000.00
f additional support timber to fixing aircon unit Nos 18 SCR 200.00
Supply and install fire smoke decetor ( batery type ) each
g office 1 and corridor 3nos Nos 21 SCR 500.00
SCR 3,000.00
SCR 750.00
SCR 350.00
SCR 2,300.00
SCR 358,200.00
SCR 1,600.00
SCR 123,500.00
SCR 20,700.00
SCR 26,400.00
SCR 41,400.00
SCR 14,400.00
SCR 10,000.00
SCR 3,600.00
SCR 10,500.00
SCR 616,700.00