TP.188 Punch List
TP.188 Punch List
DATE :
Description : TP.188
Ref. Document :
Punch
Prepared Due
List Item Priority Description of Items to be attend Action By Date of Acceptance
By/Date Date
No.
SV-02-11344-4"-A3C-01 Rev.0
aker
1 B Permanent gasket, bolt & nut not yet installed 01/06/'16 ADS
aker
2 A Trunion support shall be full welded 01/06/'16 ADS
aker
3 B SS Shim plate not yet provided 01/06/'16 ADS
aker
Cantilever shall be full welded to the structure 01/06/'16 ADS
aker
4 A Porousity at the 2" elbow body (ex arch strike) 01/06/'16 ADS
aker
5 B Weldment shall be clean (pickling) 01/06/'16 ADS
aker
6 B Remove CS wire near TUN support 01/06/'16 ADS
aker
7 B U-Bolt (U2-4) & shim plate shall be provided 01/06/'16 ADS
aker
Tee post shall be full welded to the structure 01/06/'16 ADS
aker
8 A Repair weld joint (FJ.8) there is porousity 01/06/'16 ADS
aker
9 B Weldment shall be clean (pickling) 01/06/'16 ADS
aker
10 A Support CL-2 (Elev.129,475) not yet installed 01/06/'16 ADS
aker
11 A Support CL-2 (Elev.133,779) & RF-6-A3C not yet installed 01/06/'16 ADS
aker
12 B Permanent gasket, bolt & nut not yet installed 01/06/'16 ADS
aker
13 B General comment for all weldment & HAZ shall be clean (pickling) 01/06/'16 ADS
General comment for all length of pipe; all length of pipe shall be clean from aker
14 B rust & grease 01/06/'16 ADS
Priority :
C05S2020 R3