LOT SIZING (BUSKET SMALL LOTS)

Bill of Material
Level Item Unit Lead Time
0 Basket Small Lots 1 1
1 Landasan 1 1
1 Tiang 4 1
1 Dinding 4 1
1 Pelat Penyangga 16 1
1 Jaring 5 1
2 Profil C 4 1
2 Profil L 4 1
2 Stopper 8 1
2 Hook 4 1
2 Tiang Utama 4 1
2 Profil C Atas 6 1
2 Frame Body Horizontal 8 1
2 Frame Body Vertikal 4 1

Biaya Utama
Holding Cost $ -
Order Cost $ 200.00

Level Item Biaya


0 Basket Small Lots $ 1,600.00
1 Landasan $ 1,600.00
1 Tiang $ 1,600.00
1 Dinding $ 1,600.00
1 Pelat Penyangga $ 1,600.00
1 Jaring $ 1,600.00
2 Profil C $ 1,600.00
2 Profil L $ 1,600.00
2 Stopper $ 1,600.00
2 Hook $ 1,600.00
2 Tiang Utama $ 1,600.00
2 Profil C Atas $ 1,600.00
2 Frame Body Horizontal $ 1,600.00
2 Frame Body Vertikal $ 1,600.00
TOTAL BIAYA $ 22,400.00
LEVEL 0

LEVEL 1

LEVEL 2

Periode 1 2 3 4 5 6
BASKET SMALL LOTS 35 30 40 0 10 40

LEVEL 0

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 35 30 40 0
BASKET
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0
1 Net Requirement (NR) 35 30 40 0
Periode Pemesanan Planned Order Receipts (POR) 35 30 40 0
8 Planned Order Release (PORel) 35 30 40 0 10

LEVEL 1

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 35 30 40 0 10
LANDASAN
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0
1 Net Requirement (NR) 35 30 40 0 10
Periode Pemesanan Planned Order Receipts (POR) 35 30 40 0 10
8 Planned Order Release (PORel) 35 30 40 0 10 40

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 140 120 160 0 40
TIANG
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0
1 Net Requirement (NR) 140 120 160 0 40
Periode Pemesanan Planned Order Receipts (POR) 140 120 160 0 40
8 Planned Order Release (PORel) 140 120 160 0 40 160
Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4
Gross Requirement (GR) 140 120 160 0 40
DINDING
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0
1 Net Requirement (NR) 140 120 160 0 40
Periode Pemesanan Planned Order Receipts (POR) 140 120 160 0 40
8 Planned Order Release (PORel) 140 120 160 0 40 160

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 560 480 640 0 160
PELAT PENYANGGA
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0
1 Net Requirement (NR) 560 480 640 0 160
Periode Pemesanan Planned Order Receipts (POR) 560 480 640 0 160
8 Planned Order Release (PORel) 560 480 640 0 160 640

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 175 150 200 0 50
JARING
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0
1 Net Requirement (NR) 175 150 200 0 50
Periode Pemesanan Planned Order Receipts (POR) 175 150 85 65 0
8 Planned Order Release (PORel) 175 150 85 65 40

LEVEL 2

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 140 120 160 0 40 160
PROFIL C
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 140 120 160 0 40 160
Periode Pemesanan Planned Order Receipts (POR) 140 120 160 0 160
8 Planned Order Release (PORel) 140 120 160 0 160 120

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 140 120 160 0 40 160
PROFIL L
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 140 120 160 0 40 160
Periode Pemesanan Planned Order Receipts (POR) 140 120 160 0 160
8 Planned Order Release (PORel) 140 120 160 0 160 120

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 1120 960 1280 0 320 1280
STOPPER
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 1120 960 1280 0 320 1280
Periode Pemesanan Planned Order Receipts (POR) 1120 960 1280 0 320 1280
8 Planned Order Release (PORel) 1120 960 1280 0 320 1280 960

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 560 480 640 0 160 640
HOOK
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 560 480 640 0 160 640
Periode Pemesanan Planned Order Receipts (POR) 560 480 640 0 160 640
8 Planned Order Release (PORel) 560 480 640 0 160 640 480

