CARRIAGE

Note: 1 The rates are applicable to carriage of material on pacca roads only.
For kacha roads an allowance of 25% extra shall be allowed for 2nd and subsequent mileage (Km) rates. Rate
upto 1st mile (1st Km) is however common to both kacha and pacca roads.

Note: 2 For hilly areas 25% above the rates in the plain areas shall be allowed for total mileage (Km) covered.

Note: 3 In case of articles longer than 15 ft. (4.6 m) carried in trucks, the following rates shall be allowed:-

i) Above 15 ft. to 25 ft. (4.6 to 7.6 m) :- Total rates to be paid for 15 ft. to 25 ft. (4.6 to 7.6 m) length will be 1.5 times of the
rate given in the Composite Schedule of Rates.

ii) Above 25 ft. (7.6 m) :- The total rate to be paid for above 25 ft. (7.6 m) length will be 2 times of the rate given in the
Composite Schedule of Rates.

The length measured shall not be the actual length, but the length of the form of consignment as actually
received.

Note: 4 The term 'mile' (Km) whenever used is to mean statute mile (Km).

Note: 5 The rates include loading and unloading of material from the conveyance and stacking as directed.

Note: 6 The rates for carriage by boat or steamer shall be the same as by any other mechanical means on lan
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1 Carriage of 100 Cft. (2.83 cu.m) of all materials like stone 16.1
aggregate, spawl, kankar lime (unslaked), surkhi, etc. or
150 Cft. (4.25 cu.m) of timber, by truck or by any other
means owned by the contractor.

1st chain (1st 30 m) Chain 59.95 30 59.95


2nd chain (2nd 30 m) " 10.85 Metre 10.85
3rd to 10th chain (60 to 300 m) " 7.10 " 7.10
1000 to 5000 ft. (300 to 1500 m) 1000 ft. 67.10 300 Metre 67.10

a) Upto 50 Kilometers Distance %cft / 50 KM 525 %cft / 50 KM 600


b) From 51 Kilometers to 100 kilometers distance %cft / KM 5.90 %cft / KM 7.00
c) From 101 Kilometers to 200 Kilometers Distance %cft / KM 5.30 %cft / KM 6.50
c) From 201 Kilometers to 300 Kilometers Distance %cft / KM 4.80 %cft / KM 6.00
d)Beyond 300 kilometers %cft / KM 5.00

Chap-1 (Carriage) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

2 Carriage of 5 tons of all material like coal, stone lime 16.1 Cement carried in containers other
(unslaked), etc. B.G. Rail fastenings, points and crossing, than bags will be paid according to
Bridge Girders, pipes, sheets, Rail, M.S. bars, etc. etc. this item. The word "pipes" covers
by truck or any other means owned by the contractor. G.I,C.I,R.C.C. and P.C.C.

1st chain (1st 30 m) Chain 59.95 30 59.95


2nd chain (2nd 30 m) " 10.85 Metre 10.85
3rd to 10th chain (60 to 300 m) " 7.10 7.10

1000 to 5000 ft. (300 to 1500 m) 1000 Ft. 67.10 300 67.10
Metre

1st Km Km 106.65
1st mile Mile 170.65
2nd Km " 24.65
2nd mile " 39.45
3rd Km Km 22.15
3rd mile Mile 35.40
4th Km " 20.00
4th mile " 32.00
5th Km " 18.40
5th mile " 29.40
6th Km " 16.90
6th mile " 27.00
7th Km and subsequent kilometres " 10.55
7th mile and subsequent miles " 16.90

3 Carriage of 100 maunds of fuel wood by truck 16.1


or any other means owned by the contractor:

1st chain (1st 30 m) Chain 59.95 30 M 59.95


2nd chain (2nd 30 m) " 10.85 " 10.85
3rd to 10th chain (60 to 300 m) " 7.10 " 7.10

1000 to 5000 ft. (300 to 1500 m) 1000 ft 67.10 300 M 67.10

1st Km Km 106.65
1st mile Mile 170.65
2nd Km " 24.65
2nd mile " 39.45
3rd Km " 22.15
3rd mile " 35.40
4th Km " 20.00

Chap-1 (Carriage) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

4th mile " 32.00


5th Km " 18.40
5th mile " 29.40
6th Km " 16.90
6th mile " 27.00
7th Km and subsequent kilometres " 10.55
7th mile and subsequent miles " 16.90

4 Carriage of 1000 Nos. bricks 10"x5"x3" (250x125x75 mm) ditto Reduce the rate by 33% in case of
or 1000 Nos. tiles 12"x6"x2" (300x150x50 mm) by truck or carriage of 1000 Nos. tiles size
any other means owned by the contractor :- 12"x6"x1¼" (300 x 150 x 30 mm).

1st chain (1st 30 m) Chain 59.95 30 M 59.95


2nd chain (2nd 30 m) " 10.85 " 10.85
3rd to 10th chain (60 to 300 m) " 7.10 " 7.10

1000 to 5000 ft. (300 to 1500 m) 1000 Ft 67.10 300 M 67.10

1st Km Km 106.65
1st mile Mile 170.65
2nd Km " 24.65
2nd mile " 39.45
3rd Km " 22.15
3rd mile " 35.40
4th Km " 20.00
4th mile " 32.00
5th Km " 18.40
5th mile " 29.40
6th Km " 16.90
6th mile " 27.00
7th Km and subsequent kilometres " 10.55
7th mile and subsequent miles " 16.90

5 Carriage of 100 cft. (2.83 cu.m) of all material like stone 16.1 Material trolly to be supplied by the
aggregate, spawl, kankar lime(unslaked), surkhi, etc. o Government and maintained and run
150 cft. (4.25 cu.m) of timber, by means of material trolly by the contractor.

1st chain (1st 30 m) Chain 59.95 30 M 59.95


2nd chain to 10th chain (2nd 30 m to 300 m) " 10.85 " 10.85

1000 to 5000 ft. (300 to 1500 m) 1000 Ft. 67.10 300 M 67.10

1st Km Km 87.45
1st mile Mile 139.95
2nd Km " 29.60

Chap-1 (Carriage) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

2nd mile " 47.35


3rd Km " 25.00
3rd mile " 40.00
4th Km 20.00
4th mile 32.00
5th Km 15.05
5th mile 29.40
6th Km 13.80
6th mile 27.00
7th Km and subsequent kilometres 8.65
7th mile and subsequent miles 16.90

6 Carriage of 5 tons of all material like coal, stone lim 16.1 Material trolly to be supplied by the
(unslaked), etc. B.G. Rail fastening, points and crossing Government and maintained and run
Bridge girders, pipes, sheets, Rail, M.S. bars, etc. etc. b by the contractor.
means of material trolly

1st chain (1st 30 m) Chain 59.95 30 M 59.95


2nd chain (2nd 30 m) " 10.85 " 10.85

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 67.10 300 M 67.10

1st Km Km 87.45
1st mile Mile 139.95
2nd Km " 29.60
2nd mile " 47.35
3rd Km " 25.00
3rd mile and subsequent miles " 40
4th Km 20.00
4th mile 32.00
5th Km 18.40
5th mile 29.40
6th Km 16.90
6th mile 27.00
7th Km and subsequent kilometres 10.55
7th mile and subsequent miles 16.90
7 Carriage of 100 maunds of fuel wood, by means o ditto Material trolly to be supplied
material trolly. by the Government and
maintained and run by the
1st chain (1st 30 m) Chain 59.95 30 M 59.95 contractor.
2nd chain (2nd 30 m) " 10.85 " 10.85

1000 to 5000 ft. (300 to 1500 m) 1000 Ft 67.10 300 M 67.10

1st Km Km 87.45
1st mile Mile 139.95
2nd Km " 29.60
2nd mile " 47.35

Chap-1 (Carriage) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

3rd Km and subsequent kilometers " 25.00


3rd mile subsequent miles " 40.00
4th Km 20.00
4th mile 32.00
5th Km 18.40
5th mile 29.40
6th Km 16.90
6th mile 27.00
7th Km and subsequent kilometres 10.55
7th mile and subsequent miles 16.90

8 Carriage of 1000 Nos. tiles 12"x6"x2" (300x150x50 mm), ditto Material trolly to be supplied by the
by means of material trolly. Government and maintained and run
by the contractor.
1st chain (1st 30 m) Chain 59.95 30 M 59.95
2nd chain (2nd 30 m) " 10.85 " 10.85

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 67.10 300 M 67.10 16.1

1st Km Km 87.45
1st mile Mile 139.95
2nd Km " 29.60
2nd mile " 47.35
3rd Km and subsequent kilometers. " 25.00
3rd mile subsequent miles " 40.00
4th Km 20.00
4th mile 32.00
5th Km 18.40
5th mile 29.40
6th Km 16.90
6th mile 27.00
7th Km and subsequent kilometres 10.55
7th mile and subsequent miles 16.90

9 Carriage of 1000 No. bricks, 9"x4½"x3" ditto


(225x113x75 mm) or 8"x4"x4" (200x100x100
mm) (nominal)

1st chain (1st 30 m) Chain 49.12 30 M 5.90


2nd chain (2nd 30 m) " 9.40 3.65
3rd to 10th chain (60 to 300 m) " 5.83
34.35
1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 54.94 300 M

1st Km Km 87.45

Chap-1 (Carriage) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1st mile Mile 139.90


2nd Km " 20.20
2nd mile " 32.35
3rd Km " 18.70
3rd mile " 29.95
4th Km " 16.40
4th mile " 26.25
5th Km " 15.05
5th mile " 24.10
6th Km " 13.80
6th mile " 22.10
7th Km and subsequent kilometres " 8.65
7th mile and subsequent miles " 13.85

10 Carriage of 1000 No. tiles 9"x4½"x1½" 16.1


(225x113x38 mm).

1st chain (1st 30 m) Chain 29.64 30 M 29.64 16.1


2nd chain (2nd 30 m) " 5.36 " 5.36
3rd to 10th chain (60 to 300 m) " 3.48 " 3.48

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 33.19 300 M 33.19

1st Km Km 52.80
1st mile Mile 84.45
2nd Km " 12.20
2nd mile " 19.55
3rd Km " 10.90
3rd mile " 17.40
4th Km " 9.90
4th mile " 15.85
5th Km " 9.10
5th mile " 14.55
6th Km " 8.35
6th mile " 13.35
7th Km and subsequent kilometres " 5.20
7th mile and subsequent miles " 8.35

11 Carriage of 1 Cwt. (50 Kg) cement in bags ditto

1st chain (1st 30 m) Chain 1.13 30 M 1.13


2nd chain (2nd 30 m) " 0.13 " 0.13
3rd to 10th chain (60 to 300 m) " 0.07 " 0.07

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 0.66 300 M 0.66

1st Km Km 1.30
1st mile Mile 2.10

Chap-1 (Carriage) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

2nd Km " 0.40


2nd mile " 0.60
3rd Km and subsequent kilometers " 0.20
3rd mile subsequent miles " 0.30

12 Carriage of 100 Nos. empty cement bags including 16.1


bundling.

1st 1000 (300 m) ft. 0/00 Ft. 16.46 300 M 16.46


1000 to 5000 (300 to 1500 m) ft. " 2.05 " 2.05

1st Km Km 3.20
1st mile Mile 5.15
2nd Km to 6th Km Km 1.20
2nd mile to 6th mile Mile 1.95
7th Km and subsequent kilometres " 1.30
7th mile and subsequent miles " 2.05

13 Carriage of 100 (2.83 cu.m) cft. of Sarkanda or pilchi, frash ditto Previous lead of collection not
or brushwood, by boat or road :- to be deducted from the next
lead of carriage.

1st chain (1st 30 m) Chain 24.53 30 M 24.53


2nd chain (2nd 30 m) " 10.85 " 10.85
3rd to 10th chain (60 to 300 m) " 3.48 " 3.48

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 27.57 300 M 27.57

1st Km Km 46.95
1st mile Mile 75.10
2nd Km " 34.45
2nd mile " 55.15
3rd Km " 28.75
3rd mile " 46.00
4th Km " 21.00
4th mile " 33.60
5th Km " 17.45
5th mile " 27.90
6th Km 13.80
6th mile 22.10
7th Km and subsequent kilometres 8.65
7th mile and subsequent miles 13.85

14 Carriage of light machinery weighing upto 3 tonne Ton Tonne ditto


upto 1000 ft. (300 metre) 0/00 ft. 199.45 300 M 199.45

Chap-1 (Carriage) Page 7


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

Execeeding 1000 to 5000 ft (300 to 1500metre) 1000 ft. 48.33 " 48.33

1st Km Km 104.95
1st mile Mile 167.90
2nd Km " 19.50
2nd mile " 31.20
3rd Km " 18.40
3rd mile " 29.40
4th Km " 14.70
4th mile " 23.55
5th Km " 14.95
5th mile " 23.90
6th Km " 11.45
6th mile " 18.35
7th Km and subsequent kilometres " 8.25
7th mile and subsequent miles " 13.20

15 Carriage of small consignments weighing upto 5 maunds 16.1 For consignment weighing 5 to 10
(job rates) : maunds, rate be increased by 25%;
and for consignments weighing 10
Consig- to 20 maunds, rate be increased by
Upto 1000 ft. (300 metre) ment/ 16.20 Consign- 16.20 100%.
1000 ft. ment/
Exceeding 1000 to 5000 ft. (300 to 1500 1000 ft. 11.11 300 M 11.11
metre)

1st Km Consign- 16.45


1st mile Consign- 26.30 ment/ Km
2nd Km and subsequent kilometres ment/Mile 3.05
2nd mile and subsequent miles " 4.85 "

16 Carriage of consignments job.

i) Cooly load for distance:-


Each Each
a) Upto 5 Km Consignment 32.65 Consignment 32.65
b) Above 5 to 13 Km " 69.85 " 69.85

ii) Carriage of consignments odd jobs. Each Each


a) Donkey load for distance upto 500 feet. Consignment 10.85 Consignment 10.85
b) Upto 1000 feet. " 16.45 " 16.45
c) Upto ½ Mile/ 0.8 Km " 20.80 " 20.80
d) Upto one Mile/ 1.6 Km " 26.00 " 26.00
e) Upto three Miles/ 4.8 Km " 45.95 " 45.95
f) Exceeding 3 Miles/ 16 km " 82.25 " 82.25

Chap-1 (Carriage) Page 8


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

Each Each
iii) Cart load for a distance :- Consign- Consig-
ment nment
a) upto 4 Miles/ 6.4 Km " 89.85 " 89.85
b) Exceeding 4 Miles(6.4 Km) to10 Miles(16 Km) " 163.55 " 163.55

iv) Camel load for a distance:-

a) upto 4 Miles/ 6.4 Km.) " 66.45 " 66.45


b) exceeding 4 to 12 mills (6.4 Km to 19.2 Km) " 100.75 " 100.75

17 Hire charges of:- 1. This item will be allowed with


prior concurrence of Superintending
i) truck (10 Ton Capacity) Per 2000.00 Per 2000.00 Engineer.
day day 2. The rate includes pay of driver
ii) tractor with trolly " 6144.00 " 1000.00 and cleaner only. The repairs shall
be the responsibility of the owner
iii) tractor without trolly " 5240.00 " 800.00 and the cost of lubrication, fuel,
loading and unloading shall be paid
by the borrower.

18 Carriage of bitumen, tar or other lubricants, in drums: 16.1

1st Km Per 18.80


1st mile Per 28.00 Tonne
2nd Km Ton " 4.35
2nd mile " 4.60
3rd Km " " 3.90
3rd mile 7.35
4th Km " 3.55
4th mile
5th Km " 3.25
5th mile
6th Km " 2.95
6th mile
7th Km and subsequent kilometres " 2.70
7th mile and subsequent miles

19 Carriage of Asbestos cement pipes BSS Class 'B" with


comet joint and rubber ring, including loading, unloading
and stacking (rate per 100 Rft. (30 m pipes):-

i) 3" (75 mm) i/d pipes:-


1st chain (1st 30 m) Chain 2.35 30 M 2.35

Chap-1 (Carriage) Page 9


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

2nd chain (2nd 30 m) " 0.45 " 0.45


3rd to 10th chain (60 to 300 m) " 0.30 " 0.30

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 2.65 300 M 2.65

1st Km Km 4.20
1st mile Mile 6.75
2nd Km " 0.95
2nd mile " 1.55
3rd Km " 0.90
3rd mile " 1.40
4th Km " 0.80
4th mile " 1.25
5th Km " 0.70
5th mile " 1.15
6th Km " 0.65
6th mile " 1.05
7th Km and subsequent kilometres " 0.40
7th mile and subsequent miles " 0.65

ii) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 3.10 30 M 3.10


2nd chain (2nd 30 m) " 0.55 " 0.55
3rd to 10th chain (60 to 300 m) " 0.35 " 0.35

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 3.45 300 M 3.45

1st Km Km 5.50
1st mile Mile 8.80
2nd Km " 1.30
2nd mile " 2.05
3rd Km " 1.15
3rd mile " 1.85
4th Km " 1.05
4th mile " 1.65
5th Km " 0.95
5th mile " 1.50
6th Km " 0.90
6th mile " 1.40
7th Km and subsequent kilometres " 0.55
7th mile and subsequent miles " 0.85

iii) 6" (150 mm) i/d pipes:-


1st chain (1st 30 m) Chain 4.65 30 M 4.65

Chap-1 (Carriage) Page 10


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

2nd chain (2nd 30 m) " 0.85 " 0.85


3rd to 10th chain (60 to 300 m) " 0.55 " 0.55

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 5.20 300 M 5.20
1st Km Km 8.30
1st mile Mile 13.25
2nd Km " 1.90
2nd mile " 3.05
3rd Km " 1.70
3rd mile " 2.75
4th Km " 1.55
4th mile " 2.50
5th Km " 1.45
5th mile " 2.30
6th Km " 1.30
6th mile " 2.10
7th Km and subsequent kilometres " 0.80
7th mile and subsequent miles " 1.30

iv) 8" (200 mm) i/d pipes:


Chain 7.85
1st chain (1st 30 m) " 1.40 30 M 1.40
2nd chain (2nd 30 m) " 0.95 " 0.95
3rd to 10th chain (60 to 300 m) " 0.95
0/00 Ft. 8.80
1000 to 5000 ft. (300 to 1500 m) 300 M 8.80

1st Km Km 14.00
1st mile Mile 22.40
2nd Km " 3.25
2nd mile " 5.20
3rd Km " 2.90
3rd mile " 4.65
4th Km " 2.65
4th mile " 4.20
5th Km " 2.40
5th mile " 3.85
6th Km " 2.20
6th mile " 3.55
7th Km and subsequent kilometres " 1.40
7th mile and subsequent miles " 2.20

v) 10" (250 mm) i/d pipes:-

1st chain (1st 30 m) Chain 10.55 30 M 10.55


2nd chain (2nd 30 m) " 1.90 " 1.90
3rd to 10th chain (60 to 300 m) " 1.25 " 1.25

Chap-1 (Carriage) Page 11


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 11.85 300 M 11.85

1st Km Km 18.80
1st mile Mile 30.10
2nd Km " 4.35
2nd mile " 6.95
3rd Km " 3.90
3rd mile " 6.25
4th Km Km 3.55
4th mile Mile 5.65
5th Km " 3.25
5th mile " 5.20
6th Km " 2.95
6th mile " 4.75
7th Km and subsequent kilometres " 1.90
7th mile and subsequent miles " 3.00

vi) 12" (300 mm) i/d pipes:

1st chain (1st 30 m) Chain 13.75 30 M 13.75


2nd chain (2nd 30 m) " 2.50 " 2.50
3rd to 10th chain (60 to 300 m) " 1.60 " 1.60

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 15.40 300 M 15.40

1st Km Km 24.45
1st mile Mile 39.15
2nd Km " 5.65
2nd mile " 9.05
3rd Km " 5.05
3rd mile " 8.10
4th Km " 4.60
4th mile " 7.35
5th Km " 4.20
5th mile " 6.75
6th Km " 3.90
6th mile " 6.20
7th Km and subsequent kilometres " 2.45
7th mile and subsequent miles " 3.90

vii) 16" (400 mm) i/d pipes:-


1st chain (1st 30 m) Chain 22.55 30 M 22.55
2nd chain (2nd 30 m) " 4.10 " 4.10
3rd to 10th chain (60 to 300 m) " 2.65 " 2.65

Chap-1 (Carriage) Page 12


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 25.20 300 M 25.20

1st Km Km 40.10
1st mile Mile 64.15
2nd Km " 9.30
2nd mile " 14.85
3rd Km " 8.30
3rd mile " 13.30
4th Km " 7.55
4th mile " 12.05
5th Km " 6.90
5th mile " 11.05
6th Km " 6.35
6th mile " 10.15
7th Km and subsequent kilometres " 3.95
7th mile and subsequent miles " 6.35

viii) 18" (450 mm) i/d pipes:-

1st chain (1st 30 m) Chain 28.95 30 M 28.95


2nd chain (2nd 30 m) " 5.25 " 5.25
3rd to 10th chain (60 to 300 m) " 3.40 " 3.40

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 32.40 300 M 32.40

1st Km Km 51.55
1st mile Mile 82.45
2nd Km " 11.90
2nd mile " 19.05
3rd Km " 10.70
3rd mile " 17.10
4th Km " 9.65
4th mile " 15.45
5th Km " 8.90
5th mile " 14.20
6th Km " 8.15
6th mile " 13.05
7th Km and subsequent kilometres " 5.10
7th mile and subsequent miles " 8.15

ix) 20" (500 mm) i/d pipes:-


1st chain (1st 30 m) Chain 30.75 30 M 30.75
2nd chain (2nd 30 m) " 5.55 " 5.55
3rd to 10th chain (60 to 300 m) " 3.65 " 3.65
1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 34.40 300 M 34.40

Chap-1 (Carriage) Page 13


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1st Km Km 54.70
1st mile Mile 87.50
2nd Km " 12.65
2nd mile " 20.25
3rd Km " 11.35
3rd mile " 18.15
4th Km " 10.25
4th mile " 16.40
5th Km " 9.40
5th mile " 15.05
6th Km " 8.65
6th mile " 13.85
7th Km and subsequent kilometres " 5.40
7th mile and subsequent miles " 8.65

x) 24" (600 mm) i/d pipes:-

1st chain (1st 30 m) Chain 34.05 30 M 34.05


2nd chain (2nd 30 m) " 6.15 " 6.15
3rd to 10th chain (60 to 300 m) " 4.00 " 4.00

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 38.10 300 M 38.10

1st Km Km 60.60
1st mile Mile 96.95
2nd Km " 14.05
2nd mile " 22.45
3rd Km " 12.55
3rd mile " 20.10
4th Km Km 11.40
4th mile Mile 18.20
5th Km " 10.45
5th mile " 16.70
6th Km " 9.60
6th mile " 15.35
7th Km and subsequent kilometres " 6.00
7th mile and subsequent miles " 9.60

20 Carriage of PVC pipes B.S.S. Class 'B' including loading,


unloading and stacking (Rate per 1000 ft.) (300 metre) :-

i) 3" (75 mm) i/d pipes:-

1st chain (1st 30 m) Chain 4.65 30 M 4.65

Chap-1 (Carriage) Page 14


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

2nd chain (2nd 30 m) " 0.85 " 0.85


3rd to 10th chain (60 to 300 m) " 0.55 " 0.55

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 5.20 300 M 5.20

1st Km Km 8.25
1st mile Mile 13.20
2nd Km " 1.90
2nd mile " 3.05
3rd Km " 1.70
3rd mile " 2.75
4th Km " 1.55
4th mile " 2.50
5th Km " 1.45
5th mile Mile 2.30
6th Km Km. 1.30
6th mile " 2.10
7th Km and subsequent kilometres " 0.80
7th mile and subsequent miles " 1.30

ii) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 7.15 30 M 7.15


2nd chain (2nd 30 m) " 1.30 " 1.30
3rd to 10th chain (60 to 300 m) " 0.85 " 0.85

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 8.00 300 M 8.00

1st Km Km 12.70
1st mile Mile 20.35
2nd Km " 2.95
2nd mile " 4.70
3rd Km " 2.65
3rd mile " 4.20
4th Km " 2.40
4th mile " 3.80
5th Km " 2.20
5th mile " 3.50
6th Km " 2.00
6th mile " 3.20
7th Km and subsequent kilometres " 1.25
7th mile and subsequent miles " 2.00

iii) 5" (125 mm) i/d pipes:-

Chap-1 (Carriage) Page 15


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1st chain (1st 30 m) Chain 9.75 30 M 9.75


2nd chain (2nd 30 m) " 1.75 " 1.75
3rd to 10th chain (60 to 300 m) " 1.15 " 1.15

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 10.90 300 M 10.90

1st Km Km 17.35
1st mile Mile 27.75
2nd Km " 4.00
2nd mile " 6.40
3rd Km " 3.60
3rd mile " 5.75
4th Km " 3.25
4th mile Mile 5.20
5th Km Km. 3.00
5th mile " 4.80
6th Km " 2.75
6th mile " 4.40
7th Km and subsequent kilometres " 1.70
7th mile and subsequent miles " 2.75

iv) 6" (150 mm) i/d pipes:

1st chain (1st 30 m) Chain 13.45 30 M 13.45


2nd chain (2nd 30 m) " 2.45 " 2.45
3rd to 10th chain (60 to 300 m) " 1.60 " 1.60

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 15.05 300 M 15.05

1st Km. Km. 23.90


1st mile Mile 38.25
2nd Km " 5.55
2nd mile " 8.85
3rd Km " 4.95
3rd mile " 7.95
4th Km " 4.50
4th mile " 7.20
5th Km " 4.15
5th mile " 6.60
6th Km " 3.80
6th mile " 6.05
7th Km and subsequent kilometres " 2.40
7th mile and subsequent miles " 3.80

v) 8" (200 mm) i/d pipes:-

Chap-1 (Carriage) Page 16


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1st chain (1st 30 m) Chain 23.55 30 M 23.55


2nd chain (2nd 30 m) " 4.25 " 4.25
3rd to 10th chain (60 to 300 m) " 2.80 " 2.80

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 26.40 300 M 26.40

1st Km Km 41.95
1st mile Mile 67.10
2nd Km " 9.70
2nd mile " 15.50
3rd Km " 8.70
3rd mile Mile 13.90
4th Km Km. 7.90
4th mile " 12.60
5th Km " 7.20
5th mile " 11.55
6th Km " 6.65
6th mile " 10.60
7th Km and subsequent kilometres " 4.15
7th mile and subsequent miles " 6.65

vi) 10" (250 mm) i/d pipes:-

1st chain (1st 30 m) Chain 36.55 30 M 36.55


2nd chain (2nd 30 m) " 6.60 " 6.60
3rd to 10th chain (60 to 300 m) " 4.30 " 4.30

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 40.90 300 M 40.90

1st Km Km 65.05
1st mile Mile 104.05
2nd Km " 15.05
2nd mile " 24.05
3rd Km " 13.50
3rd mile " 21.60
4th Km " 12.20
4th mile " 19.50
5th Km " 11.20
5th mile " 17.90
6th Km " 10.30
6th mile " 16.45
7th Km and subsequent kilometres " 6.45
7th mile and subsequent miles " 10.30

Chap-1 (Carriage) Page 17


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

vii) 12" (300 mm) i/d pipes:-

1st chain (1st 30 m) Chain 51.45 30 M 51.45


2nd chain (2nd 30 m) " 9.30 " 9.30
3rd to 10th chain (60 to 300 m) " 6.05 " 6.05

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 57.60 300 M 57.60

1st Km Km 91.55
1st mile Mile 146.50
2nd Km Km 21.20
2nd mile Mile 33.90
3rd Km " 19.00
3rd mile " 30.40
4th Km " 17.15
4th mile " 27.45
5th Km " 15.80
5th mile " 25.25
6th Km " 14.50
6th mile " 23.20
7th Km and subsequent kilometres " 9.05
7th mile and subsequent miles " 14.50

viii) 14" (350 mm) i/d pipes:-

1st chain (1st 30 m) Chain 66.95 30 M 66.95


2nd chain (2nd 30 m) " 12.10 " 12.10
3rd to 10th chain (60 to 300 m) " 7.90 " 7.90

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 74.95 300 M 74.95

1st Km Km 119.15
1st mile Mile 190.65
2nd Km " 27.55
2nd mile " 44.10
3rd Km " 24.70
3rd mile " 39.55
4th Km Km 22.35
4th mile Mile 35.75
5th Km " 20.55
5th mile " 32.85
6th Km " 18.90
6th mile " 30.20
7th Km and subsequent kilometres " 11.80
7th mile and subsequent miles " 18.90

Chap-1 (Carriage) Page 18


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

21 Carriage of PVC pipes B.S.S. Class 'D' including loading,


unloading and stacking (Rates per 1000 ft.):-

i) 2" (50 mm) i/d pipes:-

1st chain (1st 30 m) Chain 3.40 30 M 3.40


2nd chain (2nd 30 m) " 0.60 " 0.60
3rd to 10th chain (60 to 300 m) " 0.40 " 0.40

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 3.80 300 M 3.80

1st Km Km 6.05
1st mile Mile 9.65
2nd Km " 1.40
2nd mile " 2.25
3rd Km " 1.25
3rd mile " 2.00
4th Km " 1.15
4th mile " 1.80
5th Km " 1.05
5th mile " 1.65
6th Km " 0.95
6th mile " 1.55
7th Km and subsequent kilometres " 0.60
7th mile and subsequent miles " 0.95

ii) 2½" (63 mm) i/d pipes:-

1st chain (1st 30 m) Chain 5.25 30 M 5.25


2nd chain (2nd 30 m) " 0.95 " 0.95
3rd to 10th chain (60 to 300 m) " 0.60 " 0.60

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 5.90 300 M 5.90

1st Km Km 9.40
1st mile Mile 15.00
2nd Km " 2.15
2nd mile " 3.45
3rd Km " 1.95
3rd mile " 3.10
4th Km " 1.75
4th mile " 2.80
5th Km " 1.65
5th mile " 2.60

Chap-1 (Carriage) Page 19


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

6th Km " 1.50


6th mile " 2.40
7th Km and subsequent kilometres " 0.95
7th mile and subsequent miles " 1.50

iii) 3" (75 mm) i/d pipes:-

1st chain (1st 30 m) Chain 7.30 30 M 7.30


2nd chain (2nd 30 m) " 1.30 " 1.30
3rd to 10th chain (60 to 300 m) " 0.85 " 0.85

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 8.20 300 M 8.20

1st Km Km 13.00
1st mile Mile 20.80
2nd Km " 3.00
2nd mile " 4.80
3rd Km " 2.70
3rd mile " 4.30
4th Km " 2.45
4th mile " 3.90
5th Km Km 2.25
5th mile Mile 3.60
6th Km " 2.05
6th mile " 3.30
7th Km and subsequent kilometres " 1.30
7th mile and subsequent miles " 2.05

iv) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 12.10 30 M 12.10


2nd chain (2nd 30 m) " 2.20 " 2.20
3rd to 10th chain (60 to 300 m) " 1.45 " 1.45

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 13.55 300 M 13.55

1st Km Km 21.55
1st mile Mile 34.45
2nd Km " 4.95
2nd mile " 7.95
3rd Km " 4.45
3rd mile " 7.15
4th Km " 4.05
4th mile " 6.45
5th Km " 3.70
5th mile " 5.95

Chap-1 (Carriage) Page 20


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

6th Km " 3.40


6th mile " 5.45
7th Km and subsequent kilometres " 2.15
7th mile and subsequent miles " 3.40

v) 5" (125 mm) i/d pipes:-

1st chain (1st 30 m) Chain 18.10 30 M 18.10


2nd chain (2nd 30 m) " 3.25 " 3.25
3rd to 10th chain (60 to 300 m) " 2.15 " 2.15

1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 20.25 300 M 20.25

1st Km Km 32.20
1st mile Mile 51.50
2nd Km " 7.45
2nd mile " 11.90
3rd Km " 6.70
3rd mile " 10.70
4th Km " 6.05
4th mile " 9.65
5th Km " 5.55
5th mile " 8.85
6th Km " 5.10
6th mile " 8.15
7th Km and subsequent kilometres " 3.20
7th mile and subsequent miles " 5.10

vi) 6" (150 mm) i/d pipes:-

1st chain (1st 30 m) Chain 26.05 30 M 26.05


2nd chain (2nd 30 m) " 4.70 " 4.70
3rd to 10th chain (60 to 300 m) " 3.10 " 3.10
1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 29.15 300 M 29.15

1st Km Km 46.40
1st mile Mile 74.20
2nd Km " 10.70
2nd mile " 17.15
3rd Km " 9.65
3rd mile " 15.40
4th Km " 8.70
4th mile " 13.90
5th Km " 8.00

Chap-1 (Carriage) Page 21


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

5th mile " 12.80


6th Km " 7.35
6th mile " 11.75
7th Km and subsequent kilometres " 4.60
7th mile and subsequent miles " 7.35

22 Hand shunting loaded Railway wagons or


trucks:-

a) upto ¼ mile / ¼ Km Each 155.90 Each 97.45


b) upto ½ mile / ½ Km No 282.20 No 176.40
c) upto ¾ mile / ¾ Km " 381.00 " 238.15
d) upto 1 (1.6 Km) mile " 453.40 " 283.40
e) 2nd mile and subsequent miles/ Each Each
2nd and subsequent kilometres No/Mile 263.50 No/Km 164.70

23 Hand shunting empty Railway wagons or trucks.

a) upto ¼ mile / ¼ Km Each 90.45 Each 56.55


b) upto ½ mile / ½ Km No. 149.85 No. 93.65
c) upto ¾ mile / ¾ Km " 197.60 " 123.50
d) upto 1 mile / 1 Km " 237.15 " 148.20
e) 2nd mile and subsequent miles/ Each Each
2nd and subsequent kilometres No/Mile 129.40 No/Km 80.90

Chap-1 (Carriage) Page 22


LOADING, UNLOADING & STACKING
1 The rate for loading into and unloading from mobile trucks, trollies and boats, etc. will be the same as for Railway wagons.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Laoding or unloading into or from Railway wagons, lead 100 Cft. 264.00 cu.m 93.25
within one chain, (30m) shingle, sand, ballast, surkhi, ashes,
kankar, brick bats, coal, lime or 1,000 Nos. tiles size
12"x6"x2" (300x150x50 mm) or 9"x4½"x1½"
(225x113x37mm) properly laid & stacked.

2 Loading or unloading bricks into or from Railway wagons


laid and stacked, lead within one chain:-

a) Bricks 10" (250 mm) size. 1000 Nos. 330.00 1000 Nos. 330.00

b) Bricks 9" (225 mm) or smaller size. ditto 264.00 ditto 264.00

3 Loading or unloading into or from Railway wagons cement 100 Bags 330.00 100 Bags 330.00
in bags (from inside or outside the godown) and stacking
within one chain (30 m)

4 Loading or unloading into or from Railway wagons empty 100 Nos. 31.70 100 Nos. 31.70
cement bags (from inside or outside the godown) and
stacking.

5 Loading or unloading into or from Railway wagons (from 100 Mds. 198.00 100 Kg 5.30
inside or outside the godown) and stacking, white lime in
bags.

6 Loading or unloading into or from Railway wagons Per 158.40 Per 155.90
Structural Steel, R.S. joists, broad, narrow or meter gauge Tonne Tonne
rail and rail fastenings, etc.

7 Loading or unloading 45 gallon (204.57 Litres) drums full Each 19.80 Each 19.80
into or from Railway wagons, lead upto one chain.

8 Loading or unloading packages of all sorts, upto one Cwt Each 9.90 Each 9.90 Except cement in jute or
(50 Kg). paper bags.
9 Loading or unloading sleepers other than wooden,
including stacking lead within one chain:-

Chap-2 (Loading/Unloading) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

a) Broad gauge sleepers 100 Nos. 660.00 100 Nos. 660.00

b) Metre gauge and narrow gauge sleepers. ditto 330.00 ditto 330.00

10 Loading or unloading timber logs or timber for shuttering, Per 82.50 Per 81.20
into or from Railway wagons of any gauge, including Ton Tonne
stacking lead within one chain (30 m)

11 Loading or unloading bhoosa in Railway wagons lead upto 100 Mds. 792.00 100 Kg 21.20
150 ft. (45 m)

12 Loading or unloading timber scrap or wooden plugs, into or Per 132.00 Per 129.90
from Railway wagons, and stacking within one chain lead. Ton Tonne

13 Loading or unloading pitching stone or spawl from Railway 100 Cft. 97.70 cu.m 34.50
wagons of any gauge (including clearing 5 ft. (1500 mm)
away from the rail).

14 Loading or unloading building stone (including clearing 5 ft. 100 Cft. 126.70 cu.m 44.75
(1.5 m) away from rails).

15 Unloading oil, bitumen tar, etc.

a) Crude oil (to be pumped from tank wagon into tank). 1000 330.00 100 7.25
Gallon litres

b) Crude oil (drained by gravity). 1000 330.00 100 7.25


Gallon litres

c) Crude oil materials from railway wagons. 100 Cft. 42.25 cu.m 14.90

d) Fuel oil from tank into empty drums, including Per 117.35 Per 115.50
stacking within one chain (30 m). Ton Tonne

e) Petrol (2 gallon tin) 100 Nos. 166.30 100 Nos. 166.30 The rate includes checking
and weighing the tins.
f) Kerosine oil (4 gallon tin) 100 Nos. 330.00 100 Nos. 330.00
16 Removing and stacking within one chain
(30 m) lead:

a) Stone, spawl, brick bats, shingle, sand, lime, 100 Cft. 132.00 cu.m 46.60
surkhi, ashes, kankar and coat, etc

Chap-2 (Loading/Unloading) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) Bricks. 1000 Nos. 352.00 1000 Nos. 352.00

c) Broad gauge wooden sleepers. 100 Nos. 211.2 100 Nos. 211.2

d) Metre gauge or narrow gauge wooden sleepers. 100 Nos. 125.70 100 Nos. 125.70

e) Rails girders, pipes, cement etc. Per 58.65 Per 57.75


Ton Tonne

f) Bridge and crossing timbers, etc. 100 No. 704.00 100 No. 704.00

17 Loading into wagons girders, rails, permanent way Per 132.00 Per 129.90
material (except wooden sleepers) iron work, M.S. bars, Ton Tonne
pipes, etc. including lead one chain (30 M) and stacking
inside wagons.

18 Unloading from wagons girders, rails, permanent way Per 75.45 Per 74.25
material (except wooden sleepers) iron work, M.S. bars, Ton Tonne
pipes, etc. lead upto one chain (30 m) but excluding
stacking.

19 Loading into wagons wooden broad gauge sleepers, 100 Nos. 528.00 100 Nos. 528.00
including one chain (30 m) lead and stacking,.

20 Unloading wooden broad gauge sleepers from wagons, 100 Nos. 251.45 100 Nos. 251.45
including one chain (30 m) lead and stacking.

21 Laoding metre gauge or narrow gauge wooden sleepers, 100 Nos. 264.00 100 Nos. 264.00
including one chain (30 m) lead and stacking inside
wagons.

22 Unloading metre gauge or narrow gauge wooden sleepers, 100 Nos. 138.95 100 Nos. 138.95
including one chain (30 m) lead but excluding stacking.

23 Loading bridge and crossing timbers, including one chain 100 Nos. 1056.00 100 Nos. 1056.00
(30 m) lead and stacking.
24 Unloading bridge and crossing timbers, including one 100 Nos. 528.00 100 Nos. 528.00
chain (30 m) lead but excluding stacking.

25 Loading or unloading bitumen, asphalt or tar in drums, into Per 79.20 Per 77.95
or from railway wagons, lead upto one chain (30 m). Ton Tonne

Chap-2 (Loading/Unloading) Page 3


EARTHWORK (EXCAVATION & EMBANKMENT)
1 Special allowances for the hardness, wetness and slush:-
The grant of allowances for hard, very hard, wet and slush will be subject to Superinteding Engineer's approval. Specific instructions regarding grant of such
allowances may be issued by the various Administrative Departments and Statutory Bodies. The earth requiring repeated blows of Kassi to break it and of
which dry bulk density is not less than 1.5, will be treated as hard.

2 Deduction for shrinkage from bank measurements:-


The following allowances should be provided for material which is not rammed, or equally consolidated:-
a) Deduction for shrinkage from the bank measurements when the earthwork is done by manual labour.......... 10%
b) Deduction for settlement from the bank measurement when the earthwork is done by machines................... 3 to 6%

Before the work is let out to be done by tractors, scrapers, etc. deduction ranging between 3% to 6% should be agreed to with the contractor
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

1 Earthwork excavation underessed lead upto a single throw 171 to 17.5


of Kassi, phaorah or shovel:-

a) In ashes, sand, soft soil or silt clearance. 1000 Cft. 990.00 -- cu.m 34.95 --
b) In ordinary soil. 1000 Cft. 1,188.00 -- cu.m 41.95 --

2 Earthwork excavation in ashes, sand and soft soil or silt 1000 Cft. 1,452.00 -- cu.m 51.30 -- ditto
clearance, undressed lead upto 50 ft (15 metre).

3 Bed clearance and dressing slopes of drains to required ditto The rate is applicable where the earth
sections including the removal of weeds, roots, etc. of the bed to be removed is of the
disposal of excavated materials within 50 ft. (15 metre) lead. type of ordinary soil. When it is silt or
a) Excavated material undressed. 1000 Cft. 1,848.00 -- cu.m 65.25 -- 1 or 2 above, whichever is applicable.
b) Excavated material dressed in the specified manner. 1000 Cft. 1,940.95 -- cu.m 68.55 -- the drains of each category.

