Professional Documents
Culture Documents
Construction Site Supervision
Construction Site Supervision
1
2/7/2023
2
2/7/2023
3
2/7/2023
4
2/7/2023
Form Works
Concrete and Reinforcement Works
Material Types
Mixing Proportion
Mixing Quality
Water/Cement Ratio
Placing
Vibration
Curing
Reinforcement, Types, Quality Control
10
5
2/7/2023
11
12
6
2/7/2023
13
14
7
2/7/2023
15
16
8
2/7/2023
17
18
9
2/7/2023
19
20
10
2/7/2023
21
11
2/7/2023
23
The Contract
A contract between parties is basically an...
24
12
2/7/2023
ELEMENTS OF CONTRACTS
Mutual Agreement and Genuine Intention
Offer & Acceptance
Capacity to Contract
Consideration in a Contract
Lawful Object of a Contract
Contract Time
The absence of any one of these elements is sufficient
to void a contract…
25
Construction Contracts
Construction Contracts therefore have certain elements. Such as:
An agreement ..’meeting of minds’
Terms & Conditions
Allocation of Risks between
Employer (Client) & Contractor
Duties, Responsibilities & Obligations
Role of the ‘Engineer/Architect’
Default & remedies
26
13
2/7/2023
Construction Contracts
The construction contract documents define the
agreement b/n the owner & the contractor.
It is a two-party agreement that does not include the
designer (For DBB project delivery).
27
28
14
2/7/2023
29
(4) Special (particular) conditions of contract (different bonds, retention, Schedules & its
revision, price adjustment etc)
30
15
2/7/2023
31
16
2/7/2023
33
34
17
2/7/2023
35
36
18
2/7/2023
37
38
19
2/7/2023
39
40
20
2/7/2023
41
42
21
2/7/2023
43
44
22
2/7/2023
23
2/7/2023
Checklist Preparation
From your previous lectures and CSS class discussion prepare
compact checklist for:
Excavation
Re bar
Formwork
Concreting
Plastering
Painting
48
24
2/7/2023
49
50
25
2/7/2023
2.Interpersonal skills
The way information is transmitted can affect the way
it is understood.
The way the inspector transmits guidance to the contract
will contribute either to a good understanding and
reception of the information or create barriers
hindering timely completion.
Therefore, the inspector develop good interpersonal
communication skills, in speaking, listening etc. in
the process of carrying out inspection duties.
52
26
2/7/2023
a) Communication skills
Communicating =exchange of information.
The sender is responsible for making the information clear,
unambiguous, & complete so that the receiver can receive it
correctly.
The receiver is responsible for making sure that the information is received in
its entirety and understood correctly.
53
b) Negotiating
Negotiating involves conferring with others to reach an agreement.
Agreements may be negotiated directly or with assistance;
mediation and arbitration are two types of assisted negotiation.
Negotiations occur around many issues, at many times and at many levels
of the project.
During the course of a typical project, project staff is likely to
negotiate for any or all of the following:
Scope, cost, and schedule objectives.
Changes to scope, cost, or schedule.
Contract terms and conditions.
Assignments.
Resources.
54
27
2/7/2023
C) Problem Solving
Problem solving involves a combination of problem
definition & decision-making. Problem definition requires
distinguishing b/n causes & symptoms.
Problems may be internal (a key employee is reassigned to
another project) or external (a permit required to begin
work is delayed).
Problems may be technical (differences of opinion about the best way to
design a product), managerial (a functional group is not producing
according to plan), or interpersonal (personality or style clashes).
55
c) Problem Solving
Decision-making includes analyzing the problem to
identify viable solutions, & then making a choice
from among them.
Decisions can be made or obtained from the
customer, from the team, or from a functional
manager. Once made, decisions must be
implemented.
Decisions also have a time element to them the
“right” decision may not be the “best” decision if it is
made too early or too late.
56
28
2/7/2023
d) Analytical skills
In the course of carrying out his tasks the inspector is required to
make decisions that may affect the progress of the work.
57
3.Legal
The supervisor assigned in any construction
projects must be familiar with the condition of
contract, codes, standards and other related laws
of the country…
58
29
2/7/2023
Assist
Facilitate
59
The Inspector …
The inspector must have a keen eye, be observant & able
to see critically.
To do this a thorough knowledge of the procedures for
executing the particular work he is inspecting is necessary.
Detailed knowledge of the plans & specifications for the particular
work is also a vitally important part of the work.
He must also be familiar with any revisions or amendments done
to the original documents, and the reason for such changes and
their incorporation into the works.
60
30
2/7/2023
61
62
31
2/7/2023
63
64
32
2/7/2023
66
33
2/7/2023
67
68
34
2/7/2023
69
70
35
2/7/2023
Measurement
71
Quality in Construction…
Construction project quality is the fulfillment of the
owner’s needs per:
Defined scope of works
Specified schedule
72
36
2/7/2023
73
74
37
2/7/2023
75
Specifications are
Written descriptions of the required quality of the
built product and its component products.
76
38
2/7/2023
Purpose of Specifications
Specifications are written descriptions which define quality.
Together they express the designer's intentions.
The specification links the drawings with the GCC.
It complements, without duplication, the information in the
drawings or the general conditions of contract.
Drawings are graphic descriptions which primarily define
quantity, position and sometimes quality.
77
39
2/7/2023
79
Quality Inspection:
An inspection is a specific examination, testing, and
formal evaluation exercise & overall appraisal of a
process, product, or service to ascertain if it conforms to
established requirements.
It involves measurements, tests, observation (visual
inspection) & gauges.