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 560 480 640 0 160 640
TIANG UTAMA
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 560 480 640 0 160 640
Periode Pemesanan Planned Order Receipts (POR) 560 480 640 0 160 640
8 Planned Order Release (PORel) 560 480 640 0 160 640 480

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


Gross Requirement (GR) 840 720 960 0 240 960
PROFIL C ATAS
Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 840 720 960 0 240 960
Periode Pemesanan Planned Order Receipts (POR) 840 720 960 0 240 960
8 Planned Order Release (PORel) 840 720 960 0 240 960 720

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


FRAME BODY Gross Requirement (GR) 560 960 1280 0 320 1280
HORIZONTAL Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 560 960 1280 0 320 1280
Periode Pemesanan Planned Order Receipts (POR) 140 960 1280 0 320 1280
8 Planned Order Release (PORel) 140 960 1280 0 320 1280 960

Item: PERIODE Q-3 Q-2 Q-1 1 2 3 4


FRAME BODY Gross Requirement (GR) 560 480 640 0 160 640
VERTIKAL Schedule Receipt (SR)
Lead Time : On Hand Inventory (OHI) 0 0 0 0 0 0
1 Net Requirement (NR) 560 480 640 0 160 640
Periode Pemesanan Planned Order Receipts (POR) 560 480 640 0 160 640
8 Planned Order Release (PORel) 560 480 640 0 160 640 480
7 8 9 10
30 0 30 55

5 6 7 8 9 10 Total Biaya Inventory


10 40 30 0 30 55
$ 1,600.00
0 0 0 0 0 0 Biaya Simpan
10 40 30 0 30 55
10 40 30 0 30 55 Biaya Pesan
40 30 0 30 55 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


40 30 0 30 55
$ 1,600.00
0 0 0 0 0 Biaya Simpan
40 30 0 30 55
40 30 0 30 55 Biaya Pesan
30 0 30 55 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


160 120 0 120 220
$ 1,600.00
0 0 0 0 0 Biaya Simpan
160 120 0 120 220
160 120 0 120 220 Biaya Pesan
120 0 120 220 $ 1,600.00
5 6 7 8 9 10 Total Biaya Inventory
160 120 0 120 220
$ 1,600.00
0 0 0 0 0 Biaya Simpan
160 120 0 120 220
160 120 0 120 220 Biaya Pesan
120 0 120 220 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


640 480 0 480 880
$ 1,600.00
0 0 0 0 0 Biaya Simpan
640 480 0 480 880
640 480 0 480 880 Biaya Pesan
480 0 480 880 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


200 150 0 150 275
$ 1,600.00
0 0 0 0 0 Biaya Simpan
200 150 0 150 275
40 150 0 150 275 Biaya Pesan
150 0 150 275 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


120 0 120 220
$ 1,600.00
0 0 0 0 Biaya Simpan
120 0 120 220
120 0 120 220 Biaya Pesan
0 120 220 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


120 0 120 220
$ 1,600.00
0 0 0 0 Biaya Simpan
120 0 120 220
120 0 120 220 Biaya Pesan
0 120 220 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


960 0 960 1760
$ 1,600.00
0 0 0 0 Biaya Simpan
960 0 960 1760
960 0 960 1760 Biaya Pesan
0 960 1760 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


480 0 480 880
$ 1,600.00
0 0 0 0 Biaya Simpan
480 0 480 880
480 0 480 880 Biaya Pesan
0 480 880 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


480 0 480 880
$ 1,600.00
0 0 0 0 Biaya Simpan
480 0 480 880
480 0 480 880 Biaya Pesan
0 480 880 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


720 0 720 1320
$ 1,600.00
0 0 0 0 Biaya Simpan
720 0 720 1320
720 0 720 1320 Biaya Pesan
0 720 1320 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


960 0 960 1760
$ 1,600.00
0 0 0 0 Biaya Simpan
960 0 960 1760
960 0 960 1760 Biaya Pesan
0 960 1760 $ 1,600.00

5 6 7 8 9 10 Total Biaya Inventory


480 0 480 880
$ 1,600.00
0 0 0 0 Biaya Simpan
480 0 480 880
480 0 480 880 Biaya Pesan
0 480 880 $ 1,600.00