4 Borrowpit excavation undressed lead upto 100 ft (30 metre).


a) Ordinary soil 1000 Cft. 1,848.00 -- cu.m 65.25 --
b) Hard soil 1000 Cft. 2,270.40 -- cu.m 80.20 --

5 Earthowrk in ordinary soil for embankments lead upto 100 *411-1 to The rate includes hire charges of
ft. (30 m), including ploughing and mixing with blade grade 411-13 and machinery, cost of fuel, lubricants, pay
or disc harrow or other suitable equipment, and 301-1 & of driver and cleaner. The rate also
compaction by mechanical means at optimum moisture 202-3 includes clearing and grubbing
content and dressing to designed section, complete in all where necessary.
respects:-
i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. 1,964.15 2,536.65 cu.m 69.35 89.60
ii) 90% maximum modified AASHO dry density. 1000 Cft. 1,964.15 2,459.35 cu.m 69.35 86.85
iii) 85% maximum modified AASHO dry density 1000 Cft. 1,964.15 2,382.05 cu.m 69.35 84.15

Chap-3 (Earthwork) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

6 Regular excavation dressed. 1000 Cft. 1,306.05 -- cu.m 46.15 -- *411-2

7 Earthwork excavation in open cutting upto 5'-0" (1.5 m) 17.1 to


depth for storm water channels, drains, sullage drains in 17.5
open areas, roads, streets, lanes, including under pinning of
walls and shoring to protect existing works, shuttering and
timbering the trenches, dressed to designed level and
dimensions, trimming, removal of surface water from
trenches, back filling and surplus excavated material
disposed of and dressed within 50 ft. (15 m) lead:-
i) ordinary 1000 Cft. 2,204.95 2,244.65 cu.m 77.90 79.30
ii) hard 1000 Cft. 2,627.35 2,667.00 cu.m 92.80 94.20
iii) very hard 1000 Cft. 3,076.15 3,115.85 cu.m 108.65 110.05
iv) gravel & shingle 1000 Cft. 5,145.90 5,185.65 cu.m 181.75 183.15

8 Earthwork excavation in open cutting 5.01 ft. (1.5 m) to ditto


10.0 ft. (3.0 mm) depth for storm water channels, drains,
sullage drains in open areas, roads, streets, lanes, including
under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed
level and dimensions, trimming, removal of surface water
from trenches, back filling and surplus excavated material
disposed of and dressed within 100 ft. (30 m) lead:-
i) ordinary 1000 Cft. 2,412.95 2,492.00 cu.m 85.25 88.00
ii) hard 1000 Cft. 2,835.35 2,914.40 cu.m 100.15 102.95
iii) very hard 1000 Cft. 3,284.15 3,363.20 cu.m 116.00 118.80
iv) gravel & shingle 1000 Cft. 5,617.90 5,697.00 cu.m 198.40 201.20

9 Excavation in shingle or gravel formation and rock, not 17.1 to 17.5


requiring blasting, undressed lead upto 100 ft (30 m).
i) Dry 1000 Cft. 5,016.00 -- cu.m 177.15 --
ii) Wet 1000 Cft. 5,808.00 -- cu.m 205.15 --
iii) In flowing water 1000 Cft. 7,392.00 -- cu.m 261.10 --

10 Earthwork excavation in irrigation channels, drains, etc. to


designed section, grades and profiles, excavated material ditto
disposed off and dressed within 50 ft. (15 m) lead:-

i) ordinary 1000 Cft. 2,016.95 -- cu.m 71.25 --


ii) hard 1000 Cft. 2,439.35 -- cu.m 86.15 --
iii) very hard 1000 Cft. 2,888.15 -- cu.m 102.00 --
iv) gravel & shingle 1000 Cft. 5,089.90 -- cu.m 179.80 --

Chap-3 (Earthwork) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

11 Excavation in rock dressed to designed section, grades and


profiles, excavated material disposed off within 100 ft. (30 m) 17.1 to 17.5 Tools and plants shall be the liability
and lift upto 5'-0" (1.5 m). of the contractor.
a) Soft rock, slate, shale, schist laterite work, with pick and 1000 Cft. 4,556.65 -- cu.m 160.95 --
crow bar.
b) Medium hard rock, requiring occasional blasting. 1000 Cft. 7,552.45 8,128.45 cu.m 266.75 287.10

12 a) Excavation in hard rock requiring blasting and disposal


of excavated material (blasted material) upto 50 ft. (15 17.1 to 17.5 1) Tools and plants required shall be
m) lead, (including dressing and levelling to designed the liability of the Contractor
section,e tc. complete).
2) Reduce the rate by 8% if the
i) Grade I 1000 Cft. 3,697.30 4,273.30 cu.m 130.60 150.95 excavated section is not dressed or
ii) Grade II 1000 Cft. 4,693.90 5,653.90 cu.m 165.80 199.70 levelled to designed section.
iii) Grade III 1000 Cft. 5,551.90 6,703.90 cu.m 196.00 236.80
iv) Grade IV 1000 Cft. 6,099.70 7,443.70 cu.m 215.45 262.90
v) Grade V 1000 Cft. 6,663.35 8,199.35 cu.m 235.35 289.60
vi) Grade VI 1000 Cft. 7,079.15 8,807.15 cu.m 250.05 311.05

b) Excavation in hard rock requiring blasting, but blasting


prohibited, and disposal of excavated material within 50 17.1 to 17.5 1) Tools and plants required shall be
ft. (15 m) lead (including dressing and levelling to the liability of the contractor.
designed section, etc. complete):-
2) Reduce the rate by 8% if the
i) Grade I 1000 Cft. 7,394.65 8,546.65 cu.m 261.20 301.85 excavated section is not dressed or
ii) Grade II 1000 Cft. 9,387.85 11,307.85 cu.m 331.60 399.40 levelled to designed section.
iii) Grade III 1000 Cft. 11,103.85 13,407.85 cu.m 392.20 473.55
iv) Grade IV 1000 Cft. 12,199.45 14,887.45 cu.m 430.90 525.85
v) Grade V 1000 Cft. 13,326.75 16,398.75 cu.m 470.70 579.20
vi) Grade VI 1000 Cft. 14,158.30 17,614.30 cu.m 500.05 622.15

13 Rehandling of earthwork:

a) Lead upto a single throw of Kassi, phaorah or shovel 1000 Cft. 660.00 -- cu.m 23.30 -- ditto
b) Upto a lead of 50 ft. (15 m). 1000 Cft. 924.00 -- cu.m 32.65 --

14 Rehandling of gravel work or excavated rock, 1000 Cft. 2,640.00 -- cu.m 93.25 -- 17.1 to 17.5
lead upto 50 ft.( 15 m)

15 Filling, watering and ramming earth under floors:- ditto

i) with surplus earth from foundation, etc. 1000 Cft. 1,185.35 -- cu.m 41.85 --
ii) with new earth excavated from outside, 1000 Cft. 2,077.70 -- cu.m 73.40 --
lead upto one chain (30 m).

Chap-3 (Earthwork) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

16 Extra for every 50 ft. (15 m) additional lead or part thereof :- This rate shall be applicable upto
1000 ft. total distance, including the
i) for earhtwork soft, ordinary, hard and very hard. 1000 Cft. 31.90 -- cu.m 1.15 -- lead covered in the item of earthwork
ii) for gravel, shingle or rock. 1000 Cft. 37.30 -- cu.m 1.30 --

17 Transportation of earth all types when the total distance, This rate will be paid inaddition to the
including the lead covered in the item of work, is more than rate of earthwork, without deducting
1000 ft. (300 m) the lead covered in the item of
a) upto ¼ mile (400 m). 1000 Cft. 944.90 -- cu.m 33.35 -- earthwork
b) for every 330 ft. (100 m) additional lead or part thereof,
beyond ¼ mile (400 m) upto one mile. (1.6 Km.) 1000 Cft. 63.45 -- cu.m 2.25 --
c) for every ¼ mile (400 m) additional lead or part thereof,
beyond one mile (1.6 Km.) upto 5 mile (8 Km). 1000 Cft. 98.65 -- cu.m 3.50 --
d) for every ½ mile (800 m) additional lead
or part thereof, beyond 5 miles (8 Km). 1000 Cft. 80.60 -- cu.m 2.85 --

18 Dressing and levelling of earhtwork to designed section, etc. 17.10 to 17.5


complete:-
a) Ashes, sand, silt or soft soil. 1000 Cft. 65.45 -- cu.m 2.30 --
b) Ordinary or hard soil. 1000 Cft. 116.15 -- cu.m 4.10 --
c) Gravel work or soft rock not requiring 1000 Cft. 300.95 -- cu.m 10.65 --
blasting.

19 Dowel dressing. Per 57.20 -- Metre 1.90 -- ditto This rate is in addition to payment for
Chain dressed earhtwork.

20 a) Dressing slopes of banks or ground surface. 100Sft. 24.80 -- sq.m 2.65 -- ditto To be paid only when exclusively
dressing is done and no earthwork is
carried out in embankment or cutting.

b) Dressing of earthwork (done by machinery or otherwise 100Sft. 54.45 -- sq.m 5.85 -- i) The surface area dressed is to be
and left undressed) to designed section. taken for measurement.

ii) The item is applicable where the


dressing is done by the contractor
other than the one who executed the
work.
21 Excavation in foundation of building, bridges and other
structures, including dagbelling, dressing, refilling around 17.1 to 17.5
structure with excavated earth, watering and rammiing lead
upto one chain (30 m) and lift upto 5 ft. (1.5 m)
a) in sand, ashes or loose soil 1000 Cft. 2,280.95 -- cu.m 80.55 --
b) in ordinary soil. 1000 Cft. 2,629.45 -- cu.m 92.85 --
c) in hard soil or soft murum. 1000 Cft. 2,935.70 -- cu.m 103.70 --

Chap-3 (Earthwork) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

22 Cutting hard rock such as granite, ballast, hard lime stone or 1000 Cft. 17,001.60 19,049.15 cu.m 600.50 672.80 17.1 to 17.5 Tools and plants required shall be the
sand stone, etc. with chisels and hammers, for small liability of the contractor.
foundations.

23 Extra for excavation requiring shoring. 1000 Cft. 356.40 489.45 cu.m 12.60 17.30 17.1 to 17.5 Composite rate includes materials,
i.e. plank, etc.
24 Compaction of earthwork (soft, ordinary or hard soil) :- ditto

a) Mixing, moistening earth to optimum moisture content 1000 Cft. 213.85 -- cu.m 7.55 --
in layers for compaction, etc. complete.

b) Compaction by rolling with animal driven


roller/hand rammed:

i) soft or sandy soil 1000 Cft. 248.15 -- cu.m 8.75 --


1) The rate does not include hire
ii) ordinary soil 1000 Cft. 277.20 -- cu.m 9.80 -- charges of the roller.
2) Roller to be 'supplied by
iii) hard soil 1000 Cft. 343.20 -- cu.m 12.10 -- Government

iv) admixture of shingle 1000 Cft. 372.25 -- cu.m 13.15 --

c) Ramming earthwork (all types of soil). 1000 Cft. 396.00 -- cu.m 14.00 --

d) Ramming earhtwork behind retaining walls. 1000 Cft. 528.00 -- cu.m 18.65 --

25 Compaction of earthwork with power road roller, including 17.1 (a)


ploughing, mixing, moistening earth to optimum moisture *411-5 and The rate also includes hire charges of
content in layers, etc. complete: 202-3 machinery, cost of fuel, lubricant, pay
of driver and cleaner, etc.
i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. -- 572.50 cu.m - 20.20

ii) 90% maximum modified AASHO dry density. 1000 Cft. -- 495.20 cu.m - 17.50

iiii) 85% maximum modified AASHO dry density. 1000 Cft. -- 417.90 cu.m - 14.75

26 Extra for wet earthwork. 1000 Cft. 924.00 -- cu.m 32.65 - 17.1 to 17.5 That will support a man's weight.

27 Extra for slush or Daldal including dewatering. 1000 Cft. 2,112.00 -- cu.m 74.60 - 17.1 to 17.5 That will not support a man's weight.

28 Extra for puddling. 1000 Cft. 1,531.20 -- cu.m 54.10 - ditto

29 Earthwork on small rain water drains, along canal banks, 100 Rft. 250.80 -- Metre 8.25 - ditto
roads and plantation drains, dressed, etc. complete

Chap-3 (Earthwork) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

30 Filling and compacting soil, earth and boulders behind 1000 Cft. 2,376.00 -- cu.m 83.90 -- 17.1 to 17.5
retaining walls (including excavation of soil and lead upto 50
ft.( 15 m).

31 Dag bailing 3" (75 mm) deep. Per mile 624.50 -- Per 388.10 -- ditto Dag bailing for layout of borrow pit, to
Km be done by contractors at their own
cost.
32 Turfing slopes of banks or lawns with grass sods including 100Sft. 440.00 -- sq.m 47.35 -- ditto
ploughing, laying, setting and watering (Turf got from within a
distance of 5 miles (8 Km.) and maintenance for 15 days).

33 Berm cutting:- 17.1 to 17.5

a) lead upto a single throw of Kassi, phaora or shovel 1000 Cft. 1,188.00 -- cu.m 41.95 --
(without dressing).
b) upto 50 ft(15 m)lead (including dressing). 1000 Cft. 2,016.95 -- cu.m 71.25 --

34 Berm trimming both sides of channels:- 17.1 to 17.5

a) upto 3½ ft. (1.06 m) depth. Per Mile 2,921.60 -- Per Km. 1826.00 --
b) exceeding 3½ ft. to 5 ft. (1.06 to 1.5 m) depth. Per Mile 3,938.00 -- Per Km. 2461.25 --
c) exceeding 5 ft. to 8 ft. (1.5 to 2.4 m) depth Per Mile 6,278.80 -- Per Km. 3924.25 --

35 Ploughing and levelling borrowpits. ditto Area ploughed to be measured.

i) upto 3 ft. (0.9 m) depth. Per Acre 554.40 -- Per Hect. 1369.95 --
ii) above 3 ft. (0.9 m) depth. Per Acre 1,108.80 -- Per Hect. 2739.90 --

36 Making boundary or service roads, including dag-belling, ditto


levelling and dressing:

i) in unploughed land:

a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 290.40 -- Metre 9.55 --
b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 360.80 -- Metre 11.85 --

ii) in ploughed land:

a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 302.85 -- Metre 9.95 --
b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 371.35 -- Metre 12.20 --

Chap-3 (Earthwork) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

37 Earthwork by boats, including hire of boats:- 17.1 to 17.5 For ordinary soil.

i) Digging and loading into boats, upto 50 ft. (15 m) lead. 1000 Cft. 1,980.00 -- cu.m 69.95 --
ii) Carriage by boats upto 10 chains (300 m). 1000 Cft. 315.05 -- cu.m 11.15 --
iii) Extra for every additional one chain (30 m) or part 1000 Cft. 33.80 -- cu.m 1.20 --
thereof beyond 10 chains (300 m).
iv) Unloading earth from boats. 1000 Cft. 924.00 -- cu.m 32.65 --

38 Unloading earth from B.G. trucks and clearing 5 ft. (1.5 m) 1000 Cft. 792.00 -- cu.m 27.95 -- 17.1 to 17.5
from rail.

39 Earthwork by tramway, digging and loading in trucks, upto 50 1000 Cft. 1,848.00 -- cu.m 65.25 -- 17.1 to 17.5
ft. (15 m) lead.

40 Unloading earth from B.G. trucks and spreading upto 1000 Cft. 1,485.00 -- cu.m 52.45 -- ditto
15 ft. (4.5 m) from rail.

41 Supplying clean and screened river or pit sand within 5 100Cft. 248.85 268.85 cu.m 87.90 94.95 ditto The rate incudes:-
chains (150 m). i) removal of top crust of earth
over burden
ii) royalty to the government or cost
to the private owner.

42 Earthwork excavation in open cutting for sewers and 17.1 to 17.5 The rate does not include back filling
manholes as shown in drawings including shuttering and **13.1 &13.4 after laying of sewer, which is payable
timbering, dressing to correct section and dimensions separately.
according to templates and levels, and removing surface
water, in all types of soil except shingle, gravel and rock:-
If the timbering and shuttering is not
i) 0 ft. to 7.0 ft. (0 to 2.10 m) depth 1000 Cft. 1,935.60 2,007.75 cu.m 68.35 70.90 actually done at site, the composite
ii) 7-01 ft. to 15.0 ft. (2.15 to 4.5 m) depth 1000 Cft. 3,433.45 3,725.00 cu.m 121.25 131.55 rate may be reduced by Rs. 72.15,
iii) above 15.0 ft. (4.5 m) depth 1000 Cft. 4,489.45 4,781.00 cu.m 158.55 168.85 106.35 and 106.35 respectively.

43 Earthwork excavation of trenches in open cutting for sewers 17.1 to 17.5 The rate does not include back filling
and manhole chambers, etc. below sub-soil water level to **13.3 & after laying of sewer, which is payable
correct section and dimensions according to templates and 13.5 separately.
levels, including shoring, timbering and shuttering of M.S.
sheets on both sides of the trenches:

i) 0 ft. to 4.0 ft. (0 to 1.20 m) depth below SSWL. 1000 Cft. 959.95 2,631.80 cu.m 33.90 92.95
ii) 4.01 ft. to 8.0 ft. (1.22 to 2.4 m) depth below SSWL. 1000 Cft. 1,199.85 3,511.40 cu.m 42.40 124.00
iii) Exceeding 8 ft. (2.4 m) depth below SSWL. 1000 Cft. 1,799.80 4,366.00 cu.m 63.55 154.20

Chap-3 (Earthwork) Page 7


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. Unit of Unit of No.
M/ment Labour Composite M/ment Labour Composite

44 Excavation of trenches in all kinds of soil, except cutting 1000 Cft. 1,932.50 -- cu.m 68.25 -- 17.1 to 17.5 The rate does not include back filling
rock, for watersupply pipelines upto 5 ft. (1.5 m) depth **8.1 after laying of pipe line, which is
from ground level, including trimming, dressing sides, payable separately.
levelling the beds of trenches to correct grade and cutting
pits for joints, etc. complete in all respects.

45 Cutting and removing trees within a distance of 100 ft. (30 m)

a) upto 2½ ft. (760 mm) girth. Each 399.30 -- Each 399.30


b) above 2½ ft. to 6 ft. (760 to 1800 mm) girth. Each 775.50 -- Each 775.50

46 Uprooting stump and removing within 100 ft. (30 m) from 2 ft. Each 495.00 -- Each 495.00
to 6 ft. (600 to 1800 mm) girth.

47 Jungle clearance and removing within 100 ft. (30 m).

a) light 1000 Sft. 66.00 -- sq.m 0.70 --


b) thick 1000 Sft. 132.00 -- sq.m 1.40 --

48 Uprooting Sarkanda growth and disposal within 100 ft. (30 m) 100Sft. 31.70 -- sq.m 3.40 --

49 Ploughing 3 times. Per 118.00 -- Per Hect. 291.50 --


Acre

50 Levelling, dressing and making lawns. 100Sft. 132.00 -- sq.m 14.20 --

51 Turfing lawns (excluding cost of turf). 100Sft. 77.00 -- sq.m 8.30 --

52 Earthwork in excavation of drains, irrigation channels through


excavator / drag lines in all kind of soil and conditions(dry,wet
slush,daldal and under water) including its disposal.
a) without path making 1000 Cft. -- 970.00 cu.m -- 34.27
b) with path making 1000 Cft. -- 1100.00 cu.m -- 38.86

53 Earthwork (other than excavation) in irrigation work, through


earth moving machinery with following leads.

1) 2000 feet 1000 Cft. -- 2025.00 cu.m -- 71.51


2) 2500 feet 1000 Cft. -- 2131.00 cu.m -- 75.26
3) 3500 feet 1000 Cft. -- 2688.00 cu.m -- 94.95
4) 5000 feet 1000 Cft. -- 3141.00 cu.m -- 110.92

* Specification number correspond to Book of "Specification for Road & Bridge Construction, 1971".
** Specification number correspond to Book of "Building & Roads Department Specification Vol. II, 1966 (Public Health Works).

Chap-3 (Earthwork) Page 8


DISMANTLING (DEMOLITION)
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.

2 The rates for dismantling roofs or upper storey floor, include the dismantling of all materials, except roof
supports such as beams and trusses.
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Stone Work

1 Dismantling dry stone masonry. 100Cft. 224.40 cu.m 79.25 18.1

2 Dismantling stone masonry in mud mortar. 100Cft. 330.00 cu.m 116.55 ditto

3 Dismantling stone masonry in lime or cement mortar. 100Cft. 792.00 cu.m 279.75 ditto Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively.

4 a) Dismantling dry stone or spawl pitching. 100Cft. 396.00 cu.m 139.85 ditto

b) Dismantling stone or spawl pitching (mud grouted). 100Cft. 501.60 cu.m 177.15 ditto

5 Dismantling stone or spawl pitching and apron in silted 100Cft. 660.00 cu.m 233.10 ditto
condition.

6 Dismantling stone pitching, cement or lime grouted. 100Cft. 1,056.00 cu.m 373.00 ditto

7 Dismantling stone in crates:

a) wooden crates 100Cft. 528.00 cu.m 186.50

b) wire crates ditto 660.00 ditto 233.10

8 Dismantling stone ware drain including base concrete. 100Cft. 369.60 cu.m 130.55 ditto

Brick Work

9 Dismantling mud/pise walling. 100Cft. 132.00 cu.m 46.60 18.1

10 Dismantling sun dried brick masonry. 100Cft. 330.00 cu.m 116.55 ditto

11 Dismantling dry brick masonry. 100Cft. 224.40 cu.m 79.25 ditto

12 Dismantling brick work in mud mortar. 100Cft. 462.00 cu.m 163.20 18.1 Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th

Chap-4 (Dismantling) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

13 Dismantling brick work in lime or cement mortar. 100Cft. 1,122.00 cu.m 396.30 ditto and subsequent floors respectively
against item No. 12, 13, 14 & 15.

14 Dismantling cement block masonry. 100Cft. 990.00 cu.m 349.65 ditto

15 Dismantling Dhajji walling. 100Cft. 264.00 cu.m 93.25 ditto

Concrete

16 Dismantling mud concrete. 100Cft. 528.00 cu.m 186.50 ditto

17 Dismantling lime concrete. 100Cft. 726.00 cu.m 256.40 Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
18 Dismantling lime or cement concrete, under water. 100Cft. 2,772.00 cu.m 979.05 and subsequent floors respectively
against item No. 17, 19 & 20.

19 a) Dismantling cement concrete plain 100Cft. 1,452.00 cu.m 512.85 ditto


1:4:8.
b) Dismantling cement concrete plain ditto 2,376.00 ditto 839.20
1:3:6.
c) Dismantling cement concrete 1:2:4 ditto 2,904.00 ditto 1025.70
plain.
d) Dismantling cement concrete with brick ditto 792.00 ditto 279.75
aggregate.
e) Dismantling D.P.C. of cement concrete ditto 396.00 ditto 139.85
1½" thick (40 mm) and clearing the site.

20 Dismantling cement concrete reinforced, 100Cft. 4,752.00 cu.m 1678.40 ditto


separating reinforcement from concrete,
cleaning and straightening the same.

Roofing

21 Dismantling sirki sarkanda or thatched 100Sft. 158.40 sq.m 17.05 18.1


roofing, supported on battens or ballies.

22 a) Dismantling 1st class tile roofing. 100Sft. 396.00 sq.m 42.60 Add extra 13%, 32 and 51% on
labour rate only for 2nd, 3rd, 4th
b) Dismantling 2nd class tile roofing. 100Sft. 330.00 sq.m 35.50 ditto and subsequent floors respectively
against items No. 22, 25, 26 and
28.

23 Dismantling from any height, asbestos sheets and ridge 100Sft. 198.00 sq.m 21.30 18.1
coping.

Chap-4 (Dismantling) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

24 a) Dismantling roof of wooden planks and battens, from 100Sft. 179.5 sq.m 19.3 ditto
any height.

b) Dismantling wooden ceiling above 20' (6.0 m) height 100Sft. 696.95 sq.m 75.00 ditto
in difficult position, including lifting with care and
special scaffolding along live electric wires and with
machines underneath.

25 Dismantling jack arch roofing, including removal of joists. 100Sft. 528.00 sq.m 56.80 ditto

26 Dismantling R.B. roof complete with mud and plaster, 100Sft. 660.00 sq.m 71.00 ditto
including separating reinforcement, cleaning and
straightening the same.

27 a) Stripping and stacking slate or tiles from the truss 100Sft. 330.00 sq.m 35.50
roofing.

b) Stripping and stacking C.I. sheet roof. ditto 295.70 ditto 31.80

c) Extra for dismantling C.I. sheet roof above 20 ft. (6m) ditto 435.60 ditto 46.85
in difficult position, including lifting with special
scaffolding along live electric wire with machine
underneath.

28 Dismantling slates or tiles including battens, purlins and 100Sft. 528.00 sq.m 56.80 18.1
planking.

Flooring

29 Dismantling brick or flagged flooring without 100Sft. 224.40 sq.m 24.15 18.1 Add extra 13%, 32% and 51% on
concrete foundation. labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively
30 Dismantling plank or wooden block flooring, 100Sft. 330.00 sq.m 35.50 ditto against items No. 29 and 30.
etc.

31 Disjoining R.C.C. pipes inside the trench and dismantling i) The rate does not include the
and removing the pipes from the trench and stacking them cost of excavation and refilling of
outside:- trench, or the demolition of any
masonry or brick work.
a) 6" to 12" (150 to 300 mm) diameter Per Lft 10.05 Metre 32.95
b) 13" to 24" (325 to 600 mm) diameter Per Lft 15.30 Metre 50.20 ii) Bends, elbows, sluice valves,
c) 25" to 36" (625 to 900 mm) diameter ditto 18.05 ditto 59.20 etc. should not be paid for extra if
d) Above 36" (Above 900 mm) diameter ditto 25.50 ditto 83.65 fixed in the length of pipe line that
is being dismantled.

Chap-4 (Dismantling) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

WOOD WORK
32 a) Removing door with chowkat. Per 132.00 Per 132.00 18.1 Add extra 13%, 32% and 51% on
No. No. labour rates only for 2nd, 3rd, 4th
b) Removing windows and sky lights with chowkat. ditto 103.60 ditto 103.60 and subsequent floors respectively
against items No. 32, 33, 34, 35 &
36.
33 Removing ventilators and wooden sunshade, etc. Per No. 55.45 Per No. 55.45 ditto

34 a) Dismantling wooden beams upto 12' (3.65m) Per No. 82.50 Per No. 82.50 ditto
length.

b) Dismantling wooden beams from 12.1' to 23' ditto 132.00 ditto 132.00
(3.65 to 7.0 m) length.

35 a) Dismantling wooden partition Jaffry work etc. 100Sft. 160.30 sq.m 17.25 ditto

b) Dismantling wooden trusses. 100Kg 471.05 %Kg 471.05

36 Dismantling wooden palisade fencing. Per Lft. 13.20 Metre 43.30 ditto

Iron work

37 Dismantling iron work of trusses, sheds, water tanks, etc. 100Kg 476.35 %Kg 476.35 18.1 Add extra 13%, 32% and 51% on
excluding cutting of rivets. labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively
against items No. 37 and 38.

38 Dismantling rolled steel beams or iron rails, etc. 100Kg 216.65 %Kg 216.65 ditto

39 Dismantling iron latrine. Per Unit/ 462.00 Per Unit/ 462.00 ditto
2 Seats 2 Seats

40 Dismantling tees, bends or sluice valves upto 12" Each per 9.15 Each per 3.65 ditto
(300 mm) bore. inch bore cm bore

41 a) Dismantling B.G. water column. Each 3,432.00 Each 3432.00 ditto

b) Dismantling M.G. or N.G. water column. Each 2,293.50 Each 2293.50 ditto

42 Dismantling all type of wire fencing, including rolling wire 100Lft. 224.40 Metre 7.35 18.1
into bundles and collecting material.

Chap-4 (Dismantling) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Miscellaneous

43 Dismantling wire netting of tennis courts and frame work. 100Sft. 105.60 sq.m 11.35 18.1

44 Dismantling cloth ceiling and supporting timber. 100Sft. 198.00 sq.m 21.30 ditto

45 Dismantling and removing road metalling. 100Cft. 528.00 cu.m 186.50 ditto

46 Dismantling and removing road pavement, etc., including 100Cft. 704.90 cu.m 248.95 ditto
screening and stacking of byproducts upto one chain lead
(30 metre).

47 Removing mud plaster from walls. 100Sft. 55.00 sq.m 5.90 ditto Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
48 Removing cement or lime plaster. 100Sft. 110.00 sq.m 11.85 ditto and subsequent floors against item
No. 47, 48, 49, & 50 respectively

49 Scraping:- 18.1

a) White wash or colour wash. 100Sft. 66.00 sq.m 7.10

b) Ordinary distemper, oil bound distemper, ditto 198.00 ditto 21.30


or paint of wall.

50 Dismantling glazed or encaustic tiles, etc. 100Sft. 739.20 sq.m 79.55 18.1

51 Scraping boulders. 100Cft. 924.00 cu.m 326.35 18.1

52 Cleaning lime or cement mortar of old stones 100Cft. 462.00 cu.m 163.20 18.1
to be used in masonry.

Electric Wiring

53 Dismantling light, fan and call bell point Per 20.90 21.20 Per 20.90 21.20
including casing and capping/strip open type, point point
and making good damaged surface (building
portion).

54 Dismantling plug point and making good Per 17.90 18.15 Per 17.90 18.15
damaged surface (building portion). point point

55 Dismantling G.I./M.S. conduit/G.I. flexible/PVC pipes or


conduit wiring, etc. of all sizes including making good
damaged surface (building portion):-

i) on surface Per foot 3.80 3.90 P.Mtr 12.45 12.80


ii) recessed in wall Per foot 8.05 8.10 P.Mtr 26.40 26.55

Chap-4 (Dismantling) Page 5


MORTAR
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD
Dry Material Required for Dry Material Required for
100 Cft. Wet (Ready) Mortar One Cum Wet (Ready) Mortar
S. No. Ratio of Mortar Cement Lime Cement Lime Sand
(50 Kg) Putty Sand (50 Kg.) Putty Cum.
Bag Cft. Cft. Bag. Cum
1 2 3 4 5 6 7 8
1 Cement : Sand
1 : 2 33.48 82 11.83 0.82
1 : 3 23.11 85 8.16 0.85
1 : 4 18.37 90 6.49 0.90
1 : 5 14.70 90 5.19 0.90
1 : 6 13.61 100 4.81 1.00
1 : 7 11.68 100 4.12 1.00
1 : 8 10.21 100 3.61 1.00

2 Cement : Lime : Sand


1 : 1 : 6 12.25 15.0 90 4.33 0.15 0.90
1 : 1 : 7 10.70 13.1 92 3.78 0.13 0.92
1 : 1 : 8 9.39 11.5 92 3.32 0.12 0.92
1 : 1 : 9 8.52 10.44 94 3.00 0.10 0.94
1 : 1 : 10 7.67 9.4 94 2.71 0.09 0.94
1 : 2 : 8 9.19 22.5 90 3.25 0.23 0.90
1 : 2 : 9 8.16 20.0 90 2.88 0.20 0.90
1 : 2 : 10 7.67 18.8 94 2.71 0.19 0.94
1 : 2 : 12 6.39 15.66 94 2.26 0.16 0.94
1 : 3 : 12 6.26 23.0 92 2.21 0.23 0.92
1 : 3 : 14 5.47 20.1 94 1.93 0.20 0.94
1 : 3 : 16 4.82 17.7 94 1.70 0.18 0.94
1 : ¼ : 3 23.11 7.0 85 8.16 0.07 0.85

3 Lime : Sand
1 : 2 43 86 0.43 0.86
1 : 3 31 93 0.31 0.93

Chap-5 (Mortar) Page 1


MORTAR
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD
Dry Material Required for 100 Cft. Dry Material Required for
Wet (Ready) Mortar one M3 Wet (Ready) Mortar
S. Ratio of Mortar Clay Lime Sand Surkhi Cinder Clay Lime Sand Surkhi Cinder
No. (Putty) 3
(Putty)
3 3
Cft. Cft. Cft. Cft. Cft. M M M M3 M3
1 2 3 4 5 6 7 3 4 5 6 7

4 Mud 135 1.35

5 Lime : Surkhi
2 : 3 49.00 - 73.5 - 0.49 - 0.74 -
1 : 2 40.75 - 81.5 - 0.41 - 0.82 -
1 : 3 30.30 - 91.0 - 0.30 - 0.91 -

6 Lime : Sand : Surkhi


1 : 1 : 1 40.50 40.5 40.5 - 0.41 0.41 0.41

7 Lime : Cinder
1 : 1 57.0 - 57.0 - 0.57 - - 0.57

Wet material required for 100 Cft. Wet material required for 1M³ (35.32 Cft)
masonry (including wastage): masonry ( including wastage) :

1 Brick Masonry :
a) Mud Mortar 35.00 Cft 0.35 M3
b) Cement, Sand 25.00 Cft 0.25 M3
c) Cement, Lime (Putty) Sand 25.00 Cft 0.25 M3
d) Lime (Putty) Sand 25.00 Cft 0.25 M3

2 Stone Masonry :
a) Random rubble, uncoursed
i) Foundation and Plinth 45.00 Cft 0.45 M3
ii) Superstructure 40.00 Cft 0.40 M33
iii) Coursed 35.00 Cft 0.35 M
b) Ashlar Block in course or Scabled masonry 30.00 Cft 0.30 M3
c) Ashlar fine masonry 20.00 Cft 0.20 M3

(1) Cement 1 Cft. = 40.8233 Kg


Notes : (2) Unslaked lime 1.7 Cft. = 37.3242 Kg
(3) Slaked lime 2.5 Cft. = 37.3242 Kg
(4) Quick lime 40 Kg Will yield 2.6 Cft. lime putty.

Chap-5 (Mortar) Page 2


CONCRETE
Notes 1 Notes (1) Rates for all finished works include the removal of surplus debris, unused material and by products.

2 If concrete mixer or high frequency vibrator, etc. is supplied by the Government, all charges including
depreciation will be recovered from the contractor.
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Mud concrete in foundation including watering and ramming, 100Cft 1454.95 2624.95 cu.m 513.90 927.15 The stone ballast, crushed bajri,
using brick or stone ballast 1½" (40 mm) gauge. round shingle from nallah, or brick
ballast may be used according to
2 Dry rammed brick or stone ballast, 1½" to 2"( 40 mm to 50 100Cft 990.00 2046.00 cu.m 349.65 722.65 their comparative cheaper rates in
mm) gauge. various areas of the Province.

3 Cement concrete brick or stone ballast 1½ " to 2" (40 mm to 20.1 -do-
50 mm) gauge, in foundation and plinth:-

(a) Ratio 1: 3: 6 100Cft 1914.00 8400.60 cu.m 676.05 2967.10


(b) Ratio 1: 4: 8 ditto 1914.00 7112.40 " 676.05 2512.10
(c) Ratio 1:5:10 ditto 1914.00 6428.70 " 676.05 2270.60
(d) Ratio 1: 6:12 ditto 1914.00 5913.85 " 676.05 2088.75
(e) Ratio 1: 6: 18 ditto 1914.00 5335.50 " 676.05 1884.50
(f) Ratio 1: 7:20 ditto 1914.00 5093.55 " 676.05 1799.05

4 Extra on item No. 3 above, for sedimentation tank or filter


beds of Public Health Engineering Works: The stone ballast, crushed bajri,
round shingle from nallah, or brick
(a) in bed 100Cft 709.50 - cu.m 250.60 - ballast may be used according to
their comparative cheaper rates in
(b) on slope ditto 1079.10 - " 381.15 - various areas of the Province.

Chap-6 (Concrete) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

5 Cement concrete plain including placing, 20.1


compacting, finishing and curing
complete (including screening and
washing of stone aggregate):

(a) Ratio 1: 1:2 100Cft 2712.60 17257.50 cu.m 958.10 6095.35


(b) Ratio 1: 1½: 1½ ditto 2712.60 17013.60 " 958.10 6009.20
(c) Ratio 1: 1½: 3 ditto 2712.60 13852.80 " 958.10 4892.80
(d) Ratio 1: 2: 3 ditto 2712.60 13228.20 " 958.10 4672.20
(e) Ratio 1: 3: 3 ditto 2712.60 11761.20 " 958.10 4154.05
(f) Ratio 1: 2: 4 100Cft 2712.60 12018.60 cu.m 958.10 4244.95
(g) Ratio 1: 2: 6 ditto 2712.60 10677.60 " 958.10 3771.35
(h) Ratio 1: 3: 6 ditto 2712.60 10303.20 " 958.10 3639.10
(i) Ratio 1: 4: 8 ditto 2712.60 9063.00 " 958.10 3201.05

6 Providing and laying reinforced cement concrete (including 20.4 1) The rate includes rendering floor
prestressed concrete), using coarse sand and screened surface smooth, and the plastering
graded and washed aggregate, in required shape and design, done for making up all surfaces
including forms, moulds, shuttering, lifting, compacting, after removing centring.
curing, rendering and finishing exposed surface, complete
(but excluding the cost of steel reinforcement, its fabrication 2) Plastering done under soffit of
and placing in position, etc.):- R.C.C. roof slab meant for human
habitation buildings shall be paid
(a) (i) Reinforced cement concrete in roof slab, beams, extra.
columns lintels, girders and other structural members laid in
situ or precast laid in position, or prestressed members cast 3) This item shall not be applicable
in situ, complete in all respects:- to factory made units.

(1) Type A (nominal mix 1:1:2) Per Cft 57.65 233.80 cu.m 2036.20 8257.80 4) Composite rate shall be reduced by
(2) Type B (nominal mix 1: 1½: 3) ditto 57.65 200.15 " 2036.20 7069.30 Rs:5/- P.Cft & Rs:7/- P.Cft if chenab sand
(3) (c) Type C (nominal mix 1: 2: 4) ditto 57.65 182.05 " 2036.2 6430 and local sand respectively is used.

Chap-6 (Concrete) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(a)(ii) Reinforced cement concrete in slab of rafts / strip


foundation, base slab of column and retaining walls; etc and
other structural members other than those mentioned in
5(a) (i) above not requiring form work (i.e. horizental
shuttering) complete in all respects:-
(1) Type A (nominal mix 1: 1: 2) Per Cft 35.00 193.55 cu.m 1236.20 6836.20
(2) Type B (nominal mix 1: 1½: 3) ditto 35.00 158.05 " 1236.20 5582.35
(3) Type C (nominal mix 1: 2: 4) ditto 35.00 140.00 " 1236.20 4944.80

(b) Precast reinforced cement concrete and prestressed


reinforced cement concrete in columns, beams, lintels, stair
cases, shelves, etc.
(1) Type A (nominal mix 1: 1: 2) Per Cft 46.25 217.35 cu.m 1633.55 7676.80
(2) Type B (nominal mix 1:1½: 3) ditto 46.25 183.55 " 1633.55 6483.00
(3) Type C (nominal mix 1: 2: 4) ditto 46.25 165.65 " 1633.55 5850.75

(c) Erecting and fixing in position, precast cement concrete


or stone slab in roofs or lintels, etc. lift unto 20 ft., (6m) Per Cft 22.45 30.25 cu.m 792.95 1068.45
including all charges.

(d) Add extra labour for R.C. concrete in Per Cft 9.90 -- cu.m 349.65 -
2nd and subsequent storeys.

7 Providing and casting in situ bored reinforced concrete piles *851-1 Composite rate shall be reduced by
with type C concrete (nominal mix 1: 2: 4 ) , using 10% extra to Rs:5/- P.Cft & Rs:7/- P.Cft if chenab sand
cement in dry mix, and course sand, including all labour and 851-10 and local sand respectively is used.
material (except the cost of steel reinforcement and its
labour for bending and laying in position, etc. which will be
paid separately, including, screening & washing of shingle
and curing:-
i) 18 " (450 mm) dia pile Per Rft 630.35 829.65 Metre 2067.55 2721.25
ii) 20" (500 mm) dia pile Per Rft 693.80 939.65 Metre 2275.65 3082.05
iii) 22" (550 mm) dia pile Per Rft 791.10 1080.60 Metre 2594.80 3544.35

Chap-6 (Concrete) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) 24" (600 mm) dia pile Per Rft 907.00 1261.50 Metre 2974.95 4137.75
8 Fabrication of mild steel reinforcement bar cage for R.C.C. *851-5 The rate includes wastage, overlaps,
bored piles, including cutting, bending, laying in position, etc.
welding and fastening, including cost of binding wire and
labour charges for binding of steel reinforcement (also
includes removal of rust from the bars):-

(a) plain bars Per Cwt. 726.00 4491.75 100 kg 1429.15 8842.05
(b) deformed bars ditto 726.00 5285.75 " 1429.15 10405.00

9 Fabrication of mild steel reinforcement for cement concrete, *851.5 The rate includes wastage, overlaps
including cutting, bending, laying in position, making joints and chairs, etc.
and fastenings, including cost of binding wire and labour
charges for binding of steel reinforcement (also includes
removal of rust from bars):-

(a) plain bars Per Cwt. 198.00 4167.60 100 kg 389.75 8203.95
(b) deformed bars ditto 198.00 5025.60 " 389.75 9892.90

10 Precast cement concrete solid or face blocks (1:2:4), Per Cft 26.40 121.65 cu.m 932.45 4296.70 20.2
including cost of templates.

