Electrical Load Estimation
Electrical Load Estimation
Revision: 0
ESTIMATED ELECTRICAL LOAD CALCULATIONS
Prep.: SM
Chd SM
Sr. Conn. Demand Load DG Load DG Load Remarks for DG backup in Mains Power
Description Area in sq.ft Area in sq.m Watt/Sq.m Diversity
No. Load (KW) (KW) (MPF case) (Fire case) Failure (MPF) and Fire Case
A Tower B (Flats)
i 2 BHK S 124 599 56 75.00 4.18 0.4 1.67
517.7 207.09 No DG power No DG power
backup for backup in
ii 2 BHK L 108 721 67 75.00 5.03 0.4 2.01 Flat case of fire
542.8 217.10
B Tower A (Flats)
i 2 BHK S 108 599 56 75.00 4.18 0.4 1.67
450.9 180.37 No DG power No DG power
backup for backup in
ii 2 BHK L 124 721 67 75.00 5.03 0.4 2.01 Flat case of fire
623.2 249.27
Total load for FLAT TOWER A & B 6,500.20 2,600.08 0.00 0.00
Sr. No. of Conn. Demand Load DG Load DG Load Remarks for DG backup in Mains Power
Description Area in sq.ft Area in sq.m Watt/Sq.ft Diversity
No. Flat Load (KW) (KW ) (MPF case) (Fire case) Failure (MPF) and Fire Case
Common Services for Tower B
3 Common area ( Lift Lobby +Corridor) 1,377 128 0.5 42.7 0.9 38.4 38.4 7.7
4 Terrace Floor 15,451 1,436 0.5 7.7 0.5 3.9 0.0 0.0
100% DG Backup both the case of MPF and
5 Stair Case (77 Landings * 18W LED)* 2 Staircases 5.5 0.9 5.0 5.0 5.0
in case of Fire.
50% DG Backup in case of MPF and only one
6 Lift - 13 Nos. 585.0 0.7 409.5 292.5 45.0
lift considered in case of Fire.
7 Fire Booster Pump 0.0 1.0 0.0 0.0 0.0
8 Pressurization Fans 767.0 1.0 0.0 0.0 767.0
Total for Common Services TOWER A & B 2,813.21 912.19 674.33 1,649.85
Project: L&T Parel Phase 2 (LTPP)
Revision: 0
ESTIMATED ELECTRICAL LOAD CALCULATIONS
Prep.: SM
Chd SM
Sr. Conn. Demand Load DG Load DG Load Remarks for DG backup in Mains Power
Description Area in sq.ft Area in sq.m Watt/Sq.m Diversity
No. Load (KW) (KW) (MPF case) (Fire case) Failure (MPF) and Fire Case
Common Services
Basement & Podium Car park 100% DG Backup in case of MPF and 20 %
703,950.00 65,422.86 0.50 32.71 0.80 26.17 26.17 5.23
(P1 & GF excluded as shops) DG backup in case of Fire.
Plumbing System 302.00 0.60 181.20 181.20 0.00 100% DG Backup in MPF case.
STP 150.00 0.70 105.00 105.00 0.00 100% DG Backup in MPF case.
Fire Fighting System 622.00 0.90 0.00 0.00 559.80 100% DG Backup in case of Fire.
HVAC
Lower Ground ventilation 195.30 0.70 136.71 0.00
100% DG Backup both the case of MPF and
Car park Ventilation Axil Fans 396.00 0.70 277.20 554.40 554.40
200% in case of Fire.
Parking Jet Fans 198.00 0.50 99.00 99.00 198.00 100% DG Backup in case of Fire.
789
Shops 117,240.00 10,892 200.00 198.00 0.67 132.00 0.00 0.00 No DG Backup
Street Lighting 5.27 1.00 5.27 0.00 0.00 No DG Backup
external/Landscape Lighting 5.00 1.00 5.00 0.00 0.00 No DG Backup
3 DG Selection Tower A
Total demand load for Common Services -Tower 825.17 kW
Overall diversity @ 0.80
Maximum demand load for Common Services - 660.14 kW
Overall power factor 0.80
Max. demand load for Common Services -Tower 825.17 kVA
DG Set Rating @ 85 % loading 970.79 kVA
Number of Transformers
Description
(with 80% Loading)