Inspection of the finished products
80
40
2/7/2023
81
41
2/7/2023
84
42
2/7/2023
85
86
43
2/7/2023
87
88
44
2/7/2023
89
Inspection Procedures
Establishment of detailed inspection procedures.
Site Procedures manual….Forms
90
45
2/7/2023
Inspection Procedures
Establishment of who will be responsible
For calling the laboratory
For pickup of samples
For testing,
Who will call for special inspectors when needed, and
To whom such outside people will be directly responsible on the
project.
91
Inspection Procedures
Identification of who must physically prepare samples for
testing, the contractor or the inspector;
Establishment of ground rules for acceptable timing of
work operations after sampling and testing;
Mandatory scheduling must be provided to
Make samples and tests,
92
46
2/7/2023
93
47
2/7/2023
95
96
48
2/7/2023
97
98
49
2/7/2023
Testing
Testing is limited to those laboratory or field tests actually
called for in the specifications. Such tests may be performed by:
The contractor,
The architect/engineer,
The owner, or
Commercial testing laboratories.
The specifications determine which items are to be
tested, which tests and procedures apply, and the
required levels of performance.
The specification also determines who should perform the test.
99
100
50
2/7/2023
Experience Qualification
A requirement that a firm performing a certain type of work
have an established reputation for the successful completion
of similar work elsewhere for a specified amount of time.
The use of an experience requirement is limited to those fields
requires a considerable amount of previous experience.
Examples of such fields of work include:
Metal Curtain Walls
Foundation Piles
Dewatering
Precast Architectural Concrete
Calking & Sealing
Spray-on Fire Protection
Laboratory Equipment
Mechanical & Electrical Equipment
101
51
2/7/2023
103
104
52
2/7/2023
105
106
53
2/7/2023
Testing
Testing is limited to those laboratory or field tests actually
called for in the specifications. Such tests may be performed by:
The contractor,
The architect/engineer,
The owner, or
Commercial testing laboratories.
The specifications determine which items are to be
tested, which tests and procedures apply, and the
required levels of performance.
The specification also determines who should perform the test.
107
108
54
2/7/2023
Warranties; Guarantees
Two types of warranties are recognized under the law:
Implied warranties
Express warranties
The term implied warranties means that the goods must be capable of
passing in trade under the contract description & are fit for the
purpose intended.
Express warranties are those that are specifically set forth in the contract
itself; they are in common use for many construction contracts.
An Express Warranty is a means of achieving good procurement
results by making the contractor responsible for its work and for
failures of its work during some part of its useful life.
Warranties are generally for packaged items such as water heaters &
compressors.
109
55
2/7/2023
111
56
2/7/2023
113
114
57
2/7/2023
A Few Facts:
The first week on each new site is the most dangerous time.
Accidents are more frequent at the end of the day.
Small building jobs are the most risky.
Construction Accidents
falls from height
trapped by something collapsing or overturning
struck by a moving vehicle
contact with electricity or electrical discharge
struck by a flying/falling object during machine lifting of materials
contact with moving machinery or material being machined
exposure to a hot or harmful substance
115
116
58
2/7/2023
117
Lethal Ladders:
Ladders kill a lot of people.
Make sure the ladder is:
Right for the job. Wood scaffolding or a cherry picker be better
in good shape
Secured near the top
On a firm base
Always have a firm grip on the ladder & keep a good balance
Never allow more than one person on a ladder
Use tool belts or hand lines to carry objects.
Do not lean out from the ladder in any direction
If you have a fear of heights –don’t climb a ladder
118
59
2/7/2023
119
Excavation Work.
If you want to avoid being buried alive apply these rules:
All excavations deeper than 1.25 meters MUST be shored or
battered.
Excavations deeper than 2 meters MUST have a guard rail or
barrier
Vehicles working too close to the side the trench or rubble piled
of the trench on the sides may cause collapse.
Make sure the excavation is inspected daily
Make sure you know where any underground pipes & cables are,
before you hit them.
Remember: There is no safe ground that “will not collapse”. Trench sides
can collapse without warning
120
60
2/7/2023
Electricity
Good practice with electricity on site:
Treat electricity with respect
Check constantly that cables are damaged or worn
Keep trailing cables off the ground & away from water
Never overload or use makeshift plugs and fuses
121
122
61
2/7/2023
PPE on-site
124
62
2/7/2023
125
63
2/7/2023
127
128
64
2/7/2023
Payment certificate
129
65
2/7/2023
132
66
2/7/2023
Cause of Variations
Causes of Variations were grouped under four categories:
1) Employer Related Variations,
2) Consultants Related Variations,
3) Contractor Related Variations &
4) Other Variations
133
67
2/7/2023
68
2/7/2023
69
2/7/2023
139
70
2/7/2023
141
142
71
2/7/2023
143
144
72
2/7/2023
145
Cause of Variations:
Others Reasons for Variations
Weather Conditions:
Safety Considerations:
Change In Government Regulations:
Change In Economic Conditions:
Socio-cultural Factors:
Unforeseen Problems:
146
73
2/7/2023
147
148
74
2/7/2023
Schedule of payments
Completion date or
149
150
75
2/7/2023
151
152
76
2/7/2023
153
Constructive Changes
Causes for constructive change:
Defective plans & specifications
Engineer’s interpretation
Higher standard of performance than specified
Improper inspection & rejection
Change in the method of performance
Change in the construction sequence
Impossibility/impracticability of performance
154
77
2/7/2023
155
156
78
2/7/2023
157
158
79
2/7/2023
159
Brief description
Descriptive drawings.
80