11 Precast cement concrete hollow blocks (1: 2: 4) , including Per Cft 58.90 121.10 cu.m 2080.35 4277.25 20.2
cost of templates and constructing walls thereof.

12 Providing and fixing ornamental cement jali 2" (50 mm) thick Per Sft 18.50 34.25 sq.m 199.05 368.55 20.1 to
(1: 2: 4), without steel. 20.4

13 Extra labour for laying concrete plain or reinforced:

(a) above 20' (6 m) upto 40'(12 m) height 100Cft 1056.00 - cu.m 373.00 -
(b) for every additional 10'(3 m) height. 100Cft 660.00 - cu.m 233.10 -

Chap-6 (Concrete) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

14 Extra labour for work of weirs, rail or road bridges, syphons, and 100Cft 264.00 - cu.m 93.25 -
concreting in superstructure

15 Making reinforced cement concrete spout, including fixing in Each 231.00 321.95 Each 231.00 321.95 20.4
position (2½' x 6" x5") (760 mmx150 mm x 125 mm)

16 Making holes upto 3"(75 mm) dia 18"(450 mm) depth in cement Per hole 554.40 - Each 554.40 - 20.1
concrete or stone masonry walls and repairing.

17 Extra labour for skipping concrete in wells. 100Cft 1540.00 - cu.m 543.95 - 20.1

18 Nicking concrete surface:


(a) Cement concrete surface 100Sft 237.60 - sq.m 25.55 -
(b) Lime concrete surface ditto 78.40 - " 8.45 -

19 Preparing, watering and ramming surface for laying concrete


(for Headworks only):-
(a) Horizontal floor 100Sft 199.05 - sq.m 21.40 -
(b) Glacis and crest ditto 303.60 - " 32.65 -
(c) Inverted filters ditto 92.40 - " 9.95 -

20 Fabrication of high tensile steel prestressing cables for 100 Kg. 2355.85 29837.45 100 Kg. 2355.85 29837.45 *811-1 The rate includes wastage in
prestressed (post tensioned) concrete, including assembling by to cutting and breakage in stressing,
drawing the H.T. wire through metal spacer plate, inserting in helix 811-11 etc.
core and taping or tying, sheathing in longitudinally welded metal
corrugated sheath, positioning , anchorage with male and female
set of anchorage cone, forming ducts for transverse cable,
stressing cables with jack at both ends as per stressing schedule,
maintaining stressing record and supply the same in the approved
proforma to the Engineer-in-charge, making loop at blind end,
including all materials required for it, grouting the cable ducts with
cement, cutting projected ends and making good recesses, etc.,
complete in all respects.

Chap-6 (Concrete) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

21 Fabrication of High Tensile steel reinforcement for prestressed 100kg 1464.30 28590.65 %kg 1464.30 28590.65 1) The rate includes wastage in
(pretension) concrete work, including inserting wire in moulds, cutting and breakage in stressing,
providing M.S. shear bars, spacers and lift hooks, male and etc.
female anchorage, tie down, struts, stressing cables, maintaining 2) Quantity of H. T. wire will form
stress record and supply the same in approved proforma to the basis of payment.
Engineer-in-charge, cutting wires and projecting ends and making 3) This item shall not be applicable
good recesses, etc., complete in all respects. to factory made units.

22 Lifting, transporting and placing precast prestressed concrete *811-1


B eam, Girder and other members (excluding battens) etc. in to
Position on the bridge to correct alignment and level, etc. 811-11
complete

i) Beam upto 50 ft. (15 m) length 100Cft 1032.95 cu.m 364.85


ii) Beam above 50 ft. (15m) upto 75 ft. (22.5m) length 100Cft 1528.29 cu.m 539.80
iii) Beam above 75ft. (22.5m) upto 100ft. (30m) length 100Cft 1914.90 cu.m 676.35
iv) Beam above 100ft. (30m) upto 150ft.(45m) length 100Cft 2434.80 cu.m 859.95
v) Beam above 150ft. (45m) length 100Cft 2912.90 cu.m 1028.85

23 Providing and laying foam concrete 3 inch (75 mm) thick, Per Sft. 15.95 40.60 sq.m. 171.60 436.85
using cement sand in the ratio of 1:2 and aluminium powder
at the rate of 0.2% of the cement, sand mix,

24 Providing and fixing 6 in(150 mm). wide curved sheet of


required shape fixed on face of the construction joint with G.I.
screw,1.5 in (40 mm) long to cover construction joints
vertically:-

i) aluminium sheet 1/16 in(1.5 mm) thick Per Rft. 10.85 36.80 Metre 35.60 120.70
ii) G.I. sheet, 18 SWG Per Rft. 6.75 65.15 Metre 22.15 213.70

25 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminium
strip on horizontal and vertical expansion joints in walls, columns,

Chap-6 (Concrete) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ceilings and floors etc., including cost of clips/screws etc.,


complete in all respects:-

a) On interior surface (without mastic strip) Per Rft. 3.90 29.85 Metre 12.80 97.90
b) On exterior surface (with mastic strip) ditto 3.90 32.70 " 12.80 107.25

26 Providing and fixing 1/16" (1.5 mm) thick copper flashing on Per Sft. 6.75 77.65 Sq.m 72.65 835.50
expansion joints complete in all respects.

27 Providing and fixing 6 in (150 mm). wideG.I. sheet 18SWG. Per Rft. 3.50 58.60 Metre 11.50 192.20
stopper to expansion joint.

28 Providing embeding 10" (250 mm) wide ¼" (6 mm) thick Per Rft. 14.85 56.85 Metre 48.70 186.40
rubber water stopper in expansion joints of R.C.C. roof
slab complete in all respects.

29 Filling expansion joints with bitumen. sand & saw dust in Per Rft Per Metre/
ratio 1:2:2. per inch 1.65 4.90 Per 25 mm 5.40 16.05
width Width

30 Filling expansion joints with bitumen. Per Rft. 22.75 - Metre 74.60 -

31 Laying asphaltic mixture in expansion joints. Per Rft. 23.10 - Metre 75.75 - Material to be paid on actuals.

32 Providing and fixing theremopore (foamed polythene)


sheet in horizontal and vertical expansion joints:

a) 1" (25 mm) thick thermopore sheet Per Sft. 3.70 8.40 Sq.m 39.80 90.40
b) 1½" (40 mm) thick thermopore sheet ditto 3.70 12.50 " 39.80 134.50

33 Providing and laying damp proof course of cement concrete


1:2: 4(using cement, sand and shingle), including bitumen
coating :-

Chap-6 (Concrete) Page 7


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(a) with one coat bitumen and one coat polythene sheet
500gauge

i) 1½" thick (40 mm) 100Sft 722.70 2758.55 sq.m 77.75 296.80
ii) 2" thick (50 mm) 100Sft 722.70 3124.70 sq.m 77.75 336.20
iii) 3" thick (75 mm) 100Sft 753.50 3946.30 sq.m 81.10 424.60

(b) with 2 coats of bitumen:

i) 1½" thick (40 mm) 100Sft 722.70 2950.65 sq.m 77.75 317.50
ii) 2" thick (50 mm) 100Sft 722.70 3316.50 sq.m 77.75 356.85
iii) 3" thick (75 mm) 100Sft 753.50 4138.05 sq.m 81.10 445.25

34 Providing and laying damp proof course with cement sand


plaster and bitumen coating:-

(a) with one coat of bitumen and one coat of polythene sheet
500 gauge :-

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 676.50 1768.35 sq.m 72.80 190.30
b) ¾" thick (20 mm) 100Sft 676.50 1949.30 sq.m 72.80 209.75

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 676.50 1825.55 sq.m 72.80 196.45
b) ¾ " thick (20mm) 100Sft 676.50 2016.60 sq.m 72.80 217.00

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 676.50 1914.10 sq.m 72.80 205.95
b) ¾ " thick (20 mm) 100Sft 676.50 2179.40 sq.m 72.80 234.50

Chap-6 (Concrete) Page 8


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(b) with 2 coats of bitumen:-

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 676.50 1873.35 sq.m 72.80 201.55
b) ¾" thick (20 mm) 100Sft 676.50 2054.55 sq.m 72.80 221.05

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 676.50 1930.80 sq.m 72.80 207.75
b) ¾ " thick (20 mm) 100Sft 676.50 2121.85 sq.m 72.80 228.30

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 676.50 2073.35 sq.m 72.80 223.10
b) ¾ " thick (20 mm) 100Sft 676.50 2358.50 sq.m 72.80 253.80

35 Providing and laying vertical damp proof course with cement


sand plaster and bitumen coating:-

(a) with one coat of bitumen and one coat of polythene sheet
500 gauge:

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 676.50 1714.05 sq.m 72.80 184.45
b) ¾" thick (20 mm) 100Sft 676.50 1895.25 sq.m 72.80 203.95

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 676.50 1771.50 sq.m 72.80 190.60
b) ¾ " thick (20 mm) 100Sft 676.50 1962.60 sq.m 72.80 211.20

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 676.50 1914.10 sq.m 72.80 205.95
b) ¾ " thick (20 mm) 100Sft 676.50 2199.20 sq.m 72.80 236.65

Chap-6 (Concrete) Page 9


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(b) with 2 coats of bitumen:-

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 676.50 1873.40 sq.m 72.80 201.60
b) ¾" thick (20 mm) 100Sft 676.50 2054.55 sq.m 72.80 221.05

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 676.50 1930.80 sq.m 72.80 207.75
b) ¾ " thick (20 mm) 100Sft 676.50 2121.85 sq.m 72.80 228.30

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 676.50 2073.45 sq.m 72.80 223.10
b) ¾ " thick (20 mm) 100Sft 676.50 2358.45 sq.m 72.80 253.70

36 Grouting concrete between, the grooves of gates, including 100Cft 3300.00 - cu.m. 1165.55 -
shuttering.

37 Chiesel dressing concrete surface on sides of grooves. 100Sft 130.70 - sq.m 14.05 -

38 Laying and ramming dry ballast or kankar. 100Cft 1072.50 - cu.m 378.80 -

39 Hoisting and placing in position R.C.C. shelves. per No. 39.20 - per No. 39.20 -

40 Breaking brick ballast, screening and stacking:-


(a) 2"(50 mm) ring 100Cft. 825.00 - cu.m 291.40 -
(b) 1½ "(40 mm) ring ditto 924.00 - " 326.35 -
(c) 1" (25 mm) ring ditto 1072.50 - " 378.80 -
(d) Jhama ballast ¾"(20 mm) ring ditto 1237.50 - " 437.10 -

Chap-6 (Concrete) Page 10


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

41 Supplying and fixing broken glasses on court yard walls, Per Rft 26.40 53.95 metre 86.60 176.95
including 1:3: 6 cement concrete coping.

42 Crushing stone ballast by machine. 100Cft 825.00 - cu.m. 291.40 - This does not include the charges
for working of crushers, but includes
manual labour for carriageof stone to
crusher within three chains (90 m)
and also stacking the product after
crushing within three chains (90 m).
43 Breaking stone ballast screened and stacked:-

(a) 2" ring (50 mm) 100Cft. 924.00 - cu.m. 326.35 -


(b) 1½ " ring (40 mm) ditto 1072.50 - " 378.80 -
(c) 1" ring (25 mm) ditto 1237.50 - " 437.10 -
d) ½ " ring (13 mm) ditto 1650.00 - " 582.80 -
(e)1/8" to ¼" ring (3 mm to 6 mm) ditto 2805.00 - " 990.75 -

44 Screening and stacking stone ballast shingle or bajri, etc. 100Cft. 264.00 - cu.m. 93.25 -

45 Washing ballast, bajri or shingle. 100Cft. 264.00 - cu.m. 93.25 -

46 Erecting and carting sun shades of precast R.C. concrete


upto 5' x 2½' (1.50 m x 0.76 m) Each 165.00 - Each 165.00 -

Specification numbers correspond to book of standard specification of Road and Bridge Construction, "1971"

Chap-6 (Concrete) Page 11


BRICK WORK
1 Rates for all finsihed works include the removal of surplus debris, unused material and byproducts.
2 The rates apply to all sizes of bricks, including the modular bricks of size 8"x4"x4" (200x100x100 mm) nominal.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Pacca brick work in mud mortar in buildings: 21.1 Masonry of boundary wall to be
to considered as masonry other than
i) in foundation and plinth 100Cft. 1502.70 6023.70 cu.m 530.75 2127.55 21.4 building.
ii) in ground floor ditto 2004.30 6525.30 ditto 707.90 2304.75
The composite rate is to be
reduced by 7% and 14%, if 2nd or
3rd class bricks are used.
2 Add extra labour on item No. 1 for brick work in:-

i) first floor 100Cft. 382.80 -- cu.m 135.20 -


ii) second floor ditto 884.40 -- ditto 312.35 -
iii) third floor ditto 1386.00 -- ditto 489.55 -
iv) fourth & subsequent floors ditto 2257.20 -- ditto 797.25 -

3 Pacca brick work in mud mortar other than building:- 21.1 to Same remarks as against
21.4 item No. 1 above
i) upto 20 ft. (6.1 m) height 100Cft. 2067.40 6588.40 cu.m 730.20 2327.00
ii) extra labour for every 5 ft. (1.5 m) ditto 382.80 -- ditto 135.20 -
additional height, or part thereof.

4 Pacca brick work in foundation and plinth in:- ditto Same remarks as against
item No. 1 above.
i) Cement, sand mortar:-

Ratio 1:2 100Cft. 1968.10 9708.10 cu.m 695.10 3428.90


Ratio 1:3 ditto 1968.10 8940.85 ditto 695.10 3157.90
Ratio 1:4 ditto 1968.10 8480.50 ditto 695.10 2995.30
Ratio 1:5 ditto 1968.10 8173.60 ditto 695.10 2886.90
Ratio 1:6 ditto 1968.10 7942.95 ditto 695.10 2805.45
Ratio 1:7 ditto 1968.10 7792.45 ditto 695.10 2752.30
Ratio 1:8 ditto 1968.10 7659.50 ditto 695.10 2705.35

chapter-7(Brickwork) Page 1
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ii) lime, cement sand mortar:- 21.1 The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 1968.10 8061.90 cu.m 695.10 2847.45
Ratio 1:1:7 ditto 1968.10 7906.85 ditto 695.10 2792.70
Ratio 1:1:8 ditto 1968.10 7781.35 ditto 695.10 2748.35
Ratio 1:1:9 ditto 1968.10 7676.10 ditto 695.10 2711.20
Ratio 1:1:10 ditto 1968.10 7597.30 ditto 695.10 2683.35

iii) lime, sand mortar 1:2 100Cft. 1968.10 7200.60 cu.m 695.10 2543.25 ditto ditto

5 Pacca brick work in ground floor:- ditto i) The composite rate is to


be reduced by 7% and 14%,
i) cement, sand mortar:- if 2nd or 3rd class bricks are
used.
Ratio 1:2 100Cft. 2601.70 10341.70 cu.m 918.90 3652.70 ii) Masonry of boundary wall
Ratio 1:3 ditto 2601.70 9574.45 ditto 918.90 3381.70 to be considered as masonry
Ratio 1:4 ditto 2601.70 9114.10 ditto 918.90 3219.10 other than building.
Ratio 1:5 ditto 2601.70 8807.20 ditto 918.90 3110.70
Ratio 1:6 ditto 2601.70 8576.55 ditto 918.90 3029.25
Ratio 1:7 ditto 2601.70 8426.05 ditto 918.90 2976.10
Ratio 1:8 ditto 2601.70 8292.10 ditto 918.90 2928.75

ii) lime, cement, sand mortar:- The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 2601.70 8695.50 cu.m 918.90 3071.25
Ratio 1:1:7 ditto 2601.70 8541.75 ditto 918.90 3016.95
Ratio 1:1:8 ditto 2601.70 8414.95 ditto 918.90 2972.15
Ratio 1:1:9 ditto 2601.70 8309.70 ditto 918.90 2935.00
Ratio 1:1:10 ditto 2601.70 8231.10 ditto 918.90 2907.25

iii) lime, sand mortar 1:2 100Cft. 2601.70 7834.15 cu.m 918.90 2767.00 The rate of lime mortar also
includes grinding of mortar.

6 Add extra labour on item No. 5 for brickwork


in:-

i) first floor 100Cft. 382.80 -- cu.m 135.20 -


ii) second floor ditto 884.40 -- ditto 312.35 -
iii) third floor ditto 1386.00 -- ditto 489.55 -
iv) fourth & subsequent floors ditto 2257.20 -- ditto 797.25 -

chapter-7(Brickwork) Page 2
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

7 Pacca brick work other than building upto 10ft. (3 m) 21.1 i) The composite rate is to be
height. to reduced by 7% and 14%, if 2nd or
21.5 3rd class bricks are used.
i) cement, sand mortar:-
ii) Workshops, godowns,, bins,
Ratio 1:2 100Cft. 2336.40 10076.40 cu.m 825.20 3559.00 house type godowns, reservoirs,
Ratio 1:3 ditto 2336.40 9309.15 ditto 825.20 3288.00 filter beds, storage tanks, wells,
Ratio 1:4 ditto 2336.40 8848.80 ditto 825.20 3125.40 screening chambers, collecting
Ratio 1:5 ditto 2336.40 8541.90 ditto 825.20 3017.00 tanks, manholes etc. are to be
Ratio 1:6 ditto 2336.40 8311.25 ditto 825.20 2935.55 treated as masonry other than
Ratio 1:7 ditto 2336.40 8160.75 ditto 825.20 2882.40 buildings.
Ratio 1:8 ditto 2336.40 8027.80 ditto 825.20 2835.40

ii) lime, cement, sand mortar:- The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 2336.40 8430.20 cu.m 825.20 2977.55
Ratio 1:1:7 ditto 2336.40 8275.10 ditto 825.20 2922.75
Ratio 1:1:8 ditto 2336.40 8149.60 ditto 825.20 2878.45
Ratio 1:1:9 ditto 2336.40 8044.35 ditto 825.20 2841.25
Ratio 1:1:10 ditto 2336.40 7965.55 ditto 825.20 2813.45

iii) lime, sand mortar 1:2 100Cft. 2336.40 7568.85 cu.m 825.20 2673.30 ditto

8 Add extra labour on item No. 7, for every 10ft.(3 m) 100Cft. 382.80 -- cu.m 135.20 -
additional height, or part thereof.

9 Extra labour for arch work in brick masonry, including 100Cft. 844.80 -- cu.m 298.40 - 21.5
labour for centring and decentring.

10 Extra for pacca brick work in steining of wells or any other 100Cft. 594.00 859.70 cu.m 209.80 303.65 21.1 The composite rate is to be
circular masonry. to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.

11 Extra labour for profile and flared walls. 100Cft. 204.35 -- cu.m 72.20 -

12 Extra labour for pacca brick work in piers and abutment:-

i) from 10ft. to 20ft. (3 m to 6 m) height 100Cft. 189.00 -- cu.m 66.75 -


ii) above 20 ft. (6 m) height. 100Cft. 382.80 -- cu.m 135.20 -

13 Extra for face work (half brick thick) using special bricks 100Cft. 4242.30 cu.m 1498.40 This item is to be executed only
instead of first class bricks. under the written permission of
Superintending Engineer.

chapter-7(Brickwork) Page 3
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

14 Reinforced brick work in lintel of openings, laid in 1:3 Per Cft. 65.15 145.75 cu.m 2300.35 5147.90
cement mortar, including all labour, material, forms,
moulds, lifting & shuttering, etc, (but excluding cost and
labour of steel reinforcement which shall be paid for
separately).

15 Extra for dressing or chamfering bricks for:-

a) special architectural bricks 100 Nos. 1515.35 - % Nos. 1515.35 -


b) all other purposes ditto 757.65 - ditto 757.65 -

16 Perforated pacca brick walling half brick thick, in ground 21.1 The composite rate is to be
floors:- to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.
i) mud mortar 100 Sft. 1000.80 2132.70 Sqm. 107.70 229.50

ii) cement, sand mortar:-

Ratio 1:2 100 Sft. 1303.10 3239.70 sq.m. 140.20 348.60


Ratio 1:3 ditto 1303.10 3047.65 ditto 140.20 327.95
Ratio 1:4 ditto 1303.10 2932.80 ditto 140.20 315.55
Ratio 1:5 ditto 1303.10 2856.10 ditto 140.20 307.30
Ratio 1:6 ditto 1303.10 2802.15 ditto 140.20 301.50
Ratio 1:7 ditto 1303.10 2760.35 ditto 140.20 297.00
Ratio 1:8 ditto 1303.10 2729.60 ditto 140.20 293.70

iii) lime, cement sand mortar The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Sft. 1303.10 2828.15 sq.m 140.20 304.30
Ratio 1:1:7 100Sft. 1303.10 2788.45 sq.m 140.20 300.05
Ratio 1:1:8 100Sft. 1303.10 2759.40 sq.m 140.20 296.90
Ratio 1:1:9 100Sft. 1303.10 2731.20 sq.m 140.20 293.90
Ratio 1:1:10 100Sft. 1303.10 2714.70 sq.m 140.20 292.10

iv) lime, sand mortar 1:2 100Sft. 1303.10 2610.65 sq.m 140.20 280.90 ditto

17 Add extra labour on item No. 16 for pacca brick work in:-

i) first floor 100Sft. 193.80 - sq.m 20.85 -


ii) second floor ditto 439.80 - ditto 47.30 -
iii) third floor ditto 695.40 - ditto 74.85 -
iv) fourth & subsequent floors ditto 1091.90 - ditto 117.50 -

chapter-7(Brickwork) Page 4
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

18 Perforated pacca brick walling one brick thick, in ground 21.1 The composite rate is to be
floor: to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.
i) mud mortar 100Sft. 1384.70 3645.20 sq.m 149.00 392.20

ii) cement, sand mortar:-

Ratio 1:2 100 Sft. 1962.85 5832.85 sq.m 211.20 627.60


Ratio 1:3 ditto 1962.85 5449.20 ditto 211.20 586.35
Ratio 1:4 ditto 1962.85 5219.05 ditto 211.20 561.55
Ratio 1:5 ditto 1962.85 5065.60 ditto 211.20 545.05
Ratio 1:6 ditto 1962.85 4957.70 ditto 211.20 533.45
Ratio 1:7 ditto 1962.85 4873.85 ditto 211.20 524.45
Ratio 1:8 ditto 1962.85 4808.60 ditto 211.20 517.40

iii) lime, cement, sand mortar:- The rate of lime mortar also
Ratio 1:1:6 100Sft. 1962.85 5009.75 sq.m 211.20 539.05 includes grinding of mortar
Ratio 1:1:7 ditto 1962.85 4930.20 ditto 211.20 530.50
Ratio 1:1:8 ditto 1962.85 4869.50 ditto 211.20 523.95
Ratio 1:1:9 ditto 1962.85 4816.85 ditto 211.20 518.30
Ratio 1:1:10 ditto 1962.85 4778.10 ditto 211.20 514.10

iv) lime, sand mortar 1:2 100Sft. 1962.85 4578.45 sq.m 211.20 492.65 ditto

19 Add extra labour on item No. 18 for perforated pacca brick


work in:-

i) first floor 100Sft. 287.10 -- sq.m 101.40 -


ii) second floor ditto 663.30 -- ditto 234.25 -
iii) third floor ditto 1039.50 -- ditto 367.15 -
iv) fourth & subsequent floors ditto 1692.90 -- ditto 597.95 -

20 Fire brick masonry in fireclay mortar:- 21.1


to
i) upto 20 ft. (6.10 m) height including all charges. Per Cft. 25.75 485.65 cu.m 909.15 17153.25 21.2

ii) Extra for every 5 ft. (1.5 m) additional height, or part 100Cft. 382.80 -- ditto 135.20 - A&C No.I dated 2.9.1998
thereof.

21 First class brick walling laid in 1:3 cement sand mortar,


reinforced with 1" (25 mm) wide 18 gauge hoop iron:- 21.19

i) 4½" (113 mm) thick walling with hoop iron, bonding 6" 100Sft. 1133.55 4731.25 sq.m 121.95 509.10
(150 mm) apart.

chapter-7(Brickwork) Page 5
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ii) 4½" (113 mm) thick walling with hoop iron, bonding 100Sft. 1027.95 4196.85 sq.m 110.60 451.60
12" (300 mm) apart.
iii) 3" (75 mm) thick walling with hoop iron, bonding 6" ditto 891.00 3659.35 ditto 95.85 393.75
(150 mm) apart.
iv) 3" (75 mm) thick walling with hoop iron, bonding 12" ditto 712.80 3004.90 ditto 76.70 323.35
(300 mm) apart.

22 Ghilafi work (1½ brick thick wall) 100Cft. 2011.70 4750.70 cu.m 710.55 1677.95 21.18

23 Dry brick pitching 100Cft. 1254.00 5628.00 cu.m 442.90 1987.80 21.1

24 Sun dried bricks in mud mortar 100Cft. 1683.00 2640.00 cu.m 594.45 932.45 21.16

25 Pise wall (mud walling) 100Cft. 768.25 -- cu.m 271.35 - 21.17

26 Eave brick moulded, weathered and throated with back 21.1 to 21.2
brick or drip course cornice, in 1:3 cement mortar:-

i) 3" (75 mm) thick drip course cornice Rft. 13.40 38.80 Metre 43.95 127.25 correction vide A&C No.I dated 2.9.98
ii) 4½" (113 mm) thick drip course cornice. ditto 15.25 55.05 ditto 50.00 180.55
iii) 4½" (113 mm) thick eave brick with back brick. ditto 10.05 69.40 ditto 32.95 227.65

27 Laying dressed or moulded brick cornices in 1:6 cement 21.1 to 21.2


mortar, plastering or painting complete:-

i) 1 brick Rft. 15.25 24.10 Metre 50.00 79.05


ii) 2 bricks ditto 22.65 49.90 ditto 74.30 163.65
iii) 3 bricks ditto 30.20 76.55 ditto 99.05 251.10
iv) 4 bricks ditto 37.90 99.95 ditto 124.30 327.85

28 Cleaning bricks dismantled from kacha pacca masonry 1,000 462.00 -- 1,000 462.00 -
Nos Nos

29 Scraping bricks dismantled from pacca masonry 1,000 871.20 -- 1,000 871.20 -
Nos Nos

30 Supplying and filling sand under floor; or plugging in wells. 100Cft. 110.00 1100.00 cu.m 38.85 388.50

31 Providing and laying 2" (50 mm) thick and 15" (375 mm) Rft. 57.75 89.80 Metre 189.40 294.55
projected tile band, laid in 1:2 cement sand mortar, with
hoop iron 1" (25 mm) wide 18 gauge flat iron sheet 9"
apart.

chapter-7(Brickwork) Page 6
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

32 First class brick tiles clad by laying tiles in stretcher This item is to be executed only
course in cement sand mortar reinforced with 18 SWG under the written permission of the
hoop iron strips bonding placed at 2.0' (600 mm) apart Superintending Engineer.
horizontally, and at 1.0' (300 mm) interval vertically.

i) 1:3 100Sft. 1027.95 4688.15 sq.m 110.60 504.45


ii) 1:4 ditto 1027.95 4504.00 ditto 110.60 484.65

33 Chamfering sides of head regulators and masonry walls to Per Sft. 30.80 -- sq.m 331.40 -
increase width.

34 Replacing kallar eaten bricks Each No. 25.30 28.05 Each 25.30 28.05

35 Repairing corners of bridges and other hydraulic masonry Each No. 154.00 174.00 Each 154.00 174.00
works

36 Extra labour for drains of bath rooms, etc. Per Lft. 14.85 -- Metre 48.70

37 Maroo corners Each 95.05 -- Each 95.05 Payable in addition to brick work
Corner Corner

chapter-7(Brickwork) Page 7
STONE MASONRY
1 The composite rates do not include the carriage of stone or spawl which will be paid separately by road and/or rail whichever means of
transport is adopted. The supply and carriage to site of work of all other materials is included in the composite rates.

2 The payment of carriage of stone or spawl will be made on the basis of the actual stack measurement (without any reduction factor) of the
stone or spawl carried.

3 Where the stone or spawl is issued from stock and the contractor is paid for its carriage and/or labour only; or where the stone or spawl is
supplied, carried or handled by the contractor in which no laying is required, the actual stack measurement (without any reduction factor)
shall form the basis of the payment of supply or carriage of stone or spawl. The quantity of finished and completed item of work shall form
the basis of laying.

4 Rates for all finished work include the removal of surplus debris, unused material and byproducts.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Random, rubble masonry (uncoursed), in foundation and 22.10,


plinth: 22.11

a) dry masonry 100 Cft. 2178.00 2928.00 cu.m 769.25 1034.15


b) in mud mortar 100 Cft. 2697.75 3636.75 cu.m 952.85 1284.50
c) in lime, sand mortar 1:2 100 Cft. 4141.50 5994.90 cu.m 1462.80 2117.40
d) in cement, sand mortar
i) ratio 1:3 100 Cft. 4141.50 8597.25 cu.m 1462.80 3036.55
ii) ratio 1:4 100 Cft. 4141.50 8099.10 cu.m 1462.80 2860.60
iii) ratio 1:6 100 Cft. 4141.50 7308.80 cu.m 1462.80 2581.45
iv) ratio 1:8 100 Cft. 4141.50 6871.50 cu.m 1462.80 2427.00

2 Coursed rubble masonry hammer dressed, in foundation 22.8


and plinth:

a) dry masonry 100 Cft. 2772.00 3522.00 cu.m 979.05 1243.95


b) in mud mortar 100 Cft. 3811.50 4750.50 cu.m 1346.20 1677.90
c) in lime, sand mortar 1:2 100 Cft. 4644.75 6375.20 cu.m 1640.55 2251.70
d) in cement, sand mortar:
i) ratio 1:3 100 Cft. 4644.75 9129.75 cu.m 1640.55 3224.65
ii) ratio 1:4 100 Cft. 4644.75 8515.95 cu.m 1640.55 3007.85
iii) ratio 1:6 100 Cft. 4644.75 7813.05 cu.m 1640.55 2759.55
iv) ratio 1:8 100 Cft. 4644.75 7426.95 cu.m 1640.55 2623.20

chapter-8(Stone masonary) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

3 Random rubble masonry (uncoursed) in 22.10


ground floor or 20 ft.(6 m) height, building/other
than building.

a) dry masonry 100 Cft. 2475.00 3225.00 cu.m 874.15 1139.05


b) in mud mortar 100 Cft. 3217.50 4156.50 cu.m 1136.40 1468.10
c) in lime, sand mortar 1:2 100 Cft. 4496.25 6349.65 cu.m 1588.10 2242.70
d) in cement, sand mortar:
i) ratio 1:3 100 Cft. 4496.25 9144.40 cu.m 1588.10 3229.80
ii) ratio 1:4 100 Cft. 4496.25 8453.85 cu.m 1588.10 2985.90
iii) ratio 1:6 100 Cft. 4496.25 7663.55 cu.m 1588.10 2706.75
iv) ratio 1:8 100 Cft. 4496.25 7226.25 cu.m 1588.10 2552.30

4 Coursed rubble masonry hammer dressed, in ground floor 22.8


or 20 ft. (6 m) height, building/other than building.

a) dry masonry 100 Cft. 3234.00 3984.00 cu.m 1142.25 1407.15


b) in mud mortar 100 Cft. 4735.50 5666.10 cu.m 1672.60 2001.25
c) in lime, sand mortar 1:2 100 Cft. 5255.25 6985.70 cu.m 1856.15 2467.35
d) in cement, sand mortar:
i) ratio 1:3 100 Cft. 5255.25 9740.25 cu.m 1856.15 3440.25
ii) ratio 1:4 100 Cft. 5255.25 9126.45 cu.m 1856.15 3223.45
iii) ratio 1:6 100 Cft. 5255.25 8423.55 cu.m 1856.15 2975.20
iv) ratio 1:8 100 Cft. 5255.25 8037.45 cu.m 1856.15 2838.85

5 Ashlar block in course or scabbled masonry (including 22.5


dressing, etc.,) in ground floor or 20 ft. (6 m) height, &
building/other than building. 22.6

a) in lime, sand mortar 1:2 100 Cft. 14302.20 15976.85 cu.m 5051.55 5643.00
b) in cement, sand mortar:
i) ratio 1:3 100 Cft. 14302.20 17840.15 cu.m 5051.55 6301.15
ii) ratio 1:4 100 Cft. 14302.20 17379.80 cu.m 5051.55 6138.55
iii) ratio 1:6 100 Cft. 14302.20 16858.05 cu.m 5051.55 5954.25

6 Ashlar fine masonry (including dressing, etc.) in ground 22.3


floor or 20 ft. 6 m) height, building/other than building. (A) to
(C) &
a) in lime, sand mortar 1:2 100 Cft. 27640.80 29254.00 cu.m 9762.75 10332.50 22.4
b) in cement, sand mortar:
i) ratio 1:3 100 Cft. 27640.80 30185.65 cu.m 9762.75 10661.55
ii) ratio 1:4 100 Cft. 27640.80 29955.25 cu.m 9762.75 10580.20
iii) ratio 1:6 100 Cft. 27640.80 29699.80 cu.m 9762.75 10489.95

chapter-8(Stone masonary) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

7 Extra labour on items 3, 4, 5 & 6 above for work in:-

i) first floor 100 Cft. 546.50 - cu.m 193.00 -


ii) second floor 100 Cft. 1256.65 - cu.m 443.85 -
iii) third floor 100 Cft. 1980.00 - cu.m 699.35 -
iv) fourth floor 100 Cft. 3189.10 - cu.m 1126.40 -

8 Extra labour on items 3,4,5 & 6 above for every 5 ft.(1.5 m) 100 Cft. 501.60 - cu.m 177.15 -
additional height, other than building, or part thereof.

9 Extra labour for arch work in stone masonry, including 100 Cft. 1464.10 - cu.m 517.10 - 22.12
centering and decentring, etc.

10 Extra labour for:- 22.7

a) coping and caps, etc. 100 Cft. 8553.60 - cu.m 3021.15 -


b) cornice & string course 100 Rft. 8553.60 - Rm. 280.55 -

11 Dressing stones:- 22.2


i) This rate of dressing shall be paid
a) hammer dressed 100 Sft. 3036.00 - sq.m 326.65 only when the supply of undressed
b) rough tooled dressed 100 Sft. 5808.00 - sq.m 624.95 stone is made.
c) chisel dressed 100 Sft. 7022.40 - sq.m 755.60 ii) In case of masonry, dressing is
d) fine dressed 100 Sft. 14995.20 - sq.m 1613.50 already included and this rate shall
not be added thereto.
iii) Only dressed surface of stone
shall be measured.

12 Dhajji walling 5"x5" (125 mmx125 mm) thick deodar 100 Sft. 5643.85 8636.10 sq.m 607.30 929.25 22.13
framing with stone laid in 1:6 cement sand mortar, and 1:4
cement sand plaster on both sides.

13 Providing and fixing stone blocks from 2 Cft. Per Cft. 216.00 240.75 cu.m 7629.10 8503.30
(0.6 cu.m) to 6 Cft (0.17 cu.m). each
including lift upto 20 ft. (6 m)

14 Providing and fixing stone blocks, under 2 Per Cft. 126.05 153.85 cu.m 4452.10 5434.00
Cft. (06 cu.m) each including lift upto 20 ft.
(6 m)

chapter-8(Stone masonary) Page 3


ROOFING
Rates for all finished works include the removal of surplus debris unused material and byproducts.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 First class tile roofing, consisting of 4" (100 mm) earth 100Sft. 3549.50 6474.80 sq.m 381.95 696.70 23.1 Add extra 13%, 32% & 51% on
and 1" (25 mm) mud plaster with Gobri leeping over ½" (13 labour rates only or 6%, 15% & 23%
mm) thick cement plaster 1:6 with 34 lbs. per %Sft or on composite rates for 2nd, 3rd, 4th
1.72 Kg/sq.m hot bitumen coating sand blinded, provided & sub- sequent floors, respectively.
over 2 layers of tiles 12"x6"x1¼" (300x150x30 mm) laid in
1:6 cement mortar with ½" (13 mm) thick sand wiched
layer of 1:6 cement mortar, including 1:2 cement pointing
underside of tiles, complete, including curing, etc.

2 Second class tile roofing consisting of 4" (100 mm) earth 100Sft. 2692.80 4912.95 sq.m 289.75 528.65 23.2 ditto
and 1" (25 mm) mud plaster with Gobri leeping over ½" (13
mm) thick cement plaster 1:6 with 34 lbs. per %Sft or
1.72 Kg/sq.m of hot bitumen coating sand blinded,
provided over one layer of 12"x6"x2" (300x150x50 mm)
tiles laid in 1:6 cement mortar, including 1:2 cement
pointing underneath of tiles complete including curing, etc.

3 Covering mud roof with coal tar, and fine sand. 100Sft. 153.80 654.15 sq.m 16.55 70.40 23.1 to 23.2 ditto

4 Filling spaces in between:-

a) Wooden battens over beams, filled with 100Sft. 264.00 1061.00 sq.m 28.40 114.15 Add extra 13%, 32% & 51% on
deodar wood pieces (spacers). roof area labour rates only or 6%, 15% &
b) RCC battens, filled with CC block 1:3:6. -ditto- 513.25 748.10 55.25 80.50 23% on composite rates for 2nd,
c) Spaces filled with bricks. -ditto- 144.15 376.55 15.50 40.50 3rd, 4th & sub- sequent floors,
respectively.

5 Single layer of tiles 9"x4½"x1½" (225x113x40 mm) laid 100Sft. 825.00 3355.85 sq.m 88.75 361.10 23.1 ditto
over 4"(100 mm) earth and 1" (25 mm) mud plaster without
Bhoosa, grouted with cement sand 1:3 on top of RCC roof
slab, provided with 34 lbs. per %Sft. or 1.72 Kg/Sq.m
bitumen coating sand blinded.

chapter-9(Roofing) Page 1
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

6 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 to For steel part and its erection etc.
mortar, including an average depth of 4" (100 mm) cement 23.5 items 10 & 14 under Chapter IRON
concrete in haunches and over crown, with 3" (75 mm) WORK be referred.
earth and 1" (25 mm) plaster, soffits of arches cement
plaster 1:6 and ½" (13 mm) thick. The rate also includes Add extra 13%, 32% & 51% on
bitumen coating, centring, laying skew bricks in cement labour rates only or 6%, 15% & 23%
mortar (1:3), and encasing exposed flanges of the joints on composite rates for 2nd, 3rd, 4th
with fine cement concrete 1:2:4 using stone aggregate:- & sub- sequent floors, respectively.

a) cement concrete in haunches 1:6:12. 100Sft. 3880.80 9664.40 sq.m 417.55 1039.90
b) cement concrete in haunches 1:3:6. ditto 3880.80 10466.70 ditto 417.55 1126.20

7 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 For steel part and its erection etc.
mortar, including an average depth of 4" (100 mm) cement to items 10 & 14 under Chapter IRON
concrete in haunches and over crown, with ½" (13 mm) 23.5 WORK be referred.
cement plaster 1:6 on top (except earth filling mud plaster
and gobri) soffit of arches cement plastered. The rate also Add extra 13%, 32% & 51% on
includes bitumen coating, centring, laying skew bricks in labour rates only or 6%, 15% & 23%
cement sand mortar (1:3), and encasing exposed flanges on composite rates for 2nd, 3rd, 4th
of the joints with fine cement concrete 1:2:4 using stone & sub- sequent floors, respectively.
aggregate:-

a) cement concrete in haunches 1:6:12. 100Sft. 3128.40 9075.20 sq.m 336.60 976.50
b) cement concrete in haunches 1:3:6. ditto 3128.40 9525.70 ditto 336.60 1024.95

8 Extra for vaulted jack arch roofing. 100Sft. 844.80 sq.m 90.90 - ditto

9 Jack arch roofing of shingle and cement concrete 1:3:6, 100Sft. 3960.00 8845.30 sq.m 426.10 951.75 23.3 ditto
4½" (113 mm) thick at crown, with ½" (13 mm) cement to
plaster including cost of supplying, erecting and 23.5
dismantling centring.

