WORK BREAKDOWN STRUCTURE

PERUSAHAAN : PT. SEIRAMA LAJU


PEKERJAAN : RELOKASI DPPU DEPATI AMIR - PANGKAL PINANG

WBS CODE WBS NAME LEVEL

1 RELOKASI DPPU DEPATI AMIR - PANGKAL PINANG


1.1 MILESTONE Level 1
1.1.1 Asumsi start awal pekerjaan Level 2
1.1.2 Design pondasi tangki approved Level 2
1.1.3 Hydrotest dan dewatering finished Level 2
1.1.4 Tera tangki oleh DIMET finished Level 2
1.1.5 Jet Fuel Storage Tank 4 x 500 KL dan Fire Water Tank 750 KL finished Level 2
1.1.6 Mechanical Completion, PSSR, Precomissioning dan Comissioning Level 2
1.2 PREPARATION WORK & TEMPORARY FACILITIES Level 1
1.2.1 Head Office Level 2
1.2.2 Site Office Level 2
1.2.3 Mobilisasi dan Demobilisasi Alat dan Personil Level 2
1.2.4 Administration & Construction Permit Level 2
1.2.5 Transportasi Material Level 2
1.2.6 Operational Car Level 2
1.2.7 Safety Lines / Temporary Fences Level 2
1.3 ENGINEERING Level 1
1.3.1 ENGINEERING & PROJECT MANAGEMENT Level 2
1.3.1.1 Survey Pengukuran/Setting Out, Soil Investigasi Level 3
1.3.1.2 Detail Engineering Design Level 3
1.3.1.2.1 Mechanical Level 4
1.3.1.2.1.1 Data Sheet Level 5
1.3.1.2.1.1.1 DS Jest Fuel Storage Tank Level 6
1.3.1.2.1.1.2 DS Drain tank Level 6
1.3.1.2.1.1.3 DS Diesel Fuel Storage Tangk Level 6
1.3.1.2.1.1.4 DS Floating suction Level 6
1.3.1.2.1.1.5 DS Receiving pump Level 6
1.3.1.2.1.1.6 DS Supply pump Level 6
1.3.1.2.1.1.7 DS Fire Pump Level 6
1.3.1.2.1.1.8 DS Drain pump Level 6
1.3.1.2.1.1.9 DS Jockey pump Level 6
1.3.1.2.1.1.10 DS Fire water tank Level 6
1.3.1.2.1.1.11 DS Utility water tank Level 6
1.3.1.2.1.1.12 DS Sulvage pump Level 6
1.3.1.2.1.1.13 DS Diesel fuel pump Level 6
1.3.1.2.1.1.14 DS Deepweel pump for fire water tank Level 6
1.3.1.2.1.1.15 DS Deepweel pump Utility pump Level 6
1.3.1.2.1.1.16 DS Utilty water pump Level 6
1.3.1.2.1.1.17 DS Booster pump fire tank Level 6
1.3.1.2.1.1.18 DS Booster pump Utility Tank Level 6
1.3.1.2.1.1.19 DS Submersible pump drain tank Level 6
1.3.1.2.1.1.20 DS Emergency Vent Level 6
1.3.1.2.1.1.21 DS Slop dipping device Level 6
1.3.1.2.1.1.22 DS Free Vent Level 6
1.3.1.2.1.1.23 DS Diesel Fuel Dipenser Level 6
1.3.1.2.1.1.24 DS Recovery Vessel Level 6
1.3.1.2.1.1.25 DS Sampling Jar Level 6
1.3.1.2.1.1.26 DS Drain collector Level 6
1.3.1.2.1.1.27 DS Receiving Filter Separator Level 6

1/29
WBS CODE WBS NAME LEVEL

1.3.1.2.1.1.28 DS Supply Filter Separator Level 6


1.3.1.2.1.1.29 DS Drain Filter Separator Level 6
1.3.1.2.1.1.30 DS Drain pit Blower & fan Level 6
1.3.1.2.1.1.31 DS Ductin blower & Fan Level 6
1.3.1.2.1.1.32 DS Receiving Aviation hose loading Level 6
1.3.1.2.1.1.33 DS Supply aviation hose loading Level 6
1.3.1.2.1.1.34 DS Receiving Fuel (diesel) Hose loading Level 6
1.3.1.2.1.1.35 DS Supply Sulvage hose loading Level 6
1.3.1.2.1.1.36 DS Receiving Drain hose loading Level 6
1.3.1.2.2 Electrical Level 4
1.3.1.2.2.1 Data Sheet Level 5
1.3.1.2.2.1.1 Deg Level 6
1.3.1.2.2.1.2 Trafo Level 6
1.3.1.2.2.1.3 MV Switchgear Level 6
1.3.1.2.2.1.4 LV Switchgear Level 6
1.3.1.2.2.1.5 UPS Level 6
1.3.1.2.2.1.6 Capacitor Level 6
1.3.1.2.2.1.7 Lightning system Level 6
1.3.1.2.2.1.8 Lighting panel & Small power distrubution board Level 6
1.3.1.2.2.1.9 Lighting & Receptacle Level 6
1.3.1.2.2.2 Specification Level 5
1.3.1.2.2.2.1 Power kabel Level 6
1.3.1.2.3 Piping Level 4
1.3.1.2.3.1 Data Sheet Level 5
1.3.1.2.3.1.1 Valve Level 6
1.3.1.2.3.1.2 Fitting Level 6
1.3.1.2.3.1.3 Specialities Level 6
1.3.1.2.3.2 Specification Level 5
1.3.1.2.3.2.1 Pipe Level 6
1.3.1.2.3.2.2 Coating/Painting Level 6
1.3.1.2.4 Instrument Level 4
1.3.1.2.4.1 Data Sheet Level 5
1.3.1.2.4.1.1 Pressure gauge Level 6
1.3.1.2.4.1.2 Pressure Indicating Transmitter Level 6
1.3.1.2.4.1.3 Flow indicator Level 6
1.3.1.2.4.1.4 Flow switch Level 6
1.3.1.2.4.1.5 Restriction Oriface Level 6
1.3.1.2.4.1.6 Rotameter Level 6
1.3.1.2.4.1.7 ATG (radar type) Level 6
1.3.1.2.4.1.8 Level gauge - transparent glass type Level 6
1.3.1.2.4.1.9 Level switch - Tuning Fork Type Level 6
1.3.1.2.4.1.10 Temperature Indicating Transmitter Level 6
1.3.1.2.4.1.11 MOV Level 6
1.3.1.2.4.1.12 PSV Level 6
1.3.1.2.4.1.13 Flame detector Level 6
1.3.1.2.4.1.14 Smoke detector Level 6
1.3.1.2.4.1.15 Heat detector Level 6
1.3.1.2.4.1.16 Manual call point (outdoor) Level 6
1.3.1.2.4.1.17 Sirene & Beacon (outdoor) Level 6
1.3.1.2.4.1.18 Manual call point (Indoor) Level 6
1.3.1.2.4.1.19 Sirene & beacon (indoor) Level 6

1.3.1.2.4.1.20 Emergency push button (outdoor) Level 6

1.3.1.2.4.1.21 metering system Level 6

1.3.1.2.4.1.22 Juction box Level 6

2/29
WBS CODE WBS NAME LEVEL

1.3.1.2.4.2 Specification Level 5


1.3.1.2.4.2.1 TAS Level 6
1.3.1.2.4.2.2 Instrument cable Level 6
1.3.1.2.5 Process Safety Level 4
1.3.1.2.5.1 Data Sheet Level 5
1.3.1.2.5.1.1 Foam Pressure Propositioner + Foam Storage Tank Level 6
1.3.1.2.5.1.2 Fasilitas Foam Chamber Level 6
1.3.1.2.5.1.3 Protable Foam Level 6
1.3.1.2.5.1.4 Fire water hydrant Level 6
1.3.1.2.5.1.5 Hydrant cabinet Level 6
1.3.1.2.5.1.6 Fire extiguser Level 6
1.3.1.2.5.1.7 Oil spill kit Level 6
1.3.1.2.6 Civil Level 4
1.3.1.2.6.1 Specification Level 5
1.3.1.2.6.1.1 Specification Civil structure Level 6
1.3.1.2.6.1.2 Specification Tiang Pancang/Spun Pile Level 6
1.3.1.2.6.1.3 Specification for Conrete Level 6
1.3.1.2.6.1.4 Specification for Baja Profil & Tulangan Level 6
1.3.1.3 Project Management Level 3
1.4 PROCUREMENT Level 1
1.4.1 CIVIL Level 2
1.4.1.1 Precast Concrete Spun Pile Dia 450mm Level 3
1.4.1.1.1 Inquiry and bidding Level 4
1.4.1.1.2 TBE Level 4
1.4.1.1.3 CBE Level 4
1.4.1.1.4 PO Level 4
1.4.1.1.5 Fabrication Level 4
1.4.1.1.6 Delivery Level 4
1.4.1.1.7 On Site Level 4
1.4.1.2 (Material) Office Building include Control Room Level 3
1.4.1.3 (Material) Fire Pump House Level 3
1.4.1.4 (Material) Electrical House (MCC & Deg Building) Level 3
1.4.1.5 (Material) Full Loading - Unloading Shed Level 3
1.4.1.6 (Material) Trafo Shelter Level 3
1.4.1.7 (Material) Parking Area Shelter Level 3
1.4.1.8 (Material) Parking Area Refueller Shelter Level 3
1.4.1.9 (Material) Workshop & Warehouse (include maintenance) Building Level 3
1.4.1.10 (Material) Shelter for Pump Diesel Oil Tank Level 3
1.4.1.11 (Material) APAR Shelter Level 3
1.4.1.12 (Material) B3 Warehouse Shelter Level 3
1.4.1.13 (Material) Guard House Level 3
1.4.1.14 (Material) Fuel Pump Shed for Delivery Pumps Level 3
1.4.1.15 (Material) Fuel Pump Shed for Receiving Pumps Level 3
1.4.1.16 (Material) Drain Tank Shed Level 3
1.4.1.17 (Material) Shelter for Gate in-out for Bridger & Refueller Level 3
1.4.1.18 (Material) Pump Foundation Level 3
1.4.1.19 (Material) Filter Pump Foundation Level 3
1.4.1.20 (Material) Deg (Genset) Foundation Level 3
1.4.1.21 (Material) Trafo Foundation Level 3
1.4.1.22 (Material) Pekerjaan sipil lainnya Level 3
1.4.2 MECHANICAL Level 2
1.4.2.1 Pumps Level 3
1.4.2.1.1 Receiving Pump Level 4
1.4.2.1.1.1 Inquiry and bidding Level 5
1.4.2.1.1.2 TBE Level 5

