Professional Documents
Culture Documents
Chapter 8-Project Control and Close-Out 2.2023
Chapter 8-Project Control and Close-Out 2.2023
Chapter 8-Project Control and Close-Out 2.2023
MANAGEMENT
INSTRUCTOR: DR. NGUYEN THI HOA HONG
FACULTY OF BUSINESS ADMINISTRATION
EMAIL: HONGNTH@FTU.EDU.VN
PHONE NUMBER: 0936831031
8-1
Project Control and Close-out
CHAPTER 8
8-2
Chapter Objectives
Understand the nature of the control cycle and the four key steps in a general project
control model
Recognize the strengths and weaknesses of common project evaluation and control
methods
Understand how Earned Value Management can assist project tracking and evaluation
Understand critical issues in the effectiveness use of Earned Value Management
Understand behavioral concepts and other human issues in evaluation and control.
Distinguish among the four main forms of project termination
Recognize the seven key steps in formal project closeout
Know the challenges and components of a final project report
8-3
The Project Control Cycle
8-4
The Project S-Curve
Cumulative Cost
($ in thousands)
60
Cumulative
20 Budgeted Cost
Cumulative
Actual Cost
5 10 15 20 25 30 35 40 45 50
Elapsed Time (in weeks)
8-5
Project S-curve
ADVANTAGES DISADVANTAGES
8-6
Milestone Analysis
Milestones are events or stages of the project that represent a significant
accomplishment.
Milestones
…show completion of important steps
…can motivate the team
…offer reevaluation points
…help coordinate schedules with vendors and suppliers
…identify key review gates
…signal the team and suppliers
…delineate work packages
8-7
Tracking Gantt Chart
8-8
Tracking Gantt Chart
BENEFITS DRAWBACKS
8-9
Earned Value Management
Cost
Project
S-Curves
Cost
Performance Schedule
Earned Cost
Value
Performance Schedule
Performance Schedule
Tracking Control Charts
8-10
Earned Value Terms
❖Planned value (PV): cost estimate of budgeted resource across project life
❖Earned value (EV): real budgeted cost/”value” of work that has been performed to date
8-11
Steps in Earned Value Management
1. Clearly define each activity including its resource needs and budget
5. Calculate both the budget variance (CV) and schedule variance (SV)
8-12
Earned Value Milestones
AC
Actual
Cost Overspend
PV EV
Budget
Slip
Schedule Performed
Schedule
8-13
Earned Value Example 8.1
8-14
Earned Value Example 8.1
Schedule Variances
Planned Value (PV) = 38 = 15+10+10+3
Earned Value (EV) = 30 = 15+8+6+1
Schedule Performance Index = .79 = 30/38 = EV/PV
Estimated Time to Completion = (1/.79)x4=5
Cost Variances
Actual Cost of Work Performed (AC) = 40 = 8+11+8+13
Cost Performance Index = .75 = 30/40 = EV/AC
Estimated Cost to Completion = 50.7 = (1/.75)x38
8-15
Completion Values in EVM
Accurate and up-to-date information is critical in the use of EVM
8-16
Human Factors in Project Evaluation & Control
❖Optimistic progress reports
❖Level of detail
❖Process evaluation
8-17
Project Termination
All activities consistent with closing out the project
❖Extinction
❖Addition
❖Integration
❖Starvation
8-18
Termination by extinction
The project may end because it has been successful and achieved its goals
The project may also be stopped because it is unsuccessful or has been
superseded
When a decision is made to terminate a project by extinction, the most
noticeable event is that all activity on the substance of the project ceases
Examples:
1. The product has been developed and handed over to the client.
2. The building has been completed and accepted by the owner
8-19
Termination by addition
If a project is a major success, it may be terminated by institutionalizing it as a
formal part of the parent organization
Project personnel, property, and equipment are often simply transferred from
the dying project to the newly born division
8-20
Termination by integration
•This method of terminating projects is the most common way of dealing with
successful projects, and the most complex
• The property, equipment, material, personnel, and functions of the project are
reintegrated into within the existing structure of the parent organization
8-21
Termination by starvation
This type of project termination is a “slow starvation by budget decrement”
A form of neglect by slowly decreasing the budget to the point that the project
cannot possibly remain viable.
8-22
Elements of Project Closeout Management
Gaining Harvesting
Finishing Handing
Over the Acceptance the Benefits
The Work
Product for the Reviewing
Product How
It All Went
8-23
Lessons Learned Meetings
Common Errors
➢Misidentifying systematic errors
➢Misinterpreting lessons based on events
➢Failure to pass along conclusions
Meeting Guidelines
✓Establish clear rules of behavior
✓Describe objectively what occurred
✓Fix the problem, not the blame
8-24
Closeout Paperwork
Documentation
Legal
Cost
Personnel
8-25
Final Report Elements
❑Project performance
❑Administrative performance
❑Organizational structure
❑Team performance
8-26