10 Earth filling over roof including watering, ramming with 1" 23.1 Add extra 13%, 32% & 51% on
(25 mm) mud plaster finished, with gobri leeping: to labour rates only or 6%, 15% & 23%
23.3 on composite rates for 2nd, 3rd, 4th
a) 3" (75 mm) thick earth filling and 1" (25 mm) mud 100Sft. 343.20 569.85 sq.m 36.95 61.30 & sub- sequent floors, respectively.
plaster

b) 4" (100 mm) thick earth filling and 1" (25mm) 100Sft. 442.85 711.50 sq.m 47.65 76.55
mud plaster

11 1/8" (3 mm) thick gobri leeping on roofs or floors. 100Sft. 56.75 68.90 sq.m 6.10 7.40 ditto ditto

chapter-9(Roofing) Page 2
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

12 Two coats of bitumen laid hot using 34 lbs. per %Sft, or 100Sft. 264.00 1226.70 sq.m 28.40 132.00 23.1
1.72 Kg per square metre over roof and blinded with sand
at one Cft. per %Sft. (0.003 cu.m per sq.m)

13 Providing & Fixing corrugated galvanized iron sheets with G.I. bolts, 23.7 Add extra 13%, 32% & 51% on
nuts, limpet and bitumen washers, wind ties, complete in labour rates only or 6%, 15% & 23%
all respects without valleys and ridges:- on composite rates for 2nd, 3rd, 4th
& sub- sequent floors, respectively,
a) 20 BWG 100Sft. 528.00 13305.40 sq.m 56.80 1431.65 on items 13 to 18.
b) 22 BWG 100Sft. 528.00 11230.20 sq.m 56.80 1208.35
c) 24 BWG 100Sft. 528.00 9035.40 sq.m 56.80 972.20

14 Khassi parnalas in cement, sand mortar 1:2, 12" (300 Rft. 42.65 56.60 Metre 139.90 185.65 23.10
mm) outside width finished smooth with a floating coat of
neat cement.

15 Khuras on roof 2'x2'x6" (600 x 600 x 150 mm) Each 157.10 268.75 Each Each 268.75 23.10

16 Bottom Khuras of brick masonry in cement mortar 1:6, Each 157.10 400.70 Each 157.10 400.70 23.10
4'x2'x4½" (1200x600x113 mm) over 3" (75 mm) cement
concrete 1:4:8.

17 Plain galvanized iron sheets 22 SWG rain water down pipe


including clamp and fixing in position.

a) 4" (100 mm) diameter down pipe Per Rft. 33.25 119.05 Metre 109.05 390.50
b) 5" (125 mm) diameter down pipe Per Rft. 33.25 139.55 Metre 109.05 457.70

18 Plain galvanized iron sheet flashing, 22 gauge. Per Sft. 33.25 103.05 sq.m 357.75 1108.80 23.11

19 Providing and fixing 1/16" (1.5 mm) thick lead flashing over Per Sft. 6.80 68.25 Sq.m 73.15 734.35
roof expansion joint complete in all respects.

20 Cast iron rain water downpipe fixed in position, excluding Add extra 13%, 32% & 51% on
heads and shoes, but including painting and clamps, etc:- labour rates only or 6%, 15% & 23%
on composite rates for 2nd, 3rd, 4th
a) 4" dia (100 mm) cast iron down pipe. Per Rft. 30.80 173.95 Metre 101.00 570.55 & sub- sequent floors, respectively,
b) 3" (75 mm) cast iron down pipe. Per Rft. 30.80 150.65 Metre 101.00 494.15 on items 19 to 24

21 Rain water down pipe cast iron head fixed in place, Each 112.85 379.25 Each 112.85 379.25
including cost of clamp holdfast and painting.

chapter-9(Roofing) Page 3
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

22 Shoes, bends or offsets for cast iron rain water down pipe, Each 27.70 247.40 Each 27.70 247.40
including fixing and painting.

23 Plain GI sheet iron spouts fixed in position, including Each 138.60 239.00 Each 138.60 239.00 23.10
painting.

24 Laying ½" (13 mm) thick deodar ceiling complete, 100Sft. 2838.00 9237.35 sq.m 305.35 993.95 26.1
including sawing, planing and fixing.

25 Flat sheet roof with galvanized iron plain sheets, including


battens, rolls, screws, clips etc. (Planking to be paid for
separately):-

a) 22 BWG sheets roofing 100Sft. 1669.80 11868.40 sq.m 179.65 1277.05 23.60
b) 24 BWG sheets roofing 100Sft. 1669.80 10501.20 sq.m 179.65 1129.95

26 Asbestos cement corrugated sheet roofing including 100Sft. 1122.00 4690.80 sq.m 120.75 504.75 23.8
necessary overlaps, and GI hook bolts, nuts, screws,
washers and bitumen washers, etc. (excluding valleys and
ridges, etc).

27 Extra labour for erection of GI sheets, flat sheet or 100Sft. 123.20 -- sq.m 13.25 - 23.6
asbestos sheet roofing, above 20' (6.10 m) height in
difficult position, including lifting with care and special
scaffolding along live electric wires.

28 Fixing asbestos cement sheet ridges and valleys ¼" Per Rft. 13.55 58.95 Metre 44.45 193.35 23.8
(6 mm) thick.

29 Plain galvanized iron sheet ridging, including fixture, 23.6


timber for ridge roll and ridge sheeting:-

a) 6" (150 mm) lap and 18" (450 mm) Per Rft. 37.60 229.40 Per Metre 123.35 752.45
overall, of 22 gauge G.I sheet ridging.
b) 9" (225 mm) lap and 24" (600 mm) Per Rft. 47.50 231.85 Per Metre 155.80 760.45
overall, of 24 gauge G.I sheet ridging.
c) 12" (300 mm) lap and 30" (750 mm) Per Rft. 47.50 291.10 Per Metre 155.80 954.80
overall, of 22 gauge G.I sheet ridging.

30 Plain 22 gauge G.I sheet gutter semi circular Per Rft. 16.65 124.45 Per Metre 54.60 408.20 23.11
8" (200 mm) dia meter.

chapter-9(Roofing) Page 4
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

31 Making masonry ventilators in cement, sand Each 616.00 854.05 Each 616.00 854.05
mortar 1:4

32 Fixing water spouts or parnalas. Each 184.80 -- Each 184.80 - 23.10

33 Making drip course 2"x½" (50x13 mm) under RCC slab edges Per Rft. 6.60 7.45 Metre 21.65 24.45
in outer opening, in cement, sand mortar 1:2.

34 Supplying and laying of twin G.I sheet 20 SWG duly Per Sft. 19.05 249.90 sq.m 205.00 2688.90
painted with bitumen, with polythene film in between 300
gauge, to provide a sliding joint under the bearing of the
beams, including 3" (75 mm) long, 3/8" (10 mm) dia bar to
act as holdfast on wall and beam.

35 Providing and laying roof insulation, comprising of single


layer of tiles 9"x4½"x1½" (225x113x40 mm) grouted with
cement sand mortar 1:3 laid over 2" (50 mm) thick earth
(including mud plaster) over thermopore sheet, over
polythene sheet 300 gauge over a layer of bitumen,
complete in all respects:-

i) Thermopore sheet ½ " (13 mm) thick 100Sft. 1270.50 3923.35 sq.m 136.70 422.15
ii) Thermopore sheet ¾ " (20 mm) thick 100Sft. 1270.50 4050.60 sq.m 136.70 435.85
iii) Thermopore sheet 1" (25 mm) thick 100Sft. 1273.45 4178.30 sq.m 137.00 449.60

36 Providing and fixing AC rain water down pipe 4" (100 mm) Rft. 7.90 82.70 Metre 25.90 271.25
dia, with shoe, T-bend, clamp, etc.

37 Making jharries in existing brick masonry for providing Rate will be increased by 1.5 time
recesses for bearing of RCC roof slab, including repairing for stone masonry or plain; concrete;
the damaged face:- and 2 times for reinforced cement
concrete.
i) for slabs upto 6" (150 mm) thick Rft. 11.90 13.10 Metre 39.05 42.95
ii) for slabs exceeding 6" to 12" (150 to 300 mm) thick. Rft. 19.45 21.75 Metre 63.80 71.35

38 Making recess in existing brick masonry for bearing of Rates will be increased by 1.5 times
beam, girder, R.S. Joist, etc. including repairing damaged for stone masonry and plain
face:- cement concrete and two times
for reinforced cement concrete.
i) upto 1.0' (300 mm) height of girder or beam. Each 49.50 53.65 Each 49.50 53.65

ii) for every 6" (150 mm) additional height or part thereof. Each 23.75 25.75 Each 23.75 25.75

chapter-9(Roofing) Page 5
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

39 Hoisting RS. Beams and wooden beams and placing in Each 52.80 - Each 52.80 -
position.

40 Hoisting and placing in position sahl ballies, over roof. Each 26.40 - Each 26.40 -

41 Hoisting precast R.C.C/prestressed concrete


battens and placing in position.

a) 5' to 6' (1.50 to 1.83 m) long Each 22.65 - Each 22.65 -


b) 6' to 7' (1.83 to 2.13 m) long Each 31.70 - Each 31.70 -
c) 7' to 8' (2.13 to 2.44 m) long Each 39.60 - Each 39.60 -
d) 8' to 9' (2.44 to 2.74 m) long Each 52.80 - Each 52.80 -
e) above 9' (2.74 m) length Each 63.35 - Each 63.35 -

42 Hoisting and placing in position R.C. trough: Applicable only to roof trough
(inverted tees & trough) for height of
a) upto 10' (3 m) in length Each 63.35 - Each 63.35 - 1st storey only.
b) 10' to 11' (3 to 3.36 m) in length ditto 79.20 - ditto 79.20 -
c) 11' to 12' (3.36 to 3.66 m) in length ditto 105.60 - ditto 105.60 -
d) 12' to 13' (3.66 to 3.96 m) in length ditto 121.85 - ditto 121.85 -
e) 13' to 14' (3.96 to 4.26 m) in length ditto 132.00 - ditto 132.00 -
f) 14' to 15' (4.26 to 4.57 m) in length ditto 144.00 - ditto 144.00 -
g) 15' to 16' (4.57 to 4.88 m) in length ditto 158.40 - ditto 158.40 -
h) 16' to 17' (4.88 to 5.19 m) in length ditto 176.00 - ditto 176.00 -
i) 17' to 18' (5.19 to 5.49 m) in length ditto 226.30 - ditto 226.30 -
j) 18' to 19' (5.49 to 5.80 m) in length ditto 243.70 - ditto 243.70 -
k) 19' to 20' (5.80 to 6.10 m) in length ditto 264.00 - ditto 264.00 -

43 Hoisting and placing in position R.C. inverted battens:-

i) upto 10' (3.05 m) span Each 47.85 - Each 47.85 -


ii) from 10' to 12' (3.05 to 3.66 m) span ditto 106.35 - ditto 106.35 -
iii) from 12' to 13' (3.66 to 3.96 m) span ditto 127.60 - ditto 127.60 -
iv) from 13' to 14' (3.96 to 4.26 m) span ditto 159.50 - ditto 159.50 -
v) from 14' to 15' (4.26 to 4.57 m) span ditto 174.00 - ditto 174.00 -
vi) from 15' to 16' (4.57 to 4.88 m) span ditto 191.40 - ditto 191.40 -
vii) from 16' to 18' (4.88 to 5.49 m) span ditto 239.25 - ditto 239.25 -
viii) from 18' to 20' (5.49 to 6.10 m) span ditto 382.80 - ditto 382.80 -

44 Reinforced cement concrete spout, including fixing in Each 246.40 412.50 Each 246.40 412.50
position, with top and bottom Khurras.

chapter-9(Roofing) Page 6
FLOORING
Rates for all finished works include the removal of surplus debris, unused material and byproducts
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Laying Murum flooring, consisting of 1"(25 mm) layer of 100 Sft. 1402.50 2621.10 sq.m 150.90 282.05
fine powdery or flakey variety of Murum, laid over 6"(150
mm) good hard layer of Murum spreaded over 9"(225 mm)
thick sub-base comprising of hand packed rubble or
broken bricks properly watered and rammed, provided over
well rammed earth.

2 Earth flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 462.00 672.00 sq.m 49.70 72.30 24.1
layer of moistened earth, including ramming.

3 Providing, laying, watering and ramming brick ballast 1½" 100 Cft. 1046.10 2253.60 cum. 369.50 795.95
to 2"(40 mm to 50 mm) gauge mixed with 25% sand, for
floor foundation, complete in all respects.

4 Mud flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 866.25 1198.80 sq.m 93.20 129.00 24.2
layer of moistened earth and finished off with 1"(25 mm)
mud plaster and gobri leeping.

5 Dry brick paving laid flat, sand grouted, including 100 Sft. 510.85 1719.55 sq.m 54.95 185.00 24.12
preparation of bed by watering, ramming and bringing the
same to proper camber, by ½"(13 mm) thick mud plaster

6 Dry brick on edge paving, sand grouted, including 100 Sft. 911.45 2697.05 sq.m 98.05 290.20 24.12
preparation of bed by watering, ramming & bringing the
same to proper camber, by ½ "(13 mm) thick mud plaster

7 Grouting 4½"(113 mm) dry brick work with cement mortar 100 Sft. 462.00 783.75 sq.m 49.70 84.35
ratio 1: 5

8 Flat brick flooring laid in 1:6 cement mortar, over a bed of 100 Sft. 844.80 2592.60 sq.m 90.90 278.95 24.4
3/4" (20 mm) thick cement mortar, 1:6.

9 Brick on edge flooring, laid in 1:6 cement mortar, over a 100 Sft. 1,095.60 3,610.40 sq.m 117.90 388.50 24.4
bed of ¾" (20 mm) thick cement mortar 1:6.

10 Brick tiles (12"x6"x2") (300x150x50mm) laid in 1:6 100 Sft. 1,056.00 2,024.40 sq.m 113.65 217.85 ditto
cement mortar, over a bed of ¾" (20 mm) thick cement
mortar 1:6.

chapter-10(Flooring) Page 1
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

11 Brick ties (9"x4½"x1½")(225 mm x 113 mm x 40 mm) laid 100 Sft. 1,204.50 2,927.70 sq.m 129.60 315.00 24.4
flat in 1:3 cement mortar, over a bed of 3/4"(20 mm) thick
cement mortar 1:6.

12 Cement tiles (8"x8"x¾")(200 x 200 x 20 mm) laid flat in 100 Sft. 740.50 4,407.55 sq.m 79.70 474.25 24.7
1:2 cement mortar, over 3/4" (20 mm) thick bed of cement
mortar 1:2.

13 Cement concrete tiles laid in 1:2 cement mortar, over 24.8


3/4" (20 mm) thick bed of cement mortar 1:2:-

(a) 12"x12"x1" (300 x 300 x 25 mm) 100 Sft. 740.50 3,031.35 sq.m 79.70 326.15
(b) 9"x9"x¾" (225 x 225 x 20 mm) ditto 740.50 3,978.50 ditto 79.70 428.10
(c) 6"x6"x¾"(150 x 150 x 20 mm) ditto 740.50 5,571.85 ditto 79.70 599.55

14 Coloured cement tiles (8"x8"x¾")(200 x 200 x 20 mm) of 100 Sft. 740.50 4,432.75 sq.m 79.70 476.95 24.7
approved dark shade laid flat in 1:2 cement mortar, over
¾" (20 mm) bedding mortar of 1:2.

15 Providing and laying topping of cement concrete 1:2:4, 24.9 If glass or marble strips are used
including surface finishing and dividing in panels:- for panelling, it will be paid extra as
per item No. 41 or 42.
(a) 1"(25 mm) thick 100 Sft. 897.60 1,707.35 sq.m 96.60 183.70
(b) 1¼"(30 mm) thick ditto 897.60 1,889.40 ditto 96.60 203.30
(c) 1½"(40 mm) thick ditto 1,074.15 2,248.05 ditto 115.60 241.90
(d) 1¾"(45 mm) thick ditto 1,074.15 2,437.25 ditto 115.60 262.25
(e) 2"(50 mm) thick ditto 1,250.70 2,837.40 ditto 134.60 305.30
(f) 2¼"(56 mm) thick ditto 1,283.70 3,039.80 ditto 138.15 327.10
(g) 2½"(62 mm) thick ditto 1,427.25 3,302.30 ditto 153.55 355.35
(h)2¾"(70 mm) thick ditto 1,427.25 3,553.65 ditto 153.55 382.35
(i) 3"(75 mm) thick ditto 1,427.25 3,762.75 ditto 153.55 404.85

16 Providing and laying conglomerate flooring (two coat work) 24.10 If glass or marble strips are used
with top layer of ½"(13mm) thick wearing surface, for panelling, it will be paid extra as
consisting of one part of cement and 2 parts of stone per item No. 41 or 42.
chips passing 3/16"(6 mm) sieve, over bottom layer of
cement concrete 1:3:6, including surface finishing and
dividing in panels:-

(a) 1½"(40 mm) thick 100 Sft. 1,296.90 2,434.45 sq.m 139.55 261.95
(b) 1¾"(45 mm) thick ditto 1,296.90 2,552.30 ditto 139.55 274.65
(c) 2"(50 mm) thick ditto 1,615.35 3,063.25 ditto 173.80 329.60

chapter-10(Flooring) Page 2
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

17 Add extra in cement concrete floor topping, if finished with 100 Sft. 112.20 500.45 sq.m 12.05 53.85
pigment and polishing.

18 Extra labour for each storey above ground, for mosaic, 100 Sft 198.00 - sq.m 21.30 - On items 19-25 & 29-34
conglomerate, tiles, stone and wooden floor.

19 Flag stone flooring in lime mortar 1:2, over ¾"(20 mm) 24.5
bedding mortar, in platforms and floors, etc.

(a) 2"(50 mm) thick 100 Sft. 2,570.05 3,887.95 sq.m 276.55 418.35
(b) 3"(75 mm) thick ditto 2,570.05 4,184.45 ditto 276.55 450.25

20 Asphalt flooring , including preparation of proper base 24.10


remelting, setting out, and finishing complete:-

(a) 1"(25 mm) thick topping 100 Sft. 924.00 9,668.35 sq.m 99.40 1040.30
(b) ½"(13 mm) thick topping ditto 729.30 5,189.35 ditto 78.45 558.35
(c) ¼"(6 mm) thick topping ditto 546.50 2,856.70 ditto 58.80 307.40

21 13/8"(35 mm) thick mosaic flooring, consisting of 3/8"(10 If glass or marble strips are used
mm) mosaic topping of one part of cement and marble for panelling, it will be paid extra as
powder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.
laid over 1"(25 mm) thick flooring of 1:2:4 cement concrete
including rubbing and polishing complete :-

(a) using grey cement 100 Sft. 3,298.70 4,884.65 sq.m 354.95 525.60
(b) using white cement ditto 3,298.70 5,031.30 ditto 354.95 541.35

22 1½"(40 mm) thick mosaic flooring, consisting of ½ "(13 If glass or marble strips are used
mm) mosaic topping of one part of cement and marble for panelling, it will be paid extra as
powder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.
laid over 1"(25 mm) thick floor of 1:2:4 cement concrete,
including rubbing and polishing complete with finishing :-

(a) using grey cement 100 Sft. 3,298.70 4,989.65 sq.m 354.95 536.90
(b) using white cement ditto 3,298.70 5,300.50 ditto 354.95 570.35

23 Providing and laying floor of mosaic marble chips tiles 100 Sft. 2,095.50 5,406.30 sq.m 225.50 581.70 24.8
1"(25 mm) thick of approved quality and shade, laid in
white cement and pigment, over ¾"(20 mm) thick bedding
of cement sand mortar 1:2, including finishing and
polishing, complete.

chapter-10(Flooring) Page 3
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

24 Laying floor of approved white glazed tile ¼" (6 mm) thick 100 Sft. 2,623.50 7,113.55 sq.m 282.30 765.40 24.7
in white cement 1:2 over ¾" (20mm) thick cement mortar
1:2, complete.

25 Laying floor of approved coloured glazed tiles ¼ "(6 mm) 100 Sft. 2,623.50 7,403.35 sq.m 282.30 796.60 ditto
thick, laid in white cement and pigment on a bed of ¾"
(20 mm) thick cement mortar 1:2.

26 Rubbing and polishing old grit/ mosaic floor, including 100 Sft. 590.05 697.55 sq.m 63.50 75.05 The composite rate will be reduced
repairing voids, uneven surface, complete in all respects. by Rs. 150.00 per % Sft or Rs.13.95 per
Sq. metre respectively, if no
polishing is done.

27 Rubbing and polishing grit floor, including repairing voids, 100 Sft. 617.75 738.35 sq.m 66.45 79.45 The composite rate will be reduced
uneven surface, complete in all respects by Rs. 150.00 per % Sft or Rs.13.95 per
Sq. metre respectively, if no
polishing is done.

28 Cleaning and washing mosaic or marble floor with caustic 100 Sft. 108.00 149.70 sq.m 11.60 16.10 24.6
soda mixture.

29 Shisham wood boarding or strip flooring 3/4" (20mm) thick 100 Sft. 2,123.00 16,442.05 sq.m 228.45 1769.15 24.13
(sawn to required size) tongued and grooved or splayed
rebated fixed with brass screws on deodar wood battens
1½ "x2"(40 x 50 mm),size placed at 12"(300 mm) centre
to centre, including two coats of bitumen laid hot on the
base.

30 Deodar wood boarding or strip flooring 3/4" (20 mm) thick 100 Sft. 2,376.00 19,583.75 sq.m 255.65 2107.20 ditto
(sawn to required size) tongued and grooved or splayed
rebated fixed with brass screws on deodar wood battens
1½"x2"(40 x 50 mm) size , placed at 12"(300 mm) centre,
to centre including two coats of bitumen laid hot on the
base.

31 Teak wood boarding or strip flooring ½" (13 mm) "thick 100 Sft. 2,090.00 32,809.75 sq.m 224.90 3530.35 ditto
(sawn to required size) to tongued and grooved screwed
on deodar wood battens 1½ " x2"(40 x 50 mm) size,
placed at 12"(300 mm) centre to centre, including 2 coats
of bitumen laid hot on base.

chapter-10(Flooring) Page 4
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

32 Shisham wood block flooring 1"(25 mm) thick cut to 100 Sft. 2,211.00 18,811.20 sq.m 237.90 2024.10 24.13
required size, fixed on a layer of asphalt bitumen laid on
base.

33 Teak wood block 1"(25 mm) thick cut to required size, 100 Sft. 2,090.00 60,641.45 sq.m 224.90 6525.00 ditto
fixed on a layer of asphalt bitumen laid on base.

34 Laying wooden paving of hard wood on edge in coal tar ditto


and asphalt:- 100 Sft. sq.m
Per Inch per cm
(a) Shisham wood thickness 1,364.00 11,398.55 thickness 146.75 1226.50
(b) Kikar wood ditto 1,364.00 5,550.35 ditto 146.75 597.20

35 Tile skirting laid in 1:2 cement mortar, over ¾"(20 mm)


thick cement mortar, 1:2 including cement washing and
filling joints complete:-

(a) cement tiles 100 Sft. 1,220.10 5,167.50 sq.m 131.30 556.00
(b) mosaic tiles ditto 2,070.75 7,249.95 ditto 222.80 780.10

36 Providing grey cement skirting or dado 3/8"(10 mm) thick


including rounding of corner and straight ening of top edge
and finishing to smooth surface afterplastering :-

(a) 1:2 cement, sand mortar 100 Sft. 1,646.85 2,051.75 sq.m 177.20 220.75
(b) 1:3 cement, sand mortar ditto 1,646.85 1,933.45 ditto 177.20 208.05
(c) Extra if skirting or dado is finished ditto 82.50 311.00 ditto 8.90 33.45
with pigment of any colour.

37 White glazed tile¼"(6 mm) thick dado jointed in white 100 Sft. 3,250.50 7,740.55 sq.m 349.75 832.90 24.7
cement and laid over 1:2 cement sand mortar 3/4" (20mm)
thick, including finishing.

38 Coloured glazed tile dado ¼" (6mm) thick in pigment over 1:2 100 Sft. 3,250.50 8,015.75 sq.m 349.75 862.50 ditto
cement, sand mortar 3/4"(20mm) thick, including finishing.

39 Mosaic dado or skirting with one part of cement and


marble powder in the ratio of 3:1 and two parts of marble
chips, laid over ½"(13 mm) thick cement plaster 1:3,
including rubbing and polishing, complete with finishing:

(a) using grey cement:


i) 3/8"(10 mm) thick 100 Sft. 3,828.00 4,592.20 sq.m 411.90 494.10
ii) ½"(13 mm) thick ditto 3,828.00 5,133.35 ditto 411.90 552.35

chapter-10(Flooring) Page 5
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(b) using white cement :

'i) 3/8"(10 mm) thick 100 Sft. 3,828.00 5,142.60 sq.m 411.90 553.35
ii) ½"(13 mm) thick ditto 3,828.00 5,331.45 ditto 411.90 573.65

40 Rubber flooring, consisting of 12"x12"x1/8" Per Sft. 10.90 67.90 sq.m 117.30 730.60 24.14 The cost of base for rubber flooring
(300x300x3mm) rubber tiles, laid on firm foundation. is not included in the rate and is
payable separately.

41 Providing and fixing glass strip 5mm thick and 1½" Per Rft. - 3.95 Metre - 12.95 Labour for fixing already included in
(40 mm) wide, for dividing the mosaic flooring into panels. items No. 15, 16, 21and 22 of this
Chapter.

42 Providing and fixing marble strip of any shade for dividing


the mosaic flooring into panels

a) sSize 1½" x 3/8" (40 x 10 mm) Per Rft. - 5.30 Metre - 17.40
b) sSize 1½" x ¼" (40 x 6 mm) ditto - 3.70 ditto - 12.15

chapter-10(Flooring) Page 6
SURFACE RENDERING
1 PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING AND DISTEMPERING, ETC.
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Mud plaster on walls (excluding Gobri leeping) upto 20' 25.7


(6.00 m) height:-

a) ½" (13 mm) thick 100 Sft. 222.00 283.20 sq.m 23.90 30.45
b) 1" (25 mm) thick ditto 306.00 428.40 ditto 32.95 46.10

2 Mud plaster on floor or roof (excluding Gobri leeping):- ditto Add extra 13%, 32% and 51% above
the labour rates only or 6%, 15% &
a) ½" (13 mm) thick 100 Sft. 199.30 260.50 sq.m 21.45 28.05 23% on the composite rates for 2nd,
3rd, 4th and subsequenct floors,
b) 1" (25 mm) thick ditto 199.30 321.70 ditto 21.45 34.60 respectively.

3 Cement lime plaster 1:7:12 (cement, lime and sand) upto 25.1 to 25.6
20' (6.00 m) height.

a) ¼" (6 mm) thick 100 Sft. 666.60 765.80 sq.m 71.75 82.40

b) ½" (13 mm) thick ditto 666.60 864.90 ditto 71.75 93.05

4 Cement Neru plaster 1:2 (cement and sand) upto 20' ditto
(6.00 m) height:-

a) ¼" (6 mm) thick 100 Sft. 666.60 970.20 sq.m 71.75 104.40
b) ½" (13 mm) thick ditto 666.60 1159.35 ditto 71.75 124.75

5 2" (50 mm) stucco cement plaster 1:2:4 (cement, sand 100 Sft. 1586.65 3377.10 sq.m 170.70 363.40 ditto
and shingle) upto 20' (6.00 m) height.

6 Providing and laying machine sprayed plaster ½" (13 mm) ditto
thick, using cement and chips zero gauge, over the
existing plastered and roughened surface, upto 20' (6.00
m) height:-

i) ratio 1:1 100 Sft. 640.75 1541.95 sq.m 68.95 165.90


ii) ratio 1:1½ ditto 640.75 1439.35 ditto 68.95 154.85
iii) ratio 1:2 ditto 640.75 1380.55 ditto 68.95 148.55

chapter-11(Surface Rendering) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

7 Cement plaster 1:2 upto 20' (6.00 m) height:- 25.1


to
a) 3/8" (10 mm) thick 100 Sft. 666.60 1071.50 sq.m 71.75 115.30 25.6
b) ½" (13 mm) thick ditto 666.60 1191.30 ditto 71.75 128.20
c) ¾" (20 mm) thick ditto 851.40 1661.20 ditto 91.60 178.75

8 Cement plaster 1:3 upto 20' (6.00 m) height:- ditto

a) 3/8" (10 mm) thick 100 Sft. 666.60 953.20 sq.m 71.75 102.55
b) ½" (13 mm) thick ditto 666.60 1048.75 ditto 71.75 112.85
c) ¾" (20 mm) thick ditto 851.40 1424.60 ditto 91.60 153.30

9 Cement plaster 1:4 upto 20' (6.00 m) height:- ditto

a) 3/8" (10 mm) thick 100 Sft. 666.60 922.00 sq.m 71.75 99.20
b) ½" (13 mm) thick ditto 666.60 991.30 ditto 71.75 106.65
c) ¾" (20 mm) thick ditto 851.40 1357.30 ditto 91.60 146.05

10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. ditto i) This item shall be applicable to
roof slabs only, upto 20' height. buildings meant for human
habitation only, such as buildings
like residences, offices,
a) 1:2 100 Sft. 785.40 1270.00 sq.m 84.50 136.65 educational institutions and
b) 1:3 ditto 785.40 1151.20 ditto 84.50 123.85 hospitals, etc. It shall not be
c) 1:4 ditto 785.40 1120.00 ditto 84.50 120.50 admissible on godowns; bins;
agriculture, poultry and animal
sheds; cycle stands; garrages; etc.
ii) The thickness of the plaster will
not be more than 3/8" (10 mm)
thick.
11 Cement plaster 1:5 upto 20' (6.00 mm) height:- 25.1 to 25.6

a) 3/8" (10 mm) thick 100 Sft. 666.60 894.30 sq.m 71.75 96.25
b) ½" (13 mm) thick ditto 666.60 943.80 ditto 71.75 101.55
c) ¾" (20 mm) thick ditto 851.40 1306.80 ditto 91.60 140.60

12 Cement plaster 1:6 upto 20' (6.00 mm) ditto


height:-
a) 3/8" (10 mm) thick 100 Sft. 666.60 854.70 sq.m 71.75 91.95
b) ½" (13 mm) thick ditto 666.60 916.10 ditto 71.75 98.55
c) ¾" (20 mm) thick ditto 851.40 1227.60 ditto 91.60 132.10

chapter-11(Surface Rendering) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

13 Applying floating coat of cement 1/32" (0.8 mm) thick. 100 Sft. 440.90 599.30 sq.m 47.45 64.50 25.4 to 25.6

14 Lime pointing flush upto 20' (6.00 m) height including 100 Sft. 481.80 548.00 sq.m 51.85 58.95 25.8
raking joints, in lime, sand mortar 1:2.

15 Lime pointing struck joints on walls, upto 20' (6.00 m) 100 Sft. 785.40 851.60 sq.m 84.50 91.65 ditto
height, including raking joints in lime sand mortar 1:2.

16 Cement pointing flush upto 20' (6.00 m) heihgt:- ditto

a) ratio 1:2 100 Sft. 666.60 969.55 sq.m 71.75 104.30


b) ratio 1:3 ditto 666.60 900.25 ditto 71.75 96.85

17 Cement pointing 1:2 flush on floor. 100 Sft. 481.80 784.75 sq.m 51.85 84.45 ditto

18 Cement pointing struck joints, on walls, upto


20' (6.00 m) hiehgt:-

a) ratio 1:2 100 Sft. 785.40 1088.35 sq.m 84.50 117.10


b) ratio 1:3 ditto 785.40 1019.05 ditto 84.50 109.65

19 Pointing flush on stone work, upto 20' (6.00 m) height. 25.8

a) in lime mortar 1:2 (lime, sand) 100 Sft. 653.40 740.40 sq.m 70.30 79.65
b) in cement mortar 1:3 ditto 653.40 887.05 ditto 70.30 95.45
c) on stone work raised:-
i) in lime mortar 1:2 100 Sft. 1260.60 1347.60 sq.m 135.65 145.00
ii) in cement mortar 1:3 ditto 1260.60 1494.25 ditto 135.65 160.80

20 Raking and washing joints of stone masonry 100 Sft. 279.85 - sq.m 30.10 - ditto
(old work).

21 Raking and washing joints of brick masonry (old work). 100 Sft. 139.90 - sq.m 15.05 - ditto

22 Priming coat of chalk under distemper. 100 Sft. 73.90 79.40 sq.m 7.95 8.55 25.11

23 Distempering:- ditto

a) new surface:-
i) one coat 100 Sft. 69.95 136.70 sq.m 7.55 14.70
ii) two coats ditto 103.40 190.15 ditto 11.15 20.45
iii) three coats ditto 136.85 243.55 ditto 14.75 26.20

chapter-11(Surface Rendering) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) old surface:-
i) one coat 100 Sft. 63.80 110.60 sq.m 6.85 11.90
ii) two coats ditto 103.40 150.20 ditto 11.15 16.15

24 Colour washing:- 25.10

a) new surface:-
i) one coat 100 Sft. 49.40 75.15 sq.m 5.30 8.10
ii) two coats ditto 74.15 111.55 ditto 8.00 12.00

b) old surface:-
i) one coat 100 Sft. 49.40 63.60 sq.m 5.30 6.85
ii) two coats ditto 74.15 94.40 ditto 8.00 10.15

25 White washing:- 25.9

a) new surface:-
i) one coat 100 Sft. 49.40 69.65 sq.m 5.30 7.50
ii) two coats ditto 74.15 104.35 ditto 8.00 11.25
iii) three coats ditto 96.05 136.30 ditto 10.35 14.65

b) old surface:-
i) one coat 100 Sft. 49.40 64.60 sq.m 5.30 6.95
ii) two coats ditto 74.15 99.35 ditto 8.00 10.70

26 Gobri leeping:- 25.7

a) on walls 100 Sft. 82.35 85.80 sq.m 8.85 9.25


b) over roofs ditto 68.10 71.55 ditto 7.35 7.70

27 Striking joints of burnt bricks in lime or cement mortar. 100 Sft. 118.80 - sq.m 12.80 - 25.8 Payable with fresh masonry, when
the face of the work is not to be
plastered/pointed.
28 Extra for lime, mud or cement plaster and pointing from 100 Sft. 123.00 - sq.m 13.25 -
20' (6.00 m) and above for each additional 10' (3.00 m)
height or part thereof.

29 Caulking joints of sleeper wall, with sand and coaltar. 100 Sft. 271.90 562.20 sq.m 29.25 60.50

30 Caulking joints of sleepers, withmud and chopped straw. 100 Sft. 271.90 292.30 sq.m 29.25 31.45

31 Extra cost of labour and material for red oxide pigment in 100 Sft. 87.45 179.85 sq.m 9.40 19.35
cement pointing to match with the colour of bricks.

chapter-11(Surface Rendering) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

32 Providing grooved cement sand plaster 1:3 over existing


plastered and roughened surface upto 20' (6.00 m) height.

i) 3/8" (10 mm) thick 100 Sft. 785.40 1072.00 sq.m 84.50 115.35
ii) ½" (13 mm) thick ditto 785.40 1167.55 ditto 84.50 125.65

33 Providing and fitting expanded metal edge bead for Rft. 4.15 28.90 Metre 13.60 94.80
corners, with nails on both sides of edges.

34 Petty repairs to fire place.

i) Single Each 129.35 163.20 Each 129.35 163.20


ii) Double Each 258.70 326.40 Each 258.70 326.40
Area above 100 Sft (10.76 sq.m)
35 Petty repair to main rooms. Each 260.70 351.30 Each 260.70 351.30
Area upto 100 Sft (10.76 sq.m)
36 Petty repair to small rooms. Each 130.35 175.60 Each 130.35 175.60

37 Petty repair to verandah. Each 260.70 333.10 Each 260.70 333.10


The height will be taken from the
38 Extra labour for white washing, colour washing, priming coat 100 Sft. 8.25 - sq.m 0.90 - floor, roof or ground uderneath as
and distempering, etc. from 20' (6.00 m) height and above, Per Per the case may be on the side
requiring scaffolding, for every additional 10' (3.00m) height coat coat towards which the work is to be
or part thereof. done.

chapter-11(Surface Rendering) Page 5


WOOD WORK
1 No extra rate is to be paid for sawing as the rates are inclusive of these
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Plain wood work sawn, wrought, planed and fixed 26.1


inposition, including cost of nails and screws etc.

a) Deodar wood Per Cft. 378.50 1825.75 cu.m 13368.60 64485.50


b) Shisham wood ditto 424.60 1458.05 ditto 14996.85 51498.35

2 Plain wood work for regulation karries or needles, etc. 26.1


including sawing, planning, wroughting wood and providing
and fixing steel parts of karries i.e. end strip and rods, etc.

a) Deodar wood Per Cft. 235.30 1697.60 cu.m 8310.80 59959.25


b) Shisham wood ditto 235.30 1294.40 ditto 8310.80 45718.20

3 First class teak wood wrought joinery in doors and 26.1


windows, etc. panelled, panelled and glazed or fully to
glazed and fixed in position, including chowkat, holdfast, 26.3
tower bolt, chocks, rubber stop, cleats/G.I. clamps, &
chords with hooks, nails, screws, etc. complete 26.7
(excluding sliding bolt and lock):-

i) 2" (50 mm) thick Per Sft. 66.60 1107.25 sq.m 716.60 11914.00
ii) 1¾" ( 45 mm) thick ditto 66.60 1032.65 ditto 716.60 11111.30
iii) 1½" (40 mm) thick ditto 66.60 959.80 ditto 716.60 10327.45

4 First class teak wood wrought joinery in wire gauze doors 26.8 i) This also includes the cost of
and windows with frames 22 SWG galvanized iron wire to wood required for extra thickness of
2
gauze 12x12 meshes to square inch, (5x5 meshes in cm ) 26.10 chowkat.
including brass fittings, sash bars, etc. complete:- ii) If 24 SWG wire gauge is used,
the composite rate shall be
a) teak wood framing 1¾" (45 mm) thick with wire gauze reduced by Rs.4.70 per sft. and
fixed in position:- Rs.50.60 per sq.m.

i) without springs or spring hinges. Per Sft. 11.80 457.50 sq.m 126.95 4922.70

ii) with springs or spring hinges ditto 11.80 461.05 ditto 126.95 4960.90

chapter-12(Wood Work) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) teak wood framing 1½" (40 mm) thick, with wire


gauze fixed in position:-
i) without springs or spring hinges. Per Sft. 11.80 421.95 sq.m 126.95 4540.20
ii) with springs or spring hinges. ditto 11.80 425.85 ditto 126.95 4582.15

c) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 21.25 141.10 sq.m 228.65 1518.25
2
inch, (5x5 meshes per cm ) fixed to chowkat with ¾"
(20 mm) teak wood strips and screws.

d) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 19.90 444.35 sq.m 214.10 4781.20
2
inch (5x5 meshes per cm ) fixed with ½" (13 mm) strip
on separate frame of teak wood 2"x2" (50x50 mm),
for windows, etc.

5 P/F expanded metal ½" to ¾" (13 to 20 mm) mesh, 16 Per Sft. 25.35 230.05 sq.m 272.75 2475.35
Guage, fixed to chowkat with 1" (25 mm) teak wood cover
strips and screw etc., complete.

6 Providing and fixing expanded metal ½" (13 mm) to ¾" Per Sft. 26.55 323.50 sq.m 285.70 3480.85
20 mm), 16 gauge, fixed to chowkat with 1" (25 mm)cover
moulding and screws, including teak wood frame 2"x2"
(50 mm x 50 mm)

7 First class deodar wood wrought joinery in doors and 26.1 to


windows, etc. panelled, or panelled or glazed, or fully 26.3 & 26.7
glazed, fixed in position, including chowkat, holdfast,
hinges, tower bolts, chocks, rubber stop, cleats/G.I.
clamps, handles and chord with hooks, etc. complete
(excluding sliding bolt or lock):-

a) 2" thick (50 mm) Per Sft. 64.30 659.70 sq.m 691.85 7098.35
b) 1¾" thick (45 mm) ditto 64.30 617.60 ditto 691.85 6645.50
c) 1½" thick (40 mm) ditto 64.30 588.20 ditto 691.85 6329.05

8 Deodar wood framed, braced and battened doors and 26.1, 26.2
windows, complete with iron fittings and fixed in position, & 26.4
including chowkats:-

a) 2¼" (56 mm) thick, with 1¼" (30 mm) Per Sft. 71.65 332.70 sq.m 770.95 3579.85
battens and 1" (25 mm) planks.
b) 1¾" (40 mm) thick with 1" (25 mm) ditto 65.30 292.40 ditto 702.65 3146.20
battens and ¾" (20 mm) planks.

chapter-12(Wood Work) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

9 1" (25 mm) thick battneded doors and windows fitted in Per Sft. 84.40 202.60 sq.m 908.15 2180.00
position, complete with iron fittings, without chowkats.

10 Deodar battened ledged and braced doors and windows 26.1, 26.2
2¼" (56 mm) thick (1¼" (30 mm) thick ledge braces and 26.4 to
1" (25 mm) thick battens complete with iron fittings, Per Sft. 77.15 191.90 sq.m 830.15 2064.85 26.6
chowkats and fixed in position.

