Professional Documents
Culture Documents
Progress Report
Progress Report
Submitted to:
Department of BCA
Mahendra Morang Adarsh Multiple Campus
Biratnagar, Morang, Nepal
Submitted by:
The following summary of the project includes development progress from 2078 Chaitra 1 st
week to 3rd week of Baisakh 2079. A detailed summary of the above-mentioned dates is
provided below along with descriptions. Additionally, upcoming plans and works to do are also
mentioned in the report below.
Weeks
1 2 3 4 5 6 7 8 9 10 11 12
Activities
Planning
Research
Designing
Implementation
Testing
Documentation
Progress:
Following the above Gantt Chart of our project currently, we are in the design phase of our
project. We divided our progress statement into the following different topics as below:
1. Analysis
We specified the requirement that is associated with the project as clearly as
possible
We did planning based on our project and its concept.
We did a small research on the relevant topics through different mediums.
We analyzed the relevant topics of our project.
We analyzed the research apart from relevant topics.
We submitted and presented the proposal which contained the description of the
above-mentioned matters.
2. Design
Appropriate analysis and acceptance of the proposal helped us to move ahead
towards designing.
Design of Frontend is done along with Backend, connection to the databases,
and other required contexts.
We have divided the project into different modules and working with it using
JAVA, HTML, CSS, and MY SQL for our project.
3. Implementation
We are looking forward to implementing our project as soon as possible
following the timeline.
o Conclusion:
After the detailed progress report of our project, we conclude that we have
completed approximately more than 50% of our task and working accordingly
to complete it within the mentioned timeline following the guidelines.