Level K10 Progress 30.6

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ID Task Task Name Duration Start Finish % % Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023

Mode Schedule Actual Apr May Jun Jul Aug Sep Oct Nov
0 K10 BUILDINGS 148 days Thu 01/06/23 Thu 26/10/23 16% 11%
1 LEVEL 1 59 days Thu 01/06/23 Sat 29/07/23 29% 0%
2 Support &  15 days Thu 01/06/23 Thu 15/06/23 100% 0%
Hanger 
3 Cable Tray  30 days Tue 06/06/23 Wed 05/07/23 83% 0%
Installation
4 Power &  15 days Wed 21/06/23 Wed 05/07/23 67% 0%
Lighting Panel 
5 Panel & Carbinet 20 days Thu 06/07/23 Tue 25/07/23 0% 0%
cable laying & 
Connection
6 Equipment  20 days Thu 06/07/23 Tue 25/07/23 0% 0%
Cable Laying & 
7 Lighting, switch,  20 days Thu 06/07/23 Tue 25/07/23 0% 0%
receptacle 
conduit & Cable 
8 Lighting Fixture  20 days Mon 10/07/23 Sat 29/07/23 0% 0%
Installation
9 Switch,  20 days Mon 10/07/23 Sat 29/07/23 0% 0%
Receptacle 
10 Ground Installatio15 days Tue 11/07/23 Tue 25/07/23 0% 0%
11 LEVEL 2 59 days Tue 27/06/23 Thu 24/08/23 16% 23%
12 Support &  15 days Tue 27/06/23 Tue 11/07/23 27% 90%
Hanger 
13 Cable Tray  30 days Sun 02/07/23 Mon 31/07/23 80% 90%
Installation
14 Power &  15 days Mon 17/07/23 Mon 31/07/23 0% 0%
Lighting Panel 
15 Panel & Carbinet 20 days Tue 01/08/23 Sun 20/08/23 0% 0%
cable laying & 
Connection
16 Equipment  20 days Tue 01/08/23 Sun 20/08/23 0% 0%
Cable Laying & 
17 Lighting, switch,  20 days Tue 01/08/23 Sun 20/08/23 0% 0%
receptacle 
conduit & Cable 

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: K10 BUILDINGS
Milestone Inactive Summary Start-only Progress
Date: Wed 28/06/23
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 1
ID Task Task Name Duration Start Finish % % Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mode Schedule Actual Apr May Jun Jul Aug Sep Oct Nov
18 Lighting Fixture  20 days Sat 05/08/23 Thu 24/08/23 0% 0%
Installation
19 Switch,  20 days Sat 05/08/23 Thu 24/08/23 0% 0%
Receptacle 
20 Ground Installatio15 days Sun 06/08/23 Sun 20/08/23 0% 0%
21 LEVEL 3 59 days Sat 15/07/23 Mon 11/09/23 18% 21%
22 Support &  15 days Sat 15/07/23 Sat 29/07/23 70% 80%
Hanger 
23 Cable Tray  30 days Thu 20/07/23 Fri 18/08/23 70% 80%
Installation
24 Power &  15 days Fri 04/08/23 Fri 18/08/23 0% 0%
Lighting Panel 
25 Panel & Carbinet 20 days Sat 19/08/23 Thu 07/09/23 0% 0%
cable laying & 
Connection
26 Equipment  20 days Sat 19/08/23 Thu 07/09/23 0% 0%
Cable Laying & 
27 Lighting, switch,  20 days Sat 19/08/23 Thu 07/09/23 0% 0%
receptacle 
conduit & Cable 
28 Lighting Fixture  20 days Wed 23/08/23 Mon 11/09/23 0% 0%
Installation
29 Switch,  20 days Wed 23/08/23 Mon 11/09/23 0% 0%
Receptacle 
30 Ground Installatio15 days Thu 24/08/23 Thu 07/09/23 0% 0%
31 LEVEL 4 59 days Tue 29/08/23 Thu 26/10/23 0% 0%

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: K10 BUILDINGS
Milestone Inactive Summary Start-only Progress
Date: Wed 28/06/23
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 2