1. Cofejok Construction & Supply Corporation was awarded a contract worth PHP 1,987,949.70 to construct a PTV Pagadian Transmitter Building.
2. The project was completed on schedule by January 5, 2022.
3. Final inspection and acceptance of the completed project was conducted on May 31, 2022.
Original Description:
PI
Original Title
Project Info for FB_Construction of PTV Pagadian Transmitter Bldg
1. Cofejok Construction & Supply Corporation was awarded a contract worth PHP 1,987,949.70 to construct a PTV Pagadian Transmitter Building.
2. The project was completed on schedule by January 5, 2022.
3. Final inspection and acceptance of the completed project was conducted on May 31, 2022.
1. Cofejok Construction & Supply Corporation was awarded a contract worth PHP 1,987,949.70 to construct a PTV Pagadian Transmitter Building.
2. The project was completed on schedule by January 5, 2022.
3. Final inspection and acceptance of the completed project was conducted on May 31, 2022.
JOB ORDER NO: 21-10-0017 PROJECT: CONSTRUCTION OF PTV PAGADIAN TRANSMITTER BUILDING SUPPLIER: COFEJOK CONSTRUCTION & SUPPLY CORPORATION CONTRACT AMOUNT: PhP 1,987,949.70
NO. DATE PARTICULARS REMARKS
PTNI awarded the project, Awarded to Cofejok Construction 1 September 22, 2021 dated September 22, 2021. & Supply Corporation. Delivery period for this project is within Ninety (90) calendar days 2 October 8, 2021 Receipt of Notice to Proceed upon receipt of Notice to Proceed. The target completion is on January 05, 2022. Cofejok Construction & Supply Corporation claimed 53.2044086% of Contract Amount equivalent to Php 3 November 16, 2021 Progress Billing No. 01 1,052,383.20 and evaluated by PTNI-Project Management Office and came up with 45.99% of Contract Amount equivalent to Php 914,314.52 Cofejok Construction & Supply Corporation requested for Variation Order No. 01 Construction of Water Tank Steel 4 December 16, 2021 Variation Order No. 01 Platform and Access Ladder on November 29, 2021 and evaluated by Project Management Office and approved on December 16, 2021. Cofejok Construction & Supply Corporation claimed 36.9434851% of Contract Amount equivalent to Php 5 December 18, 2021 Progress Billing No. 02 734,428.14 and evaluated by PTNI-Project Management Office and came up with 43.29% of Contract Amount equivalent to Php 874,923.30 Cofejok Construction & Supply Corporation completed the 6 January 05, 2022 Project Completion project: Construction of PTV Pagadian Transmitter Building, ITB No. 2021-0004 NO. DATE PARTICULARS REMARKS Cofejok Construction and Supply Corporation requested preliminary inspection and Preliminary Inspection and acceptance on March 17, 2022 7 March 28, 2022 Acceptance and Project Management Office scheduled the preliminary inspection and acceptance on March 28, 2022 Cofejok Construction and Supply Corporation requested final inspection and acceptance on Final Inspection and 8 May 31, 2022 May 24, 2022 and Project Acceptance Management Office scheduled the final inspection and acceptance on May 31, 2022 Cofejok Construction & Supply Corporation claimed 11.47% of Revised Contract Amount equivalent to Php 231,771.82 9 July 01, 2022 Final Billing and evaluated by PTNI-Project Management Office and came up with 11.47% of Revised Contract Amount equivalent to Php 231,771.82 Cofejok Construction & Supply Corporation requested to release 10% of Revised Contract 10 July 01, 2022 10% Retention Amount Retention equivalent to Php 202,100.96 with attached retention/warranty bond.
Prepared by:
ENGR. WESLEY A. DAHILI
Sr. Admin. Asst. I (Project Engineer) Project Management Office
Certified Correct by:
MR. GERARDO A. LEDONIO III
Supervisor, Project Management Office & Head Executive Assistant