11 a) Deodar wood framed with braces and 22 SWG G.I. 26.1, 26.2 If 24 gauge G.I. sheet is used, the
sheet facing, including holdfast, wooden beadings, & 26.4 composite rate will be reduced by
hinges, and locking arrangements as directed by the Re.4.70 per Sft. (Rs. Per 50.60
Engineer incharge:- Sq.m) for G.I. facing on one side
and Rs.9.40 per Sft. (Rs.101.20
i) G.I. sheet facing on one side. Per Sft. 33.45 343.65 sq.m 359.90 3697.65 per Sq.m) for G.I. sheet facing on
ii) G.I. sheet facing on both sides. ditto 37.05 364.00 ditto 398.65 3916.65 both sides.

b) Partal wood framed with braces and 22 SWG G.I.


sheet facing, including holdfast, wooden beadings, -ditto-
hinges and locking arrangements, as directed by the
Engineer-in-charge:-

i) G.I. sheet facing on one side. Per Sft. 33.45 127.10 sq.m 359.90 1367.60
ii) G.I. sheet facing on both sides. ditto 37.05 147.45 ditto 398.65 1586.55

12 First class deodar wood wrought joinery work in wire 26.8 to i) This also includes the cost of
gauze doors and windows, with 22 SWG G.I. wire gauze, 26.10 wood required for extra thickness
2
12x12 meshes per square inches (5x5 per cm ) including of chowkat.
iron fittings etc. complete:-
ii) If 24 SWG wire gauze is used
a) deodar wood framing 1¾" (45 mm) thick with wire the composite rate shall be
gauze fixed in position:- reduced by Rs.4.70 per sft or
Rs.50.60 per sq.m.
i) without springs or spring hinges. Per Sft. 35.40 289.10 sq.m 380.90 3110.70
ii) with springs or spring hinges. ditto 35.40 293.00 ditto 380.90 3152.70

b) deodar wood framing 1½" (40 mm) thick, with wire


gauze fixed in position:-
i) without springs or spring hinges Per Sft. 35.40 269.55 sq.m 380.90 2900.35
ii) with springs or spring hinges ditto 35.40 272.45 ditto 380.90 2931.55

c) G.I. wire gauze 22 SWG, 12x12 meshes per square


2
inch, (5x5 in cm ) fixed to chowkat, with ¾" Per Sft. 26.55 97.35 sq.m 285.70 1047.50
('20 mm) thick deodar wood strip and screws.

chapter-12(Wood Work) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

d) G.I. wire gauze 22 SWG 12x12 meshes per square


2
inch, (5x5 meshes in cm ) fixed to chowkat, with ½" Per Sft. 39.80 259.60 sq.m 428.25 2793.30
(13 mm) strip on separate frame of deodar wood 2" x
2" (50 mm x 50 mm).

13 Making and fixing trellis doors and windows of deodar Per Sft. 57.95 227.50 sq.m 623.55 2447.90 26.1
wood, complete. 26.2

14 Providing and fixing mild steel chowkat of doors, windows,


C.window, etc. including holdfast, making and threading
holes for hinges, etc. complete:-

a) M.S. angle iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 15.75 131.05 sq.m 169.45 1410.10
with M.S. flat 2"x ¼" (50 mm x 6 mm)

b) M.S. tee iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 15.75 98.30 sq.m 169.45 1057.70
with M.S. flat 2"x ¼" (50 mm x 6 mm)

15 Providing and fixing M.S. sheet hollow pressed frame of


doors, windows, C. windows, etc. (chowkat only) of 20
SWG welded with M.S. flat 6"x 1¼" x 1/8" (150
mmx30mmx3mm) M.S. holdfast 9"x1"x1/8"
(225mmx25mmx3mm) welded/screwed 4" (100 mm) long
iron hinges, including filling chowkat with cement sand
mortar 1:8 and embedding holdfast in cement concrete
1:2:4, complete in all respects:

a) single rebate Per Sft. 20.40 114.05 sq.m 219.50 1227.20


b) double rebate ditto 24.50 130.20 ditto 263.60 1400.95

16 Extra for providing and fixing iron double spring hinges, Per Sft. 1.95 29.95 sq.m 21.00 322.25 26.2
with brass fittings (it shall include brass finger plate, 6" door area door area
(150 mm) tower bolt).

17 Providing and fixing brass spring hinges to wire gauzed Each 40.60 160.60 Each 40.60 160.60
doors.

18 Providing and fixing sliding bolt to doors:-

i) iron sliding bolt, 10" (250 mm) long Each 39.80 87.80 Each 39.80 87.80
ii) iron sliding bolt, 12" (300 mm) long ditto 39.80 123.80 ditto 39.80 123.80
iii) brass sliding bolt, 10" (250 mm) long ditto 39.80 129.80 ditto 39.80 129.80
iv) brass sliding bolt, 12" (300 mm) long ditto 39.80 291.80 ditto 39.80 291.80

chapter-12(Wood Work) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

19 Extra for brass fittings to doors and windows, except for


hinges, which shall be of iron:-

i) deodar wood panelled or panelled and Per Sft. 1.15 10.00 sq.m 12.35 107.60
glazed or fully glazed.
ii) deodar wood wire gauzed shutters. ditto 1.15 8.20 ditto 12.35 88.25

20 Extra for providing and fixing approved quality rim lock Each 124.00 311.20 Each 124.00 311.20
adjustable over the style surface.

21 Providing and fixing, approved quality mortice lock. Each 173.80 358.60 Each 173.80 358.60

22 Providing and fixing, expended metal ½" to ¾" (13 mm to


20 mm) mesh 16 gauge.

a) fixed to chowkat with 1" (25 mm) thick deodar wood Per Sft. 25.35 162.00 sq.m 272.75 1743.10
strip and screws, etc.
b) fixed with 1" (25 mm) cover moulding and screws, ditto 26.55 217.05 ditto 285.70 2335.45
including deodar wood frame 2"x2" (50 x 50 mm)

23 a) Providing and fixing deodar wood almirah 9" to 12" For hollow frame shutter with
(225 mm to 300 mm) depth, including boxing with Per Sft. 88.65 935.25 sq.m 954.00 10063.25 commercial ply on one side, the
back, shelves, shutter and brass fittings, etc. composite rate shall be reduced by
complete. Rs.54.00 per Sft;or Rs.580.00
per Sqm and for hollow frame
shutter with commercial ply on
both sides, the composite rate
shall be reduced by Rs.22.80 per
Sft. or Rs.245.00 per Sq. metre.
b) Providing and fixing deodar wood almirah 9" to 12"
(225 mm to 300 mm)depth with shelves, shutters, Per Sft. 65.55 252.35 sq.m 705.45 2715.40
brass fittings, etc., without boxing and back,
complete.

24 Providing and fixng class room almirah consiting of 1" (25 Per Sft. 42.75 255.90 Sq.m 459.90 2753.40
mm) thick solid flush shutter with deodar wood lipping ¼"
(6 mm) thick all around (sterling made) fixed in deodar
wood frame 3"x1" (75mm x 25mm) including full hinges
C.P. fittings with RCC (1:1½:3) shelves 1½" (40 mm) thick
including 3 coats of painting.

chapter-12(Wood Work) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

25 Providing and fixing wooden box type wardrobe 22" (550 If hollow flush door leaves 1" thick
mm) deep including ¾" (20 mm) thick boxing and shelves, (25 mm) with commercial ply
hanger rods, hard board back drawers, brass fittings, 3 ply) on both sides of deodar
locking arrangements, handles, internal bolts, shoe rods, wood frame and partal wood
etc. including three coats of enamel paint:- bracing and deodar wood lipping is
used, the composite rate will be
i) Partal wood boxing and deodar wood reduced by Rs.13.00 per Sft. or
shelves and leaves, etc. Per Sft. 98.00 346.30 sq.m 1054.30 3725.95 Rs.140.00 per Sq. metre.

ii) Deodar wood boxing, and deodar wood ditto 95.05 426.25 ditto 1022.65 4586.65
shelves and leaves, etc.

26 Providing and fixing wardrobe 22" (550 mm) deep


consisting of RCC shelves 1½" (40 mm) thick including ½"
thick vinboard boxing and back (one side ply) vinboard Per Sft. 38.30 320.70 Sq.m 411.90 3450.60
shutter ¾" (20 mm) thick including deodar wood lipping ¼"
(6 mm) on all edges, fixes including deodar wood frame
3"x1" (75mm x 25mm) with hanger rod in centre position
drawers at bottom and openable shutter on upper portion
including full hinges C.P. fitting and painting 3 coats
complete.

27 Providing and fixing chowkat for doors, windows and C.


windows, including holdfast, etc.

a) Teak wood Per Sft. 18.45 377.75 Sq.m 198.60 4064.55


b) Deodar wood ditto 11.80 215.95 ditto 126.90 2323.85
c) Shisham wood ditto 13.75 81.15 ditto 147.80 873.25

28 Making and fixing deodar wood planking in eave boards, 26.1


etc. planed on both sides, rebated and fixed including 26.2
nails and screws, bolts and brackets:-

a) 1" (25 mm) thick Sft. 22.00 136.25 sq.m 236.50 1466.20
b) ¾" (20 mm) thick ditto 22.00 107.70 ditto 236.50 1158.90
c) ½" (13 mm) thick ditto 22.00 79.25 ditto 236.50 852.90

29 Making and fixing deodar wood shelves, including ditto


brackets:-

i) 1" (25 mm) thick Sft. 22.00 136.25 sq.m 236.50 1466.20
ii) 1½" (40 mm) thick ditto 22.00 193.25 ditto 236.50 2079.55
iii) 2" (50 mm) thick ditto 22.00 250.25 ditto 236.50 2692.85

chapter-12(Wood Work) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

30 a) Making and fixing cleats for doors and windows, Each 25.50 79.80 Each 25.50 79.80 26.1 and
including hinges and screws. 26.2

b) Making and fixing cleats with brass hooks for roof Each 32.45 49.80 Each 32.45 49.80
ventilators.

c) Providing and fixing door stops of 1½" (40 mm) dia Each 3.85 51.65 Each 3.85 51.65
rubber block.

d) Providing and fixing G.I. hook with clamps for doors. Each 1.25 6.35 Each 1.25 6.35

31 Hard wood railing of any shape and design, including ditto


bends and corners, fixed in position, including polishing
complete as directed.

a) Shisham wood Per Rft. 93.35 160.55 Metre 306.25 526.65


b) Teak wood ditto 70.30 507.35 ditto 230.55 1664.05

32 Deodar wood dado or picture rail 3"x1½" (75x40 mm) as Per Rft. 35.15 112.40 Metre 115.30 368.65 26.1
per approved design including moulding and fixed in place, 26.2
cost of screws, nails, plugs, and painting complete.

33 Sawing wood by hand:-

a) Soft wood (deodar, kail or chir). 100Sft. 339.90 - sq.m 36.55 -


b) Hard wood (shisham, kikar, teak or ditto 453.20 - ditto 48.75 -
sahl).

34 Sawing wood by machine:

a) Soft wood 100Sft. 199.78 - sq.m 21.50 -


b) Hard wood ditto 300.25 - ditto 32.30 -

35 Making and fixing sun-shade of deodar wood including Per Sft. 30.10 166.40 sq.m 323.85 1790.65 26.1
fixing brackets.

36 Making and fixing 1" (25 mm) thick kail or chir wooden ditto
notice board with frame. Per Sft. 33.85 89.55 sq.m 364.25 963.55

37 Making deodar punkha pole 10'x6"x6" Each 127.40 3156.20 Each 127.40 3156.20 ditto
(3.0 m x 150 mm x 150 mm)

38 Dismantling and refixing eave boards. Per Rft. 9.10 -- Metre 29.85 --

chapter-12(Wood Work) Page 7


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

39 Making wooden stair-cases complete 2' to 3' (600 to 900 Per Rft. 130.70 1032.65 Metre 428.65 3387.10 26.1
mm) wide frame 1½" (40 mm) thick planks of deodar
wood, including hand rails.

40 Providing and fixing partition, including frame work:-

a) Sheets on one side of framework:-

i) Hard board 100Sft. 634.20 5612.40 sq.m 68.25 603.90


ii) Ply wood ¼" (6 mm) thick ditto 634.20 6462.90 ditto 68.25 695.40
iii) Masonite ditto 262.95 7351.65 ditto 28.30 791.05

b) Sheets on both sides of frame work:-

i) Hard board 100Sft. 761.05 6411.95 sq.m 81.90 689.95


ii) Ply wood ¼" (6 mm) thick ditto 761.05 13445.25 ditto 81.90 1446.70
iii) Masonite ditto 761.05 10632.95 ditto 81.90 1144.10

41 Providing and fixing ceiling, including frame work:-

i) Hard board 100Sft. 1258.15 4822.90 sq.m 135.35 518.95


ii) Chip board ditto 1258.15 5902.90 ditto 135.35 635.15
iii) Ply wood ¼" (6 mm) thick ditto 1258.15 5752.90 ditto 135.35 619.00
iv) Masonite ditto 1258.15 7072.90 ditto 135.35 761.05

42 Providing and fixing thermopore false ceiling, including In case of acoustic


wooden frame panelling, cost of M.S. clamps, making Thermopore sheet, the
holes in walls and repairing damaged surface, complete in composite rate will be
all respects:- increased by Rs.9.00 per Sft.

a) Deodar wood frame panelling:

i) ¾" (20 mm) thick 100Sft. 1425.40 4972.95 sq.m 153.40 535.10
ii) 1" (25 mm) thick ditto 1425.40 5055.80 ditto 153.40 544.00

b) Partal wood frame panelling:

i) ¾" (20 mm) thick 100Sft. 1425.40 3832.10 sq.m 153.40 412.35
ii) 1" (25 mm) thick ditto 1425.40 3951.45 ditto 153.40 425.20

43 a) Fixing door, including chowkats. Each 231.00 - Each 231.00 -


b) Fixing windows, including chowkats. ditto 115.50 - ditto 115.50 -

chapter-12(Wood Work) Page 8


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

44 a) Glazing with panes (16 oz. to 18 oz.,) Per Sft. 12.15 34.30 sq.m 130.60 368.95 26.12
including cost of putty

b) Glazing with panes (16 oz. to 18 oz.) Per Sft. 16.45 53.65 sq.m 176.80 577.05
using deodar wooden fillets and putty

45 Glazing with panes (24 oz. to 26 oz.), using Per Sft. 24.10 60.70 sq.m 259.15 653.00 26.12
putty and deodar wooden fillets

46 a) Cutting to required size and fixing glas Per Sft. 8.45 9.50 sq.m 91.05 102.10
panes with putty

b) Cutting to required size and fixing glass panes with Per Sft. 13.55 21.95 sq.m 146.05 236.40
wooden fillets and putty

47 Glazing with plate glass 1/4" (6 mm) thick including the co


of deodar wood fillets and putty:-

a) Glazing upto 8 sft (0.75 sq.m) Per Sft. 20.55 72.05 sq.m 220.95 775.50

b) Glazing exceeding 8 Sft (0.75 sq.m) but not exceeding 24 sf Per Sft. 20.60 72.35 sq.m 221.85 778.35
(2.25 sq.m).

48 Providing and fixing 1½" (40 mm) thick deodar wood


panelled or panelled and glazed, doors and windows, with
mild steel chowkat (frame), etc. complete in all respect
(excluding sliding bolt or lock) with:

i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 91.25 395.95 sq.m 981.85 4260.15
i) (40 mmx 40 mmx 6mm) with M.S. flat
2"x¼" (50 mm x 6 mm)
ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 91.25 353.05 sq.m 981.85 3799.00
(40 mmx40 mmx 6mm) with M.S. flat
½"x¼" (13 mm x 6 mm)

49 Providing and fixing 1½" (40 mm) thick hollow flush door Teak ply would be used under the
and windows with commercial ply (3 ply) on both faces o written permission of the
deodar wood shutter frame 1¼" (30 mm) thick and partal superintending Engineer, and the
wood braces at about 3" (75 mm) apart and deodar wood composite rate of using teak ply
lipping 1½"x3/8" (40 mmx10 mm) fixed with M.S. chowka will be increased by Rs.20.00 per
(frame) including chromium plated fittings, etc. complet Sft. ( 216.00 per Sq.m)
in all respects (without sliding bolt or lock)

i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 64.30 330.95 sq.m 691.75 3560.95
(40 mmx40 mmx 6mm) with M.S. flat
2"x¼" (50 mm x 6 mm)

chapter-12(Wood Work) Page 9


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 64.30 298.20 sq.m 691.75 3208.45
(40 mmx40 mmx 6mm) with M.S. flat
½"x¼" (13 mm x 6 mm)

50 Providing and fixing 1½" (40mm) thick solid flush door It C.P. Finger plate and kick plate
shutter sterling with commercial ply (5 mm thick) are not provided/fixed the
on both sides double pressed and deodar wood lipping Per Sft. 33.15 214.00 sq.m 356.55 2302.80 composite rate will be reduced by
1½"x3/8" (40mm x 10mm) around shutter including Rs.15.20 per Sft.
chromium plated fitting, iron hinges with aluminium kick Reduce composite rate by Rs.13.00
plate 22 SWG on both sides & finger plate complete in all per. Sq/ft or Rs.140 per sq.meter if
respect. 3-mm commmercial ply is used

51 Providing and fixing panelled door of M.S. sheet, with Per Sft. 63.65 338.15 sq.m 684.80 3638.50
forged door leaves of M.S. sheet 22 SWG fitted in hollow
frame chowkat 3"x4½" (75 mmx113 mm) made of M.S.
sheet 18 SWG filled with plain cement concrete 1:3:6 etc.
complete with all fittings and hammer painting, including
carriage to site and fixing in position.

52 Providing and laying 24 SWG aluminum kick plate 4" (100 Per Rft. 13.85 21.40 Metre 45.45 70.25
mm) high, fixed with screws 4" (100 mm) centre to centre,
on bottom rail of flush doors only of commercial ply.

53 Providing and fitting curtain railing to doors and windows, Per Rft. 5.80 80.40 Metre 18.95 263.65
comprising of TOSO-elite Japan made superior type of
railing or equivalent, fixed over 4"x¾" (100mmx20mm)
deodar wood strip, including painting.

54 Providing and fixing M.S. flat ½"x1/8" (13mm x 3mm) grill Per Sft. 34.90 156.45 sq.m 375.80 1683.40
including ¾" x 1/8" (20 mmx3 mm) M.S. flat frame, in
windows of approved design, including painting three
coats, complete in all respects.

55 Providing and fixing G.I. wire gauze 22 SWG, 12x12 Per Sft. 10.95 42.25 sq.m 117.75 454.65 It 24 SWG wire gauze is used, the
2
meshes per square inch, (5x5 meshes in cm ) fixed to composite rate shall be reduced by
steel window, complete with flat iron patti ½"x 1/8" (13 Rs.4.70 per Sft. or Rs.50.60 per square
mmx3 mm) and machine made screws. metre.

56 Providing and fixing wooden moulding stopper 2½"x5/8"


(63 x 16 mm) on door frame fitted with ply of approved
quality complete in all respects.

a) Teak wood moulding Per Sft. 14.45 82.15 sq.m 155.35 884.20
b) Deodar wood moulding ditto 14.45 33.15 ditto 155.35 356.65

chapter-12(Wood Work) Page 10


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

57 Providing and fixing deodar wood dolly frame having Rate shall be paid as per surface area of
1½"x1½" (40 x 40 mm) vertical and horizontal double post dolly frame e-g 0.75' x (3.5' + (2 x 7))
with 1½"x1½" (40 x 40 mm) full width of james braces at
12" (300 mm) including filling of the spaces in between
braces with 1:3:6 PCC fixing ply of approved quality
including holdfasts complete in all respects.

a) Teak wood ply Per Sft. 31.20 174.75 sq.m 335.95 1880.10
b) With commercial ply ditto 31.20 147.00 ditto 335.95 1581.50

58 Providing and fixing ornamental wooden architrave 3" x


(1½" tapered to ¼") all along the door frame complete in all
respect.

a) Teak wood architrave Per Sft. 6.15 51.45 sq.m 66.20 553.60
b) Deodar wood architrave ditto 6.15 17.90 ditto 66.20 192.50

59 Providing and fixing Vin board cabinet 3/4" thick with


drawers 3"deep in 'Kitchen including termite proofing and
polishing with synthetic enamel as specified, with handles
hinges,screws etc., complete in all respects.
i) 1-1/2' deep,without back Per Sft 69.10 290.40 sq.m 743.45 3124.85
ii) 1-1/2' deep,with back Per Sft 69.10 315.90 sq.m 743.45 3399.20
iii) 2' deep,without back Per Sft 69.10 315.25 sq.m 743.45 3392.35
iv) 2' deep,with back Per Sft 69.10 340.75 sq.m 743.45 3666.75

chapter-12(Wood Work) Page 11


PAINTING AND VARNISHING
1 The rates include charges for scaffolding and other arrangements.

2 The rates for all finished works include the removal of surplus debris, unused material and by products
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 a) Cleaning painted wood work with oil and water. 100 Sft. 66.00 76.85 sq.m 7.10 8.25

b) Oiling woodwork with boiled linseed oil. 100 Sft. 44.00 83.60 sq.m 4.75 9.00 27.7

2 Brushing and scraping blisters of old paints from 100 Sft. 132.00 -- sq.m 14.20 - 27.3
woodwork.

3 Scraping, brushing and removing old paint from metal 100 Sft. 528.00 -- sq.m 56.80 - 27.9
surface.

4 Painting old surfaces:- 27.1


27.3 &
a) Painting corrugated surfaces, patent roofing, etc. with 27.9
oil paint.

i) first coat 100 Sft. 167.00 302.60 sq.m 17.95 32.55


ii) each subsequent coat ditto 126.50 196.10 ditto 13.60 21.10

b) Painting sashes, fanlights, glazed or gauzed doors


and windows:-

i) first coat 100 Sft. 101.20 174.40 sq.m 10.90 18.75


ii) each subsequent coat ditto 86.00 146.00 ditto 9.25 15.70

c) Painting doors and windows, any type:

i) first coat 100 Sft. 167.00 306.20 sq.m 17.95 32.95


ii) each subsequent coat ditto 126.50 232.70 ditto 13.60 25.05

d) Painting guard bars, gates of iron bars, gratings,


railing (including standards, braces etc.) and similar
open work:-
i) first coat 100 Sft. 101.20 174.40 sq.m 10.90 18.75
ii) each subsequent coat ditto 86.00 146.00 ditto 9.25 15.70

chapter-13(Painting & Var) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

e) Painting fillets, framings, skirtings, pipes, gutters and


similar linear work not exceeding 6" in girth:-

i) first coat 100 Lft. 86.00 159.20 Metre 2.80 5.20


ii) each subsequent coat ditto 60.70 120.70 ditto 2.00 3.95

f) Painting small detached articles, not exceeding one


square foot (Sq.m) of painted surface:-

i) first coat 100 Nos. 255.75 391.35 100 Nos. 255.75 391.35
ii) each subsequent coat ditto 231.00 304.20 ditto 231.00 304.20

g) Painting small detached articles, exceeding one


square foot (Sq.m) but not exceeding three square
feet (Sq.m) of painted surface:-

i) first coat 100 Nos 584.55 987.75 100 Nos 584.55 987.75
ii) each subsequent coat ditto 339.45 541.05 ditto 339.45 541.05

5 Painting new surface:- 27.1


27.2 &
a) Preparing surface and painting corrugated surface, 27.9
patent roofing, etc.

i) priming coat. 100 Sft. 254.10 426.90 sq.m 27.35 45.95


ii) each subsequent coat of paint. ditto 89.10 257.70 ditto 9.60 27.75

b) Preparing surface and painting sashes, fan light,


glazed or gauzed doors and windows etc. any type
(including edges):-

i) priming coat. 100 Sft. 106.90 229.60 sq.m 11.50 24.70


ii) each subsequent coat of paint. ditto 72.85 168.85 ditto 7.85 18.15

c) Preparing surface and painting of doors and windows


any type (including edges):-

i) priming coat. 100 Sft. 254.10 423.30 sq.m 27.35 45.55


ii) each subsequent coat of paint. ditto 89.10 257.70 ditto 9.60 27.75

d) Preparing surface and painting guard bars, gates of


iron bars, gratings, railing (including standards,
braces, etc.) and in similar open work:-
i) priming coat. 100 Sft. 163.35 267.15 sq.m 17.60 28.75
ii) each subsequent coat of paint. ditto 72.85 168.85 ditto 7.85 18.15

chapter-13(Painting & Var) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

e) Preparing surface and painting of fillets, framing,


skirtings, pipes, gutters, and similar linear work not
exceeding 6" (150 mm) girth:-

i) priming coat. 100 Lft. 129.05 208.00 Metre 4.25 6.80


ii) each subsequent coat of paint. ditto 48.60 128.40 ditto 1.60 4.20

f) Preparing surface and painting of small detached


articles, not exceeding one sq. ft. (Sq.m) of painted
surface:-

i) priming coat. 100 Nos. 379.50 799.20 100 Nos. 379.50 799.20
ii) each subsequent coat of paint. ditto 187.00 520.60 ditto 187.00 520.60

g) Preparing surface and painting of small detached


articles, exceeding one Sft. but not exceeding 3 Sft.
(Sq.m) of painted surface:-

i) priming coat. 100 Nos. 1080.75 1750.35 100 Nos. 1080.75 1750.35
ii) each subsequent coat of paint. ditto 324.50 922.10 ditto 324.50 922.10

h) Extra for knotting and stopping to 100 Sft. 17.15 29.05 sq.m 1.85 3.15
priming coat on new surface of wood.

6 Applying Khanki Mixture hot to barrage 27.10


gates:-

i) first coat 100 Sft. 126.50 182.35 sq.m 13.60 19.60


ii) second coat ditto 100.75 139.50 ditto 10.85 15.00

7 French polishing complete:- 27.6

a) on new work 100 Sft. 1291.70 1343.05 sq.m 139.00 144.50


b) on old work ditto 678.85 707.20 ditto 73.05 76.10

8 Varnishing wood work, including cleaning and preparing


surface.

a) first coat 100 Sft. 101.20 198.40 sq.m 10.90 21.35


b) second coat ditto 37.95 111.75 ditto 4.10 12.00
c) third coat ditto 37.95 96.15 ditto 4.10 10.35

chapter-13(Painting & Var) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

9 Bitumen coating to plastered or cement concrete surface:-

i) 20 lbs. per 100 Sft. (9.07 Kg per Sq.m) 100 Sft. 110.00 675.95 sq.m 11.85 72.75
ii) 14 lbs. per 100 Sft. (6.35 Kg per Sq.m) ditto 105.60 391.45 ditto 11.35 42.10
iii) 10 lbs. per 100 Sft. (4.54 Kg per Sq.m) ditto 87.10 372.95 ditto 9.35 40.15

10 Writing letters or figures, per letter, per inch (25 mm) Per No. 5.05 5.55 Per No. 5.05 5.55 27.1
height.

11 Writing letters or figures at any surface with reflective paint Per Letter 5.05 5.35 Per Letter 5.05 5.35 27.1
of approved quality and colour per letter per inch height. per inch per 25 mm
height height

12 Writing letters of figures on any surface with reflective tape ditto 5.95 6.70 ditto 5.95 6.70 ditto
of approved quality and colour per letter per inch (25 mm)
height.

13 Coaltar painting: 27.8


to
a) first coat, laid hot 100 Sft. 92.35 540.95 sq.m 9.95 58.20 27.11
b) second coat, laid hot ditto 55.95 337.00 ditto 6.00 36.25

14 Solignum painting:- 27.8

a) one coat, applied hot 100 Sft. 94.40 117.20 sq.m 10.15 12.60
b) two coats, applied hot ditto 143.00 179.10 ditto 15.40 19.25

15 Creosote painting:- ditto

a) one coat, applied hot 100 Sft. 113.25 216.45 sq.m 12.20 23.30
b) two coats, applied hot ditto 171.60 344.40 ditto 18.45 37.05

16 Burning off or rubbing down with pumice stone, old paint 100 Sft. 345.85 360.25 sq.m 37.20 38.75 27.3
from wood work.

17 Removing with caustic soda, old paint from wood work. 100 Sft. 132.00 139.20 sq.m 14.20 15.00 ditto

18 Painting distance marks for white ground and black Each 25.30 29.15 Each 25.30 29.15 27.1
lettering on both sides.

19 Painting two feet wide gauges, reading to 10th of a foot Per Rft. 50.60 57.90 per Metre 165.95 190.00 ditto
(metre).

chapter-13(Painting & Var) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

20 Painting sounding rods and other gauges, reading to 10th Per Lft. 25.30 27.65 per Metre 83.00 90.65 27.1
of a foot (metre)

21 Painting leveling staves. Per Lft. 79.20 82.85 per Metre 259.80 271.80

22 a) Painting and lettering mile/Km stones, ditto


on both sides:

i) one coat Each 23.10 49.80 Each 23.10 49.80


ii) two coats ditto 94.90 135.70 ditto 94.90 135.70

b) Painting and lettering Furlong/½ Km 27.1


stones, on both sides:-

i) one coat Each 3.10 6.10 Each 3.10 6.10


ii) two coats ditto 12.65 18.05 ditto 12.65 18.05

c) Painting and lettering Sign posts:-

i) one coat Each 60.70 76.30 Each 60.70 76.30


ii) two coats ditto 100.20 129.00 ditto 100.20 129.00

23 Removing paint or varnish from wall. 100 Sft. 264.00 - sq.m 28.40 - 27.12

24 Scraping from hydraulic gates:- 27.1

a) Khanki paint 100 Sft. 528.00 - sq.m 56.80 -


b) Aluminium paint ditto 528.00 - ditto 56.80 -

25 Painting letters with shade. per letter 8.10 8.10 per letter 8.10 8.10 27.1
per inch per 25 mm
height height

26 Scraping rust from old rail or girders. 100 Sft. 396.00 432.00 sq.m 42.60 46.50 27.9
27.10

27 Chiselling old paint from brick work. 100 Sft. 528.00 552.00 sq.m 56.80 59.40 27.12

28 Cleaning glasses with chalk and spirit, etc. 100 Sft. 440.00 450.00 sq.m 47.35 48.40

29 Cleaning and oiling rafter or rolled steel 100 Sft. 132.00 156.50 sq.m 14.20 16.85 27.9
beams.

chapter-13(Painting & Var) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

30 Cleaning and painting punkha poles, including fixing Each 87.45 93.75 Each 87.45 93.75 27.3
hooks.

31 Preparing surface and painting with emulsion paint:- 27.12

a) first coat 100 Sft. 129.10 253.05 sq.m 13.90 27.25


b) 2nd and each subsequent coat ditto 99.00 197.95 ditto 10.65 21.30

32 Preparing surface and painting with water proof coloured 27.12


cement finish, like duracem, buxcem or other finishes with
similar specifications, on walls, etc.

a) new surface:

i) 1st coat 100 Sft. 129.10 194.80 sq.m 13.90 20.95


ii) 2nd and subsequent coat ditto 99.00 156.95 ditto 10.65 16.90

b) old surface:

i) 1st coat 100 Sft. 129.10 157.35 sq.m 13.90 16.95


ii) 2nd and subsequent coat ditto 99.00 126.55 ditto 10.65 13.60

32A Providing and applying weather shield paint of approved


quality on external surface of building including preparation of
surface, application of primer complete in all respect:

a) new surface:

i) 1st coat %sft 435.60 731.15 sq.m 46.85 78.65


ii) 2nd coat %sft 239.25 359.05 sq.m 25.75 38.65

b) old surface: %sft 239.25 359.05 sq.m 25.75 38.65

33 Painting traffic lane 5" (125 mm) wide, with road marking Per Rft. 0.75 1.45 Metre 2.50 4.80
enamel.

34 Painting traffic lane 5" (125 mm) wide with reflective Per Rft. 0.90 6.95 Metre 2.95 22.80 AASHTO Rates shall be reduced by Rs.0.50
clorinated rubber (CR) paint including glass beads comlpete M248-91 P.Rft or Rs.1.65 P.Mtr. If glass beads
in all respect. (2000) are not used.
35 Repainting of ceiling fan (all sizes and types), including Per Job 30.65 57.65 Job 30.65 57.65
painting of blades, canopy, suspension rod and regulator,
with suitable enamel paint.

chapter-13(Painting & Var) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

36 Repainting of iron poles with cross arms, with bitumen or Per Job 71.50 164.50 Job 71.50 164.50
other approved paint.

37 Repainting of pipes and specials of G.I., M.S. or conduit,


etc., fixed for on surface electric wiring, with approved
paint:

i) upto 40 mm (1½") dia Per Rft. 0.65 2.15 Metre 2.15 5.25
ii) above 40 mm (1½") to 50 mm (2") dia ditto 1.30 2.90 ditto 4.30 9.45
iii) above 50 mm (2") to 100 mm (4") dia ditto 2.20 4.55 ditto 7.15 14.90

38 Repainting main switches and branch distribution boards Per Job 6.75 45.35 Job 6.75 45.35
of all sizes and types, with approved paint (complete set).

39 Extra labour for painting, varnishing, etc. from 20' (6.10 m) 100 Sft. 42.25 - sq.m 4.55 - The height will be taken from the
height and above, for every additional 10' (3.05 m) height, per coat floor, roof or ground underneath, as
or part thereof, requiring scaffolding. the case may be on the side
towards which the work is to be
done.

chapter-13(Painting & Var) Page 7


LINING OF CANALS
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts
2 The rates also include curing for specified period wherever necessary.
3 Nominal dimension of tile or brick shall be taken for the purpose of measurement and payment
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Formation, dressing and preparing sub-grade:- 28.1 to 28.3

a) in bed 100Sft. 259.05 - sq.m 27.85 -


b) on slope ditto 348.50 - ditto 37.50 -

2 Stabilized layer of cement, sand ratio 1:30, 2" (50 mm) 100Sft. 726.00 1102.20 sq.m 78.10 118.60 ditto
thick on slope.

3 Cement plaster ½" (13 mm) thick ratio 1:10. ditto

a) in bed 100Sft. 513.20 689.45 sq.m 55.20 74.20


b) on slope ditto 660.00 836.20 ditto 71.00 90.00

4 Cement plaster 3/8" (10 mm) thick ratio 1:3. ditto

a) in bed 100Sft. 513.20 815.15 sq.m 55.20 87.70


b) on slope ditto 660.00 961.95 ditto 71.00 103.50

5 Cement plaster 1½" (40 mm) thick ratio 1:6. ditto

a) in bed 100Sft. 660.00 1393.60 sq.m 71.00 149.95


b) on slope ditto 844.80 1578.40 ditto 90.90 169.85

6 Tile lining 12"x6"x2" (300x 150x50 mm) in 1:6 cement, 28.2 to 28.3 The rates are only for laying tiles
sand mortar:- over 1/8" (3 mm) thick layer of 1:6
mortar. Items 1 to 5 above are
a) in bed 100Cft. 3308.25 7516.90 cu.m 1168.45 2655.00 payable separately.
b) on slope ditto 3786.75 7995.40 ditto 1337.50 2824.00

7 Tile lining 12"x6"x2" (300x150x50 mm) in 28.2 to 28.3 The rates are only for laying tiles
1:3 cement, sand mortar:- over 1/8" (3 mm) thick layer of 1:3
mortar. Items 1 to 5 above are
a) in bed 100Cft. 3308.25 8499.00 cu.m 1168.45 3001.85 payable separately.

b) on slope ditto 3786.75 8977.50 ditto 1337.50 3170.85

chapter-14(Lining of canal) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

8 Brick lining 9"x4½"x3" (225x113x75 mm) in 1:6 cement, 28.2 The rates are only for laying bricks
sand mortar:- over 1/8" (3 mm) thick layer of 1:6
mortar. Items 1 to 5 above are
a) in bed 100Cft. 3308.25 9298.90 cu.m 1168.45 3284.40 payable separately.
b) on slope ditto 3786.75 9777.40 ditto 1337.50 3453.40

9 Brick lining 9"x4½"x3" (225x113x75 mm), in 1:3 cement, ditto The rates are only for laying
sand mortar:- bricks over 1/8" (3 mm) thick
layer of 1:3 mortar. Items 1 to
a) in bed 100Cft. 3308.25 10281.00 cu.m 1168.45 3631.25 5 above are payable
b) on slope ditto 3786.75 10759.50 ditto 1337.50 3800.25 separately.

10 Cement concrete lining, using washed screened and 20.1, 28.1


graded stone aggregate:- & 28.3

a) in bed:-

i) ratio 1:2:4 100Cft. 2712.60 12018.60 cu.m 958.10 4244.95


ii) ratio 1:3:6 ditto 2712.60 10303.20 ditto 958.10 3639.10
iii) ratio 1:4:8 ditto 2712.60 9063.00 ditto 958.10 3201.05

b) on slope:-

i) ratio 1:2:4 100Cft. 3168.00 12474.00 cu.m 1118.95 4405.80


ii) ratio 1:3:6 ditto 3168.00 10758.60 ditto 1118.95 3799.95
iii) ratio 1:4:8 ditto 3168.00 9518.40 ditto 1118.95 3361.90

chapter-14(Lining of canal) Page 2


SHEET PILING
Rates for all finished works include the removal of surplus debris, unused material and by produc

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Cutting Ransome and Larson piles. Per 92.40 - Per 92.40 - 29.1-
cut cut 29.3

2 Cutting universal piles. Per cut 136.75 - Per cut 136.75 - ditto

3 Driving steel piles, 25' to 30'. (7.5 to 9.0 m) 100Sft. 1717.30 - sq.m 184.80 - ditto 1) The rate includes laying and
removing of track and also carriage
of piles to machine, average
distance of 3 chains (90 metre).

2) The rates are for the tackle


gangs only supplied by the
contractor, Mechanical staff
on-machines will be supplied by
Government.

3) T-piles and adjustable junction


piles will be counted as two piles.

4 Driving steel piles,more than 15' (4.6 m) and less than 25' 100Sft. 1647.35 - sq.m 177.25 - ditto ditto
(7.5 m).

5 Driving steel piles, 15' (4.5 m) and under. 100Sft. 1227.60 - sq.m 132.10 - ditto ditto

6 Dolleying piles. Each 108.75 - Each 108.75 - ditto Upto 5' (1.5 m) dolleying.

7 Drilling holes in piles by hand. Each 12.70 - Each 12.70 - ditto

8 Raising and lowering machine. Per Ft. 1592.80 - Metre 5224.40 - ditto

9 Turning Machine, 90o . Per 2423.50 - Per 2423.50 - 29.1 to


Job Job 29.3

10 Turning Machine, 135o . Per 2983.20 - Per 2983.20 - ditto


Job Job

chapter-15(Sheet piling) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

11 Turning Machine, 180o . Per 4070.90 - Per 4070.90 - 29.1 to


Job Job 29.3

12 Travelling machine (light). Per 4812.70 - 30 M. 4812.70 - ditto


Chain

13 Loading and unloading piles. Ton 97.70 - Tonne 96.15 - ditto To be done by hand carts or
ramps, including cost of ropes.

14 Dismantling piling machine. Each 9508.40 - Each 9508.40 - ditto

15 Erecting piling machine. Each 10971.25 - Each 10971.25 - ditto

16 Carriage of piling machine under different conditions. per 1953.60 - 30 M 1953.60 - ditto
chain

chapter-15(Sheet piling) Page 2


PROTECTION & DIVERSION WORKS
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts
2 The composite rates of the items in which stone, boulders, shingle spawl are used do not contain the carriage
of the these stone materials, which will be paid separately by road, and/or rail, whichever means of transport is
adopted. The supply and carriage to site of work of all other material required in the item, is included in the
composite rates.
3 The carriage of stone or spawl will be paid on the basis of actual stack measurement (without any reduction
factor) of the stone, boulders, shingle or spawl carried.
4 Where stone, boulder or spawl is issued from stock and contractor is paid for its carriage and/or labour only;
or where such stone product is supplied, carried or handled by the contractor in which no laying is required,
the actual stack measurement (without any reduction factor) shall from the basis of payment of supply or
carriage of the stone, boulder or spawl, etc. The quantity of finished and completed item of work shall form the
basis of laying.
5 In case of the items in which the rates include carriage of stakes, bushing, Pilchi, sarkanda or farash, etc. within
one mile (1.6 Km.)

i) the cost of the carriage within one mile (one Km) shall not be deducted from the carriage charges to follow thereafter
from the point of supply.

ii) if the site of work happens to be within one mile (one Km.) of the source of supply, the materials will be collected
and measured at site of work and no extra carriage would be admissible in such cases.

iii) where the site of the work is situated at more than one mile (one Km.) distance from the source of supply, the point
of supply will be fixed carefully by the Engineer-in-charge in such a way that the carriage charges would
be arrived at, most economically. Extra carriage will be admissible from the place of supply of the
material which will be considered its starting point. The demarcation of the place of supply will be
pre-determined before calling the tenders.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Cutting pilchi frash or sarkanda inlcuidng carriage within 100Cft. 501.60 cu.m 177.15
one mile.

2 Weaving matresses. 100Cft. 950.40 cu.m 335.65

3 a) Supplying and filling jute bags 1.25 (o.o35 cum) Cft., Per 14.85 27.20 Per Baq 14.85 27.2 The rate does not include supply of
capacity, with sand or earth, sewing and stacking, in Bag sand or earth for filling bags, which
dry. will be paid extra.

b) Supply and filling jute bags 1.25 (0.35 ccum) Cft. ditto 23.10 35.45 Per Baq 23.10 35.45 -ditto-
capacity, with sand or earth, sewing and laying in
position, under water.

chapter-16(Protec & Div) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

4 a) Supplying and filling jute bags 4 to 5 cft Per 35.55 82.35 Per 35.55 82.35 The rate does not include supply of
(0.11 to 0.14 cum) capacity, with sand or earth, Bag Bag sand or earth for filling bags, which
sewing and stacking, in dry. will be paid extra.

b) Supply and filling new jute bags 4 to 5 cft (0.11 to ditto 50.75 97.55 ditto 50.75 97.55 -ditto-
0.14 cu.m) capacity, with sand or earth, sewing and
laying in position, under water.

