The daily construction report from the Nepalgunj Airport terminal building project provides the following updates:
1) Formwork for beams and slabs was being laid in blocks A and C, though subgrade work on some footings was delayed due to site clearance needs.
2) New drawings for the first floor beam and slab layout were received and provided to the contractor, though initial reluctance to modify formwork designs has slowed work.
3) Reinforcing bar and props required for upcoming work have been ordered but not yet arrived on site.
The daily construction report from the Nepalgunj Airport terminal building project provides the following updates:
1) Formwork for beams and slabs was being laid in blocks A and C, though subgrade work on some footings was delayed due to site clearance needs.
2) New drawings for the first floor beam and slab layout were received and provided to the contractor, though initial reluctance to modify formwork designs has slowed work.
3) Reinforcing bar and props required for upcoming work have been ordered but not yet arrived on site.
The daily construction report from the Nepalgunj Airport terminal building project provides the following updates:
1) Formwork for beams and slabs was being laid in blocks A and C, though subgrade work on some footings was delayed due to site clearance needs.
2) New drawings for the first floor beam and slab layout were received and provided to the contractor, though initial reluctance to modify formwork designs has slowed work.
3) Reinforcing bar and props required for upcoming work have been ordered but not yet arrived on site.
CONSTRUCTION OF NEW TERMINAL BUILDING AT NEPALGUNJ AIRPORT
DAILY CONSTRUCTION REPORT
Time of Photos Explanation
the Day Morning • The formwork for beam and slab are being laid on the eastern part of block 'A' and western part of block 'C'. • The subgrade for the isolated footing on the south side of each block 'A' and 'C' couldn't be prepared because some good effort on site clearance is required, and most workers are busy on formwork. • The drawings for beam and slab layout of first floor has been received, and the same has been provided in hard copy and soft copy to the contractor engineer as well as the sub-contractor himself. At first, there was some reluctance to join formwork for layout with downslab. The day's work at Guest House was called off because the contractor thought lots of effort was required to make the formwork as per the new drawing. However, with exclusion of downslab, now the work has now resumed. • The schedule has been checked for secondary and main beam and the layout was also checked for whether it was followed or not. • No significant work was done on Tubewell and Drainage. • With the inadequacy of supports for beam and slabs, the pace is going quite slow. • The 10 mm 𝜙 rebar for slab is yet to arrive on site, which is expected to be 14 m long. • The props are also said to be ordered, but yet to arrive.