3/29
WBS CODE WBS NAME LEVEL

1.4.2.1.1.3 CBE Level 5


1.4.2.1.1.4 PO Level 5
1.4.2.1.1.5 Fabrication Level 5
1.4.2.1.1.6 Delivery Level 5
1.4.2.1.1.7 On Site Level 5
1.4.2.1.2 Supply Pump Level 4
1.4.2.1.2.1 Inquiry and bidding Level 5
1.4.2.1.2.2 TBE Level 5
1.4.2.1.2.3 CBE Level 5
1.4.2.1.2.4 PO Level 5
1.4.2.1.2.5 Fabrication Level 5
1.4.2.1.2.6 Delivery Level 5
1.4.2.1.2.7 On Site Level 5
1.4.2.1.3 Drain Pump Level 4
1.4.2.1.3.1 Inquiry and bidding Level 5
1.4.2.1.3.2 TBE Level 5
1.4.2.1.3.3 CBE Level 5
1.4.2.1.3.4 PO Level 5
1.4.2.1.3.5 Fabrication Level 5
1.4.2.1.3.6 Delivery Level 5
1.4.2.1.3.7 On Site Level 5
1.4.2.1.4 Sulvage Pump Level 4
1.4.2.1.4.1 Inquiry and bidding Level 5
1.4.2.1.4.2 TBE Level 5
1.4.2.1.4.3 CBE Level 5
1.4.2.1.4.4 PO Level 5
1.4.2.1.4.5 Fabrication Level 5
1.4.2.1.4.6 Delivery Level 5
1.4.2.1.4.7 On Site Level 5
1.4.2.1.5 Diesel Fuel Receiving Pump Level 4
1.4.2.1.5.1 Inquiry and bidding Level 5
1.4.2.1.5.2 TBE Level 5
1.4.2.1.5.3 CBE Level 5
1.4.2.1.5.4 PO Level 5
1.4.2.1.5.5 Fabrication Level 5
1.4.2.1.5.6 Delivery Level 5
1.4.2.1.5.7 On Site Level 5
1.4.2.1.6 Fire Water Pump Level 4
1.4.2.1.6.1 Inquiry and bidding Level 5
1.4.2.1.6.2 TBE Level 5
1.4.2.1.6.3 CBE Level 5
1.4.2.1.6.4 PO Level 5
1.4.2.1.6.5 Fabrication Level 5
1.4.2.1.6.6 Delivery Level 5
1.4.2.1.6.7 On Site Level 5
1.4.2.1.7 Jockey Pump Level 4
1.4.2.1.7.1 Inquiry and bidding Level 5
1.4.2.1.7.2 TBE Level 5
1.4.2.1.7.3 CBE Level 5

1.4.2.1.7.4 PO Level 5

1.4.2.1.7.5 Fabrication Level 5

1.4.2.1.7.6 Delivery Level 5

1.4.2.1.7.7 On Site Level 5

4/29
WBS CODE WBS NAME LEVEL

1.4.2.1.8 Utility Water Pump Level 4

1.4.2.1.8.1 Inquiry and bidding Level 5


1.4.2.1.8.2 TBE Level 5
1.4.2.1.8.3 CBE Level 5
1.4.2.1.8.4 PO Level 5
1.4.2.1.8.5 Fabrication Level 5
1.4.2.1.8.6 Delivery Level 5
1.4.2.1.8.7 On Site Level 5
1.4.2.1.9 Booster Pump Fire Tank Level 4
1.4.2.1.9.1 Inquiry and bidding Level 5
1.4.2.1.9.2 TBE Level 5
1.4.2.1.9.3 CBE Level 5
1.4.2.1.9.4 PO Level 5
1.4.2.1.9.5 Fabrication Level 5
1.4.2.1.9.6 Delivery Level 5
1.4.2.1.9.7 On Site Level 5
1.4.2.1.10 Booster Pump Utility Tank Level 4
1.4.2.1.10.1 Inquiry and bidding Level 5
1.4.2.1.10.2 TBE Level 5
1.4.2.1.10.3 CBE Level 5
1.4.2.1.10.4 PO Level 5
1.4.2.1.10.5 Fabrication Level 5
1.4.2.1.10.6 Delivery Level 5
1.4.2.1.10.7 On Site Level 5
1.4.2.1.11 Submersible Pump Drain Pit Level 4
1.4.2.1.11.1 Inquiry and bidding Level 5
1.4.2.1.11.2 TBE Level 5
1.4.2.1.11.3 CBE Level 5
1.4.2.1.11.4 PO Level 5
1.4.2.1.11.5 Fabrication Level 5
1.4.2.1.11.6 Delivery Level 5
1.4.2.1.11.7 On Site Level 5
1.4.2.1.12 Deepwell Pump Fire Tank Level 4
1.4.2.1.12.1 Inquiry and bidding Level 5
1.4.2.1.12.2 TBE Level 5
1.4.2.1.12.3 CBE Level 5
1.4.2.1.12.4 PO Level 5
1.4.2.1.12.5 Fabrication Level 5
1.4.2.1.12.6 Delivery Level 5
1.4.2.1.12.7 On Site Level 5
1.4.2.1.13 Deepwell Pump Utility Tank Level 4
1.4.2.1.13.1 Inquiry and bidding Level 5
1.4.2.1.13.2 TBE Level 5
1.4.2.1.13.3 CBE Level 5
1.4.2.1.13.4 PO Level 5
1.4.2.1.13.5 Fabrication Level 5
1.4.2.1.13.6 Delivery Level 5
1.4.2.1.13.7 On Site Level 5
1.4.2.2 Packaged Unit Level 3
1.4.2.2.1 Inquiry and bidding Level 4
1.4.2.2.2 TBE Level 4
1.4.2.2.3 CBE Level 4
1.4.2.2.4 PO Level 4
1.4.2.2.5 Fabrication Level 4
1.4.2.2.6 Delivery Level 4
1.4.2.2.7 On Site Level 4

5/29
WBS CODE WBS NAME LEVEL

1.4.2.3 Vessel/torage Level 3


1.4.2.3.1 Drain Tank Level 4
1.4.2.3.1.1 Inquiry and bidding Level 5
1.4.2.3.1.2 TBE Level 5
1.4.2.3.1.3 CBE Level 5
1.4.2.3.1.4 PO Level 5
1.4.2.3.1.5 Fabrication Level 5
1.4.2.3.1.6 Delivery Level 5
1.4.2.3.1.7 On Site Level 5
1.4.2.3.2 Diesel Fuel Tank Level 4
1.4.2.3.2.1 Inquiry and bidding Level 5
1.4.2.3.2.2 TBE Level 5
1.4.2.3.2.3 CBE Level 5
1.4.2.3.2.4 PO Level 5
1.4.2.3.2.5 Fabrication Level 5
1.4.2.3.2.6 Delivery Level 5
1.4.2.3.2.7 On Site Level 5
1.4.2.4 Tanks Level 3
1.4.2.4.1 Plate Level 4
1.4.2.4.1.1 Inquiry and bidding Level 5
1.4.2.4.1.2 TBE Level 5
1.4.2.4.1.3 CBE Level 5
1.4.2.4.1.4 PO Level 5
1.4.2.4.1.5 Fabrication Level 5
1.4.2.4.1.6 Delivery Level 5
1.4.2.4.1.7 On Site Level 5
1.4.2.4.2 All Nozzles and Tank Appurtenance Level 4
1.4.2.4.2.1 Inquiry and bidding Level 5
1.4.2.4.2.2 TBE Level 5
1.4.2.4.2.3 CBE Level 5
1.4.2.4.2.4 PO Level 5
1.4.2.4.2.5 Fabrication Level 5
1.4.2.4.2.6 Delivery Level 5
1.4.2.4.2.7 On Site Level 5
1.4.2.4.3 Level Switch Level 4
1.4.2.4.3.1 Inquiry and bidding Level 5
1.4.2.4.3.2 TBE Level 5
1.4.2.4.3.3 CBE Level 5
1.4.2.4.3.4 PO Level 5
1.4.2.4.3.5 Fabrication Level 5
1.4.2.4.3.6 Delivery Level 5
1.4.2.4.3.7 On Site Level 5
1.4.2.4.4 Pressure Transmitter Level 4
1.4.2.4.4.1 Inquiry and bidding Level 5
1.4.2.4.4.2 TBE Level 5
1.4.2.4.4.3 CBE Level 5
1.4.2.4.4.4 PO Level 5
1.4.2.4.4.5 Fabrication Level 5
1.4.2.4.4.6 Delivery Level 5
1.4.2.4.4.7 On Site Level 5
1.4.2.4.5 Foam Chamber Level 4
1.4.2.4.5.1 Inquiry and bidding Level 5
1.4.2.4.5.2 TBE Level 5
1.4.2.4.5.3 CBE Level 5
1.4.2.4.5.4 PO Level 5

6/29
WBS CODE WBS NAME LEVEL

1.4.2.4.5.5 Fabrication Level 5


1.4.2.4.5.6 Delivery Level 5
1.4.2.4.5.7 On Site Level 5
1.4.2.4.6 Free Vent Level 4
1.4.2.4.6.1 Inquiry and bidding Level 5
1.4.2.4.6.2 TBE Level 5
1.4.2.4.6.3 CBE Level 5
1.4.2.4.6.4 PO Level 5
1.4.2.4.6.5 Fabrication Level 5
1.4.2.4.6.6 Delivery Level 5
1.4.2.4.6.7 On Site Level 5
1.4.2.4.7 Level Indicating Transmitter Level 4
1.4.2.4.7.1 Inquiry and bidding Level 5
1.4.2.4.7.2 TBE Level 5
1.4.2.4.7.3 CBE Level 5
1.4.2.4.7.4 PO Level 5
1.4.2.4.7.5 Fabrication Level 5
1.4.2.4.7.6 Delivery Level 5
1.4.2.4.7.7 On Site Level 5
1.4.2.4.8 Temperature Transmitter Level 4
1.4.2.4.8.1 Inquiry and bidding Level 5
1.4.2.4.8.2 TBE Level 5
1.4.2.4.8.3 CBE Level 5
1.4.2.4.8.4 PO Level 5
1.4.2.4.8.5 Fabrication Level 5
1.4.2.4.8.6 Delivery Level 5
1.4.2.4.8.7 On Site Level 5
1.4.2.4.9 Slot Dipping Device Level 4
1.4.2.4.9.1 Inquiry and bidding Level 5
1.4.2.4.9.2 TBE Level 5
1.4.2.4.9.3 CBE Level 5
1.4.2.4.9.4 PO Level 5
1.4.2.4.9.5 Fabrication Level 5
1.4.2.4.9.6 Delivery Level 5
1.4.2.4.9.7 On Site Level 5
1.4.2.4.10 Floating Suction Level 4
1.4.2.4.10.1 Inquiry and bidding Level 5
1.4.2.4.10.2 TBE Level 5
1.4.2.4.10.3 CBE Level 5
1.4.2.4.10.4 PO Level 5
1.4.2.4.10.5 Fabrication Level 5
1.4.2.4.10.6 Delivery Level 5
1.4.2.4.10.7 On Site Level 5
1.4.2.4.11 ATG Stilling Well Level 4
1.4.2.4.11.1 Inquiry and bidding Level 5
1.4.2.4.11.2 TBE Level 5
1.4.2.4.11.3 CBE Level 5
1.4.2.4.11.4 PO Level 5
1.4.2.4.11.5 Fabrication Level 5
1.4.2.4.11.6 Delivery Level 5
1.4.2.4.11.7 On Site Level 5
1.4.2.4.12 SDD Stilling Well Level 4
1.4.2.4.12.1 Inquiry and bidding Level 5
1.4.2.4.12.2 TBE Level 5
1.4.2.4.12.3 CBE Level 5

7/29
WBS CODE WBS NAME LEVEL

1.4.2.4.12.4 PO Level 5
1.4.2.4.12.5 Fabrication Level 5
1.4.2.4.12.6 Delivery Level 5
1.4.2.4.12.7 On Site Level 5
1.4.2.4.13 Temperature Sensor Stilling Well Level 4
1.4.2.4.13.1 Inquiry and bidding Level 5
1.4.2.4.13.2 TBE Level 5
1.4.2.4.13.3 CBE Level 5
1.4.2.4.13.4 PO Level 5
1.4.2.4.13.5 Fabrication Level 5
1.4.2.4.13.6 Delivery Level 5
1.4.2.4.13.7 On Site Level 5
1.4.2.4.14 Emergency Vent Level 4
1.4.2.4.14.1 Inquiry and bidding Level 5
1.4.2.4.14.2 TBE Level 5
1.4.2.4.14.3 CBE Level 5
1.4.2.4.14.4 PO Level 5
1.4.2.4.14.5 Fabrication Level 5
1.4.2.4.14.6 Delivery Level 5
1.4.2.4.14.7 On Site Level 5
1.4.2.4.15 End of Line Flame Arrester Level 4
1.4.2.4.15.1 Inquiry and bidding Level 5
1.4.2.4.15.2 TBE Level 5
1.4.2.4.15.3 CBE Level 5
1.4.2.4.15.4 PO Level 5
1.4.2.4.15.5 Fabrication Level 5
1.4.2.4.15.6 Delivery Level 5
1.4.2.4.15.7 On Site Level 5
1.4.2.4.16 Level Gauge Level 4
1.4.2.4.16.1 Inquiry and bidding Level 5
1.4.2.4.16.2 TBE Level 5
1.4.2.4.16.3 CBE Level 5
1.4.2.4.16.4 PO Level 5
1.4.2.4.16.5 Fabrication Level 5
1.4.2.4.16.6 Delivery Level 5
1.4.2.4.16.7 On Site Level 5
1.4.2.4.17 BackWater PRV Level 4
1.4.2.4.17.1 Inquiry and bidding Level 5
1.4.2.4.17.2 TBE Level 5