5 Carriage of jute bags 1.25 Cft. (0.035 cu m) capacity, filled


with sand or earth:-

a) 1st chain (30 m) 100 Nos 132.00 % Nos 132.00

b) 2nd to 4th chain (30 m to 120 m) Per chain 47.50 Per 30 m 47.50
per 100 Per 100 Nos/
Nos

c) 5th and subsequent chains ditto 18.50 ditto 18.50


(150 m and subsequent every 30 m)

6 Carriage of new jute bags 4 to 5 Cft.(0.11 to 0.14 cu.m)


capacity, filled with sand or earth:-

a) 1st chain (Ist 30 metre) 100 Nos 528.00 % Nos 528.00

b) 2nd to 4th chain (60 m to 120 m) per chain 184.80 Per 30 m 184.80
per 100Nos per %Nos

c) 5th and subsequent chains (150 m and ditto 71.30 ditto 71.30
subsequent every 30 m)

7 Rolling matresses to river edge and floating,


after unroling:-

a) area of matress upto 2,000 Sft. 100Sft. 297.00 sq.m 31.95


( 186 sq.m)

chapter-16(Protec & Div) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) area of matress 2,000 to 2,500 Sft. 100Sft. 495.00 sq.m 53.25


(186 sq.m to 232 sq.m)

c) area of matress over 2,500 Sft. ditto 577.50 ditto 62.15


(232 sq.m)

8 Sewing empty cement bags in sheets. 100 Nos 462.00 490.00 % Nos 462.00 490

9 Making compact round pilchi, frash or sarkanda round 100Cft. 643.50 715.75 cu.m 227.30 252.8 Measured in the shape of compact
bundles of specified size for the work. round bundles and of size specified
for the work, before filling at site.

10 Launching the above and placing in position. 100Cft. 316.80 cu.m 111.90

11 Supply within 5 chains (150 m):-

a) Boulders 9" (225 mm) and above 100Cft. 955.70 cu.m 337.50

b) Over size shingle 3" to 9"(75 to 225 mm) ditto 638.90 ditto 225.60

c) Mixed graded shingle ditto 757.70 ditto 267.60

12 Supplying Munj or Patha Trungers 6" (150 mm) mesh to hold Each 41.25 72.65 Each 41.25 72.65
3 Cft. (0.085 cu.m)

13 Providing and weaving G.I. wire netting for wire crates, with
G.I. wire of approved size (including siding and partition to
make crate):-

a) 6" (150 mm) mesh

i) 15 SWG wire 100Sft. 554.40 813.10 sq.m 59.65 87.50


ii) 10 SWG wire ditto 594.00 1434.00 ditto 63.90 154.30
iii) 8 SWG wire ditto 594.00 1911.10 ditto 63.90 205.65

b) 4" (100 mm) mesh

i) 15 SWG wire 100Sft. 712.80 1101.70 sq.m 76.70 118.55


ii) 10 SWG wire ditto 792.00 2049.50 ditto 85.20 220.50
iii) 8 SWG wire ditto 792.00 2763.50 ditto 85.20 297.35

14 Providing and laying shingle on top of bund, including 100Cft. 330.00 620.40 cu.m 116.55 219.10
handling of materials within three chains.

chapter-16(Protec & Div) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

15 Supply and dumping at site, without boat, including


handling of materials within three chains (90 m)

a) stone or boulder 100Cft. 577.50 973.50 cu.m 203.95 343.8 The rate includes supply of brick
b) shingle or spawl ditto 577.50 867.90 ditto 203.95 306.5 bats to site of work.
c) brick bats ditto 445.50 1237.50 ditto 157.35 437.10

16 Supply and dumping by boat, including loading into boat The rate includes supply of brick
within three chains (90 m) lead, and hire charges of boat and bats to site of work.
boatman.

a) stone or boulder 100Cft. 871.20 1267.20 cu.m 307.70 447.6


b) shingle or spawl ditto 871.20 1161.60 ditto 307.70 410.30
c) brick bats ditto 739.20 1531.20 ditto 261.10 540.80

17 Providing and filling brick bats in crates 100Cft. 778.80 1570.80 cu.m 275.05 554.8 The rate includes supply of brick
(excluding cost of crates). bats to site of work.

18 Supplying and filling bricks in crates and hand packing 100Cft. 943.80 5803.80 cu.m 333.35 2049.9 The rate includes supply of bricks
(excluding cost of crates). to site of work.

19 Supply and filling in wire crates, including sewing crates


(excluding cost of crates):-

i) stone or boulder 100Cft. 1075.80 1471.80 cu.m 379.95 519.85


ii) shingle or spawl ditto 1075.80 1366.20 ditto 379.95 482.55

20 Extra for anchoring boat, for dumping by boats or tipping 100Cft. 51.10 - cu.m 18.05 -
crates.

21 Extra for tipping crates (in addition to anchoring boats). 100Cft. 580.80 - cu.m 205.15 -

22 Pilchi reventment, including carriage upto one mile 100Sft. 330.00 730.00 sq.m 35.50 78.55 30.1
(1.6 km.)

23 Surface protection with pilchi matresses, carriage upto 100Sft. 825.00 865.00 sq.m 88.75 93.05 ditto
one mile (1.6 Km).

24 Pilchi, sarkanda or frash pitching on slopes, including The cost of placing earth between
supply of pilchi, sarkanda or frash within one mile, (1.6 km) 100Sft. 551.05 1482.00 sq.m 59.30 159.45 rolls shall be paid separately, as
also supply and driving of pegs 1½' (460 mm) long earthwork.
sharpened at one end and, tying with wire or Munj Ban
(excluding cost of placing earth between rolls).

chapter-16(Protec & Div) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

25 Constructing Groynes upto 5' (1.5 m) height, with single 100Sft. 627.35 688.80 sq.m 67.50 74.10 Measurement to be made of the
row of wooden vertical stakes 7" to 12" (175 to 300 mm) area of elevation on one face only.
dia, 1' (300 mm) apart, average lead one mile (1.6 km.)

26 Construction Groynes upto 10' (3.0 m) height, with double 100Sft. 1079.75 1153.15 sq.m 116.20 124.1
row of wooden vertical stakes 7" to 12" (175 to 300 mm)
dia, 2' (600 mm) apart, average lead one mile (1.6 Km).

27 Providing and laying stone pitching/filling, dry hand 100Cft. 679.80 1352.10 cu.m 240.10 477.55
packed, as filling behind retaining walls or in pitching and
aprons.

28 Providing and laying stone pitching with hammer dressed 100Cft. 2326.50 2924.10 cu.m 821.70 1032.8
stones on surface, laid in courses.

29 Providing and laying stone pitching, for top layer only:-

a) one slope 100Cft. 1881.00 2478.60 cu.m 664.35 875.45


b) on level ditto 1716.00 2313.60 ditto 606.10 817.15

30 Providing and laying stone or spawl filling:-

a) on level 100Cft. 478.50 742.50 cu.m 169.00 262.25

b) on slope ditto 615.10 879.10 ditto 217.25 310.5

31 Providing and laying stone pitching, hand packed, with


surface levelled off to the correct section and voids filled in
1:8 cement, sand mortar, in floors of bridges along banks
and in appons etc.

i) top layer on slope 100Cft. 2517.90 4446.05 cu.m 889.30 1570.35


ii) top layer on level ditto 2352.90 4281.05 ditto 831.05 1512.05
iii) stone pitching/filling on slope or on level ditto 1322.95 3325.85 ditto 467.25 1174.7
(other than top layer).

32 Grouting stone pitching or apron, etc. in:-


a) cement, sand mortar 1:3 100Sft. 796.95 3393.70 sq.m 85.75 365.15
b) cement, sand mortar 1:8 ditto 684.75 1320.75 ditto 73.70 142.10

33 Sand grouting in stone apron, with high 100Sft. 86.50 279.50 sq.m 9.30 30.10
pressure hose.

chapter-16(Protec & Div) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

34 Grouting stone filling or pitching, with bajri. 100Cft. 412.50 1060.50 cu.m 145.70 374.55

35 Removing stone and repitching hand packed, on slopes or 100Cft. 1729.20 - cu.m 610.75 -
level after making good damaged slope/portion.

36 Collecting and stacking boulders from nullah beds or loose 100Cft. 528.00 - cu.m 186.50 -
shale, or from any other site, within 3 chains (90 m) lead.

37 Levelling and dressing stone filling under blocks and 100Cft. 478.50 1126.50 cu.m 169.00 397.90
grouting with shingle.

38 Grouting jharies between blocks with bajri. 100Cft. 478.50 910.50 cu.m 169.00 321.60

39 Breaking stone into spawls and stacking 100Cft. 396.00 - cu.m 139.85 -

Canal and Roads

40 Fixing floating spurs, with material from canal plantation


within one mile (1.6 Km) lead:-

a) upto 2.0' (600 mm) F.S. depth Each 13.00 - Each 13.00 -

b) above 2.0' to 3.0' (600 to 900 mm) F.S. depth ditto 14.65 - ditto 14.65 -

c) above 3.0' to 4.0' F.S. (900 mm to 1200mm) depth Each 19.55 - ditto 19.55 -

d) above 4.0' (1200 mm) F.S. depth ditto 48.85 - ditto 48.85 -

41 Staking and bushing from canal plantation, royalty to be


paid to Forest Department or cost to private owner, if and
when required:-

a) i) Cutting and supply unsharpened pegs 3.5' (1.07 100 Nos 660.00 688.00 % Nos 660.00 688.00
m) long, 3" to 6" (75 to 150 mm) dia, within one mile
(1.6 Km) lead.

ii) Sharpening one end of 3.5' (1.07 m) long pegs, 3" 100 Nos 316.80 - 100 Nos 316.80 -
to 6" (75 to 150 mm) dia.

iii) Driving pegs 3.5' (1.07 m) long, 3" to 6" (75 to 150 100 Nos 391.80 - 100 Nos 391.80 -
mm) dia (driven 1.0' (300 mm) below the available bed
or ground (average).

chapter-16(Protec & Div) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) Tying pegs with Munj, Patha ban (one line, Per Chain 33.00 54.85 Per 30 33.00 54.85
incuding tying around the pegs). of One Metre
Row of one
row

v) Cutting and supplying brush wood from canal ditto 523.50 673.90 ditto 523.50 673.90
plantation or private owners, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

b) i) Cutting and supplying unsharpened pegs 4.0' 100 Nos 79.65 111.50 100 Nos 79.65 111.50
(1.20 m) long, 3" to 6" (75 to 150 mm) dia, from canal
plantation, lead within one mile (1.6 Km).

ii) Sharpening one end of 4' (1.20 M) long pegs, 3" 100 Nos 316.80 - 100 Nos 316.80 -
to 6" (75 to 150 mm) dia.

iii) Driving pegs 4' (1.20 m) long, 3" to 6" (75 to 150 100 Nos 472.55 - 100 Nos 472.55 -
mm) dia (driven 1.0' (300 mm) below the available bed
or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per 33.00 Per 33.00
incuding tying around the pegs). Chain of 30 M of
one row one row

v) Cutting and supplying brush wood from canal ditto 1174.80 ditto 1174.80
plantation or private source, lead within one mile
(1.6 Km). and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

c) i) Cutting and supplying unsharpened pegs 5.0' (1.5 100 Nos 99.65 139.50 100 Nos 99.65 139.50
m) long, 3" to 6" (75 to 150 mm) dia, from canal
plantation, lead within one mile (1.6 Km).

ii) Sharpening one end of 5' (1.5 m) long pegs, 3" to 100 Nos 335.30 - 100 Nos 335.30 -
6" (75 to 150 mm) dia.

iii) Driving pegs 5' (1.5 m) long, 3" to 6" (75 to 150 100 Nos 543.85 - 100 Nos 543.85 -
mm) dia (driven 1.5' (450 mm) below the available bed
or ground (average).

chapter-16(Protec & Div) Page 7


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) Tying pegs with Munj, Patha ban (one line, Per 33.00 54.85 Per 33.00 54.85
incuding tying around the pegs). Chain of 30 M
one row of one
row

v) Cutting and supplying brush wood from canal Per chain 524.70 735.10 Per 30 M 524.70 735.10
plantation or private source, lead within one mile of one row of one row
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

d) i) Cutting and supplying unsharpened 100 Nos 1320.00 1367.85 100 Nos 1320.00 1367.85
pegs 6.0' (1.8 m) long, 3" to 6" (75 to
150 mm) dia, from canal plantation, lead
within one mile (1.6 Km).

ii) Sharpening one end of 6' (1.8 m) long pegs, 3" to 100 Nos 398.65 - 100 Nos 398.65 -
6" (75 to 150 mm) dia.

iii) Driving pegs 6' (1.8 m) long, 3" to 6" (75 to 150 100 Nos 652.60 - 100 Nos 652.60 -
mm) dia (driven 1.75' (530 mm) below the available
bed or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per Per Chain
incuding tying around the pegs). Chain of 33.00 54.85 of one row 33.00 54.85
one row

v) Cutting and supplying brush wood from canal ditto 1339.80 1595.30 ditto 1339.80 1595.30
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

e) i) Cutting and supplying unsharpened pegs 6'-1" to 100 Nos 990.00 1089.20 100 Nos 990.00 1089.20
8.0' long (1.85 to 2.45 m), 4" to 8" (100 to 200 mm)
dia, from canal plantation, lead within one mile
(1.6 Km).

ii) Sharpening one end of 6'-1" to 8.0' (1.85 to 2.45m) 100 Nos 506.90 - 100 Nos 506.90 -
long pegs, 4" to 8" (100 to 200 mm) dia.

chapter-16(Protec & Div) Page 8


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iii) Driving pegs 6'-1" to 8.0' (1.85 to 2.45 m) long, 3" 100 Nos 720.20 - 100 Nos 720.20 -
to 6" (75 to 150 mm) dia driven 2' (600 mm) below
the available bed or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per chain 33.00 45.10 Per 30 M 33.00 45.1
incuding tying around the pegs). of one row of one row

v) Cutting and supplying brush wood from canal Per 1514.70 1815.30 Per 30 M 1514.70 1815.30
plantation or private source, lead within one mile Chain of of one row
(1.6 Km) and wattling between stakes and intertwining one row
(thickness of wattled brushwood 1.0' (300 mm)
average).

42 Staking with Bamboo from market and bushing from canal


plantation or private source (royalty of brushwood to be
paid to Forest Department or cost to private owner, if and
when required):-

a) i) Supplying Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 6600.00 - 100 Nos 6600.00 -
long, 2½" to 5" (63 m to 125 mm) dia.

ii) Sharpening one end of 8'-1" to 10.0' (2.46 to 30.5 100 Nos 443.50 - 100 Nos 443.50 -
m) long Bomboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 788.55 - 100 Nos 788.55 -
long 2½" to 5" (63 to 125 mm) dia, driven 2.5' (750
mm) below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Per 30 M
Munj, Patha Ban, two lines, including tying around Chain of 49.50 83.75 of one 49.50 83.75
the Bamboos. one row Row

v) Cutting and supplying brushwood from canal ditto 1854.60 2245.00 ditto 1854.60 2245.00
plantation or private source, lead within one mile
(1.6 Km), and wattling between stakes and
intertwining (thickness of wattled brushwood 1.0'
(300 mm) average).

b) i) Supplying Bamboos 10'-1" to 12.0' (3.07 to 3.66 100 Nos - 10200.00 100 Nos - 10200
m) long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 10'-1" to 12.0' 100 Nos 506.90 - 100 Nos 506.90 -
(3.07 to 3.66 m) long Bamboos, 2½" to
5" (63 to 125 mm) dia.

chapter-16(Protec & Div) Page 9


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iii) Driving Bamboos 10'-1" to 12.0' (3.07 to 3.66 m) 100 Nos 856.15 - 100 Nos 856.15 -
long 2½" to 5" (63 to 125 mm) dia, driven 2.75'
(840 mm) below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 165.00 775.70 of one Row 165.00 775.70
the Bamboos and third tie around the top end only. row

v) Cutting and supplying brushwood from canal ditto 2272.05 2768.05 ditto 2272.05 2768.05
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' ( 300 mm)
average).

c) i) Supplying Bamboos 12'-1" to 14.0' (3.68 to 4.27 100 Nos - 10800.00 100 Nos - 10800.00
m) long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 12'-1" to 14.0' (3.68 to 4.27 100 Nos 570.25 - 100 Nos 570.25 -
m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 12'-1" to 14.0' (3.68 to 4.27 m) 100 Nos 978.90 - 100 Nos 978.90 -
long 2½" to 5" dia, driven 3.5' (1.07 mm) below the
available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one row 165.00 775.70 of one row 165.00 775.70
the Bamboos and third tie around the top end only.

v) Cutting and supplying brushwood from canal ditto 2689.50 3260.70 ditto 2689.50 3260.70
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

d) i) Supplying Bamboos 14'-1" to 16.0' (4.30 to 4.90 m) 100 Nos - 12000.00 100 Nos - 12000.00
long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 14'-1" to 16.0' (4.30 to 100 Nos 633.60 - 100 Nos 633.60 -
4.90 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.
iii) Driving Bamboos 14'-1" to 16.0' long (4.30 to 4.90m) 100 Nos 1087.70 - 100 Nos 1087.70 -
2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)
below the available bed or ground (average).

chapter-16(Protec & Div) Page 10


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 165.00 775.70 of one 165.00 775.70
the Bamboos and third tie around the top end only. Row Row

v) Cutting and supplying brushwood from canal ditto 3095.40 3756.75 ditto 3095.40 3756.75
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

e) i) Supplying Bamboos 16'-1" to 20' (4.9 to 6.10 m) 100 Nos - 12600.00 100 Nos - 12600.00
long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 16'-1" to 20' (4.9 to 100 Nos 760.30 - 100 Nos 760.30 -
6.10 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 16'-1" to 20' long (4.9 to 6.10 m) 100 Nos 1305.20 - 100 Nos 1305.20 -
2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)
below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 165.00 775.70 of one 165.00 775.70
the Bamboos and third tie around the top end only. row row

v) Cutting and supplying brushwood from canal ditto 3874.20 4715.80 ditto 3874.20 4715.80
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

43 Cutting and supplying brushwood from canal plantation or 100Cft. 165.00 225.00 cu.m 58.30 79.45 Royalty to be paid to the Forest
from any other source, within one mile (1.6 Km). Department or cost to the private
owner, if and when required.

44 Filling brush wood only, thoroughly packed. 100Cft. 132.00 - cu.m 46.60 - Measured in compacted and
packed shape before filling.

45 Covering road 10' to 12' (3.00 to 3.65 m) wide, with 3" Per 316.80 - Per 316.80 -
(75 mm) sarkanda or jungle upto one chain lead (30 m). Chain 30 M

46 a) Gachi pitching 1' (300 mm) thick. 100Sft. 1716.00 - Sq.m 184.65 -
b) Gachi pitching done with silt clearance 100Sft. 1452.00 - Sq.m 156.25 -
and berm dressing.

chapter-16(Protec & Div) Page 11


OUTLETS
Rates for all finished works include the removal of surplus debris, unused material and byproduc

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Earthwork for outlets, excavation refilling, ramming and 17.1 Includes consolidation of earth after
puddling:- to refilling.
17.5
a) channels, discharge upto 50 cusecs. Job 550.00 - Job 550.00 -

b) channels, discharge from 51 to 100 cusecs. Job 726.00 - Job 726.00 -

c) channels, discharge from 101 to 200 cusecs. Job 1100.00 - Job 1100.00 -

d) channels, discharge from 201 to 350 cusecs. Job 1485.00 - Job 1485.00 -

e) channels, discharge over 350 cusecs. Job 2200.00 - Job 2200.00 -

2 Dismantling outlets:- 18.1 These rates are for total


dismantlement and removal
a) old types, such as K.G.O's orifices, etc. Each 550.00 - Each 550.00 - of material. The rates do not
include earth work for which
b) A.P.M. or O.F., "H" upto 2.0 ft. (600 mm) ditto 825.00 - ditto 825.00 - rates are given in item 1,
above.
c) A.P.M. or O.F., "H" from 2.1 ft. to 3.0'. ditto 1100.00 - ditto 1100.00 -
(630 mm to 900 mm)

d) A.P.M. or O.F., "H" above 3.0'. ditto 1375.00 - ditto 1375.00 -


(900 mm)

e) Tail cluster bifurcation ditto 825.00 - ditto 825.00 -

f) Tail cluster trifurcation ditto 1100.00 - ditto 1100.00 -

g) Tail cluster quardification ditto 1375.00 - ditto 1375.00 -

3 Making temporary A.P.M. bricks block and fixing at site. Each 304.90 478.60 Each 304.90 478.60 21.1 & 21.2

4 Dismantling walls, taking out temporary Job 620.40 - Job 620.40 - 18.1, 21.1
A.P.M. brick block, fixing iron block and & 21.2
rebuilding dismantled walls

chapter-17(Outlet) Page 1
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

5 Dismantling walls and fitting iron block of O.F. outlet. Each 620.40 - Each 620.40 - 18.1, 21.1
& 21.2

6 Constructing, watching and removing bund for outlet built 17.1


in running water:- to
17.2
a) upto 3.0' (0.300 m) depth Each 1320.00 - Each 1320.00 -
b) above 3.0' (0.300 m) depth ditto 1782.00 - ditto 1782.00 -

7 Adjusting "B" of tail cluster by dismantling and rebuilding Each 323.40 559.20 Each 323.40 559.20 18.1, 21.1
throat walls. & 21.2

8 Adjusting "Y" of an A.P.M. outlet, including dismantling Each 627.00 1006.80 Each 627.00 1006.80 ditto
and rebuilding.

9 Extra labour in fixing A.P.M. and O.F. outlet blocks, 21.1 & 21.2 Rates to be Rs. 4.00 less in case
including dressing of bricks:- of O.F. outlets, where there is no
O.F. iron block.
a) for channel depth of 5.0'. (1.5 m) Each 739.20 828.30 Each 739.20 828.30
b) for channel depth of 4.0'. (1.2 m) ditto 554.40 643.50 ditto 554.40 643.50
c) for channel depth of 3.0'. (900 mm) ditto 443.50 532.60 ditto 443.50 532.60
d) for channel depth of 2.0'. (600 mm) ditto 369.60 438.90 ditto 369.60 438.90
e) for channel depth of less than 2.0'. (600 mm) ditto 295.70 345.20 ditto 295.70 345.20

10 Repairing damaged reducing collar of Hume pipe outlets. Each 304.90 435.40 Each 304.90 435.40

11 Laying iron pipes for outlets. Per Lft. 14.80 - Metre 48.50 - 21.1, 21.2
& 17.1 to
17.5

12 Water allowance for constructing outlets or culverts, when Each 268.40 Each 268.40 At the discretion of the
canal water is not flowing. to to Engineer-in-charge depending upon
550.00 550.00 the distance and source of supply.

13 Hoisting and placing R.C. slab or stone in position on Each 222.20 - Each 222.20 -
outlets or W.C. culverts.

14 Fixing pipe outlet, including back filling of earth and 17.1 to 17.5
puddling:- & 21.1 to
21.2
a) portion under bank. Rft. 53.90 59.85 Metre 176.85 196.35
b) portion under road, beyond bank. ditto 24.40 30.35 ditto 80.10 99.6

chapter-17(Outlet) Page 2
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

15 Removing pipe outlet, refilling earth and puddling. 17.1


to
a) portion under bank. Rft. 44.00 - Metre 144.35 - 17.5
b) portion under road, beyond bank. ditto 16.50 - ditto 54.15 -

16 Changing pipe outlets by removing one pipe and replacin


it at the same site with another pipe complete with eart
and puddling.

a) portion under bank. Rft. 62.90 68.85 Metre 206.45 225.9


b) portion under road, beyond bank ditto 31.45 37.40 ditto 103.20 122.7

chapter-17(Outlet) Page 3
ROAD & ROAD STRUCTURE
1 Specification No. correspond to Book of "Standard Specification for Road and Bridge Construction 1971".
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
3 The rates include the provision and maintenance of field test laboratory, pay of laboratory staff, cost of material for testing, etc.
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Sub-base & base construction

1 Providing and laying sub-base course of brick on edge 100Cft. 1908.50 6662.30 cu.m 674.10 2353.10 521-1 The nominal thickness of bricks shall
4½" (113 mm) thick, including compaction to required to be taken for the purpose of
camber and grade. 521-6 measurement and payment.

2 Providing and laying sub-base course of brick aggregate, 100Cft. 1326.60 2003.40 cu.m 468.55 707.60 501-1 To be used only when brick
including compaction of sub-base course material to to aggregate is cheaper than stone
required depth, camber, grade & density. 501-6 aggregate.

3 a) Providing and laying sub-base course of stone product ditto


of approved quality and grade, including placing, mixing,
spreading and compaction of sub-base material to
required depth, camber, grade to achieve 100%
maximum modified AASHO dry density, including
carriage of all material to site of work except gravel and.
aggregate.

i) Pit run or bed run gravel. 100Cft. 1326.60 1686.60 cu.m 468.55 595.70
ii) Crushed stone aggregate. 100Cft. 1326.60 1758.60 cu.m 468.55 621.15

(b) Subsequent carriage of gravel and crushed stone 100Cft. of 1) The carriage of the whole distance
aggregate consoli- to the site of work shall be
dated calculated on the basis of the rates
sub-base of the actual means of transport
used in carriage, i.e. road and/or rail,
as the case may be.

chapter-18(R & Road Struc) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

2) It shall be payable from the


nearest approved quarry.
3) The quantity of pit run or bed run gravel
and crushed stone aggregate for payment of
carriage shall be taken as per actual loose
volume but not more than 120 Cft.

4 a) Providing and laying base course of crushed stone 100Cft. 1501.50 2760.90 cu.m 530.35 975.15 501-1
aggregate of approved quality and grade, and supply and to
spreading of stone screening, including placing, mixing, 501-6
spreading and compaction of base course material to
required depth, camber and grade to achieve 100%
maximum modified AASHO dry density, including
carriage of all materials to site of work except gravel and.
aggregate.

b) Subsequent carriage of crushed stone aggregate. 100Cft. of 1) The carriage for the whole
console- distance to the site of work shall be
dated calculated on the basis of the rates
base of the actual means of transport
used in carriage, i.e. road and/or
rail, as the case may be.

2) It shall be payable from the


nearest approved quarry.
3) The quantity of crushed stone aggregate
for payment of carriage shall be taken as
per actual loose volume but not more than
122 Cft.

5 Providing and laying road edging of 3" (75 mm) wide and Per Rft. 4.70 14.05 Metre 15.50 46.10 552-1 to
9" (225 mm) deep brick on end, complete in all respects. 552-5

Bituminous Work & Resurfacing


6 Providing and laying bituminous priming coat, using 10 100Sft. 66.00 613.20 sq.m 7.10 66.00 601-1 to
lbs. kerosene oil and 10 lbs. binder per 100 Sft. or 0.5 Kg 601-6
kerosene and 0.5 Kg binder per square metre.

chapter-18(R & Road Struc) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

7 Providing and laying bituminous tack coat, using 15 lbs. of 100Sft. 66.00 479.20 sq.m 7.10 51.55 611-1 to
bitumen per 100 Sft (0.75 Kg of bitumen per sq.m.) 611-5

8 a) Providing surface treatment to roads, including supply 612-1 to


of bitumen and bajri/crushed stone aggregate of 612-6
approved quality, including cleaning of road surface,
heating and spraying bitumen, spreading bajri and rolling
with road roller (including its operation cost, fuel and
hire charges, etc.) etc. complete including carriage of all
materials to site of work except bajjri/crushed stone
aggregate.

1) 1st coat:-

i) 40 lbs. bitumen, and 5.5 Cft. bajri of nominal size 1" (25 100Sft. 72.35 1398.10 Sq.m 7.80 150.45
mm) per 100 sq. feet or 1.96 Kg bitumen and 0.017
cu.metre bajri per square metre..

ii) 35 lbs. bitumen, and 4.0 Cft. bajri of nominal size ¾" 100Sft. 72.35 1224.60 Sq.m 7.80 131.75
(20 mm) per %Sft. or 1.72 Kg bitumen and 0.013 cu.metre
bajri per sq.metre.

2) 2nd coat:-

i) 25 lbs. bitumen, and 2.75 Cft. bajri of nominal size ½" 100Sft. 55.65 877.50 Sq.m 6.00 94.40
(13 mm) per %sft or 1.23 Kg bitumen and 0.008 cu. metre bajri per
sq.metre.

ii) 18 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 55.65 647.65 Sq.m 6.00 69.70
(10 mm) per %Sft. or 0.89 Kg bitumen and 0.006 cu.metre
bajri per sq. metre.

3) 3rd coat:-

14 lbs. bitumen, and 1.5 Cft. bajri of nominal size ¼" (6 100Sft. 38.10 497.70 sq.m 4.10 53.55
mm) per %sft or 0.69 Kg bitumen and 0.005 cubic metre bajjri
per sq.metre.

chapter-18(R & Road Struc) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) Subsequent carriage of crushed stone aggregate/bajri, 100Cft. cu.m 1) The carriage for the whole
distance to the site of work shall be
calculated on the basis of the rates
of the actual means of transport
used in carriage, i.e. road and/or rail,
as the case may be.

2) It shal be payable from the


nearest approved quarry.

9 a) Resurfacing of road, including supply of bitumen and 612-1


bajri/crushed stone aggregate of approved quality, to
including cleaning of road surface, heating and spraying 612-6
of bitumen, and spreading bajri/crushed stone
aggregate and rolling with road roller (including its
operation cost, fuel and hire charges, etc.) complete,
including carriage of all materials to site of work.

i) 22 lbs. bitumen, and 2.5 Cft. bajri of nominal size ½" 100Sft. 48.25 772.20 sq.m 5.20 83.10
(13 mm) per %Sft. or 1.07 Kg bitumen and bajjri 0.007 cu.m
per sq.m.

ii) 20 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 48.25 702.85 sq.m 5.20 75.65
(10 mm) per % Sft. or 0.79 Kg bitumen and 0.006
cu.metre bajri per sq.metre.

b) Subsequent carriage of crushed stone aggregate/bajri. 100Cft. cu.m Same remarks as against
item 8(b) above.

10 Providing and laying plant premixed bituminous carpet, per inch per 25mm 641-1 to
including compaction and finishing to required camber, grade thickness thickness 642-6
and density. per 100Sft. per Sq.m
(i) 3% Bitumen -do- 647.40 1904.30 -do- 69.65 205.00
(ii) 3.5% Bitumen -do- 647.40 2073.95 -do- 69.65 223.25
(iii) 4% Bitumen -do- 647.40 2243.55 -do- 69.65 241.50
(iv) 4.5% Bitumen -do- 647.40 2413.20 -do- 69.65 259.75
(v) 5% Bitumen -do- 647.40 2582.70 -do- 69.65 278.00
(vi) 5.5% Bitumen -do- 647.40 2752.45 -do- 69.65 296.25
(vii) 6% Bitumen -do- 647.40 2922.05 -do- 69.65 314.55

chapter-18(R & Road Struc) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

11 Scarifying old road surface including removal of debris within 100Sft. 32.65 - Sq.m 3.50 -
1 chain (30 m).

Incidental Construction

12 Providing R.C.C. railing on bridges, as per standard drawing. Per Rft. 59.75 261.70 Metre 196.10 858.55 901-1 The rate includes cost of steel, its
to fabrication, laying in position and
901-4 fastening, including cost of binding
wire and removal of rust from the
bars, etc.

13 Providing and fixing G.I. pipe railing, as per Per Rft. of 42.60 355.45 Metre 139.70 1166.10 ditto
standard drawing. 3 rows of
Pipes

14 Providing and fixing steel bearings of standard quality and Each Set - 2184.00 Each set - 2184.00 911-1 to
type at site of work. of one of one 911-6
end end

15 Providing and fixing rubber bearing pad at site Per - 15.60 cu.cm - 0.95 ditto
of work. Cu. Inch

16 Providing and laying expansion joint of neoprine strip 4"x¼" Per Rft. 35.00 119.10 Metre 114.75 390.80 921-1 to
(100 mmx 6 mm) and plastic bitumen. 921-4

17 Providing and fixing rain water outlet of A.C. pipe. Each 17.50 83.30 Each 17.50 83.30 931-1 to
933-4

18 Providing and erection at site of work:- 941-1 to The rate is for complete item of
941-5 work according to Standard design
i) R.C.C. mile/Km. stone Each 1172.90 2793.05 Each 1172.90 2793.05 including cement concrete
ii) R.C.C. furlong/½ Km. stone Each 57.05 128.10 Each 57.05 128.10 foundation block and painting
iii) R.C.C. boundary pillar. Each 101.80 334.15 Each 101.80 334.15 letters etc.
iv) Sign post of M.S. plate 1/8" thick (3 mm)

a) Mandatory. Each 370.40 3547.10 Each 370.40 3547.10


b) Warning/Direction/Informatory. Each 357.75 3306.95 Each 357.75 3306.95

19 Providing and laying dry brick pavement/soling in streets or 100Cft. 1369.85 6123.65 cu.m 483.80 2162.85 The nominal thickness of bricks (2-11/16")
roads, etc. sand grounted, laid in proper camber, including shall be taken for the purpose of
preparation, watering, compaction of bed to proper camber, measurement and payment.
and sand cushion. ( 9" x 4-3/8"x 2-11/16")

chapter-18(R & Road Struc) Page 5


PLUMBING, SANITARY INSTALLATION & GAS FITTINGS
1 Rates for all finished works include the removal of surplus debris, unused material & by products.
2 The material used shall conform to Schedule of Rates, Vol. I, Part I, (Specifications for Materials of
Construction, 1964, and the work will be executed according to Buildings & Roads Department Specifications,
Vol II, 1966 (Public Health Works).
3 The rates include cutting and making good of the surface of walls, roof, floor, etc. where necessary.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Providing and fitting glazed earthen ware water closet


European type, excluding seat and cover:-

i) white Each 202.95 1,405.30 Each 202.95 1,405.30


ii) coloured Each 202.95 1,972.90 Each 202.95 1,972.90

2 Providing and fixing, double seat and cover only.

i) bakelite Each 2.40 362.40 Each 2.40 362.40


ii) plastic Each 2.40 230.40 Each 2.40 230.40

3 Providing and fitting glazed earthen ware water closet,


squatter type (Orisa pattern), combined with foot rest.

i) white Each 156.75 1,065.60 Each 156.75 1,065.60


ii) coloured Each 156.75 1,209.60 Each 156.75 1,209.60

4 Providing and fitting white glazed earthen ware water closet, Each 156.75 1,810.35 Each 156.75 1,810.35
squartter type, with separate foot rest.

5 Providing and fitting water closet, squatter type of terrazzo Each 156.75 465.60 Each 156.75 465.60
concrete.

6 Providing and fitting glazed earthen ware wash hand basin


56x40 cm (22"x16") including bracket set, waste pipe and
waste coupling, etc.
i) white, with pedestal Each 198.00 2,176.80 Each 198.00 2,176.80
ii) coloured, with pedestal Each 198.00 2,323.20 Each 198.00 2,323.20
iii) white, without pedestal Each 177.40 1,472.20 Each 177.40 1,472.20
iv) coloured, without pedestal Each 177.40 1,529.80 Each 177.40 1,529.80

chapter-19(PSI & GF) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

7 Providing and fixing stainless steel sink with drain board, size Each 177.40 4,024.50 Each 177.40 4,024.50
120x60 cm (48"x24") including bracket set, waste pipe and
waste coupling.

8 Providing and fitting terrazzo concrete sink 60x45 cm (24"x18") Each 177.40 975.90 Each 177.40 975.90
with drain board of mosaic, including bracket set, waste pipe
and waste coupling.

9 Providing and fixing glazed earthen ware sink, including


bracket set, waste pipe and waste coupling:-

i) 60x45 cm (24"x18") Each 177.40 1,449.00 Each 177.40 1,449.00


ii) 37.5x45 cm (15"x18") Each 177.40 1,269.00 Each 177.40 1,269.00

10 Providing and fixing glazed earthen ware flat back urinal. Each 115.50 779.10 Each 115.50 779.10

11 Providing and fitting glazed earthen ware low down flushing


cistern 13,63 litres (3 gallons) capacity, including bracket
set, copper connection, etc.

i) white Each 177.40 1,131.50 Each 177.40 1,131.50


ii) coloured Each 177.40 1,211.90 Each 177.40 1,211.90

12 Providing and fitting plastic made low down flushing cistern


1363 litre (3 gallons) capacity, including bracket set, copper
connection, etc. complete.

i) white Each 177.40 987.50 Each 177.40 987.50 If rubber connection is used, the
ii) coloured Each 177.40 987.50 Each 177.40 987.50 composite rate will be reduced by
Rs. 12.50

13 Providing and fixing white enameled cast iron low down flushing Each 177.40 1,122.25 Each 177.40 1,122.25
cistern 13.63 litres (3 gallons) capacity, including bracket
set, copper connection, etc.

14 Providing and fixing cast iron high level flushing cistern


including cost of bracket set, copper connection, etc.

i) 13.63 litres (3 gallons) capacity Each 188.95 2,201.80 Each 188.95 2,201.80
ii) 4.55 litres (1 gallon) capacity Each 188.95 1,421.80 Each 188.95 1,421.80

15 Providing and fixing, chromium plated soap dish. Each 11.55 169.15 Each 11.55 169.15

chapter-19(PSI & GF) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

16 Providing and fitting, glazed earthen ware soap dish.

i) white Each 11.55 433.15 Each 11.55 433.15


ii) coloured Each 11.55 217.15 Each 11.55 217.15

17 Providing and fixing, chromium plated toilet paper holder. Each 15.40 291.95 Each 15.40 291.95

18 Providing and fixing, chromium plated towel rail:-

i) 60 cm (24") long, and 2 cm (¾") dia. Each 15.40 317.40 Each 15.40 317.40
ii) 50 cm (20") long, and 1.5 cm (½") dia. Each 15.40 287.40 Each 15.40 287.40

19 Providing and fixing looking glass 55x40 cm (22"x16") size, Each 28.90 344.10 Each 28.90 344.10
and 5 mm thick, first quality.

20 Providing and fixing glass shelf 60x13 cm (24"x5"), with


5mm thick glass:-

i) with chromium plated brackets and railing. Each 34.35 316.90 Each 34.35 316.90
ii) glass shelf only, without chromium plated brackets Each 23.10 71.10 Each 23.10 71.10
and railing.

21 Providing and fitting glazed earthen ware shelf 60x13 cm


(24"x5"), with chromium plated bracket and railing:-

i) White Each 34.35 640.90 Each 34.35 640.90


ii) Coloured Each 34.35 700.90 Each 34.35 700.90

22 Providing and fitting:-

i) plastic soap dish Each 11.55 147.45 Each 11.55 147.45


ii) plastic toilet paper holder Each 15.40 175.15 Each 15.40 175.15
iii) plastic towel rail Each 15.40 235.15 Each 15.40 235.15
iv) plastic shelf 60x13 cm (24"x5") with bracket and railing. Each 15.40 388.40 Each 15.40 388.40

23 Providing and fixing chromium plated pillar-cock, heavy:-

i) 2 cm (¾") Each 15.40 495.40 Each 15.40 495.40


ii) 1.5 cm (½") Each 15.40 652.60 Each 15.40 652.60

24 Providing and fixing chromium plated stop cock, heavy:-


i) 2 cm (¾") Each 15.40 279.40 Each 15.40 279.40
ii) 1.5 cm (½") Each 15.40 175.00 Each 15.40 175.00

chapter-19(PSI & GF) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

25 Providing and fixing underground stop cock 13 mm (½"), Each 22.00 441.90 Each 22.00 441.90
with chromium plated cover.

26 Providing and fixing chromium plated bib cock:-


i) 2 cm (¾") Each 15.40 369.40 Each 15.40 369.40
ii) 1.5 cm (½") Each 15.40 301.00 Each 15.40 301.00

27 Providing and fixing chromium plated tee stop cock Each 15.40 428.20 Each 15.40 428.20
15mm (½").

28 Providing and fixing chromium plated shower rose:-

i) 1.5x10 cm (½"x4") Each 15.40 314.20 Each 15.40 314.20


ii) 2x15 cm (¾"x6") Each 15.40 375.40 Each 15.40 375.40

29 Providing and fixing, chromium plated mixing valve, for wash Each 19.25 1,450.85 Each 19.25 1,450.85
hand basin, sink or shower.

30 Providing and fixing gun metal peet/gate valve (screwed):- For brass peet/gate valve (screwed),
the composite rates of items (i) to (v)
i) 30 mm (1¼") dia Each 23.10 407.10 Each 23.10 407.10 will be reduced by Rs. 66, 77, 95, 107
ii) 40 mm(1½") dia Each 23.10 563.10 Each 23.10 563.10 and 120 respectively.
iii) 50 mm(2") dia Each 23.10 767.10 Each 23.10 767.10
iv) 65 mm(2½") dia Each 23.10 1,211.10 Each 23.10 1,211.10
v) 80 mm(3") dia Each 23.10 1,793.10 Each 23.10 1,793.10

31 Providing and fitting, chromium plated or brass oxidised,


swan neck cock 15 mm (½") dia.

i) single way Each 15.40 351.40 Each 15.40 351.40


ii) two way Each 23.10 605.10 Each 23.10 605.10
iii) three way Each 30.80 732.80 Each 30.80 732.80

32 Providing and fixing, union brass cock.

i) 13 mm (½") dia Each 15.40 69.40 Each 15.40 69.40


ii) 20 mm (¾") dia Each 15.40 207.40 Each 15.40 207.40

33 Providing and fixing, floor trap of cast iron, including concrete


chamber all round, and C.I. grating:-

i) 10x5 cm (4"x2") Each 46.20 344.20 Each 46.20 344.20


ii) 10x7.5 cm (4"x3") Each 46.20 332.20 Each 46.20 332.20

chapter-19(PSI & GF) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

34 Providing and fitting "P" trap:-

i) 10 cm (4") of cast iron. Each 38.50 407.00 Each 38.50 407.00


ii) 10 cm (4") glazed. Each 38.50 107.00 Each 38.50 107.00

35 Providing and fitting 10 cm (4") gully trap, including cement Each 57.75 478.55 Each 57.75 478.55
concrete, cost of PVC grating 15x15 cm (6"x6") and
masonry chamber 30x30 cm (12"x12").

