Professional Documents
Culture Documents
Level K10 Progress 30.6
Level K10 Progress 30.6
Level K10 Progress 30.6
Mode Schedule Actual Apr May Jun Jul Aug Sep Oct Nov
0 K10 BUILDINGS 148 days Thu 01/06/23 Thu 26/10/23 16% 11%
1 LEVEL 1 59 days Thu 01/06/23 Sat 29/07/23 29% 0%
2 Support & 15 days Thu 01/06/23 Thu 15/06/23 100% 0%
Hanger
3 Cable Tray 30 days Tue 06/06/23 Wed 05/07/23 83% 0%
Installation
4 Power & 15 days Wed 21/06/23 Wed 05/07/23 67% 0%
Lighting Panel
5 Panel & Carbinet 20 days Thu 06/07/23 Tue 25/07/23 0% 0%
cable laying &
Connection
6 Equipment 20 days Thu 06/07/23 Tue 25/07/23 0% 0%
Cable Laying &
7 Lighting, switch, 20 days Thu 06/07/23 Tue 25/07/23 0% 0%
receptacle
conduit & Cable
8 Lighting Fixture 20 days Mon 10/07/23 Sat 29/07/23 0% 0%
Installation
9 Switch, 20 days Mon 10/07/23 Sat 29/07/23 0% 0%
Receptacle
10 Ground Installatio15 days Tue 11/07/23 Tue 25/07/23 0% 0%
11 LEVEL 2 59 days Tue 27/06/23 Thu 24/08/23 16% 23%
12 Support & 15 days Tue 27/06/23 Tue 11/07/23 27% 90%
Hanger
13 Cable Tray 30 days Sun 02/07/23 Mon 31/07/23 80% 90%
Installation
14 Power & 15 days Mon 17/07/23 Mon 31/07/23 0% 0%
Lighting Panel
15 Panel & Carbinet 20 days Tue 01/08/23 Sun 20/08/23 0% 0%
cable laying &
Connection
16 Equipment 20 days Tue 01/08/23 Sun 20/08/23 0% 0%
Cable Laying &
17 Lighting, switch, 20 days Tue 01/08/23 Sun 20/08/23 0% 0%
receptacle
conduit & Cable
Page 1
ID Task Task Name Duration Start Finish % % Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mode Schedule Actual Apr May Jun Jul Aug Sep Oct Nov
18 Lighting Fixture 20 days Sat 05/08/23 Thu 24/08/23 0% 0%
Installation
19 Switch, 20 days Sat 05/08/23 Thu 24/08/23 0% 0%
Receptacle
20 Ground Installatio15 days Sun 06/08/23 Sun 20/08/23 0% 0%
21 LEVEL 3 59 days Sat 15/07/23 Mon 11/09/23 18% 21%
22 Support & 15 days Sat 15/07/23 Sat 29/07/23 70% 80%
Hanger
23 Cable Tray 30 days Thu 20/07/23 Fri 18/08/23 70% 80%
Installation
24 Power & 15 days Fri 04/08/23 Fri 18/08/23 0% 0%
Lighting Panel
25 Panel & Carbinet 20 days Sat 19/08/23 Thu 07/09/23 0% 0%
cable laying &
Connection
26 Equipment 20 days Sat 19/08/23 Thu 07/09/23 0% 0%
Cable Laying &
27 Lighting, switch, 20 days Sat 19/08/23 Thu 07/09/23 0% 0%
receptacle
conduit & Cable
28 Lighting Fixture 20 days Wed 23/08/23 Mon 11/09/23 0% 0%
Installation
29 Switch, 20 days Wed 23/08/23 Mon 11/09/23 0% 0%
Receptacle
30 Ground Installatio15 days Thu 24/08/23 Thu 07/09/23 0% 0%
31 LEVEL 4 59 days Tue 29/08/23 Thu 26/10/23 0% 0%
Page 2