1.4.2.4.17.3 CBE Level 5

1.4.2.4.17.4 PO Level 5

1.4.2.4.17.5 Fabrication Level 5

1.4.2.4.17.6 Delivery Level 5

1.4.2.4.17.7 On Site Level 5

1.4.2.4.18 Utility Water Tank Level 4

1.4.2.4.18.1 Inquiry and bidding Level 5

1.4.2.4.18.2 TBE Level 5

1.4.2.4.18.3 CBE Level 5

1.4.2.4.18.4 PO Level 5

1.4.2.4.18.5 Fabrication Level 5

1.4.2.4.18.6 Delivery Level 5

1.4.2.4.18.7 On Site Level 5

8/29
WBS CODE WBS NAME LEVEL

1.4.3 PIPING Level 2

1.4.3.1 Pipe Level 3

1.4.3.1.1 Inquiry and bidding Level 4

1.4.3.1.2 TBE Level 4


1.4.3.1.3 CBE Level 4
1.4.3.1.4 PO Level 4
1.4.3.1.5 Fabrication Level 4
1.4.3.1.6 Delivery Level 4
1.4.3.1.7 On Site Level 4
1.4.3.2 Fittings Level 3
1.4.3.2.1 Inquiry and bidding Level 4
1.4.3.2.2 TBE Level 4
1.4.3.2.3 CBE Level 4
1.4.3.2.4 PO Level 4
1.4.3.2.5 Fabrication Level 4
1.4.3.2.6 Delivery Level 4
1.4.3.2.7 On Site Level 4
1.4.3.3 Valves Level 3
1.4.3.3.1 Inquiry and bidding Level 4
1.4.3.3.2 TBE Level 4
1.4.3.3.3 CBE Level 4
1.4.3.3.4 PO Level 4
1.4.3.3.5 Fabrication Level 4
1.4.3.3.6 Delivery Level 4
1.4.3.3.7 On Site Level 4
1.4.3.4 Spring Loaded Valve Level 3
1.4.3.4.1 Inquiry and bidding Level 4
1.4.3.4.2 TBE Level 4
1.4.3.4.3 CBE Level 4
1.4.3.4.4 PO Level 4
1.4.3.4.5 Fabrication Level 4
1.4.3.4.6 Delivery Level 4
1.4.3.4.7 On Site Level 4
1.4.3.5 Flange, Gasket, Bolt and Nut Level 3
1.4.3.5.1 Inquiry and bidding Level 4
1.4.3.5.2 TBE Level 4
1.4.3.5.3 CBE Level 4
1.4.3.5.4 PO Level 4
1.4.3.5.5 Fabrication Level 4
1.4.3.5.6 Delivery Level 4
1.4.3.5.7 On Site Level 4
1.4.3.6 Bucket Type Strainer Level 3
1.4.3.6.1 Inquiry and bidding Level 4
1.4.3.6.2 TBE Level 4
1.4.3.6.3 CBE Level 4
1.4.3.6.4 PO Level 4
1.4.3.6.5 Fabrication Level 4
1.4.3.6.6 Delivery Level 4
1.4.3.6.7 On Site Level 4
1.4.3.7 Sight Glass Level 3
1.4.3.7.1 Inquiry and bidding Level 4
1.4.3.7.2 TBE Level 4
1.4.3.7.3 CBE Level 4
1.4.3.7.4 PO Level 4

9/29
WBS CODE WBS NAME LEVEL

1.4.3.7.5 Fabrication Level 4


1.4.3.7.6 Delivery Level 4
1.4.3.7.7 On Site Level 4
1.4.3.8 Show Flow Level 3
1.4.3.8.1 Inquiry and bidding Level 4
1.4.3.8.2 TBE Level 4
1.4.3.8.3 CBE Level 4
1.4.3.8.4 PO Level 4
1.4.3.8.5 Fabrication Level 4
1.4.3.8.6 Delivery Level 4
1.4.3.8.7 On Site Level 4
1.4.3.9 Expansion Joint Level 3
1.4.3.9.1 Inquiry and bidding Level 4
1.4.3.9.2 TBE Level 4
1.4.3.9.3 CBE Level 4
1.4.3.9.4 PO Level 4
1.4.3.9.5 Fabrication Level 4
1.4.3.9.6 Delivery Level 4
1.4.3.9.7 On Site Level 4
1.4.3.10 Flexible Joint Level 3
1.4.3.10.1 Inquiry and bidding Level 4
1.4.3.10.2 TBE Level 4
1.4.3.10.3 CBE Level 4
1.4.3.10.4 PO Level 4
1.4.3.10.5 Fabrication Level 4
1.4.3.10.6 Delivery Level 4
1.4.3.10.7 On Site Level 4
1.4.3.11 Y-Type Strainer Level 3
1.4.3.11.1 Inquiry and bidding Level 4
1.4.3.11.2 TBE Level 4
1.4.3.11.3 CBE Level 4
1.4.3.11.4 PO Level 4
1.4.3.11.5 Fabrication Level 4
1.4.3.11.6 Delivery Level 4
1.4.3.11.7 On Site Level 4

1.4.3.12 Basket Strainer Level 3

1.4.3.12.1 Inquiry and bidding Level 4

1.4.3.12.2 TBE Level 4

1.4.3.12.3 CBE Level 4

1.4.3.12.4 PO Level 4

1.4.3.12.5 Fabrication Level 4

1.4.3.12.6 Delivery Level 4

1.4.3.12.7 On Site Level 4

1.4.3.13 Insulation Flange Level 3

1.4.3.13.1 Inquiry and bidding Level 4

1.4.3.13.2 TBE Level 4

1.4.3.13.3 CBE Level 4

1.4.3.13.4 PO Level 4

1.4.3.13.5 Fabrication Level 4

1.4.3.13.6 Delivery Level 4

1.4.3.13.7 On Site Level 4

10/29
WBS CODE WBS NAME LEVEL

1.4.4 INSTRUMENT Level 2


1.4.4.1 Terminal Automatic System - Control System (TAS - CS) Level 3
1.4.4.1.1 Industrial PC for Processing and Interface System Level 4
1.4.4.1.1.1 Inquiry and bidding Level 5
1.4.4.1.1.2 TBE Level 5
1.4.4.1.1.3 CBE Level 5
1.4.4.1.1.4 PO Level 5
1.4.4.1.1.5 Fabrication Level 5
1.4.4.1.1.6 Delivery Level 5
1.4.4.1.1.7 On Site Level 5
1.4.4.1.2 Process Control System (PCS) Level 4
1.4.4.1.2.1 Inquiry and bidding Level 5
1.4.4.1.2.2 TBE Level 5
1.4.4.1.2.3 CBE Level 5
1.4.4.1.2.4 PO Level 5
1.4.4.1.2.5 Fabrication Level 5
1.4.4.1.2.6 Delivery Level 5
1.4.4.1.2.7 On Site Level 5
1.4.4.1.3 Safety Instrumented System (SIS) Level 4
1.4.4.1.3.1 Inquiry and bidding Level 5
1.4.4.1.3.2 TBE Level 5
1.4.4.1.3.3 CBE Level 5
1.4.4.1.3.4 PO Level 5
1.4.4.1.3.5 Fabrication Level 5
1.4.4.1.3.6 Delivery Level 5
1.4.4.1.3.7 On Site Level 5
1.4.4.1.4 Server System Level 4
1.4.4.1.4.1 Inquiry and bidding Level 5
1.4.4.1.4.2 TBE Level 5
1.4.4.1.4.3 CBE Level 5
1.4.4.1.4.4 PO Level 5
1.4.4.1.4.5 Fabrication Level 5
1.4.4.1.4.6 Delivery Level 5
1.4.4.1.4.7 On Site Level 5
1.4.4.1.5 System Accessories Level 4
1.4.4.1.5.1 Inquiry and bidding Level 5
1.4.4.1.5.2 TBE Level 5
1.4.4.1.5.3 CBE Level 5
1.4.4.1.5.4 PO Level 5
1.4.4.1.5.5 Fabrication Level 5
1.4.4.1.5.6 Delivery Level 5
1.4.4.1.5.7 On Site Level 5
1.4.4.1.6 Software/Firmware/License (International License) Level 4
1.4.4.1.6.1 Inquiry and bidding Level 5
1.4.4.1.6.2 TBE Level 5
1.4.4.1.6.3 CBE Level 5
1.4.4.1.6.4 PO Level 5
1.4.4.1.6.5 Fabrication Level 5
1.4.4.1.6.6 Delivery Level 5
1.4.4.1.6.7 On Site Level 5
1.4.4.1.7 Sub-System (MOV & ATG) Cabinet Level 4
1.4.4.1.7.1 Inquiry and bidding Level 5
1.4.4.1.7.2 TBE Level 5
1.4.4.1.7.3 CBE Level 5
1.4.4.1.7.4 PO Level 5

11/29
WBS CODE WBS NAME LEVEL

1.4.4.1.7.5 Fabrication Level 5


1.4.4.1.7.6 Delivery Level 5
1.4.4.1.7.7 On Site Level 5
1.4.4.1.8 MOV Master Station Level 4
1.4.4.1.8.1 Inquiry and bidding Level 5
1.4.4.1.8.2 TBE Level 5
1.4.4.1.8.3 CBE Level 5
1.4.4.1.8.4 PO Level 5
1.4.4.1.8.5 Fabrication Level 5
1.4.4.1.8.6 Delivery Level 5
1.4.4.1.8.7 On Site Level 5
1.4.4.1.9 Tank Gauging Interface System Level 4
1.4.4.1.9.1 Inquiry and bidding Level 5
1.4.4.1.9.2 TBE Level 5
1.4.4.1.9.3 CBE Level 5
1.4.4.1.9.4 PO Level 5
1.4.4.1.9.5 Fabrication Level 5
1.4.4.1.9.6 Delivery Level 5
1.4.4.1.9.7 On Site Level 5
1.4.4.1.10 Fire Alarm Control Panel (FACP) Level 4
1.4.4.1.10.1 Inquiry and bidding Level 5
1.4.4.1.10.2 TBE Level 5
1.4.4.1.10.3 CBE Level 5
1.4.4.1.10.4 PO Level 5
1.4.4.1.10.5 Fabrication Level 5
1.4.4.1.10.6 Delivery Level 5
1.4.4.1.10.7 On Site Level 5
1.4.4.2 Terminal Automatic System Management System (TAS -MS) Level 3
1.4.4.2.1 Inquiry and bidding Level 4
1.4.4.2.2 TBE Level 4
1.4.4.2.3 CBE Level 4
1.4.4.2.4 PO Level 4
1.4.4.2.5 Fabrication Level 4
1.4.4.2.6 Delivery Level 4
1.4.4.2.7 On Site Level 4