36 Providing and fitting, cast iron soil pipe with:-

i) lead caulked, yarn joint:-

a) 10 cm (4") i/d Per foot 17.10 185.70 Metre 56.10 609.05


b) 5 cm (2") i/d Per foot 6.85 92.80 Metre 22.45 304.30

ii) cement caulked joint:-

a) 10 cm (4") i/d Per foot 4.15 121.45 Metre 13.60 398.35


b) 5 cm (2") i/d Per foot 1.65 82.80 Metre 5.45 271.60

37 Providing and fitting, A.C. soil pipe with cement caulked


joint, including all specials:-

i) 60 (2¼)" mm i/d Per foot 3.30 25.30 Metre 10.90 83.00


ii) 80 (3") mm i/d Per foot 3.70 61.90 Metre 12.10 203.00
iii) 100 (4") mm i/d Per foot 4.15 96.45 Metre 13.60 316.35
iv) 150 (6") mm i/d Per foot 5.55 121.00 Metre 18.15 396.90

38 Providing and fitting cast iron specials, such as tee bend, In case of plug type, the composite
collar, cross, etc. plain type:- rate shall be increased by Rs.2 per kg.

i) lead caulked joint Kg 14.30 130.45 Kg 14.30 130.45


ii) cement caulked joint Kg 8.80 100.25 Kg 8.80 100.25

39 Supply and fitting of cast iron manhole cover


with frame, etc. complete.

i) 30 cm (12") dia Each 23.10 167.10 Each 23.10 167.10


ii) 45 cm (18") dia Each 23.10 773.10 Each 23.10 773.10
iii) 60 cm (24") dia Each 36.30 1,248.30 Each 36.30 1,248.30
40 Providing and fitting R.C.C. pipe 10 cm (4") dia, including Per foot 8.55 32.55 Metre 28.05 106.75
laying and jointing in trenches.

chapter-19(PSI & GF) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

41 Providing and fitting chromium plated or oxidised, gas cock


6'mm (¼"):-

i) single way Each 15.40 181.00 Each 15.40 181.00


ii) two way Each 23.10 275.10 Each 23.10 275.10
iii) three way Each 30.80 468.80 Each 30.80 468.80

42 Providing and fitting nipple or bush, 6 mm to Each 11.55 23.55 Each 11.55 23.55
10 mm (¼" to 3/8") i/d.

43 Providing and fixing, brass gas cock:-

a) 15 mm (½") dia Each 2.40 74.40 Each 2.40 74.40


b) 20 mm (¾") dia Each 87.50 92.40 Each 87.50 92.40

44 Providing and fixing brass stop cock/bib cock:-

a) 15 mm (½") dia Each 3.85 73.45 Each 3.85 73.45


b) 20 mm (¾") dia Each 3.85 111.85 Each 3.85 111.85

45 Hoisting and placing in position, precast R.C. latrine seats. Each 188.95 - Each 188.95 -

Replacement

1 Providing and fixing, chromium plated waste coupling:-

i) 3 cm (1¼") Each 23.10 113.10 Each 23.10 113.10


ii) 4 cm (1½") Each 23.10 119.10 Each 23.10 119.10

2 Providing and fixing rubber plug with chain:-

i) 3 cm (1¼") Each 0.90 45.30 Each 0.90 45.30


ii) 4 cm (1½") Each 0.90 42.90 Each 0.90 42.90

3 Providing and fixing, waste pipe of PVC:-

i) 3 cm (1¼") Each 11.55 41.55 Each 11.55 41.55


ii) 4 cm (1½") Each 11.55 53.55 Each 11.55 53.55

4 Providing and fixing, flushing bend of PVC.

i) 3 cm (1¼") Each 10.25 40.25 Each 10.25 40.25


ii) 4 cm (1½") Each 10.25 52.25 Each 10.25 52.25

chapter-19(PSI & GF) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

5 Providing and fixing chromium plated bottle trap with waste


pipe, etc. complete:-

i) 3 cm (1¼") i/d Each 23.10 533.10 Each 23.10 533.10


ii) 4 cm (1½") Each 23.10 623.10 Each 23.10 623.10

6 Providing and fixing, angle iron brackets for:-

i) wash hand basin and cistern Each 23.10 135.90 Each 23.10 135.90
ii) sinks Each 23.10 147.90 Each 23.10 147.90

7 Providing and fixing 1.5 cm (½") dia connection, including


check nuts, etc.:-

i) plastic rubber connection Each 9.25 51.25 Each 9.25 51.25


ii) copper connection Each 9.25 81.25 Each 9.25 81.25

8 Providing and fixing brass ball float valve:-

i) 1.5 cm (½") dia Each 19.25 199.25 Each 19.25 199.25


ii) 2.0 cm (¾") dia Each 19.25 259.25 Each 19.25 259.25
iii) 2.5 cm (1") dia Each 19.25 319.25 Each 19.25 319.25
iv) 3 cm (1¼") dia Each 19.25 343.25 Each 19.25 343.25
v) 4.0 cm (1½") dia Each 19.25 487.25 Each 19.25 487.25
vi) 5 cm (2") dia Each 19.25 559.25 Each 19.25 559.25

chapter-19(PSI & GF) Page 7


SURFACE DRAINAGE
1. Specification No. correspond to Book of Specification (B & R Department ) Vol. 11, 1966 (public Health Works).
2. Rates for all finished works include the removal of surplus debris, unused material and by produc
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Tega formed of pacca bricks on end, laid in and over 17.1


cement sand mortar projecting to a height of not more
than 6" (150 mm) top of drain along the property side
where required, laid to lines, grades, slopes and shape
according to the Engineer's drawing:-

a) 3" thick (75 mm)

i) ratio 1:3 100Rft 628.60 1,882.80 Metre 20.60 61.75


ii) ratio 1:5 ditto 628.60 1,764.00 ditto 20.60 57.85

B) 4½" thick (113 mm)

i) ratio 1:3 100Rft 941.40 2,733.95 ditto 30.90 89.65


ii) ratio 1:5 ditto 941.40 2,552.80 ditto 30.90 83.75

2 Pacca flat brick 3" (75 mm ) thick, laid in reimbursement, 17.1


in cement, sand mortar, on sides of drains and in other
works where required. All joints to be completely filled
and struck flush:-

a) ratio 1:3 100Sft. 932.20 2,715.60 Sqm. 100.30 292.20


b) ratio 1:5 ditto 932.20 2,524.05 ditto 100.30 271.60
c) ratio 1:6 ditto 932.20 2,470.10 ditto 100.30 265.80

3 Pacca brick on edge, laid in reimbursement, in cement, 17.1


sand mortar, on sides of drains and on other works where
required. All joints to be completely filled and struck
flush:-

a) ratio 1:3 100Sft. 1,333.20 4,029.65 Sqm. 143.45 433.60


b) ratio 1:5 ditto 1,333.20 3,722.25 ditto 143.45 400.50
c) ratio 1:6 ditto 1,333.20 3,645.80 ditto 143.45 392.30

chapter-20(Surface Drainage) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

4 Pacca flat brick, Herring bond pitching in cement, sand 17.2


mortar, laid to lines, grades, shapes and slopes as per
Engineer's drawing:-

a) ratio 1:3 100Sft. 844.80 2,628.25 Sqm. 90.90 282.80


b) ratio 1:5 ditto 844.80 2,436.70 ditto 90.90 262.20
c) ratio 1:6 ditto 844.80 2,382.70 ditto 90.90 256.40

5 Pacca brick on edge, Herring bond pitching in cement, 17.2


sand mortar, laid to lines, grades, shapes and slopes as
per Engineer's drawing:-

a) ratio 1:3 100Sft. 1,306.80 4,003.25 Sqm. 140.60 430.75


b) ratio 1:5 ditto 1,306.80 3,695.85 ditto 140.60 397.65
c) ratio 1:6 ditto 1,306.80 3,619.40 ditto 140.60 389.45

6 Constructing Punjab Standard Drains. of cement concrete


1:2 ½ :5, with cement concrete bedding ratio 1:6:12, 17.1
complete, laid to lines, grades, slopes and shapes,
rendering exposed surface of concrete with 1:1 cement,
sand mortar, ¼" (6 mm) thick, as per Engineer's drawing
(excluding excavation):-

a) Type I Per Rft 20.55 57.10 Metre 67.40 187.35


b) Type II ditto 41.10 105.55 ditto 134.75 346.15
c) Type III ditto 52.35 135.75 ditto 171.65 445.30
d) Type IV ditto 62.20 161.75 ditto 204.00 530.60
e) Type V ditto 81.65 220.25 ditto 267.80 722.40
f) Type VI ditto 93.85 252.35 ditto 307.85 827.75
g) Type VII ditto 104.00 271.80 ditto 341.15 891.40
h) Type VIII ditto 116.15 312.05 ditto 381.05 1,023.60
i) Type IX ditto 154.15 441.20 ditto 505.70 1,447.20
j) Type X ditto 169.40 483.65 ditto 555.60 1,586.35
k) Type XI ditto 189.50 538.00 ditto 621.55 1,764.60
l) Type XII ditto 202.00 570.70 ditto 662.55 1,871.95

7 Laying R.C.C hume pipes in position, including jointing:-


a) 6" to 12" (150 mm to 300 mm ) dia Per Lft. 38.30 40.50 Metre 125.55 132.85
b) 12" to 24" (300 mm to 600 mm) dia ditto 58.10 62.50 ditto 190.50 205.05
c) 24" to 36" (600 mm to 900 mm) dia ditto 76.55 83.25 ditto 251.10 273.05

chapter-20(Surface Drainage) Page 2


SEWERAGE
1 Specification No. correspond to Book of Specification of B&R Department Vol. II, 1966 (Public Health Works).
2 Rate for all finished works include the removal of surplus debris, unused material and byproducts
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Providing and laying R.C.C. pipe, moulded with cement Chapter - 8


concrete 1:1½:3, with spigot socket or collar joint, etc.
including cost of reinforcement, conforming to B.S. 5911:
Part I: 1981, Class "L" including carriage of pipe from
factory to site of work, lowering in trenches to correct
alignment and grade, jointing, cutting pipes where
necessary, finishing and testing, etc., complete.
i) 100 mm (4") i/d Rft. 10.15 62.60 Metre 33.30 205.35
ii) 150 mm (6") i/d Rft. 12.35 100.20 Metre 40.50 328.65
iii) 225 mm (9:) i/d Rft. 23.90 229.10 Metre 78.40 751.45

2 Providing and laying non-reinforced concrete pipe, ditto


moulded with cement concrete 1:1½:3, conforming to
ASTM Specification C-14-73, Class 2, including carriage
of pipe from factory to site of work, lowering in trenches to
correct alignment and grade, jointing, cutting pipe where
necessary, finishing and testing, etc. complete.
i) 100 mm (4") i/d Rft. 7.65 30.85 Metre 25.10 101.20
ii) 150 mm (6") i/d Rft. 9.30 44.70 Metre 30.50 146.60
iii) 200 mm (8") i/d Rft. 14.85 61.25 Metre 48.70 200.95
iv) 225 mm (9:) i/d wall thickness 1 inch (25 mm) Rft. 16.15 78.55 Metre 52.95 257.65
v) 250 mm (10") i/d Rft. 16.50 87.45 Metre 54.10 286.85

3 Providing and laying R.C.C. pipe sewers, moulded with ditto


cement concrete 1:1½:3 conforming to ASTM
Specification C-76-79, Class II. Wall B, including carriage
of pipe from factory to site of work, lowering in trenches to
correct alignment and grade, jointing with rubber ring,
cutting pipes where necessary, testing, etc., complete.

i) 310 mm (12") i/d Rft. 25.00 291.25 Metre 82.00 955.30


ii) 380 mm (15") i/d Rft. 31.45 355.10 Metre 103.15 1164.75
iii) 460 mm (18") i/d Rft. 38.00 430.05 Metre 124.65 1410.55
iv) 530 mm (21":) i/d Rft. 47.65 548.50 Metre 156.30 1799.10
v) 610 mm (24") i/d Rft. 55.10 661.05 Metre 180.75 2168.25
vi) 690 mm (27") i/d Rft. 79.90 831.35 Metre 262.05 2726.85
vii) 760 mm (30") i/d Rft. 95.75 956.00 Metre 314.05 3135.70
viii) 840 mm (33") i/d Rft. 119.00 1116.20 Metre 390.30 3661.15

chapter-21(Sewerage) Page 1
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ix) 910 mm (36") i/d Rft. 146.70 1534.20 Metre 481.20 5032.20
x) 1070 mm (42") i/d Rft. 190.65 2075.25 Metre 625.35 6806.80
xi) 1220 mm (48") i/d Rft. 354.05 2632.25 Metre 1161.30 8633.80
xii 1370 mm (54") i/d Rft. 484.75 3314.10 Metre 1590.00 10870.25
xiii) 1520 mm (60") i/d Rft. 623.75 4142.85 Metre 2045.90 13588.55
xiv) 1680 mm (66") i/d Rft. 965.00 5344.40 Metre 3165.20 17529.65
xv) 1830 mm (72") i/d Rft. 1192.15 6490.75 Metre 3910.25 21289.65

4 Providing and laying R.C.C. pipe sewers, moulded with Chapter-8


cement concrete 1:1½:3 conforming to ASTM Specification
C-76-79, Class III, Wall B, including carriage of pipes from
factory to site of work, lowering in trenches to correct
alignment and grade, jointing with rubber ring, cutting pipes
where necessary, testing, etc. complete:-

i) 310 mm (12") i/d Rft. 25.00 347.55 Metre 82.00 1139.95


ii) 380 mm (15") i/d Rft. 31.45 410.15 Metre 103.10 1345.30
iii) 460 mm (18") i/d Rft. 38.00 509.60 Metre 124.65 1671.50
iv) 530 mm (21":) i/d Rft. 47.65 679.45 Metre 156.30 2228.60
v) 610 mm (24") i/d Rft. 55.10 798.15 Metre 180.75 2617.95
vi) 690 mm (27") i/d Rft. 79.95 885.30 Metre 262.30 2903.80
vii) 760 mm (30") i/d Rft. 95.85 1177.65 Metre 314.45 3862.70
viii) 840 mm (33") i/d Rft. 119.15 1361.15 Metre 390.80 4464.55
ix) 910 mm (36") i/d Rft. 146.65 1818.15 Metre 481.05 5963.55
x) 1070 mm (42") i/d Rft. 190.85 2372.45 Metre 626.05 7781.65
xi) 1220 mm (48") i/d Rft. 358.85 2738.45 Metre 1177.05 8982.10
xii 1370 mm (54") i/d Rft. 491.45 3632.10 Metre 1612.00 11913.30
xiii) 1520 mm (60") i/d Rft. 632.15 4539.95 Metre 2073.45 14891.05
xiv) 1680 mm (66") i/d Rft. 978.45 5732.95 Metre 3209.30 18804.10
xv) 1830 mm (72") i/d Rft. 1208.90 7012.10 Metre 3965.25 22999.70

5 Providing and laying R.C.C. pipe sewers, moulded with Chapter - 8


cement concrete 1:1½:3 conforming to ASTM
Specification C-76-79, Class IV, Wall B, including carriage
of pipes from factory to site of work, lowering in trenches
to correct alignment and grade, jointing with rubber ring,
cutting pipes where necessary, testing, etc. complete:-

i) 310 mm (12") i/d Rft. 25.00 296.15 Metre 82.00 971.40


ii) 380 mm (15") i/d Rft. 31.45 355.10 Metre 103.10 1164.65
iii) 460 mm (18") i/d Rft. 38.00 458.20 Metre 124.65 1502.85
iv) 530 mm (21":) i/d Rft. 47.65 636.60 Metre 156.30 2088.10
v) 610 mm (24") i/d Rft. 55.10 853.25 Metre 180.75 2798.60
vi) 690 mm (27") i/d Rft. 79.90 1123.90 Metre 262.00 3686.30
vii) 760 mm (30") i/d Rft. 95.75 1391.70 Metre 314.05 4564.95
viii) 840 mm (33") i/d Rft. 119.00 1544.60 Metre 390.30 5066.30
ix) 910 mm (36") i/d Rft. 146.50 2313.70 Metre 480.45 7588.85

chapter-21(Sewerage) Page 2
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

x) 1070 mm (42") i/d Rft. 190.65 2647.65 Metre 625.25 8684.20


xi) 1220 mm (48") i/d Rft. 358.90 3405.45 Metre 1176.85 11169.95
xii) 1370 mm (54") i/d Rft. 491.50 4623.65 Metre 1612.30 15165.40
xiii) 1520 mm (60") i/d Rft. 632.20 5812.95 Metre 2073.60 19066.45
xiv) 1680 mm (66") i/d Rft. 978.50 6853.00 Metre 3209.50 22477.70
xv) 1830 mm (72") i/d Rft. 1209.00 8113.80 Metre 3965.50 26613.25

6 Lowering of sub-soil water table, by installation of tubewells 1) This rate shall be payable, in
along sewer line and pumping out water, for excavation in addition to the item of excavation
open cutting below sub-soil water level, concreting, curing, below SSWL for sewers and
laying and jointing pipes, filling haunches, etc. till the manholes under Chapter,
completion of sewer line, including disposal of pumped out EARTHWORK
water:- 2) The grant of these rates shall be
Rft of Metre of subject to Superintending Engineer's
1) 0-1 ft. (0 to 310 mm) below SSWL laid sewer - 148.60 laid sewer - 487.50 approval.
2) 0-2 ft. (0 to 610 mm) below SSWL ditto - 290.05 ditto - 951.35
3) 0-3 ft. (0 to 910 mm) below SSWL ditto - 487.90 ditto - 1600.40 3) The rate includes cost of
4) 0-4 ft. (0 to 1220 mm) below SSWL ditto - 700.55 ditto - 2297.80 providing pumps, POL and all
5) 0-5 ft. (0 to 1520 mm) below SSWL ditto - 967.25 ditto - 3172.50 operation charges at the site
6) 0-6 ft. (0 to 1830 mm) below SSWL ditto - 1197.45 ditto - 3927.70 of work, etc.
7) 0-7 ft. (0 to 2170 mm) below SSWL ditto - 1429.25 ditto - 4687.85
8) 0-8 ft. (0 to 2480 mm) below SSWL ditto - 1641.45 ditto - 5383.90
9) 0-9 ft. (0 to 2790 mm) below SSWL ditto - 1788.75 ditto - 5867.05
10) 0-10 ft. (0 to 3100 mm) below SSWL ditto - 2057.30 ditto - 6747.95
11) 0-11 ft. (0 to 3410 mm) below SSWL ditto - 2284.15 ditto - 7492.05
12) 0-12 ft. (0 to 3720 mm) below SSWL ditto - 2529.10 ditto - 8295.45

7 Constructing gully grating chamber, 12"x12", ( 300x300 16.2 Pipe connection to be paid
mm) complete in all respects: separately.

a) with C.I. gully trap, weighing 81 lbs. (36.75 Kg.) frame Each 424.10 1499.95 Each 424.10 1499.95
hinged safety type.

b) concrete Gully trap. ditto 424.10 1539.95 ditto 424.10 1539.95

8 Constructing standard gully grating chamber, 3'x2½' Each 1290.05 5003.20 Each 1290.05 5003.20 ditto Pipe connection to be paid
(900x750 mm), with chinaware trap as per PHED Drawing separately.
STD/PD No. 3 of 1977, complete in all respects.

9 Extra for making and finishing benching floor work in 100Sft. 584.45 913.10 Sq.m 62.90 98.25 14.4
manhole chamber, with 1/8" (3 mm) thick cement finish

10 Restoration of brick pavement on edge, over laid service 100Sft. 817.10 1549.40 Sq.m 87.90 166.70 13.1
line, with 2" (50 mm) sand cushion under soling

chapter-21(Sewerage) Page 3
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

11 Restoration of flat brick pavement sand grouted, over 2" 100Sft. 496.65 1041.05 Sq.m 53.45 112.00 13.1
(50 mm) thick dry sand cushion, under soling on laid
service line.

12 Restoration of metalled road, on laid service line, including 13.1


compaction:-

a) Carpetted road, with 2" (50 mm) carpet and 10" (250 100Sft. 1659.65 5290.20 Sq.m 178.60 569.25
mm) depth of stone metal for sub-base and base

b) Carpeted road, with 1½" (38 mm) carpet and 6" (150 100Sft. 1192.65 3901.45 Sq.m 128.35 419.80
mm) depth of stone metal, for sub-base and base

c) Black Topped Road with two coats of surfacing & 10" 100Sft. 496.55 2339.85 Sq.m 53.45 251.75
(250 mm) depth of stone metal, for sub base & base

13 Providing and fixing 1¼"x1¼"x3/16" (31x31x5 mm) angle 14.7


iron step, in manhole chambers, including carriage and Each 38.25 187.45 Each 38.25 187.45
setting the same in work to correct lines and levels.

14 Fixing manhole frame and cover in R.C.C. slab including Per 128.15 - Per 128.15 - ditto
carriage to site. set set

15 Providing and fixing 3" (75 mm) thick R.C.C. manhole Per 95.85 2608.05 Per 95.85 2608.05 ditto
cover, 22" (550 mm) dia, with tee shaped C.I. frame of 20" set set
(500 mm) clear i/d (frame weighing 37.324 Kg. or one
maund) as per Standard Drawing STD/PD No. 5, of 1977,
complete in all respects.

15-A Providing and fixing 6" thick R.C.C. manhole Per 182.28 3709.74 Per 182.28 3709.74
cover with tee shaped C.I. frame of 22" I/d (frame set set
weighing 37.324 Kg. or one maund as per Standard
Drawing STD/PD No. 6, of 1977, complete in all respect.

16 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 164.25 2225.95 Per 164.25 2225.95 ditto
cover for 22" as per standard drawing STD/PD No. 6 of set set
1977, complete in all respects.

17 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 143.70 3643.70 Per 143.70 3643.70 ditto
cover with 3"x3"x¼" (75x75x6mm) angle iron frame, 22" set set
(550 mm) i/d as per standard drawing STD/PD No. 7 of
1977, complete in all respects.

18 Desilting of disposal work collecting tank, including 100Cft. 377.15 431.45 cum 133.20 152.40 16.2
removal of sludge within 3 chains (90 metre).

chapter-21(Sewerage) Page 4
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

19 Providing and installing, C.I. ventilating shaft painted with 14.6


bituminous paint with foundation bolts, as per PHED
Standard Drawing STD/PD No. 4 of 1977, complete in all
respects (except concrete foundation block):-

a) 6" (150 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 103.15 2134.70 %kg 203.00 4202.15
ii) 24 ft. (7.30 metre) long ditto 114.60 2151.75 ditto 225.55 4235.75
iii) 30 ft. (9.15 metre) long ditto 123.75 2159.60 ditto 243.60 4251.15
iv) 36 ft. (11 metre) long ditto 129.50 2165.65 ditto 254.90 4263.05

b) 9" (225 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 92.40 2120.25 %kg 181.90 4173.65
ii) 24 ft. (7.30 metre) long ditto 99.55 2126.90 ditto 196.00 4186.80
iii) 30 ft. (9.15 metre) long ditto 106.60 2134.40 ditto 209.85 4201.60
iv) 36 ft. (11 metre) long ditto 128.35 2155.95 ditto 252.65 4244.00

c) 12" (300 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 82.50 2111.45 %kg 162.40 4156.40
ii) 24 ft. (7.30 metre) long ditto 106.05 2132.35 ditto 208.80 4197.60
iii) 30 ft. (9.15 metre) long ditto 123.75 2149.40 ditto 243.60 4231.10

20 Silt clearing 10' (3.00 m) dia wells, and


removal of slush outside the compound:-

a) upto 10' (3.00 m) depth of slush Per well 2804.35 - Per well 2804.35 -
b) beyond 10' (3.00 m) depth of slush Per well 5610.00 - Per well 5610.00 -

chapter-21(Sewerage) Page 5
SINKING OF WELLS
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
2 Well curbs to be laid at spring level or as deep as possible.
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Excavation of well in dry upto 20'(6 metre) below ground


level, and disposal of soil within one chain (30 metre)

a) in ordinary soil or sand :- 1000 Cft. cu.m

i) from 0' to 5' (o to 1.5 m) depth ditto 1961.50 - ditto 69.30 -


ii) from 5.1' to 10' (1.5 to 3.0 metre) depth ditto 2048.65 - ditto 72.35 -
iii) from 10.1' to 15' (3.0 to 4.5 metre) depth ditto 2304.70 - ditto 81.40 -
iv) from 15.1' to 20' (4.5 metre to 6.0 metre) depth ditto 2645.30 - ditto 93.45 -

b) in hard soil

i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 2389.20 - cu.m 84.40 -
ii) from 5.1' to 10'(1.5 to 3.0 metre) depth ditto 2497.45 - ditto 88.20 -
iii) from 10.1' to 15'(3.0 to 4.5 metre) depth ditto 2729.75 - ditto 96.40 -
iv) from 15.1' to 20'(4.5 to 6.0 metre) depth ditto 3070.30 - ditto 108.45 -

c) in hard strata, such as shingle, gravel, etc.

i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 5153.30 - cu.m 182.00 -
ii) from 5.1' to 10'(1.5 to 3.0 metre) depth ditto 5338.10 - ditto 188.55 -
iii) from 10.1' to 15'(3.0 to 4.5 metre) depth ditto 5565.10 - ditto 196.55 -
iv) from 15.1' to 20'(4.5 to 6.0 metre ) depth ditto 5974.30 - ditto 211.00 -

2 Dry sinking of well, including loading, and removing


excavated material within one chain (30 m):-

a) in ordinary soil :-

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 10560.00 - cu.m 373.00
ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 13200.00 - ditto 466.20
iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 15840.00 - ditto 559.45
iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 18480.00 - ditto 652.70
v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 21120.00 - ditto 745.95
vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 23760.00 - ditto 839.20
vii) from 40.1'to 45'(12.0 to 13.5 m) depth ditto 26400.00 - ditto 932.45
viii) from 45'(13.5 Sm) to any depth ditto 29040.00 - ditto 1025.70

chapter-22(Sinking of Wells) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) in hard soil :-

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 14520.00 - cu.m 512.85 -
ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 17160.00 - ditto 606.10 -
iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 19800.00 - ditto 699.35 -
iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 22440.00 - ditto 792.60 -
v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 25080.00 - ditto 885.85 -
vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 27720.00 - ditto 979.05 -
vii) from 40.1' to 45'(12.0 to 13.5 m) depth ditto 30360.00 - ditto 1072.30 -
viii) from 45'(13.5 m) to any depth ditto 33000.00 - ditto 1165.55 -

c) in hard strata, such as shingle, gravel, etc.

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 19800.00 - cu.m 699.35 -
ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 22440.00 - ditto 792.60 -
iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 25080.00 - ditto 885.85 -
iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 25410.00 - ditto 897.50 -
v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 30360.00 - ditto 1072.30 -
vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 33000.00 - ditto 1165.55 -
vii)from 40.1' to 45'(12.0 to 13.5 m) depth ditto 35640.00 - ditto 1258.80 -
viii) from 45'-1" (13.5 m) to any depth ditto 38280.00 - ditto 1352.05 -

3 Wet sinking of well in ordinary soil (value of C upto 5), for *841-1 The outer dimensions of the curb
depths below spring level, including charges of machinery, to shall form basis of payment.
shoring, kentledge and removal of excavated spoil within 841-9
one chain (30 m):-

i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. 10621.65 - cu.m 198.60 -
ii) above 10' to 20'(3.0 to 6.0 m) depth ditto 33000.00 - ditto 1165.55 -
iii) above 20' to 30'(6.0 to 9.0 m) depth ditto 40615.40 - ditto 1434.55 -
iv) above 30' to 40'(9.0 to 12.0 m) depth ditto 52800.00 - ditto 1864.90 -
v) above 40' to 50'(12.0 to 15.0 m) depth ditto 58666.65 - ditto 2072.10 -
vi) above 50' to 60'(15.0 to 18.0 m) depth ditto 66000.00 - ditto 2331.10 -
vii) above 60' to 70'(18.0 to 21.0 m) depth ditto 67692.30 - ditto 2390.90 -
viii) above 70' to 80'(21.0 to 24.0 m) depth ditto 69473.70 - ditto 2453.80 -
ix) above 80'(24.0 m) to any depth ditto 75428.55 - ditto 2664.15 -

chapter-22(Sinking of Wells) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

4 Wet sinking of well in cohesive soil (value of Cmore than *841-1 The outer dimensions of the curb
5), for depths below spring level, including charges of to shall form basis of payment.
machinery shoring, kentledge and removal of excavated 841-9
spoil within one chain (30 m):-

i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 22792.80 cu.m - 805.05
ii) above 10' to 20'(3.0 to 6.0 m) depth ditto - 28491.00 ditto - 1006.30
iii) above 20' to 30'(6.0 to 9.0 m) depth ditto - 34189.15 ditto - 1207.55
iv) above 30' to 40'(9.0 to 12.0 m) depth ditto - 45585.55 ditto - 1610.10
v) above 40' to 50'(12.0 to 15.0 m) depth ditto - 52598.75 ditto - 1857.80
vi) above 50' to 60'(15.0 to 18.0 m) depth ditto - 56981.95 ditto - 2012.60
vii) above 60' to 70'(18.0 to 21.0 m) depth ditto - 62162.15 ditto - 2195.55
viii) above 70' to 80'(21.0 to 24.0 m) depth ditto - 64507.85 ditto - 2278.40
ix) above 80'(24.0 m) to any depth ditto - 68378.35 ditto - 2415.10

5 Wet sinking of well in shingle, or gravel, etc, for depths *841-1 The outer dimensions of the curb
below spring level, including charges of machinery, to shall form basis of payment.
shoring, kentledge and removal of excavated spoil within 841-9
one chain (30 m) :-
i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 31081.05 cu.m - 1097.80
ii) above 10' to 20'(3.0 to 6.0 m) depth ditto - 37987.95 ditto - 1341.75
iii) above 20' to 30'(6.0 to 9.0 m) depth ditto - 45585.55 ditto - 1610.10
iv) above 30' to 40'(9.0 to 12.0 m) depth ditto - 62162.15 ditto - 2195.55
v) above 40' to 50'(12.0 to 15.0 m) depth ditto - 68378.35 ditto - 2415.10
vi) above 50' to 60'(15.0 to 18.0 m) depth ditto - 75975.95 ditto - 2683.45
vii) above 60' to 70'(18.0 to 21.0 m) depth ditto - 79509.70 ditto - 2808.30
viii) above 70' to 80'(21.0 to 24.0 m) depth ditto - 81402.80 ditto - 2875.15
ix) above 80'(24.0 m) to any depth ditto - 89971.50 ditto - 3177.80

6 Making and fixing in position, kiker wood well curb. Per Cft. 478.20 1264.70 cu.m 16890.75 44669.85

7 Laying well curb in position only. Each 184.80 - Each 184.80 -

8 Providing, making and laying R.C.C. well curb in position, *841-1 1) If concrete mixer is supplied by
using coarse sand, including all kinds of form, moulds, to Government, all charges including
curing, shuttering, rendering and finishing the exposed 841-9 depreciation will be recovered from
surface, (including screening and washing of aggregate :- the contractor.
2) The rate does not include cost of
a) Ratio 1:1½:3 Per Cft. 113.20 241.30 cu.m 3997.85 8522.50 steel reinforcement and its labour for
b) ratio 1:2:4 ditto 113.20 219.40 ditto 3997.85 7748.85 bending, which is payable, separately.

chapter-22(Sinking of Wells) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

9 Providing and fixing structural steel for cutting 100Kg 330.00 9936.40 100Kg 330.00 9936.40 841-1 to
edge. 841-9

10 Making and removing false masonry on well. 100Cft. 3520.00 8177.40 cu.m 1243.25 2888.25 21.1 to The rate includes dismantling of false
21.5 & 18.1 masonry, scraping bricks obtained
from dismantling and credit of
byproducts.

* Specification No. correspond to Book of "Standard Specification for Road and Bridge Construction, 1971".

chapter-22(Sinking of Wells) Page 4


TUBEWELL AND WATER SUPPLY
1 Specification No. correspond to Book of "Specification for B&R Department, 1966, Vol. II (Public Health Works)".
2 Rates for all finished works include the removal of surplus debris, unused material and byproduc
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Boring for tubewell in all types of soil except shingle and Chap. 2
rock, from ground level to 100 ft. (30 m) depth, including
sinking and withdrawing of casing pipe, complete:-

a) 3" (75 mm) i/d Per Rft. 26.45 Per Metre 86.75
b) 4" (100 mm) i/d of bore 37.20 of bore 121.95
c) 5" (125 mm) i/d ditto 68.40 ditto 224.40
d) 6" (150 mm) i/d ditto 104.45 ditto 342.50
e) 8" (200 mm) i/d ditto 140.35 ditto 460.25
f) 10" (250 mm) i/d ditto 175.95 ditto 577.10
g) 12" (300 mm) i/d ditto 192.45 ditto 631.20
h) 15" (375 mm) i/d ditto 285.00 ditto 934.75
i) 18" (450 mm) i/d ditto 303.75 ditto 996.35

2 Boring for tubewell in all types of soil except shingle, ditto


gravel & rock, from a depth of 100.1 ft. to 200 ft.
(30 to 60 m) below ground level, including sinking and
withdrawing of casing pipe, complete:-

a) 5" (125 mm) i/d Per Rft. 116.45 Per Metre 381.90
b) 6" (150 mm) i/d of bore 163.25 of bore 535.45
c) 8" (200 mm) i/d ditto 189.15 ditto 620.50
d) 10" (250 mm) i/d ditto 215.20 ditto 705.90
e) 12" (300 mm) i/d ditto 239.50 ditto 785.55
f) 15" (375 mm) i/d ditto 334.10 ditto 1095.90
g) 18" (450 mm) i/d ditto 352.90 ditto 1157.45

3 Boring for tubewell in all types of soil except shingle, ditto


gravel & rock, from a depth of 200.1 ft. to 300 ft. (60
to 90 m) below ground level, including sinking and
withdrawing of casing pipe, complete:-
a) 5" (125 mm) i/d Per Rft. 162.05 Per Metre 531.50
b) 6" (150 mm) i/d of bore 208.85 of bore 685.05
c) 8" (200 mm) i/d ditto 238.00 ditto 780.70
d) 10" (250 mm) i/d ditto 266.75 ditto 874.95
e) 12" (300 mm) i/d ditto 283.85 ditto 931.00
f) 15" (375 mm) i/d ditto 366.85 ditto 1203.30
g) 18" (450 mm) i/d ditto 386.85 ditto 1268.80

chapter-23(Tubewell) Page 1
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

4 Boring for tubewell in all types of soil except shingle, Chap. 2


gravel & rock, from a depth of 300.1 ft. to 400 ft.
(90 to 120 m) below ground level, including sinking and
withdrawing of casing pipe, complete:-

a) 8" (200 mm) i/d Rft of bore 286.85 Per Metre 940.90
b) 10" (250 mm) i/d ditto 318.30 of bore 1044.05
c) 12" (300 mm) i/d ditto 337.80 ditto 1108.00
d) 15" (375 mm) i/d ditto 447.55 ditto 1467.95
e) 18" (450 mm) i/d ditto 451.75 ditto 1481.70

5 Direct Rotary/Reverse Rotary drilling of bore for tubewells, ditto


in all types of soil except shingle, gravel and rock:-

a) from ground level to 250 ft. (75 m) below ground level:-

Per Rft. Per Metre


i) 15" to 18" (375 to 450 mm) i/d of bore 265.35 of bore 870.35 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 381.60 ditto 1251.70 Above 2 cusec discharge

b) exceeding 250 ft. (75 m) depth below


ground level:-
Rft Per Metre
i) 15" to 18" (375 to 450 mm) i/d of bore 265.35 of bore 870.35 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 381.60 ditto 1251.70 Above 2 cusec discharge

6 Boring for tubewell in shingle, gravel and rock, including ditto Location and depth of shingle,
sinking and withdrawing of casing pipe:- gravel or rock is to be determined
from the bore log.
a) from ground level to 200 ft. (60 m) below ground level:-

Per Rft. Per Metre


i) 12" to 18" (300 to 450 mm) i/d of bore 598.45 of bore 1962.85 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 809.35 ditto 2654.75 Above 2 cusec discharge

b) exceeding 200 ft. (60 m) depth below


ground level:-
i) 12" to 18" (300 to 450 mm) i/d ditto 598.45 ditto 1962.85 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 809.35 ditto 2654.70 Above 2 cusec discharge

7 Providing strong substantially built box of deodar wood Job for 446.40 5136.00 Job for 446.40 5136.00 ditto
4'x2½'x9" (1200x750x225 mm), with compartments, lock compl- compl-
and locking arrangement, for preserving samples of strata ete bore ete bore
from bore hole.

chapter-23(Tubewell) Page 2
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

8 Furnishing sample of water from bore hole. Per Set 108.00 156.00 Per Set 108.00 156.00 Chap. 2
of 2 of 2
bottles bottles

9 Providing and installing, brass strainer in tubewell bore ditto Cost/labour of jointing both ends is
hole, including sockets, special sockets, studs, etc. included in the rate.
complete:-

a) 2" i/d, 5/32" (50 mm i/d 4 mm) thick Per Rft. 13.45 635.05 Per Metre 44.10 2083.00
b) 3" i/d, 5/32" (75 mm i/d 4 mm) thick Per Rft. 13.45 968.95 Per Metre 44.15 3178.15
c) 4" i/d, 3/16" (100 mm i/d 5 mm) thick Per Rft. 17.75 1109.75 Per Metre 58.20 3639.95
d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 20.00 1385.00 Per Metre 65.65 4542.85
e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 22.65 2017.65 Per Metre 74.20 6617.80
f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 26.30 2073.80 Per Metre 86.30 6802.10
g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 32.45 2709.95 Per Metre 106.40 8888.60
h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 32.45 2625.95 Per Metre 106.40 8613.10
i) 10" i/d, 3/16" (250 mm i/d 5 mm) thick Per Rft. 36.40 3186.40 Per Metre 119.35 10451.35
j) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 36.40 3858.40 Per Metre 119.35 12655.50
k) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 37.60 4080.10 Per Metre 123.30 13382.70
l) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 42.85 4410.85 Per Metre 140.55 14467.60
m) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 42.85 4752.10 Per Metre 140.55 15586.90
n) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 50.20 5237.20 Per Metre 164.70 17178.10
o) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 51.40 6057.40 Per Metre 168.65 19868.35

10 Providing and installing M.S. Bail plug in tubewell bore In the case of increase or decrease
hole: in the length of Bail plug, the rates
will be increased or decreased as
a) 2" i/d, 1.5 ft. (50 mm i/d 450 mm) long. Each 60.30 427.90 Each 60.30 427.90 per rates given in serial No. 14 of
b) 3" i/d, 1.5 ft. (75 mm i/d 450 mm) long. Each 60.30 583.55 Each 60.30 583.55 this chapter for the respective
c) 4" i/d, 2 ft. (100 mm i/d 600 mm) long. Each 100.70 1174.15 Each 100.70 1174.15 diameter.
d) 5" i/d, 2 ft. (125 mm i/d 600 mm) long. Each 100.70 1500.95 Each 100.70 1500.95
e) 6" i/d, 2 ft. (150 mm i/d 600 mm) long. Each 135.50 1895.75 Each 135.50 1895.75
f) 7" i/d, 2 ft. (175 mm i/d 600 mm) long. Each 135.50 2198.35 Each 135.50 2198.35
g) 8" i/d, 2 ft. (200 mm i/d 600 mm) long Each 167.50 2437.35 Each 167.50 2437.35
h) 9" i/d, 2 ft. (225 mm i/d 600 mm) long Each 167.50 2718.10 Each 167.50 2718.10
i) 10" i/d, 2 ft. (250 mm i/d 600 mm) long Each 167.50 3531.45 Each 167.50 3531.45
j) 12" i/d, 2 ft. (300 mm i/d 600 mm) long Each 201.05 4247.70 Each 201.05 4247.70
k) 15" i/d, 2 ft. (375 mm i/d 600 mm) long Each 201.05 5254.95 Each 201.05 5254.95
l) 18" i/d, 2 ft. (450 mm i/d 600 mm) long Each 241.30 5975.95 Each 241.30 5975.95
m) 20" i/d, 2 ft. (500 mm i/d 600 mm) long Each 262.70 6662.50 Each 262.70 6662.50
n) 22" i/d, 2 ft. (550 mm i/d 600 mm) long Each 262.70 7335.55 Each 262.70 7335.55

chapter-23(Tubewell) Page 3
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

