Professional Documents
Culture Documents
Week 5 Lecture Hand-Outs
Week 5 Lecture Hand-Outs
• Learning Objectives
–Identify/appreciate the key issues/challenges
associated with allocating resources to a project
–Apply resource allocating techniques (methods) to
ensure efficient and effective utilisation of resources –
hence to meet project deliverables
–Apply selected techniques for reducing project duration
under different resource conditions
8–2
FIGURE 8.1
1
21/03/2023
Schedule
Compression
Resources Smoothing
Resources Levelling
Schedule Compression
Resources Smoothing
Painters
4
3
2
1
1 2 3 4 5 6 7 8 9 10 11 12
Painters
3
2
1
1 2 3 4 5 6 7 8 9 10 11 12
Resources Levelling
Only 2 painters
are available
3 4 5 6 7 8 9 10 11 12
Painters
3
2
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
2
21/03/2023
• Physical Constraints
– activities that cannot occur in parallel or are affected by
contractual or environmental conditions (e.g. confined space)
• Resource Constraints
– the absence, shortage, or unique interrelationship and interaction
characteristics of resources that require a particular sequencing of
project activities (only one overhead crane is available to share)
– types of resource: people, materials, equipment
Constraint Examples
Building construction?
Software development?
the number of
people available?
FIGURE 8.2
8–9
3
21/03/2023
• Classification of Problem
–using a priority matrix will help determine if the project
is time-constrained or resource-constrained
• Time-constrained Project
–must be completed by an imposed date
• time is fixed, resources are flexible: additional resources may
be required to ensure project meets the set completion date
• Resource-constrained Project
–the level of resources available cannot be exceeded
• resources are fixed (by availability or cost), time is flexible:
lack of resources means the project will be delayed
4–11
Performance-constrained
4
21/03/2023
Time-constrained
Time-constrained
FIGURE 4.2b
4–14
Time-constrained
5
21/03/2023
Cost-constrained
FIGURE 4.2c
4–16
Cost-constrained
• Limiting Assumptions
–splitting activities is not allowed—once an activity is
started, it is carried to completion
–level of resources used on an activity cannot be changed
• Risk Assumptions
–activities with the highest slack pose the lowest risk
–reduction of flexibility does not increase risk???
–the nature of a task (easy, complex) doesn’t increase risk
6
21/03/2023
• Time-Constrained Projects
–must be completed by an imposed date
–require use of levelling techniques that focus
on balancing or smoothing resource demands
–use positive slack (delaying non-critical activities)
to manage resource utilization over the duration
of the project
FIGURE 8.3
8–20
2Bh
FIGURE 8.3
8–21
7
21/03/2023
2Bh
FIGURE 8.3
8–22
Resource-constrained Scheduling
8
21/03/2023
Parallel Method
Assumptions
• Limiting Assumptions
– splitting activities is not allowed—once an activity
is started, it is carried to completion
– level of resources used for an activity cannot be
changed
• Risk Assumptions
– activities with the most slack pose the least risk
– reduction of flexibility does not increase risk
– the nature of an activity (easy, complex) doesn’t
increase risk
9
21/03/2023
1. minimum slack
2. smallest (least) duration
Only 3 programmers are available
3. lowest activity identification number
10
21/03/2023
Resource-constrained Scheduling:
Implications?
11
21/03/2023
Splitting
• Splitting
– A scheduling technique use to get a better project
schedule and/or increase resource utilization.
• involves interrupting work on an activity to employ
the resource on another activity, then returning the
resource to finish the interrupted work
• is feasible when startup and shutdown costs are low
• is considered the major reason why projects fail to
meet schedule
Splitting Activities
FIGURE 8.11
3. Resource bottlenecks
• shortages of critical resources required for multiple
projects cause delays and schedule extensions.
12
21/03/2023
– reducing ‘time-to-market’.
• e.g. new product/technology development
• Resources Not
Constrained
–project crashing (add
resources or work overtime)
–outsourcing project work • Resources Constrained
–establishing a core –fast-tracking (undertake
project team (reduces the critical activates concurrently)
need for multi-tasking) –critical-chain (Goldratt)
–do it twice – first, fast –reducing project scope
and then correctly (may
incur a much higher cost!)
–compromise quality
13
21/03/2023
14
21/03/2023
Reducing duration
15
21/03/2023
Activity Graph
16
21/03/2023
17
21/03/2023
18
21/03/2023
https://www.youtube.com/watch?v=soOl_FpfBOM
https://www.youtube.com/watch?v=hJQW9_I-0hI
19