1.4.4.3 Metering System Level 3

1.4.4.3.1 Refueler Loading Metering Package Level 4

1.4.4.3.1.1 Inquiry and bidding Level 5

1.4.4.3.1.2 TBE Level 5

1.4.4.3.1.3 CBE Level 5

1.4.4.3.1.4 PO Level 5

1.4.4.3.1.5 Fabrication Level 5

1.4.4.3.1.6 Delivery Level 5

1.4.4.3.1.7 On Site Level 5

1.4.4.3.2 Master Meter (Mobile Meter Prover) Level 4

1.4.4.3.2.1 Inquiry and bidding Level 5

1.4.4.3.2.2 TBE Level 5

1.4.4.3.2.3 CBE Level 5

1.4.4.3.2.4 PO Level 5

1.4.4.3.2.5 Fabrication Level 5

1.4.4.3.2.6 Delivery Level 5

1.4.4.3.2.7 On Site Level 5

12/29
WBS CODE WBS NAME LEVEL

1.4.4.4 Field Instrument Level 3


1.4.4.4.1 Pressure Instrument Level 4
1.4.4.4.1.1 Pressure Gauge Level 5
1.4.4.4.1.1.1 Inquiry and bidding Level 6
1.4.4.4.1.1.2 TBE Level 6
1.4.4.4.1.1.3 CBE Level 6
1.4.4.4.1.1.4 PO Level 6
1.4.4.4.1.1.5 Fabrication Level 6
1.4.4.4.1.1.6 Delivery Level 6
1.4.4.4.1.1.7 On Site Level 6
1.4.4.4.1.2 Pressure Indicating Transmitter Level 5
1.4.4.4.1.2.1 Inquiry and bidding Level 6
1.4.4.4.1.2.2 TBE Level 6
1.4.4.4.1.2.3 CBE Level 6
1.4.4.4.1.2.4 PO Level 6
1.4.4.4.1.2.5 Fabrication Level 6
1.4.4.4.1.2.6 Delivery Level 6
1.4.4.4.1.2.7 On Site Level 6
1.4.4.4.2 Temperature Instrument Level 4
1.4.4.4.2.1 Temperature Transmitter Level 5
1.4.4.4.2.1.1 Inquiry and bidding Level 6
1.4.4.4.2.1.2 TBE Level 6
1.4.4.4.2.1.3 CBE Level 6
1.4.4.4.2.1.4 PO Level 6
1.4.4.4.2.1.5 Fabrication Level 6
1.4.4.4.2.1.6 Delivery Level 6
1.4.4.4.2.1.7 On Site Level 6
1.4.4.4.3 Level Instrument Level 4
1.4.4.4.3.1 Automatic Tank Gauge - (Radar Type) Level 5
1.4.4.4.3.1.1 Inquiry and bidding Level 6
1.4.4.4.3.1.2 TBE Level 6
1.4.4.4.3.1.3 CBE Level 6
1.4.4.4.3.1.4 PO Level 6
1.4.4.4.3.1.5 Fabrication Level 6
1.4.4.4.3.1.6 Delivery Level 6
1.4.4.4.3.1.7 On Site Level 6

1.4.4.4.3.2 Level Switch - (Tuning Fork Type) Level 5

1.4.4.4.3.2.1 Inquiry and bidding Level 6

1.4.4.4.3.2.2 TBE Level 6

1.4.4.4.3.2.3 CBE Level 6

1.4.4.4.3.2.4 PO Level 6

1.4.4.4.3.2.5 Fabrication Level 6

1.4.4.4.3.2.6 Delivery Level 6

1.4.4.4.3.2.7 On Site Level 6

1.4.4.4.3.3 Level Switch - Float Type Level 5

1.4.4.4.3.3.1 Inquiry and bidding Level 6

1.4.4.4.3.3.2 TBE Level 6

1.4.4.4.3.3.3 CBE Level 6

1.4.4.4.3.3.4 PO Level 6

1.4.4.4.3.3.5 Fabrication Level 6

1.4.4.4.3.3.6 Delivery Level 6

1.4.4.4.3.3.7 On Site Level 6

13/29
WBS CODE WBS NAME LEVEL

1.4.4.4.3.4 Level Indicating Transmitter - (GWR Type) Level 5


1.4.4.4.3.4.1 Inquiry and bidding Level 6
1.4.4.4.3.4.2 TBE Level 6
1.4.4.4.3.4.3 CBE Level 6
1.4.4.4.3.4.4 PO Level 6
1.4.4.4.3.4.5 Fabrication Level 6
1.4.4.4.3.4.6 Delivery Level 6
1.4.4.4.3.4.7 On Site Level 6
1.4.4.4.3.5 Level Indicating Transmitter - (DP Type) Level 5
1.4.4.4.3.5.1 Inquiry and bidding Level 6
1.4.4.4.3.5.2 TBE Level 6
1.4.4.4.3.5.3 CBE Level 6
1.4.4.4.3.5.4 PO Level 6
1.4.4.4.3.5.5 Fabrication Level 6
1.4.4.4.3.5.6 Delivery Level 6
1.4.4.4.3.5.7 On Site Level 6
1.4.4.4.3.6 Level Gauge - (Transparent Glass Type) Level 5
1.4.4.4.3.6.1 Inquiry and bidding Level 6
1.4.4.4.3.6.2 TBE Level 6
1.4.4.4.3.6.3 CBE Level 6
1.4.4.4.3.6.4 PO Level 6
1.4.4.4.3.6.5 Fabrication Level 6
1.4.4.4.3.6.6 Delivery Level 6
1.4.4.4.3.6.7 On Site Level 6
1.4.4.4.4 Flow Instrument Level 4
1.4.4.4.4.1 Rotameter (Transmitter) Level 5
1.4.4.4.4.1.1 Inquiry and bidding Level 6
1.4.4.4.4.1.2 TBE Level 6
1.4.4.4.4.1.3 CBE Level 6
1.4.4.4.4.1.4 PO Level 6
1.4.4.4.4.1.5 Fabrication Level 6
1.4.4.4.4.1.6 Delivery Level 6
1.4.4.4.4.1.7 On Site Level 6
1.4.4.4.4.2 Flow Indicator (DP Type) Level 5
1.4.4.4.4.2.1 Inquiry and bidding Level 6
1.4.4.4.4.2.2 TBE Level 6
1.4.4.4.4.2.3 CBE Level 6
1.4.4.4.4.2.4 PO Level 6
1.4.4.4.4.2.5 Fabrication Level 6
1.4.4.4.4.2.6 Delivery Level 6
1.4.4.4.4.2.7 On Site Level 6
1.4.4.4.4.3 Flow Switch (Thermal Differential Type) Level 5
1.4.4.4.4.3.1 Inquiry and bidding Level 6
1.4.4.4.4.3.2 TBE Level 6
1.4.4.4.4.3.3 CBE Level 6
1.4.4.4.4.3.4 PO Level 6
1.4.4.4.4.3.5 Fabrication Level 6
1.4.4.4.4.3.6 Delivery Level 6
1.4.4.4.4.3.7 On Site Level 6
1.4.4.4.4.4 Restriction Orifice Level 5
1.4.4.4.4.4.1 Inquiry and bidding Level 6
1.4.4.4.4.4.2 TBE Level 6
1.4.4.4.4.4.3 CBE Level 6
1.4.4.4.4.4.4 PO Level 6
1.4.4.4.4.4.5 Fabrication Level 6

14/29
WBS CODE WBS NAME LEVEL

1.4.4.4.4.4.6 Delivery Level 6


1.4.4.4.4.4.7 On Site Level 6
1.4.4.4.5 Actuated Valves Level 4
1.4.4.4.5.1 Pressure Safety Valve Level 5
1.4.4.4.5.1.1 Inquiry and bidding Level 6
1.4.4.4.5.1.2 TBE Level 6
1.4.4.4.5.1.3 CBE Level 6
1.4.4.4.5.1.4 PO Level 6
1.4.4.4.5.1.5 Fabrication Level 6
1.4.4.4.5.1.6 Delivery Level 6
1.4.4.4.5.1.7 On Site Level 6
1.4.4.4.5.2 Motor Operated Valve (MOV) Level 5
1.4.4.4.5.2.1 Inquiry and bidding Level 6
1.4.4.4.5.2.2 TBE Level 6
1.4.4.4.5.2.3 CBE Level 6
1.4.4.4.5.2.4 PO Level 6
1.4.4.4.5.2.5 Fabrication Level 6
1.4.4.4.5.2.6 Delivery Level 6
1.4.4.4.5.2.7 On Site Level 6
1.4.4.4.6 Fire & Gas Device System Level 4
1.4.4.4.6.1 Inquiry and bidding Level 5
1.4.4.4.6.2 TBE Level 5
1.4.4.4.6.3 CBE Level 5
1.4.4.4.6.4 PO Level 5
1.4.4.4.6.5 Fabrication Level 5
1.4.4.4.6.6 Delivery Level 5
1.4.4.4.6.7 On Site Level 5
1.4.4.5 Instrument Cable Level 3
1.4.4.5.1 Inquiry and bidding Level 4
1.4.4.5.2 TBE Level 4
1.4.4.5.3 CBE Level 4
1.4.4.5.4 PO Level 4
1.4.4.5.5 Fabrication Level 4
1.4.4.5.6 Delivery Level 4
1.4.4.5.7 On Site Level 4
1.4.4.6 Instrument Junction Box Level 3
1.4.4.6.1 Inquiry and bidding Level 4
1.4.4.6.2 TBE Level 4
1.4.4.6.3 CBE Level 4
1.4.4.6.4 PO Level 4
1.4.4.6.5 Fabrication Level 4
1.4.4.6.6 Delivery Level 4
1.4.4.6.7 On Site Level 4
1.4.4.7 Instrument Bulk Material Level 3
1.4.4.7.1 Inquiry and bidding Level 4
1.4.4.7.2 TBE Level 4
1.4.4.7.3 CBE Level 4
1.4.4.7.4 PO Level 4
1.4.4.7.5 Fabrication Level 4
1.4.4.7.6 Delivery Level 4
1.4.4.7.7 On Site Level 4
1.4.4.8 Cable Tray, Support & Accessories Level 3
1.4.4.8.1 Inquiry and bidding Level 4
1.4.4.8.2 TBE Level 4
1.4.4.8.3 CBE Level 4

15/29
WBS CODE WBS NAME LEVEL

1.4.4.8.4 PO Level 4
1.4.4.8.5 Fabrication Level 4
1.4.4.8.6 Delivery Level 4
1.4.4.8.7 On Site Level 4
1.4.4.9 Instrument Hookup Level 3
1.4.4.9.1 Inquiry and bidding Level 4
1.4.4.9.2 TBE Level 4
1.4.4.9.3 CBE Level 4
1.4.4.9.4 PO Level 4
1.4.4.9.5 Fabrication Level 4
1.4.4.9.6 Delivery Level 4
1.4.4.9.7 On Site Level 4
1.4.4.10 Steel Support Level 3
1.4.4.10.1 Inquiry and bidding Level 4
1.4.4.10.2 TBE Level 4
1.4.4.10.3 CBE Level 4
1.4.4.10.4 PO Level 4
1.4.4.10.5 Fabrication Level 4
1.4.4.10.6 Delivery Level 4
1.4.4.10.7 On Site Level 4
1.4.5 ELECTRICAL Level 2
1.4.5.1 Diesel Engine Generator Level 3
1.4.5.1.1 Inquiry and bidding Level 4
1.4.5.1.2 TBE Level 4
1.4.5.1.3 CBE Level 4
1.4.5.1.4 PO Level 4
1.4.5.1.5 Fabrication Level 4
1.4.5.1.6 Delivery Level 4
1.4.5.1.7 On Site Level 4
1.4.5.2 Power Transformer Level 3
1.4.5.2.1 Inquiry and bidding Level 4
1.4.5.2.2 TBE Level 4
1.4.5.2.3 CBE Level 4
1.4.5.2.4 PO Level 4
1.4.5.2.5 Fabrication Level 4
1.4.5.2.6 Delivery Level 4
1.4.5.2.7 On Site Level 4
1.4.5.3 MV Switchgear 20 kV Level 3

