JOB SAFETY ANALYSIS

Job: Date: 20.12.2021. JSA Team:

Identification and removal of Sonu:

unwanted cables above the roof of Raja:

the lab building Vetrivel:

Muflih:

Document no: Approval:

ASC/P165/JSA/15 Magesh.Jabel :

Naveed/Rupam :

Work Location & Equipment:

Admin building and Lab building

Hand tools

Required Personal Protective Equipment for the above job (PPE):

Safety Helmet, Full sleeve coverall, Safety Shoe, Hand Gloves, Safety Eye Glass, Covid 19 Mask, Full body

safety harness

Activity:

 Planning, Preparation, and obtaining a permit.

 Mobilization of equipment and materials

 Identifying cable

 Pulling out the unwanted cables.

 Wind up & Housekeeping.

QF-HSSE-030
JOB SAFETY ANALYSIS

Activity Potential Hazards / Consequence Risk Control Measures

 Planning, Preparation, and  Lack of information.  Write clearly about the

obtaining permits. work.

 Lack of communication.  Get required work permit

 Lack of planning from authorized person &

they aware work is going on.

 Use of damaged tools and ladder  Proper inspection tools and

ladder

 Mobilization of hand tools.  Manual Handling  Don’t carry weight over

20kg

 Lift the material close to the

body.

 Slip, trip, and falls  Make sure access is clear

from all obstructions.

 Working area shall be clear

from obstructions

 Fall from cage ladder  Use a safety harness while

climbing on a ladder

 Identifying cables  Cuts, injuries  Use proper hand gloves

 Activity carried out by


trained personnel.

QF-HSSE-030
JOB SAFETY ANALYSIS

 Assistance of SEOT
Technicians

 Working at height  Parapet edge protection

 Electric shock.  Assistance of SEOT


technician

 Trained electrician carrying


out the activity.

 Pulling out the unwanted  Manual handling  Workers shall be taught in


cable laying and pulling
cables techniques including the
requirement for ensuring
good manual handling
techniques.

 Wind up & Housekeeping  Tools left in the work area  All tools and materials are
checked with a list while
 Removed cables winding up
 Avoid storing materials on
walkways or ingress or
egress.
 Store the materials at
designated places

QF-HSSE-030