1.4.5.3.1 Inquiry and bidding Level 4

1.4.5.3.2 TBE Level 4

1.4.5.3.3 CBE Level 4

1.4.5.3.4 PO Level 4

1.4.5.3.5 Fabrication Level 4

1.4.5.3.6 Delivery Level 4

1.4.5.3.7 On Site Level 4

1.4.5.4 LV Switchgear 0.4 kV Level 3

1.4.5.4.1 Inquiry and bidding Level 4

1.4.5.4.2 TBE Level 4

1.4.5.4.3 CBE Level 4

1.4.5.4.4 PO Level 4

1.4.5.4.5 Fabrication Level 4

1.4.5.4.6 Delivery Level 4

1.4.5.4.7 On Site Level 4

16/29
WBS CODE WBS NAME LEVEL

1.4.5.5 Capacitor Bank Level 3


1.4.5.5.1 Inquiry and bidding Level 4
1.4.5.5.2 TBE Level 4
1.4.5.5.3 CBE Level 4
1.4.5.5.4 PO Level 4
1.4.5.5.5 Fabrication Level 4
1.4.5.5.6 Delivery Level 4
1.4.5.5.7 On Site Level 4
1.4.5.6 UPS -AC Level 3
1.4.5.6.1 Inquiry and bidding Level 4
1.4.5.6.2 TBE Level 4
1.4.5.6.3 CBE Level 4
1.4.5.6.4 PO Level 4
1.4.5.6.5 Fabrication Level 4
1.4.5.6.6 Delivery Level 4
1.4.5.6.7 On Site Level 4
1.4.5.7 UPS -DC Level 3
1.4.5.7.1 Inquiry and bidding Level 4
1.4.5.7.2 TBE Level 4
1.4.5.7.3 CBE Level 4
1.4.5.7.4 PO Level 4
1.4.5.7.5 Fabrication Level 4
1.4.5.7.6 Delivery Level 4
1.4.5.7.7 On Site Level 4
1.4.5.8 Lighting Panel & Small Power Distribution Board Level 3
1.4.5.8.1 Inquiry and bidding Level 4
1.4.5.8.2 TBE Level 4
1.4.5.8.3 CBE Level 4
1.4.5.8.4 PO Level 4
1.4.5.8.5 Fabrication Level 4
1.4.5.8.6 Delivery Level 4
1.4.5.8.7 On Site Level 4
1.4.5.9 Local Control Station Level 3
1.4.5.9.1 Inquiry and bidding Level 4
1.4.5.9.2 TBE Level 4
1.4.5.9.3 CBE Level 4
1.4.5.9.4 PO Level 4
1.4.5.9.5 Fabrication Level 4
1.4.5.9.6 Delivery Level 4
1.4.5.9.7 On Site Level 4
1.4.5.10 Power & Control Cable Level 3
1.4.5.10.1 Inquiry and bidding Level 4
1.4.5.10.2 TBE Level 4
1.4.5.10.3 CBE Level 4
1.4.5.10.4 PO Level 4
1.4.5.10.5 Fabrication Level 4
1.4.5.10.6 Delivery Level 4
1.4.5.10.7 On Site Level 4
1.4.5.11 Lighting & Receptacle Cable Level 3
1.4.5.11.1 Inquiry and bidding Level 4
1.4.5.11.2 TBE Level 4
1.4.5.11.3 CBE Level 4
1.4.5.11.4 PO Level 4
1.4.5.11.5 Fabrication Level 4
1.4.5.11.6 Delivery Level 4
1.4.5.11.7 On Site Level 4

17/29
WBS CODE WBS NAME LEVEL

1.4.5.12 Grounding Cable Level 3


1.4.5.12.1 Inquiry and bidding Level 4
1.4.5.12.2 TBE Level 4
1.4.5.12.3 CBE Level 4
1.4.5.12.4 PO Level 4
1.4.5.12.5 Fabrication Level 4
1.4.5.12.6 Delivery Level 4
1.4.5.12.7 On Site Level 4
1.4.5.13 Lightning & Grounding System Level 3
1.4.5.13.1 Inquiry and bidding Level 4
1.4.5.13.2 TBE Level 4
1.4.5.13.3 CBE Level 4
1.4.5.13.4 PO Level 4
1.4.5.13.5 Fabrication Level 4
1.4.5.13.6 Delivery Level 4
1.4.5.13.7 On Site Level 4
1.4.5.14 Lighting and Receptacle Level 3
1.4.5.14.1 Inquiry and bidding Level 4
1.4.5.14.2 TBE Level 4
1.4.5.14.3 CBE Level 4
1.4.5.14.4 PO Level 4
1.4.5.14.5 Fabrication Level 4
1.4.5.14.6 Delivery Level 4
1.4.5.14.7 On Site Level 4
1.4.5.15 Cable Tray and Accessories Level 3
1.4.5.15.1 Inquiry and bidding Level 4
1.4.5.15.2 TBE Level 4
1.4.5.15.3 CBE Level 4
1.4.5.15.4 PO Level 4
1.4.5.15.5 Fabrication Level 4
1.4.5.15.6 Delivery Level 4
1.4.5.15.7 On Site Level 4
1.4.5.16 Other Bulk Material Level 3
1.4.5.16.1 Inquiry and bidding Level 4
1.4.5.16.2 TBE Level 4
1.4.5.16.3 CBE Level 4
1.4.5.16.4 PO Level 4
1.4.5.16.5 Fabrication Level 4
1.4.5.16.6 Delivery Level 4
1.4.5.16.7 On Site Level 4
1.4.6 PROCESS SAFETY Level 2
1.4.6.1 Foam Pressure Proportioner + Foam Storage Tank Package Level 3
1.4.6.1.1 Inquiry and bidding Level 4
1.4.6.1.2 TBE Level 4
1.4.6.1.3 CBE Level 4
1.4.6.1.4 PO Level 4
1.4.6.1.5 Fabrication Level 4
1.4.6.1.6 Delivery Level 4
1.4.6.1.7 On Site Level 4
1.4.6.2 Foam Chamber Level 3
1.4.6.2.1 Inquiry and bidding Level 4
1.4.6.2.2 TBE Level 4
1.4.6.2.3 CBE Level 4
1.4.6.2.4 PO Level 4
1.4.6.2.5 Fabrication Level 4

18/29
WBS CODE WBS NAME LEVEL

1.4.6.2.6 Delivery Level 4


1.4.6.2.7 On Site Level 4
1.4.6.3 Portable foam package Level 3
1.4.6.3.1 Inquiry and bidding Level 4
1.4.6.3.2 TBE Level 4
1.4.6.3.3 CBE Level 4
1.4.6.3.4 PO Level 4
1.4.6.3.5 Fabrication Level 4
1.4.6.3.6 Delivery Level 4
1.4.6.3.7 On Site Level 4
1.4.6.4 Foam sprinkler Level 3
1.4.6.4.1 Inquiry and bidding Level 4
1.4.6.4.2 TBE Level 4
1.4.6.4.3 CBE Level 4
1.4.6.4.4 PO Level 4
1.4.6.4.5 Fabrication Level 4
1.4.6.4.6 Delivery Level 4
1.4.6.4.7 On Site Level 4
1.4.6.5 Fire Hydrant Level 3
1.4.6.5.1 Inquiry and bidding Level 4
1.4.6.5.2 TBE Level 4
1.4.6.5.3 CBE Level 4
1.4.6.5.4 PO Level 4
1.4.6.5.5 Fabrication Level 4
1.4.6.5.6 Delivery Level 4
1.4.6.5.7 On Site Level 4
1.4.6.6 Hydrant Box Package Level 3
1.4.6.6.1 Inquiry and bidding Level 4
1.4.6.6.2 TBE Level 4
1.4.6.6.3 CBE Level 4
1.4.6.6.4 PO Level 4
1.4.6.6.5 Fabrication Level 4
1.4.6.6.6 Delivery Level 4
1.4.6.6.7 On Site Level 4
1.4.6.7 Fire extinguisher Level 3
1.4.6.7.1 Inquiry and bidding Level 4
1.4.6.7.2 TBE Level 4
1.4.6.7.3 CBE Level 4
1.4.6.7.4 PO Level 4
1.4.6.7.5 Fabrication Level 4
1.4.6.7.6 Delivery Level 4
1.4.6.7.7 On Site Level 4
1.4.6.8 Dry chemical powder ABC 9 kg Level 3
1.4.6.8.1 Inquiry and bidding Level 4
1.4.6.8.2 TBE Level 4
1.4.6.8.3 CBE Level 4
1.4.6.8.4 PO Level 4
1.4.6.8.5 Fabrication Level 4
1.4.6.8.6 Delivery Level 4
1.4.6.8.7 On Site Level 4
1.4.6.9 Dry chemical powder BC 9 kg Level 3
1.4.6.9.1 Inquiry and bidding Level 4
1.4.6.9.2 TBE Level 4
1.4.6.9.3 CBE Level 4
1.4.6.9.4 PO Level 4

19/29
WBS CODE WBS NAME LEVEL

1.4.6.9.5 Fabrication Level 4


1.4.6.9.6 Delivery Level 4
1.4.6.9.7 On Site Level 4
1.4.6.10 CO 2 Extinguisher 9 kg Level 3
1.4.6.10.1 Inquiry and bidding Level 4
1.4.6.10.2 TBE Level 4
1.4.6.10.3 CBE Level 4
1.4.6.10.4 PO Level 4
1.4.6.10.5 Fabrication Level 4
1.4.6.10.6 Delivery Level 4
1.4.6.10.7 On Site Level 4
1.4.6.11 Wheel Dry chemical BC 75 kg Level 3
1.4.6.11.1 Inquiry and bidding Level 4
1.4.6.11.2 TBE Level 4
1.4.6.11.3 CBE Level 4
1.4.6.11.4 PO Level 4
1.4.6.11.5 Fabrication Level 4
1.4.6.11.6 Delivery Level 4
1.4.6.11.7 On Site Level 4

1.4.6.12 Emergency eye wash and Shower Level 3

1.4.6.12.1 Inquiry and bidding Level 4

1.4.6.12.2 TBE Level 4

1.4.6.12.3 CBE Level 4

1.4.6.12.4 PO Level 4

1.4.6.12.5 Fabrication Level 4

1.4.6.12.6 Delivery Level 4

1.4.6.12.7 On Site Level 4

1.4.6.13 Oil spill kit Level 3

1.4.6.13.1 Inquiry and bidding Level 4

1.4.6.13.2 TBE Level 4

1.4.6.13.3 CBE Level 4

1.4.6.13.4 PO Level 4

1.4.6.13.5 Fabrication Level 4

1.4.6.13.6 Delivery Level 4

1.4.6.13.7 On Site Level 4

1.5 CONSTRUCTION Level 1


1.5.1 CIVIL Level 2
1.5.1.1 Soil Clearing & Grading Level 3
1.5.1.2 Pekerjaan Penimbunan, Pemadatan dan Perataan Lahan Level 3
1.5.1.3 Fuel Storage Tank Foundation (TK-101/102/103/104) Kap.500 KL Level 3
1.5.1.3.1 TK-101 Level 4
1.5.1.3.1.1 Pemancangan pondasi Level 5
1.5.1.3.1.1.1 Pemancangan Level 6
1.5.1.3.1.1.2 Bobok tiang pancang yang muncul ke tanah Level 6
1.5.1.3.1.2 PDA test + report Level 5
1.5.1.3.1.3 Pembesian dan pengecoran pondasi Level 5
1.5.1.3.1.3.1 Pemasangan bowplank Level 6
1.5.1.3.1.3.2 Pabrikasi pembesian slab Level 6
1.5.1.3.1.3.3 Pondasi siring + urugan dan pemadatan pondasi Level 6
1.5.1.3.1.3.4 Lantai kerja Level 6
1.5.1.3.1.3.5 Pemasangan pembesian slab Level 6
1.5.1.3.1.3.6 Bekisting slab Level 6
1.5.1.3.1.3.7 Pengecoran slab Level 6
1.5.1.3.1.3.8 Pengeringan beton pondasi + uji beton umur 14 hari Level 6
1.5.1.3.1.4 Pengaspalan pondasi Level 5

20/29
WBS CODE WBS NAME LEVEL

1.5.1.3.2 TK-102 Level 4


1.5.1.3.2.1 Pemancangan pondasi Level 5
1.5.1.3.2.1.1 Pemancangan Level 6
1.5.1.3.2.1.2 Bobok tiang pancang yang muncul ke tanah Level 6
1.5.1.3.2.2 PDA test + report Level 5
1.5.1.3.2.3 Pembesian dan pengecoran pondasi Level 5
1.5.1.3.2.3.1 Pemasangan bowplank Level 6
1.5.1.3.2.3.2 Pabrikasi pembesian slab Level 6
1.5.1.3.2.3.3 Pondasi siring + urugan dan pemadatan pondasi Level 6
1.5.1.3.2.3.4 Lantai kerja Level 6
1.5.1.3.2.3.5 Pemasangan pembesian slab Level 6
1.5.1.3.2.3.6 Bekisting slab Level 6
1.5.1.3.2.3.7 Pengecoran slab Level 6
1.5.1.3.2.3.8 Pengeringan beton pondasi + uji beton umur 14 hari Level 6
1.5.1.3.2.4 Pengaspalan pondasi Level 5
1.5.1.3.3 TK-103 Level 4
1.5.1.3.3.1 Pemancangan pondasi Level 5
1.5.1.3.3.1.1 Pemancangan Level 6
1.5.1.3.3.1.2 Bobok tiang pancang yang muncul ke tanah Level 6
1.5.1.3.3.2 PDA test + report Level 5
1.5.1.3.3.3 Pembesian dan pengecoran pondasi Level 5
1.5.1.3.3.3.1 Pemasangan bowplank Level 6
1.5.1.3.3.3.2 Pabrikasi pembesian slab Level 6
1.5.1.3.3.3.3 Pondasi siring + urugan dan pemadatan pondasi Level 6
1.5.1.3.3.3.4 Lantai kerja Level 6
1.5.1.3.3.3.5 Pemasangan pembesian slab Level 6
1.5.1.3.3.3.6 Bekisting slab Level 6
1.5.1.3.3.3.7 Pengecoran slab Level 6
1.5.1.3.3.3.8 Pengeringan beton pondasi + uji beton umur 14 hari Level 6
1.5.1.3.3.4 Pengaspalan pondasi Level 5
1.5.1.3.4 TK-104 Level 4
1.5.1.3.4.1 Pemancangan pondasi Level 5
1.5.1.3.4.1.1 Pemancangan Level 6
1.5.1.3.4.1.2 Bobok tiang pancang yang muncul ke tanah Level 6
1.5.1.3.4.2 PDA test + report Level 5
1.5.1.3.4.3 Pembesian dan pengecoran pondasi Level 5
1.5.1.3.4.3.1 Pemasangan bowplank Level 6
1.5.1.3.4.3.2 Pabrikasi pembesian slab Level 6
1.5.1.3.4.3.3 Pondasi siring + urugan dan pemadatan pondasi Level 6
1.5.1.3.4.3.4 Lantai kerja Level 6
1.5.1.3.4.3.5 Pemasangan pembesian slab Level 6
1.5.1.3.4.3.6 Bekisting slab Level 6
1.5.1.3.4.3.7 Pengecoran slab Level 6
1.5.1.3.4.3.8 Pengeringan beton pondasi + uji beton umur 14 hari Level 6
1.5.1.3.4.4 Pengaspalan pondasi Level 5
1.5.1.4 Fire Water Storage Tank Foundation (TK-705) Kap.700 KL Level 3
1.5.1.4.1 Pemancangan pondasi Level 4
1.5.1.4.1.1 Pemancangan Level 5
1.5.1.4.1.2 Bobok tiang pancang yang muncul ke tanah Level 5
1.5.1.4.2 PDA test + report Level 4
1.5.1.4.3 Pembesian dan pengecoran pondasi Level 4
1.5.1.4.3.1 Pemasangan bowplank Level 5
1.5.1.4.3.2 Pabrikasi pembesian slab Level 5
1.5.1.4.3.3 Pondasi siring + urugan dan pemadatan pondasi Level 5
1.5.1.4.3.4 Lantai kerja Level 5

21/29
WBS CODE WBS NAME LEVEL

1.5.1.4.3.5 Pemasangan pembesian slab Level 5


1.5.1.4.3.6 Bekisting slab Level 5
1.5.1.4.3.7 Pengecoran slab Level 5
1.5.1.4.3.8 Pengeringan beton pondasi + uji beton umur 14 hari Level 5
1.5.1.4.4 Pengaspalan pondasi Level 4
1.5.1.5 Office Building include Control Room Level 3
1.5.1.5.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.5.2 Pekerjaan sloof Level 4
1.5.1.5.3 Pekerjaan kolom Level 4
1.5.1.5.4 Pekerjaan dinding Level 4
1.5.1.5.5 Pekerjaan balok Level 4
1.5.1.5.6 Pekerjaan atap dan talang Level 4
1.5.1.5.7 Pekerjaan lantai Level 4
1.5.1.5.8 Pekerjaan plumbing Level 4
1.5.1.5.9 Pekerjaan ceiling Level 4
1.5.1.5.10 Pekerjaan tangga, pintu dan jendela Level 4
1.5.1.5.11 Pengecatan, arsitektur & finishing Level 4
1.5.1.6 Fire Pump House Level 3
1.5.1.6.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.6.2 Pekerjaan sloof Level 4
1.5.1.6.3 Pekerjaan kolom Level 4
1.5.1.6.4 Pekerjaan dinding Level 4
1.5.1.6.5 Pekerjaan balok Level 4
1.5.1.6.6 Pekerjaan atap dan talang Level 4
1.5.1.6.7 Pekerjaan lantai Level 4
1.5.1.6.8 Pekerjaan plumbing Level 4
1.5.1.6.9 Pekerjaan ceiling Level 4
1.5.1.6.10 Pekerjaan pintu dan jendela Level 4
1.5.1.6.11 Pengecatan, arsitektur & finishing Level 4
1.5.1.7 Electrical House (MCC & Deg Building) Level 3
1.5.1.7.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.7.2 Pekerjaan sloof Level 4
1.5.1.7.3 Pekerjaan kolom Level 4
1.5.1.7.4 Pekerjaan dinding Level 4
1.5.1.7.5 Pekerjaan balok Level 4
1.5.1.7.6 Pekerjaan atap dan talang Level 4
1.5.1.7.7 Pekerjaan lantai Level 4
1.5.1.7.8 Pekerjaan plumbing Level 4
1.5.1.7.9 Pekerjaan ceiling Level 4
1.5.1.7.10 Pekerjaan pintu dan jendela Level 4
1.5.1.7.11 Pengecatan, arsitektur & finishing Level 4
1.5.1.8 Full Loading - Unloading Shed Level 3
1.5.1.8.1 Pekerjaan pondasi Level 4
1.5.1.8.2 Pekerjaan sloof Level 4
1.5.1.8.3 Pekerjaan lantai Level 4
1.5.1.8.4 Pekerjaan atap dan talang Level 4
1.5.1.8.5 Pekerjaan struktur steel Level 4
1.5.1.8.6 Pengecatan dan finishing Level 4

1.5.1.9 Trafo Shelter Level 3

1.5.1.9.1 Pekerjaan pondasi Level 4

1.5.1.9.2 Pekerjaan sloof Level 4

1.5.1.9.3 Pekerjaan lantai Level 4

1.5.1.9.4 Pekerjaan pondasi trafo Level 4

1.5.1.9.5 Pekerjaan atap dan talang Level 4

22/29
WBS CODE WBS NAME LEVEL

1.5.1.9.6 Pekerjaan struktur trafo shelter Level 4


1.5.1.9.7 Pengecatan dan finishing Level 4

1.5.1.10 Parking Area Shelter Level 3


1.5.1.10.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.10.2 Pekerjaan sloof Level 4
1.5.1.10.3 Pekerjaan lantai Level 4
1.5.1.10.4 Pekerjaan atap dan talang Level 4
1.5.1.10.5 Pekerjaan struktur steel Level 4
1.5.1.10.6 Pengecatan dan finishing Level 4
1.5.1.11 Parking Area Refueller Shelter Level 3
1.5.1.11.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.11.2 Pekerjaan sloof Level 4
1.5.1.11.3 Pekerjaan lantai Level 4
1.5.1.11.4 Pekerjaan atap dan talang Level 4
1.5.1.11.5 Pekerjaan struktur steel Level 4
1.5.1.11.6 Pengecatan dan finishing Level 4
1.5.1.12 Workshop & Warehouse (include maintenance) Building Level 3
1.5.1.12.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.12.2 Pekerjaan sloof Level 4
1.5.1.12.3 Pekerjaan kolom Level 4
1.5.1.12.4 Pekerjaan dinding Level 4
1.5.1.12.5 Pekerjaan balok Level 4
1.5.1.12.6 Pekerjaan atap dan talang Level 4
1.5.1.12.7 Pekerjaan lantai Level 4
1.5.1.12.8 Pekerjaan plumbing Level 4
1.5.1.12.9 Pekerjaan ceiling Level 4
1.5.1.12.10 Pekerjaan pintu dan jendela Level 4
1.5.1.12.11 Pengecatan, arsitektur & finishing Level 4
1.5.1.13 Shelter for Pump Diesel Oil Tank Level 3
1.5.1.13.1 Pekerjaan pondasi Level 4
1.5.1.13.2 Pekerjaan sloof Level 4
1.5.1.13.3 Pekerjaan lantai Level 4
1.5.1.13.4 Pekerjaan pondasi pompa Level 4
1.5.1.13.5 Pekerjaan atap dan talang Level 4
1.5.1.13.6 Pekerjaan struktur pump shelter Level 4
1.5.1.13.7 Pengecatan dan finishing Level 4
1.5.1.14 APAR Shelter Level 3
1.5.1.14.1 Pekerjaan pondasi Level 4
1.5.1.14.2 Pekerjaan sloof Level 4
1.5.1.14.3 Pekerjaan lantai Level 4
1.5.1.14.4 Pekerjaan atap Level 4
1.5.1.14.5 Pekerjaan struktur steel Level 4
1.5.1.14.6 Pengecatan dan finishing Level 4

1.5.1.15 B3 Warehouse Shelter Level 3

1.5.1.15.1 Pekerjaan pondasi Level 4

1.5.1.15.2 Pekerjaan sloof Level 4

1.5.1.15.3 Pekerjaan kolom Level 4

1.5.1.15.4 Pekerjaan dinding Level 4

1.5.1.15.5 Pekerjaan balok Level 4

1.5.1.15.6 Pekerjaan atap dan talang Level 4

1.5.1.15.7 Pekerjaan lantai Level 4

1.5.1.15.8 Pekerjaan struktur steel Level 4

1.5.1.15.9 Pengecatan dan finishing Level 4

23/29
WBS CODE WBS NAME LEVEL

1.5.1.16 Guard House Level 3


1.5.1.16.1 Pekerjaan pondasi Level 4
1.5.1.16.2 Pekerjaan sloof Level 4
1.5.1.16.3 Pekerjaan kolom Level 4
1.5.1.16.4 Pekerjaan dinding Level 4
1.5.1.16.5 Pekerjaan balok Level 4
1.5.1.16.6 Pekerjaan atap dan talang Level 4
1.5.1.16.7 Pekerjaan lantai Level 4
1.5.1.16.8 Pekerjaan plumbing Level 4
1.5.1.16.9 Pekerjaan ceiling Level 4
1.5.1.16.10 Pekerjaan pintu dan jendela Level 4
1.5.1.16.11 Pengecatan, arsitektur & finishing Level 4
1.5.1.17 Fuel Pump Shed for Delivery Pumps Level 3
1.5.1.17.1 Pekerjaan pondasi Level 4
1.5.1.17.2 Pekerjaan sloof Level 4
1.5.1.17.3 Pekerjaan kolom Level 4
1.5.1.17.4 Pekerjaan dinding Level 4
1.5.1.17.5 Pekerjaan balok Level 4
1.5.1.17.6 Pekerjaan atap dan talang Level 4
1.5.1.17.7 Pekerjaan lantai Level 4
1.5.1.17.8 Pekerjaan plumbing Level 4
1.5.1.17.9 Pekerjaan ceiling Level 4
1.5.1.17.10 Pekerjaan pintu dan jendela Level 4
1.5.1.17.11 Pekerjaan struktur steel Level 4
1.5.1.17.12 Pengecatan, arsitektur & finishing Level 4
1.5.1.18 Fuel Pump Shed for Receiving Pumps Level 3
1.5.1.18.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.18.2 Pekerjaan sloof Level 4
1.5.1.18.3 Pekerjaan kolom Level 4
1.5.1.18.4 Pekerjaan dinding Level 4
1.5.1.18.5 Pekerjaan balok Level 4
1.5.1.18.6 Pekerjaan atap dan talang Level 4
1.5.1.18.7 Pekerjaan lantai Level 4
1.5.1.18.8 Pekerjaan plumbing Level 4
1.5.1.18.9 Pekerjaan ceiling Level 4
1.5.1.18.10 Pekerjaan pintu dan jendela Level 4
1.5.1.18.11 Pekerjaan struktur steel Level 4
1.5.1.18.12 Pengecatan, arsitektur & finishing Level 4
1.5.1.19 Drain Tank Shed Level 3
1.5.1.19.1 Pekerjaan pondasi (pemancangan) Level 4
1.5.1.19.2 Pekerjaan sloof Level 4
1.5.1.19.3 Pekerjaan kolom Level 4
1.5.1.19.4 Pekerjaan dinding Level 4
1.5.1.19.5 Pekerjaan balok Level 4
1.5.1.19.6 Pekerjaan atap dan talang Level 4
1.5.1.19.7 Pekerjaan lantai Level 4
1.5.1.19.8 Pekerjaan plumbing Level 4
1.5.1.19.9 Pekerjaan ceiling Level 4
1.5.1.19.10 Pekerjaan struktur steel Level 4
1.5.1.19.11 Pekerjaan pintu dan jendela Level 4
1.5.1.19.12 Pengecatan, arsitektur & finishing Level 4
1.5.1.20 Shelter for Gate in-out for Bridger & Refueller Level 3
1.5.1.21 Pump Foundation Level 3
1.5.1.22 Filter Pump Foundation Level 3
1.5.1.23 Deg (Genset) Foundation Level 3

24/29
WBS CODE WBS NAME LEVEL

1.5.1.24 Trafo Foundation Level 3


1.5.1.25 Pekerjaan sipil lainnya Level 3
1.5.2 MECHANICAL Level 2
1.5.2.1 Pumps Level 3
1.5.2.1.1 Install Receiving Pump Level 4
1.5.2.1.2 Install Supply Pump Level 4
1.5.2.1.3 Install Drain Pump Level 4
1.5.2.1.4 Install Sulvage Pump Level 4
1.5.2.1.5 Install Diesel Fuel Receiving Pump Level 4
1.5.2.1.6 Install Fire Water Pump Level 4
1.5.2.1.7 Install Jockey Pump Level 4
1.5.2.1.8 Install Utility Water Pump Level 4
1.5.2.1.9 Install Booster Pump Fire Tank Level 4
1.5.2.1.10 Install Booster Pump Utility Tank Level 4
1.5.2.1.11 Install Submersible Pump Drain Pit Level 4
1.5.2.1.12 Install Deepwell Pump Fire Tank Level 4
1.5.2.1.13 Install Deepwell Pump Utility Tank Level 4
1.5.2.2 Packaged Unit Level 3
1.5.2.2.1 Install Diesel Fuel Dispenser Level 4
1.5.2.2.2 Install Recovery Vessel Level 4
1.5.2.2.3 Install Sampling Jar Level 4
1.5.2.2.4 Install Drain Collector Level 4
1.5.2.2.5 Install Receiving Filter Separator Level 4
1.5.2.2.6 Install Supply Filter Separator Level 4
1.5.2.2.7 Install Drain Filter Separator Level 4
1.5.2.2.8 Install Drain Pit Blower & Fan Level 4
1.5.2.2.9 Install Ducting Blower & Fan Level 4
1.5.2.2.10 Install Receiving Aviation Hose Loading Level 4
1.5.2.2.11 Install Supply Aviation Hose Loading Level 4
1.5.2.2.12 Install Receiving Fuel (Diesel) Hose Loading Level 4
1.5.2.2.13 Install Supply Sulvage Hose Loading Level 4
1.5.2.2.14 Install Receiving Drain Hose Loading Level 4
1.5.2.2.15 Install Floating Suction Level 4
1.5.2.2.16 Install CPI (Corrugated Plate Interceptor) Oil Separator Level 4
1.5.2.3 Vessel/torage Level 3
1.5.2.3.1 Install Drain Tank Level 4
1.5.2.3.2 Install Diesel Fuel Tank Level 4
1.5.2.4 Tanks Level 3
1.5.2.4.1 Jet Fuel Storage Tank 500 KL Level 4
1.5.2.4.1.1 TK-101 Level 5
1.5.2.4.1.1.1 Pabrikasi dan pemasangan tangki Level 6
1.5.2.4.1.1.1.1 Pekerjaan pemotongan bottom plate dan annular plate Level 7
1.5.2.4.1.1.1.2 Pengerolan shell plate 1 s.d shell plate 5 Level 7
1.5.2.4.1.1.1.3 Pemasangan bottom plate dan annular plate Level 7
1.5.2.4.1.1.1.4 Pemasangan dan penyetelan shell plate 1 s.d shell plate 2 Level 7
1.5.2.4.1.1.1.5 Pengelasan vertikal shell plate 1 Level 7
1.5.2.4.1.1.1.6 Pengelasan vertikal shell plate 2 Level 7
1.5.2.4.1.1.1.7 Pengelasan horizontal shell plate 1 dengan shell plate 2 Level 7
1.5.2.4.1.1.1.8 Pemasangan dan penyetelan shell plate 3 Level 7
1.5.2.4.1.1.1.9 Pengelasan vertikal shell plate 3 Level 7
1.5.2.4.1.1.1.10 Pengelasan horizontal shell plate 2 dengan shell plate 3 Level 7
1.5.2.4.1.1.1.11 Pemasangan dan penyetelan shell plate 4 Level 7
1.5.2.4.1.1.1.12 Pengelasan vertikal shell plate 4 Level 7
1.5.2.4.1.1.1.13 Pengelasan horizontal shell plate 3 dengan shell plate 4 Level 7
1.5.2.4.1.1.1.14 Pemasangan dan penyetelan shell plate 5 Level 7

25/29
WBS CODE WBS NAME LEVEL

1.5.2.4.1.1.1.15 Pengelasan vertikal shell plate 5 Level 7


1.5.2.4.1.1.1.16 Pengelasan horizontal shell plate 4 dengan shell plate 5 Level 7
1.5.2.4.1.1.1.17 Pemasangan dan penyetelan top angle Level 7
1.5.2.4.1.1.1.18 Pengelasan top angle Level 7
1.5.2.4.1.1.1.19 Pemasangan dan pengelasan frame roof Level 7
1.5.2.4.1.1.1.20 Pemasangan dan penyetelan roof plate Level 7
1.5.2.4.1.1.1.21 Pengelasan roof plate + pemasangan nozzle acc tangki Level 7
1.5.2.4.1.1.1.22 Pengelasan shell plate 1 dengan annular plate Level 7
1.5.2.4.1.1.1.23 Pabrikasi, pemasangan dan pengelasan nozzle Level 7
1.5.2.4.1.1.1.24 Pemasangan dan pengelasan tangga dan accessories lainnya Level 7
1.5.2.4.1.1.1.25 Pemasangan grounding Level 7
1.5.2.4.1.1.2 Pengujian NDT Final Level 6
1.5.2.4.1.1.3 Pengisian air untuk hydrotest Level 6
1.5.2.4.1.1.4 Hydrotest dan dewatering Level 6
1.5.2.4.1.1.5 Pengeringan tangki dan pengecatan dalam dan luar tangki Level 6
1.5.2.4.1.1.6 Tera tangki oleh DIMET Level 6
1.5.2.4.1.1.7 Pemasangan accessories tangki + koordinasi dengan teknisi Level 6
1.5.2.4.1.2 TK-102 Level 5
1.5.2.4.1.2.1 Pabrikasi dan pemasangan tangki Level 6
1.5.2.4.1.2.1.1 Pekerjaan pemotongan bottom plate dan annular plate Level 7
1.5.2.4.1.2.1.2 Pengerolan shell plate 1 s.d shell plate 5 Level 7
1.5.2.4.1.2.1.3 Pemasangan bottom plate dan annular plate Level 7
1.5.2.4.1.2.1.4 Pemasangan dan penyetelan shell plate 1 s.d shell plate 2 Level 7
1.5.2.4.1.2.1.5 Pengelasan vertikal shell plate 1 Level 7
1.5.2.4.1.2.1.6 Pengelasan vertikal shell plate 2 Level 7
1.5.2.4.1.2.1.7 Pengelasan horizontal shell plate 1 dengan shell plate 2 Level 7
1.5.2.4.1.2.1.8 Pemasangan dan penyetelan shell plate 3 Level 7
1.5.2.4.1.2.1.9 Pengelasan vertikal shell plate 3 Level 7
1.5.2.4.1.2.1.10 Pengelasan horizontal shell plate 2 dengan shell plate 3 Level 7
1.5.2.4.1.2.1.11 Pemasangan dan penyetelan shell plate 4 Level 7
1.5.2.4.1.2.1.12 Pengelasan vertikal shell plate 4 Level 7
1.5.2.4.1.2.1.13 Pengelasan horizontal shell plate 3 dengan shell plate 4 Level 7
1.5.2.4.1.2.1.14 Pemasangan dan penyetelan shell plate 5 Level 7
1.5.2.4.1.2.1.15 Pengelasan vertikal shell plate 5 Level 7
1.5.2.4.1.2.1.16 Pengelasan horizontal shell plate 4 dengan shell plate 5 Level 7
1.5.2.4.1.2.1.17 Pemasangan dan penyetelan top angle Level 7
1.5.2.4.1.2.1.18 Pengelasan top angle Level 7
1.5.2.4.1.2.1.19 Pemasangan dan pengelasan frame roof Level 7
1.5.2.4.1.2.1.20 Pemasangan dan penyetelan roof plate Level 7
1.5.2.4.1.2.1.21 Pengelasan roof plate + pemasangan nozzle acc tangki Level 7
1.5.2.4.1.2.1.22 Pengelasan shell plate 1 dengan annular plate Level 7
1.5.2.4.1.2.1.23 Pabrikasi, pemasangan dan pengelasan nozzle Level 7
1.5.2.4.1.2.1.24 Pemasangan dan pengelasan tangga dan accessories lainnya Level 7
1.5.2.4.1.2.1.25 Pemasangan grounding Level 7
1.5.2.4.1.2.2 Pengujian NDT Final Level 6
1.5.2.4.1.2.3 Pengisian air untuk hydrotest Level 6
1.5.2.4.1.2.4 Hydrotest dan dewatering Level 6
1.5.2.4.1.2.5 Pengeringan tangki dan pengecatan dalam dan luar tangki Level 6
1.5.2.4.1.2.6 Tera tangki oleh DIMET Level 6
1.5.2.4.1.2.7 Pemasangan accessories tangki + koordinasi dengan teknisi Level 6
1.5.2.4.1.3 TK-103 Level 5
1.5.2.4.1.3.1 Pabrikasi dan pemasangan tangki Level 6
1.5.2.4.1.3.1.1 Pekerjaan pemotongan bottom plate dan annular plate Level 7
1.5.2.4.1.3.1.2 Pengerolan shell plate 1 s.d shell plate 5 Level 7
1.5.2.4.1.3.1.3 Pemasangan bottom plate dan annular plate Level 7

26/29
WBS CODE WBS NAME LEVEL

1.5.2.4.1.3.1.4 Pemasangan dan penyetelan shell plate 1 s.d shell plate 2 Level 7
1.5.2.4.1.3.1.5 Pengelasan vertikal shell plate 1 Level 7
1.5.2.4.1.3.1.6 Pengelasan vertikal shell plate 2 Level 7
1.5.2.4.1.3.1.7 Pengelasan horizontal shell plate 1 dengan shell plate 2 Level 7
1.5.2.4.1.3.1.8 Pemasangan dan penyetelan shell plate 3 Level 7
1.5.2.4.1.3.1.9 Pengelasan vertikal shell plate 3 Level 7
1.5.2.4.1.3.1.10 Pengelasan horizontal shell plate 2 dengan shell plate 3 Level 7
1.5.2.4.1.3.1.11 Pemasangan dan penyetelan shell plate 4 Level 7
1.5.2.4.1.3.1.12 Pengelasan vertikal shell plate 4 Level 7
1.5.2.4.1.3.1.13 Pengelasan horizontal shell plate 3 dengan shell plate 4 Level 7
1.5.2.4.1.3.1.14 Pemasangan dan penyetelan shell plate 5 Level 7
1.5.2.4.1.3.1.15 Pengelasan vertikal shell plate 5 Level 7
1.5.2.4.1.3.1.16 Pengelasan horizontal shell plate 4 dengan shell plate 5 Level 7
1.5.2.4.1.3.1.17 Pemasangan dan penyetelan top angle Level 7
1.5.2.4.1.3.1.18 Pengelasan top angle Level 7
1.5.2.4.1.3.1.19 Pemasangan dan pengelasan frame roof Level 7
1.5.2.4.1.3.1.20 Pemasangan dan penyetelan roof plate Level 7
1.5.2.4.1.3.1.21 Pengelasan roof plate + pemasangan nozzle acc tangki Level 7
1.5.2.4.1.3.1.22 Pengelasan shell plate 1 dengan annular plate Level 7
1.5.2.4.1.3.1.23 Pabrikasi, pemasangan dan pengelasan nozzle Level 7
1.5.2.4.1.3.1.24 Pemasangan dan pengelasan tangga dan accessories lainnya Level 7
1.5.2.4.1.3.1.25 Pemasangan grounding Level 7
1.5.2.4.1.3.2 Pengujian NDT Final Level 6
1.5.2.4.1.3.3 Pengisian air untuk hydrotest Level 6
1.5.2.4.1.3.4 Hydrotest dan dewatering Level 6
1.5.2.4.1.3.5 Pengeringan tangki dan pengecatan dalam dan luar tangki Level 6
1.5.2.4.1.3.6 Tera tangki oleh DIMET Level 6
1.5.2.4.1.3.7 Pemasangan accessories tangki + koordinasi dengan teknisi Level 6
1.5.2.4.1.4 TK-104 Level 5
1.5.2.4.1.4.1 Pabrikasi dan pemasangan tangki Level 6
1.5.2.4.1.4.1.1 Pekerjaan pemotongan bottom plate dan annular plate Level 7
1.5.2.4.1.4.1.2 Pengerolan shell plate 1 s.d shell plate 5 Level 7
1.5.2.4.1.4.1.3 Pemasangan bottom plate dan annular plate Level 7
1.5.2.4.1.4.1.4 Pemasangan dan penyetelan shell plate 1 s.d shell plate 2 Level 7
1.5.2.4.1.4.1.5 Pengelasan vertikal shell plate 1 Level 7
1.5.2.4.1.4.1.6 Pengelasan vertikal shell plate 2 Level 7
1.5.2.4.1.4.1.7 Pengelasan horizontal shell plate 1 dengan shell plate 2 Level 7
1.5.2.4.1.4.1.8 Pemasangan dan penyetelan shell plate 3 Level 7
1.5.2.4.1.4.1.9 Pengelasan vertikal shell plate 3 Level 7
1.5.2.4.1.4.1.10 Pengelasan horizontal shell plate 2 dengan shell plate 3 Level 7
1.5.2.4.1.4.1.11 Pemasangan dan penyetelan shell plate 4 Level 7
1.5.2.4.1.4.1.12 Pengelasan vertikal shell plate 4 Level 7
1.5.2.4.1.4.1.13 Pengelasan horizontal shell plate 3 dengan shell plate 4 Level 7
1.5.2.4.1.4.1.14 Pemasangan dan penyetelan shell plate 5 Level 7
1.5.2.4.1.4.1.15 Pengelasan vertikal shell plate 5 Level 7
1.5.2.4.1.4.1.16 Pengelasan horizontal shell plate 4 dengan shell plate 5 Level 7
1.5.2.4.1.4.1.17 Pemasangan dan penyetelan top angle Level 7
1.5.2.4.1.4.1.18 Pengelasan top angle Level 7
1.5.2.4.1.4.1.19 Pemasangan dan pengelasan frame roof Level 7
1.5.2.4.1.4.1.20 Pemasangan dan penyetelan roof plate Level 7
1.5.2.4.1.4.1.21 Pengelasan roof plate + pemasangan nozzle acc tangki Level 7
1.5.2.4.1.4.1.22 Pengelasan shell plate 1 dengan annular plate Level 7
1.5.2.4.1.4.1.23 Pabrikasi, pemasangan dan pengelasan nozzle Level 7
1.5.2.4.1.4.1.24 Pemasangan dan pengelasan tangga dan accessories lainnya Level 7
1.5.2.4.1.4.1.25 Pemasangan grounding Level 7

27/29
WBS CODE WBS NAME LEVEL

1.5.2.4.1.4.2 Pengujian NDT Final Level 6


1.5.2.4.1.4.3 Pengisian air untuk hydrotest Level 6
1.5.2.4.1.4.4 Hydrotest dan dewatering Level 6
1.5.2.4.1.4.5 Pengeringan tangki dan pengecatan dalam dan luar tangki Level 6
1.5.2.4.1.4.6 Tera tangki oleh DIMET Level 6
1.5.2.4.1.4.7 Pemasangan accessories tangki + koordinasi dengan teknisi Level 6
1.5.2.4.2 Fire Water Tank 700 KL Level 4
1.5.2.4.2.1 TK-750 Level 5
1.5.2.4.2.1.1 Pabrikasi dan pemasangan tangki Level 6
1.5.2.4.2.1.1.1 Pekerjaan pemotongan bottom plate dan annular plate Level 7
1.5.2.4.2.1.1.2 Pengerolan shell plate 1 s.d shell plate 6 Level 7
1.5.2.4.2.1.1.3 Pemasangan bottom plate dan annular plate Level 7
1.5.2.4.2.1.1.4 Pemasangan dan penyetelan shell plate 1 s.d shell plate 2 Level 7
1.5.2.4.2.1.1.5 Pengelasan vertikal shell plate 1 Level 7
1.5.2.4.2.1.1.6 Pengelasan vertikal shell plate 2 Level 7
1.5.2.4.2.1.1.7 Pengelasan horizontal shell plate 1 dengan shell plate 2 Level 7
1.5.2.4.2.1.1.8 Pemasangan dan penyetelan shell plate 3 Level 7
1.5.2.4.2.1.1.9 Pengelasan vertikal shell plate 3 Level 7
1.5.2.4.2.1.1.10 Pengelasan horizontal shell plate 2 dengan shell plate 3 Level 7
1.5.2.4.2.1.1.11 Pemasangan dan penyetelan shell plate 4 Level 7
1.5.2.4.2.1.1.12 Pengelasan vertikal shell plate 4 Level 7
1.5.2.4.2.1.1.13 Pengelasan horizontal shell plate 3 dengan shell plate 4 Level 7
1.5.2.4.2.1.1.14 Pemasangan dan penyetelan shell plate 5 Level 7
1.5.2.4.2.1.1.15 Pengelasan vertikal shell plate 5 Level 7
1.5.2.4.2.1.1.16 Pengelasan horizontal shell plate 4 dengan shell plate 5 Level 7
1.5.2.4.2.1.1.17 Pemasangan dan penyetelan shell plate 6 Level 7
1.5.2.4.2.1.1.18 Pengelasan vertikal shell plate 6 Level 7
1.5.2.4.2.1.1.19 Pengelasan horizontal shell plate 5 dengan shell plate 6 Level 7

1.5.2.4.2.1.1.20 Pemasangan dan penyetelan top angle Level 7

1.5.2.4.2.1.1.21 Pengelasan top angle Level 7

1.5.2.4.2.1.1.22 Pemasangan dan pengelasan frame roof Level 7

1.5.2.4.2.1.1.23 Pemasangan dan penyetelan roof plate Level 7

1.5.2.4.2.1.1.24 Pengelasan roof plate + pemasangan nozzle acc tangki Level 7

1.5.2.4.2.1.1.25 Pengelasan shell plate 1 dengan annular plate Level 7

1.5.2.4.2.1.1.26 Pabrikasi, pemasangan dan pengelasan nozzle Level 7

1.5.2.4.2.1.1.27 Pemasangan dan pengelasan tangga dan accessories lainnya Level 7

1.5.2.4.2.1.1.28 Pemasangan grounding Level 7

1.5.2.4.2.1.2 Pengujian NDT Final Level 6

1.5.2.4.2.1.3 Pengisian air untuk hydrotest Level 6

1.5.2.4.2.1.4 Hydrotest dan dewatering Level 6

1.5.2.4.2.1.5 Pengeringan tangki dan pengecatan dalam dan luar tangki Level 6

1.5.2.4.2.1.6 Tera tangki oleh DIMET Level 6

1.5.2.4.2.1.7 Pemasangan accessories tangki + koordinasi dengan teknisi Level 6

1.5.2.4.3 Install Utility Water Tank Level 4

1.5.3 PIPING Level 2


1.5.3.1 PIPING FOR AVTUR Level 3
1.5.3.1.1 Pengeceran pipa Level 4
1.5.3.1.2 Penyetelan pipa dan fitting Level 4
1.5.3.1.3 Pengelasan pipa dan fitting Level 4
1.5.3.1.4 Pemasangan pipa diatas support Level 4
1.5.3.1.5 Pemasangan valve dan accessories lainnya Level 4
1.5.3.1.6 Pengecatan dan finishing pipa Level 4
1.5.4 INSTALLATION INSTRUMENT Level 2
1.5.5 INSTALLATION ELECTRICAL Level 2