11 Providing and installing, P.V.C. strainer B.S.S. Class 'B', Chap. 2


in tubewell bore hole, including sockets and solvents, etc.
complete:-

a) 3" i/d (75 mm) Per Rft. 9.90 85.40 Per Metre 32.55 280.10
b) 4" i/d (100 mm) Per Rft. 11.25 126.50 Per Metre 36.90 414.95
c) 5" i/d (125 mm) Per Rft. 11.90 168.95 Per Metre 38.95 554.20
d) 6" i/d (150 mm) Per Rft. 14.10 236.45 Per Metre 46.15 775.50
e) 8" i/d (200 mm) Per Rft. 19.50 640.70 Per Metre 64.05 2101.50
f) 10" i/d (250 mm) Per Rft. 19.95 892.05 Per Metre 65.40 2925.90
g) 12" i/d (300 mm) Per Rft. 19.95 1062.40 Per Metre 65.40 3484.60

12 Providing and installing P.V.C. strainer B.S.S. Class `D' ,


in tubewell bore hole, including sockets and solvent, etc.
complete:-

a) 1¼" i/d (30 mm) Per Rft. 6.45 34.00 Per Metre 21.10 111.45
b) 1½" i/d (40 mm) Per Rft. 6.70 42.40 Per Metre 21.90 139
c) 2" i/d (50 mm) Per Rft. 6.80 61.85 Per Metre 22.25 202.95
d) 3" i/d (75 mm) Per Rft. 9.90 126.30 Per Metre 32.55 414.35
e) 4" i/d (100 mm) Per Rft. 11.35 206.95 Per Metre 37.25 678.85
f) 5" i/d (125 mm) Per Rft. 12.20 303.80 Per Metre 40.05 996.5
g) 6" i/d (150 mm) Per Rft. 32.75 456.35 Per Metre 107.50 1496.9

13 Providing and installing P.V.C. Bail/End plug, in tubewell


bore hole:-

i) B.S.S. Class `B'

a) 3" i/d (75 mm) Each 5.05 53.05 Each 5.05 53.05
b) 4" i/d (100 mm) Each 5.75 71.75 Each 5.75 71.75
c) 5" i/d (125 mm) Each 6.40 109.60 Each 6.40 109.60
d) 6" i/d (150 mm) Each 7.95 157.95 Each 7.95 157.95
e) 8" i/d (200 mm) Each 9.85 309.85 Each 9.85 309.85
f) 10" i/d (250 mm) Each 10.35 437.55 Each 10.35 437.55
g) 12" i/d (300 mm) Each 11.95 587.95 Each 11.95 587.95
h) 14" i/d (350 mm) Each 11.95 619.15 Each 11.95 619.15

ii) B.S.S. Class `D'

a) 1¼" i/d (30 mm) Each 3.30 27.30 Each 3.30 27.30
b) 1½" i/d (40 mm) Each 3.60 39.60 Each 3.60 39.60
c) 2" i/d (50 mm) Each 3.75 57.75 Each 3.75 57.75
d) 3" i/d (75 mm) Each 5.00 77.00 Each 5.00 77.00

chapter-23(Tubewell) Page 4
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

e) 4" i/d (100 mm) Each 5.75 101.75 Each 5.75 101.75
f) 5" i/d (125 mm) Each 6.40 144.40 Each 6.40 144.40
g) 6" i/d (150 mm) Each 8 188 Each 8 188

14 Providing and installing M.S. blind pipe socketed/welded Chap.


joint, M.S. reducer (where necessary), in tubewell bore 2
hole, including jointing/welding with strainer, etc.
complete:-

a) 2" i/d, 1/8" (50 mm i/d 3 mm) thick Per Rft. 35.75 177.35 Per Metre 117.25 581.70
b) 3" i/d, 1/8" (75 mm i/d 3 mm) thick Per Rft. 35.75 245.75 Per Metre 117.25 806.05
c) 4" i/d, 1/8" (100 mm i/d 3 mm) thick Per Rft. 44.70 341.10 Per Metre 146.60 1118.80
d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 44.70 578.70 Per Metre 146.60 1898.15
e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 63.80 660.20 Per Metre 209.25 2165.45
f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 63.80 729.80 Per Metre 209.25 2393.75
g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 74.45 942.05 Per Metre 244.20 3089.90
h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 74.45 1154.45 Per Metre 244.20 3786.60
i) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 74.45 1394.45 Per Metre 244.20 4573.80
j) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 89.35 1734.55 Per Metre 293.05 5689.30
k) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 89.35 1967.35 Per Metre 293.05 6452.90
l) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 109.45 2509.45 Per Metre 359.00 8231.00
m) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 117.95 2757.95 Per Metre 386.90 9046.10
n) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 117.95 2877.95 Per Metre 386.90 9439.70

15 Providing and installing P.V.C. blind pipe, B.S.S. Class ditto


`B', in tubewell bore hole, including sockets and solvents
and jointing with strainer, etc. complete.

a) 3" i/d (75 mm) Per Rft. 12.95 88.45 Per Metre 42.50 290.10
b) 4" i/d (100 mm) Per Rft. 14.60 129.85 Per Metre 47.95 426.00
c) 5" i/d (125 mm) Per Rft. 15.25 172.35 Per Metre 50.00 565.25
d) 6" i/d (150 mm) Per Rft. 18.65 241.05 Per Metre 59.75 789.10
e) 8" i/d (200 mm) Per Rft. 24.90 367.65 Per Metre 81.75 1205.85
f) 10" i/d (250 mm) Per Rft. 25.90 647.10 Per Metre 84.95 2122.45
g) 12" i/d (300 mm) Per Rft. 30.75 902.85 Per Metre 100.95 2961.40
h) 14" i/d (350 mm) Per Rft. 28.35 1070.80 Per Metre 93.05 3512.25

16 Providing and installing P.V.C. blind pipe, B.S.S. Class


`D', in tubewell bore hole, including sockets and solvents
and jointing with strainer, etc. complete.
a) 1¼" i/d (30 mm) Per Rft. 7.90 35.40 Per Metre 25.85 116.15
b) 1½" i/d (40 mm) Per Rft. 8.10 43.80 Per Metre 26.60 143.70
c) 2" i/d (50 mm) Per Rft. 8.65 63.75 Per Metre 28.45 209.10
d) 3" i/d (75 mm) Per Rft. 11.20 127.60 Per Metre 36.80 418.55

chapter-23(Tubewell) Page 5
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

e) 4" i/d (100 mm) Per Rft. 14.75 210.35 Per Metre 48.40 689.95
f) 5" i/d (125 mm) Per Rft. 15.60 307.20 Per Metre 51.10 1007.55
g) 6" i/d (150 mm) Per Rft. 18.70 442.30 Per Metre 61.35 1450.75

17 Testing and developing of tubewell of size 6" (150 mm)


i/d and above continuously.

i) upto 1.5 cs. discharge Per 560.05 Per 560.05


Hour Hour
ii) above 1.5 cs. discharge ditto 674.40 ditto 674.40

18 Shrouding with graded pea gravel 3/8" to 1/8" (10 to 3 Per Cft. 14.90 42.20 cu.m 526.25 1490.50 The rate includes wastage, etc.
mm), around tubewell in bore hole.

19 Laying cutting, jointing, testing and disinfecting cast iron Chap. 1) Pipes to be supplied by
pipe line in trenches, with spigot and socket caulked lead 2 Government.
joints, including cost of materials, such as lead, yarn, etc. 2) Providing and installing specials
complete in all respects:- and valves is not included in the
rate, which is payable separately.

a) 3" (75 mm) i/d Per Rft. 33.85 Per Metre 110.95
b) 4" (100 mm) i/d Per Rft. 42.15 Per Metre 138.20
c) 5" (125 mm) i/d Per Rft. 52.50 Per Metre 172.25
d) 6" (150 mm) i/d Per Rft. 62.55 Per Metre 205.10
e) 8" (200 mm) i/d Per Rft. 77.20 Per Metre 253.20
f) 10" (250 mm) i/d Per Rft. 114.50 Per Metre 375.50
g) 12" (300 mm) i/d Per Rft. 134.05 Per Metre 439.70
h) 15" (375 mm) i/d Per Rft. 174.10 Per Metre 571.10
i) 18" (450 mm) i/d Per Rft. 230.90 Per Metre 757.40

20 Laying, cutting, jointing, testing and disinfecting cast iron ditto 1) Pipes to be supplied by
pipe line in trenches, with flanged and flanged joints, Government.
complete in all respects:- 2) Providing and installing specials
and valves is not included in the
a) 3" (75 mm) i/d Per Rft. 15.00 Per Metre 49.20 rate, which is payable separately.
b) 4" (100 mm) i/d Per Rft. 16.70 Per Metre 54.75
c) 5" (125 mm) i/d Per Rft. 25.65 Per Metre 84.15
d) 6" (150 mm) i/d Per Rft. 28.05 Per Metre 92.00
e) 8" (200 mm) i/d Per Rft. 32.90 Per Metre 107.95
f) 10" (250 mm) i/d Per Rft. 46.50 Per Metre 152.50
g) 12" (300 mm) i/d Per Rft. 54.00 Per Metre 177.15
h) 15" (375 mm) i/d Per Rft. 73.55 Per Metre 241.10
i) 18" (450 mm) i/d Per Rft. 90.90 Per Metre 298.10

chapter-23(Tubewell) Page 6
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

21 Laying, cutting, jointing, testing and disinfecting cast iron Chap. 2 1) Pipes to be supplied by
pipe line in trenches with Tyton joints, complete in all Government.
respects:- 2) Providing and installing specials
and valves is not included in the
a) 3" (75 mm) i/d Per Rft. 7.35 Per Metre 24.20 rate, which is payable separately.
b) 4" (100 mm) i/d Per Rft. 8.60 Per Metre 28.15
c) 5" (125 mm) i/d Per Rft. 11.00 Per Metre 36.10
d) 6" (150 mm) i/d Per Rft. 12.45 Per Metre 40.85
e) 8" (200 mm) i/d Per Rft. 16.85 Per Metre 55.35
f) 10" (250 mm) i/d Per Rft. 21.45 Per Metre 70.30
g) 12" (300 mm) i/d Per Rft. 25.75 Per Metre 84.40
h) 15" (375 mm) i/d Per Rft. 39.85 Per Metre 130.65
i) 18" (450 mm) i/d Per Rft. 47.80 Per Metre 156.75

22 Providing, laying, cutting, jointing, testing and disinfecting Chap. Cost of sockets, tees, elbows,
G.I. pipeline in trenches, with socket joints, using G.I. 2 bends, valves, crosses, unions and
pipes of B.S.S. 1387-1967 complete in all respects, with plugs, etc. is included in the rates.
specials and valves.

i) Light Quality

a) ½" i/d (15 mm) 2mm thick Per Rft. 4.20 45.20 Per Metre 13.80 148.30
b) ¾" i/d (20 mm) 2.35mm thick Per Rft. 4.70 63.25 Per Metre 15.45 207.50
c) 1" i/d (25 mm) 2.65mm thick Per Rft. 5.55 88.00 Per Metre 18.15 288.70
d) 1¼" i/d (32 mm) 2.65mm thick Per Rft. 5.25 110.85 Per Metre 17.20 363.55
e) 1½" i/d (40 mm) 2.9mm thick Per Rft. 5.75 139.35 Per Metre 18.90 457.00
f) 2" i/d (50 mm) 2.9mm thick Per Rft. 6.50 174.50 Per Metre 21.30 572.35
g) 2"½ i/d (65 mm) 3.25mm thick Per Rft. 6.85 237.05 Per Metre 22.50 777.55
h) 3" i/d (75 mm) 3.25mm thick Per Rft. 7.90 277.80 Per Metre 25.85 911.25
i) 4" i/d (100 mm) 3.65mm thick Per Rft. 8.80 396.80 Per Metre 28.80 1301.55

ii) Medium Quality i. Cost of sockets, tees, elbow, bends,


valves, crosses, unions and plugs etc is
a) ½" i/d (15 mm) 2.65mm thick Per Rft. 4.20 55.60 Per Metre 13.80 182.30 included in the rates except for internal
b) ¾" i/d (20 mm) 2.65mm thick Per Rft. 4.70 70.30 Per Metre 15.45 230.60 G.I piping (1"dia, 3/4"dia & 1/2"dia)
c) 1" i/d (25 mm) 3.25mm thick Per Rft. 5.55 103.60 Per Metre 18.15 339.90 for Bath rooms/ Levorotary.
d) 1¼" i/d (32 mm) 3.25mm thick Per Rft. 5.25 131.15 Per Metre 17.20 430.25
e) 1½" i/d (40 mm) 3.25mm thick Per Rft. 5.80 150.45 Per Metre 19.10 493.40 ii. For internal G.I piping (1"dia,
f) 2" i/d (50 mm) 3.65mm thick Per Rft. 6.50 205.40 Per Metre 21.30 673.75 3/4"dia & 1/2"dia) Bath room(s)/
g) 2"½ i/d (65 mm) 3.65mm thick Per Rft. 6.85 256.80 Per Metre 22.50 842.30 Levorotary of rate (composite) shall be
h) 3" i/d (75 mm) 4.05mm thick Per Rft. 7.90 329.95 Per Metre 25.85 1082.15 reduced by 8% and specials mentioned
i) 4" i/d (100 mm) 4.5mm thick Per Rft. 8.80 480.05 Per Metre 28.80 1574.60 above may be paid at the rates placed on
j) 5" i/d (150 mm) 4.85mm thick Per Rft. 10.10 652.25 Per Metre 33.15 2139.40 Website as per actual quantity used.
k) 6" i/d (200 mm) 4.85mm thick Per Rft. 10.40 769.20 Per Metre 34.15 2522.95

chapter-23(Tubewell) Page 7
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iii) Heavy Quality

a) ½" i/d (15 mm) 3.25mm thick Per Rft. 4.20 78.80 Per Metre 13.80 258.4
b) ¾" i/d (20 mm) 3.25mm thick Per Rft. 4.70 101.00 Per Metre 15.45 331.2
c) 1" i/d (25 mm) 4.05mm thick Per Rft. 5.55 157.40 Per Metre 18.15 516.3
d) 1¼" i/d (32 mm) 4.05mm thick Per Rft. 5.25 203.20 Per Metre 17.20 666.55
e) 1½" i/d (40 mm) 4.05mm thick Per Rft. 5.80 233.65 Per Metre 19.10 766.3
f) 2" i/d (50 mm) 4.5mm thick Per Rft. 6.50 326.50 Per Metre 21.30 1070.95
g) 2"½ i/d (65 mm) 4.5mm thick Per Rft. 6.85 416.35 Per Metre 22.50 1365.7
h) 3" i/d (75 mm) 4.85mm thick Per Rft. 7.90 543.50 Per Metre 25.85 1782.7
i) 4" i/d (100 mm) 5.4mm thick Per Rft. 8.80 769.50 Per Metre 28.80 2523.95
j) 5" i/d (125 mm) 5.4mm thick Per Rft. 10.10 948.45 Per Metre 33.15 3110.95
k) 6" i/d (150 mm) 5.4mm thick Per Rft. 10.40 1125.05 Per Metre 34.15 3690.15

23 Providing, laying, cutting, jointing, testing and disinfecting


Asbestos cement/Fibre Cement pipe line in trenches, with PS 428 & Providing and installing specials
comet joint and rubber ring, complete in all respects:- ISO 160 and valves is not included in the
rate, which is payable separately.
B Class WOrking Pressure

a) 3" i/d (75 mm) Per Rft. 7.05 74.00 Per Metre 23.20 242.65
b) 4" i/d (100 mm) Per Rft. 7.50 93.45 Per Metre 24.60 306.50
c) 6" i/d (150 mm) Per Rft. 10.30 156.25 Per Metre 33.70 512.50
d) 8" i/d (200 mm) Per Rft. 14.20 270.50 Per Metre 46.55 887.30
e) 10" i/d (250 mm) Per Rft. 18.35 394.25 Per Metre 60.15 1293.20
f) 12" i/d (300 mm) Per Rft. 23.30 527.85 Per Metre 76.45 1731.40
g) 14" i/d (350 mm) Per Rft. 26.70 670.15 Per Metre 87.65 2198.15
h) 16" i/d (400 mm) Per Rft. 30.05 945.40 Per Metre 98.60 3100.90
i) 18" i/d (450 mm) Per Rft. 35.40 1201.20 Per Metre 116.05 3939.95
j) 20" i/d (500 mm) Per Rft. 41.55 1435.40 Per Metre 136.30 4708.15
k) 24" i/d (600 mm) Per Rft. 48.90 1957.75 Per Metre 160.30 6421.45
24 C Class Working Pressure PS 428 &
a) 3" i/d (75 mm) Per Rft. 7.05 74.00 Per Metre 23.20 242.65 ISO 160
b) 4" i/d (100 mm) Per Rft. 7.50 97.70 Per Metre 24.60 320.45
c) 6" i/d (150 mm) Per Rft. 10.30 180.45 Per Metre 33.70 591.85
d) 8" i/d (200 mm) Per Rft. 14.20 288.50 Per Metre 46.55 946.30
e) 10" i/d (250 mm) Per Rft. 18.35 434.35 Per Metre 60.15 1424.65
f) 12" i/d (300 mm) Per Rft. 23.30 610.65 Per Metre 76.45 2002.90
g) 14" i/d (350 mm) Per Rft. 26.70 905.95 Per Metre 87.65 2971.50
h) 16" i/d (400 mm) Per Rft. 30.05 1309.25 Per Metre 98.60 4294.30
i) 18" i/d (450 mm) Per Rft. 35.40 1683.70 Per Metre 116.05 5522.55
j) 20" i/d (500 mm) Per Rft. 41.55 2023.55 Per Metre 136.30 6637.20
k) 24" i/d (600 mm) Per Rft. 49.60 2789.20 Per Metre 162.75 9148.50

chapter-23(Tubewell) Page 8
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

25 D Class Working Pressure PS 428 &


a) 3" i/d (75 mm) Per Rft. 7.05 74.00 Per Metre 23.20 242.65 ISO 160
b) 4" i/d (100 mm) Per Rft. 7.50 110.85 Per Metre 24.60 363.55
c) 6" i/d (150 mm) Per Rft. 10.30 220.80 Per Metre 33.70 724.30
d) 8" i/d (200 mm) Per Rft. 14.20 395.45 Per Metre 46.55 1297.10
e) 10" i/d (250 mm) Per Rft. 18.35 617.95 Per Metre 60.15 2026.85
f) 12" i/d (300 mm) Per Rft. 23.30 892.10 Per Metre 76.45 2926.05
g) 14" i/d (350 mm) Per Rft. 26.70 1293.80 Per Metre 87.65 4243.70
h) 16" i/d (400 mm) Per Rft. 30.05 1869.00 Per Metre 98.60 6130.30
i) 18" i/d (450 mm) Per Rft. 35.40 2390.85 Per Metre 116.05 7842.05
j) 20" i/d (500 mm) Per Rft. 41.55 2919.90 Per Metre 136.30 9577.25
k) 24" i/d (600 mm)

26 Providing, laying, cutting, jointing, testing and disinfecting Chap Providing and installing specials
P.V.C. pipe line of B.S.S. with `B' Class working pressure 2 and valves is not included in the
pipe, in trenches, complete in all respects:- rate, which is payable separately.

a) 3" i/d (75 mm) Per Rft. 2.40 79.40 Per Metre 7.85 260.35
b) 4" i/d (100 mm) Per Rft. 3.00 120.55 Per Metre 9.75 395.40
c) 5" i/d (125 mm) Per Rft. 3.70 163.90 Per Metre 12.05 537.60
d) 6" i/d (150 mm) Per Rft. 4.00 230.80 Per Metre 13.05 757.00
e) 8" i/d (200 mm) Per Rft. 5.60 355.20 Per Metre 18.40 1165.00
f) 10" i/d (250 mm) Per Rft. 7.20 640.85 Per Metre 23.70 2101.90
h) 12" i/d (300 mm) Per Rft. 8.90 898.45 Per Metre 29.20 2946.90
g) 14" i/d (350 mm) Per Rft. 11.25 1074.55 Per Metre 37.00 3524.55

27 Providing, laying, cutting, jointing, testing and disinfecting ditto Providing and installing specials
pipe line in trenches with P.V.C. pipes of B.S.S. with `D' and valves is not included in the
Class working pressure complete in all respects:- rate, which is payable separately.
a) 2" i/d (50 mm) Per Rft. 2.00 58.15 Per Metre 6.55 190.80
b) 3" i/d (75 mm) Per Rft. 2.40 121.10 Per Metre 7.85 397.25
c) 4" i/d (100 mm) Per Rft. 3.00 202.50 Per Metre 9.75 664.15
d) 5" i/d (125 mm) Per Rft. 3.70 301.10 Per Metre 12.05 987.65
e) 6" i/d (150 mm) Per Rft. 4.00 436.05 Per Metre 13.05 1430.25

28 Providing and fixing cast iron special of B.S.S. Class `B' 9.1 i) Labour rates include the cost of
(such as bend, tee cross collar, reducer, tail piece, jointing material & labour.
flanged spigot, cap, flanged socket, taper, angle branch,
plug etc.) for cast iron pipe line , complete:- ii) The internal dia of the pipe, from
which the branch is taken out wil
a) C.I.S.S. Specials, with spigot. and be considered the internal dia for
socket joint:- the purpose of payments of
i) 3" to 6" (75 to 150 mm) i/d Per Kg. 14.85 57.40 Per Kg 14.85 57.40 specials.
ii) 8" to 12" (200 to 300 mm) i/d Per Kg. 8.30 50.85 Per Kg 8.30 50.85
iii) 15" to 18" (375 to 450 mm) i/d Per Kg. 4.90 47.45 Per Kg 4.90 47.45

chapter-23(Tubewell) Page 9
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) C.I. flanged specials, with flanged and


flanged joints:-

i) 3" to 6" (75 to 150 mm) i/d Per Kg 6.75 49.30 Per Kg 6.75 49.30
ii) 8" to 12" (200 to 300 mm) i/d Per Kg 2.25 44.75 Per Kg 2.25 44.75
iii) 15" to 18" (375 to 450 mm) i/d Per Kg 3.00 44.75 Per Kg 3.00 44.75

c) C.I. Specials, with tyton joints:-

i) 3" to 6" (75 to 150 mm) i/d Per Kg 7.25 49.75 Per Kg 7.25 49.75
ii) 8" to 12" (200 to 300 mm) i/d Per Kg 7.25 49.75 Per Kg 7.25 49.75
iii) 15" to 18" (375 to 450 mm) i/d Per Kg 7.25 49.75 Per Kg 7.25 49.75

29 Providing and fixing cast iron specials of B.S.S. Class 'B' 9.1 1) Labour rates include the cost of
(such as bend, tee, cross collar, reducer, tail piece, jointing material and labour.
flanged socket, flanged spigot, cap, taper, angle branch,
plug, etc) for Asbestos cement pipe line, with comet joint 2) The internal dia of the pipe, from
and rubber ring, complete. which the branch is taken out, will
i) 3" to 6" (75 to 150 mm) i/d Per Kg 10.50 53.00 Per Kg 10.50 53.00 be considered the internal dia for
ii) 8" to 18" (200 to 450 mm) i/d Per Kg 5.55 48.05 Per Kg 5.55 48.05 the purpose of payment.
iii) 20" to 24" (500 to 600 mm) i/d Per Kg 4.40 46.95 Per Kg 4.40 46.95

30 Providing and fixing sluice valve of B.S.S. quality and 9.1 Labour rates include cost of jointing
weight, Class `B', for cast iron pipe line, and Asbestos material and labour.
cement pipe line (including cost of jointing material):-
a) 3" i/d (75 mm) Each 394.95 4594.95 Each 394.95 4594.95
b) 4" i/d (100 mm) Each 429.80 5829.80 Each 429.80 5829.80
c) 5" i/d (125 mm) Each 773.65 8213.65 Each 773.65 8213.65
d) 6" i/d (150 mm) Each 824.75 9224.75 Each 824.75 9224.75
e) 8" i/d (200 mm) Each 962.95 15362.95 Each 962.95 15362.95
f) 10" i/d (250 mm) Each 1619.40 20819.40 Each 1619.40 20819.40
g) 12" i/d (300 mm) Each 1819.80 25819.80 Each 1819.80 25819.80
h) 16" i/d (400 mm) Each 2413.60 44413.60 Each 2413.60 44413.60
i) 18" i/d (450 mm) Each 2777.95 86777.95 Each 2777.95 86777.95
31 Providing and fixing, sluice valve of B.S.S. quality and Labour rates include cost of jointing
weight, for Asbestos cement pipe line, with comet joint 9.1 material and labour.
and rubber ring, complete (including cost of jointing
materials):-
a) 3" i/d (75 mm) Each 324.45 4524.45 Each 324.45 4524.45
b) 4" i/d (100 mm) Each 401.90 5801.90 Each 401.90 5801.90
c) 6" i/d (150 mm) Each 512.25 8912.25 Each 512.25 8912.25
d) 8" i/d (200 mm) Each 856.95 15256.95 Each 856.95 15256.95
e) 10" i/d (250 mm) Each 1095.85 20295.85 Each 1095.85 20295.85

chapter-23(Tubewell) Page 10
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

f) 12" i/d (300 mm) Each 1262.85 25262.85 Each 1262.85 25262.85
g) 16" i/d (400 mm) Each 1498.60 43498.60 Each 1498.60 43498.60
h) 18" i/d (450 mm) Each 1815.15 85815.15 Each 1815.15 85815.15

32 Providing and fixing, fire hydrants B.S.S. quality and Each 49.95 1969.95 Each 49.95 1969.95 9.1 1) Labour rates include cost of
weight of 2½" (65 mm) dia (including cost of jointing jointing material and labour.
material).
2) Connecting pipes and specials,
if used, will be paid extra.

33 Providing and fixing, air valve 2½ (65mm) dia of B.S.S. ditto


quality and weight (complete with jointing material).

a) single Each 100.90 3400.90 Each 100.90 3400.90

b) double Each 100.90 6100.90 Each 100.90 6100.90

34 Providing and fitting C.I. flanges on pipes, including


turning, threading, facing and fitting, etc. complete in all ditto
respects:-

a) 3" to 6" (75 to 150 mm) i/d Per Kg 17.30 50.75 Per Kg 17.30 50.75

b) 8" to 12" (200 to 300 mm) i/d Per Kg 11.25 44.70 Per Kg 11.25 44.70

c) 15" to 18" (375 to 450 mm) i/d Per Kg 9.20 42.65 Per Kg 9.20 42.65

35 Cutting C.I. pipe, and welding spigot or socket, flanged or


tyton end, after finishing ends of pipes:
Per Inch Per cm i/d
a) 3" to 6" (75 to 150 mm) i/d i/d of pipe 37.55 of pipe 15.05
b) 8" to 12" (200 to 300 mm) i/d ditto 45.95 ditto 18.40
c) 15" to 18" (375 to 450 mm) i/d ditto 42.60 ditto 17.05

36 Providing, laying, cutting, jointing, testing and disinfecting Cost of sockets, tees, elbows,
G.I. pipe line in trenches, with flanged joints, using G.I. bends, valves, crosses, unions and
pipe of B.S.S. 1387-1967 complete in all respects, plugs, etc. is included in the rates.
including specials and valves:-

i) G.I. flanged joints (Heavy Quality)


a) 1½" i/d (40 mm) Per Rft. 7.95 235.75 Per Metre 26.05 773.30
b) 2" i/d (50 mm) Per Rft. 7.95 327.95 Per Metre 26.05 1075.75
c) 2½" i/d (65 mm) Per Rft. 8.40 417.90 Per Metre 27.55 1370.75
d) 3" i/d (75 mm) Per Rft. 8.50 544.10 Per Metre 27.80 1784.65

chapter-23(Tubewell) Page 11
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

e) 4" i/d (100 mm) Per Rft. 10.00 770.75 Per Metre 32.85 2528.00
f) 6" i/d (150 mm) Per Rft. 11.50 949.85 Per Metre 37.70 3115.50
g) 8" i/d (200 mm) Per Rft. 11.55 1126.15 Per Metre 37.85 3693.80

ii) C.I. flanged joints (Medium Quality)

a) 1½" i/d (40 mm) Per Rft. 9.10 170.35 Per Metre 29.80 558.70
b) 2" i/d (50 mm) Per Rft. 8.45 230.25 Per Metre 27.75 755.25
c) 2½" i/d (65 mm) Per Rft. 9.50 288.20 Per Metre 31.20 945.30
d) 3" i/d (75 mm) Per Rft. 9.60 368.65 Per Metre 31.45 1209.25
e) 4" i/d (100 mm) Per Rft. 11.20 536.70 Per Metre 36.80 1760.45
f) 6" i/d (150 mm) Per Rft. 12.80 728.80 Per Metre 41.95 2390.50
g) 8" i/d (200 mm) Per Rft. 12.90 858.95 Per Metre 42.25 2817.35

37 Providing and installing P.V.C. bends, of B.S.S.

i) Class `B' working pressure:-


a) 3" i/d (75 mm) Each 63.50 176.30 Each 63.50 176.30
b) 4" i/d (100 mm) Each 75.00 316.20 Each 75.00 316.20
c) 5" i/d (125 mm) Each 93.80 563.00 Each 93.80 563.00
d) 6" i/d (150 mm) Each 97.50 789.90 Each 97.50 789.90

ii) Class `D' working pressure:-


a) 1¼" i/d (30 mm) Each 39.40 69.40 Each 39.40 69.40
b) 1½" i/d (40 mm) Each 43.30 75.70 Each 43.30 75.70
c) 2" i/d (50 mm) Each 47.70 111.30 Each 47.70 111.30
d) 3" i/d (75 mm) Each 63.50 231.50 Each 63.50 231.50
e) 4" i/d (100 mm) Each 75.00 469.80 Each 75.00 469.80
f) 5" i/d (125 mm) Each 93.80 1005.80 Each 93.80 1005.80
g) 6" i/d (150 mm) Each 97.50 1377.90 Each 97.50 1377.90

38 Providing and installing P.V.C. tees, of B.S.S.

i) Class `B' working pressure:-

a) 3" i/d (80 mm) Each 95.25 511.65 Each 95.25 511.65
b) 4" i/d (100 mm) Each 114.25 957.85 Each 114.25 957.85
c) 5" i/d (125 mm) Each 138.15 1826.55 Each 138.15 1826.55
d) 6" i/d (150 mm) Each 146.20 1886.20 Each 146.20 1886.20

ii) Class `D' working pressure:-


a) 1¼" i/d (30 mm) Each 60.50 175.70 Each 60.50 175.70
b) 1½" i/d (40 mm) Each 65.20 206.80 Each 65.20 206.80
c) 2" i/d (50 mm) Each 71.15 259.55 Each 71.15 259.55

chapter-23(Tubewell) Page 12
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

d) 3" i/d (75 mm) Each 95.25 511.65 Each 95.25 511.65
e) 4" i/d (100 mm) Each 114.25 957.85 Each 114.25 957.85
f) 5" i/d (125 mm) Each 138.15 1826.55 Each 138.15 1826.55
g) 6" i/d (150 mm) Each 146.20 1886.20 Each 146.20 1886.20

39 Providing and installing P.V.C. sockets, B.S.S.

i) Class `B' working pressure:-

a) 3" i/d (75 mm) Each 48.20 99.80 Each 48.20 99.80
b) 4" i/d (100 mm) Each 59.70 152.10 Each 59.70 152.10
c) 5" i/d (125 mm) Each 74.65 192.25 Each 74.65 192.25
d) 6" i/d (150 mm) Each 78.35 252.35 Each 78.35 252.35
e) 8" i/d (200 mm) Each 114.30 522.30 Each 114.30 522.30
f) 10" i/d (250 mm) Each 136.50 1289.70 Each 136.50 1289.70
g) 12" i/d (300 mm) Each 157.50 2983.50 Each 157.50 2983.50
h) 14" i/d (350 mm) Each 178.60 3058.60 Each 178.60 3058.60

ii) Class `D' working pressure:-


a) 1¼" i/d (30 mm) Each 26.65 41.05 Each 26.65 41.05
b) 1½" i/d (40 mm) Each 30.50 49.70 Each 30.50 49.70
c) 2" i/d (50 mm) Each 34.95 66.15 Each 34.95 66.15
d) 3" i/d (75 mm) Each 48.20 152.60 Each 48.20 152.60
e) 4" i/d (100 mm) Each 59.70 243.30 Each 59.70 243.30
f) 5" i/d (125 mm) Each 74.65 407.05 Each 74.65 407.05
g) 6" i/d (150 mm) Each 78.35 665.15 Each 78.35 665.15

40 Providing and installing P.V.C. Tapered core, B.S.S.

i) Class `B' working pressure:-

a) 3" i/d (75 mm) Each 63.50 99.50 Each 63.50 99.50
b) 4" i/d (100 mm) Each 75.00 123.00 Each 75.00 123.00
c) 5" i/d (125 mm) Each 65.00 125.00 Each 65.00 125.00
d) 6" i/d (150 mm) Each 97.50 169.50 Each 97.50 169.50
e) 8" i/d (200 mm) Each 139.85 259.85 Each 139.85 259.85
f) 10" i/d (250 mm) Each 162.05 318.05 Each 162.05 318.05
g) 12" i/d (300 mm) Each 188.10 380.10 Each 188.10 380.10
h) 14" i/d (350 mm) Each 209.25 449.25 Each 209.25 449.25

ii) Class `D' working pressure:-


a) 1¼" i/d (30 mm) Each 39.40 57.40 Each 39.40 57.40
b) 1½" i/d (40 mm) Each 43.30 67.30 Each 43.30 67.30
c) 2" i/d (50 mm) Each 47.70 77.70 Each 47.70 77.70

chapter-23(Tubewell) Page 13
MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

41 Making connection for new watersupply lines with the The rate includes the component of
running main, including excavation of trench and refilling, bailing out water from the trench
complete, but excluding cost of pipe and specials, etc. and cutting of existing pipe line.

Diameter of running main:


Per Per
i) upto 6" i/d (150 mm) Connection 775.50 Connection 775.50
ii) upto 8" i/d (200 mm) ditto 973.50 ditto 973.50
iii) upto 10" i/d (250 mm) ction 1267.20 ction 1267.20
iv) upto 12" i/d (300 mm) ditto 1762.20 ditto 1762.20
v) upto 16" i/d (400 mm) ditto 2140.05 ditto 2140.05
vi) upto 20" i/d (500 mm) ditto 2808.30 ditto 2808.30
vii) upto 24" i/d (600 mm) ditto 3359.40 ditto 3359.40

chapter-23(Tubewell) Page 14
ELECTRIC INSTALLATION
Rates for all finished works include the removal of surplus debris, unused material and byproducts.

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Supply and erection of G.I. pipes for wiring purposes, including


pull boxes, inspection boxes, bends, tees, etc. complete with
all specials.

a) on surface, including clamps, etc. 38.4

i) 15 mm i/d Per Rft. 9.90 48.15 Per Metre 32.45 157.90


ii) 20 mm i/d Per Rft. 9.90 60.90 Per Metre 32.45 199.75
iii) 25 mm i/d Per Rft. 9.90 80.20 Per Metre 32.45 262.95
iv) 32 mm i/d Per Rft. 12.05 101.10 Per Metre 39.45 331.65
v) 40 mm i/d Per Rft. 12.05 125.20 Per Metre 39.45 410.60
vi) 50 mm i/d Per Rft. 14.35 155.00 Per Metre 47.00 508.45
vii) 80 mm i/d Per Rft. 18.25 245.70 Per Metre 59.80 805.85

b) recessed in walls, including hooks, cutting jharries and


repairing surface: 38.3

i) 15 mm i/d Per Rft. 14.15 51.75 Per Metre 46.45 169.65


ii) 20 mm i/d Per Rft. 14.15 65.50 Per Metre 46.45 214.75
iii) 25 mm i/d Per Rft. 14.75 85.60 Per Metre 48.40 280.70
iv) 32 mm i/d Per Rft. 14.75 104.75 Per Metre 48.40 343.60
v) 40 mm i/d Per Rft. 16.10 129.95 Per Metre 52.80 426.25
vi) 50 mm i/d Per Rft. 22.15 163.50 Per Metre 72.60 536.35
vii) 80 mm i/d Per Rft. 35.40 264.40 Per Metre 116.15 867.20

2 Supply and erection of M.S. conduit pipes for wiring, including 38.4 & 38.6
pull boxes, inspection boxes, bends, tees, etc. complete with
all specials.

a) on surface, including clamps, etc.

i) 16 mm i/d Per Rft. 6.90 23.90 Per Metre 22.55 78.35


ii) 20 mm i/d Per Rft. 6.90 28.75 Per Metre 22.55 94.35
iii) 25 mm i/d Per Rft. 6.90 35.00 Per Metre 22.55 114.80
iv) 32 mm i/d Per Rft. 6.90 38.40 Per Metre 22.55 125.95
v) 40 mm i/d Per Rft. 7.75 49.55 Per Metre 25.35 162.55
vi) 50 mm i/d Per Rft. 9.50 60.85 Per Metre 31.20 199.60

chapter-24(Electric Installation) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) recessed in walls, including cutting jharries, cost of 38.3 &


hooks and repairing surface etc. 38.7

i) 16 mm i/d Per Rft. 12.65 31.45 Per Metre 41.50 103.15


ii) 20 mm i/d Per Rft. 12.65 36.05 Per Metre 41.50 118.25
iii) 25 mm i/d Per Rft. 14.15 43.35 Per Metre 46.45 142.20
iv) 32 mm i/d Per Rft. 14.75 47.80 Per Metre 48.40 156.80
v) 40 mm i/d Per Rft. 15.40 57.90 Per Metre 50.50 189.90
vi) 50 mm i/d Per Rft. 16.10 69.85 Per Metre 52.80 229.15

3 Supply and erection of PVC pipe for wiring recessed in walls, 38.3 &
including inspection boxes, pull boxes, hooks, cutting jharries, 38.5
and repairing surface, etc., complete with all specials.

i) 12 mm i/d Per Rft. 11.40 19.25 Per Metre 37.45 63.15


ii) 20 mm i/d Per Rft. 11.80 21.75 Per Metre 38.70 71.30
iii) 25 mm i/d Per Rft. 13.10 26.30 Per Metre 43.00 86.30
iv) 32 mm i/d Per Rft. 14.15 31.25 Per Metre 46.45 102.45
v) 40 mm i/d Per Rft. 14.75 37.65 Per Metre 48.40 123.50
vi) 50 mm i/d Per Rft. 15.40 46.40 Per Metre 50.50 152.25

4 Supply and erection of PVC pipe for wiring on surface


including clamps inspection boxes, pull boxes, bends, tees,
repairing surface, etc., complete with all specials:-

i) 12 mm i/d Per Rft. 3.10 10.55 Per Metre 10.15 34.55


ii) 20 mm i/d Per Rft. 3.10 12.50 Per Metre 10.15 41.00
iii) 25 mm i/d Per Rft. 3.10 16.45 Per Metre 10.15 54.00
iv) 32 mm i/d Per Rft. 3.55 21.20 Per Metre 11.60 69.45
v) 40 mm i/d Per Rft. 3.55 27.95 Per Metre 11.60 91.60
vi) 50 mm i/d Per Rft. 4.25 39.95 Per Metre 14.00 131.00

5 Supply and erection of G.I. flexible pipe for wiring, including 38.4
welding of sockets, nipples and check nuts, etc. complete:-

i) 12 mm i/d Per Rft. 8.15 34.50 Per Metre 26.75 113.15


ii) 20 mm i/d Per Rft. 8.70 43.10 Per Metre 28.50 141.30
iii) 25 mm i/d Per Rft. 9.00 57.30 Per Metre 29.50 187.90
iv) 32 mm i/d Per Rft. 10.85 76.00 Per Metre 35.65 249.25
v) 40 mm i/d Per Rft. 11.85 93.80 Per Metre 38.90 307.70
vi) 50 mm i/d Per Rft. 13.05 129.00 Per Metre 42.75 423.15
vii) 80 mm i/d Per Rft. 17.40 285.20 Per Metre 57.00 935.40

chapter-24(Electric Installation) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

6 Supply and erection PVC pipe for recessed wiring (main and 38.2 &
sub-main) purpose, including bends, specials, etc. in floor, 38.3
wall or trenches:-

i) 50 mm i/d Per Rft. 15.40 47.90 Per Metre 50.50 157.05


ii) 80 mm i/d Per Rft. 17.70 60.90 Per Metre 58.10 199.70
iii) 100 mm i/d Per Rft. 17.70 78.85 Per Metre 58.10 258.65

7 Supply and erection of PVC pipe for surface wiring (main and
sub-main) including clamps, inspection boxes, pull boxes
bends etc., complete with all specials:-

i) 50 mm i/d Per Rft. 4.25 36.30 Per Metre 14.00 119.05


ii) 80 mm i/d Per Rft. 6.20 61.55 Per Metre 20.30 201.85
iii) 100 mm i/d Per Rft. 7.05 75.25 Per Metre 23.20 246.90

8 Supply and erection of wooden strip batten for wiring Per Rft. 1.25 2.80 Per Metre 4.05 9.20 38.8 Additional width required to
purposes, including clips, insulation cleats, etc. accommodate wires will be provided
by erection of additional strips.

9 Supply and erection of Sahl wood casing and capping for Per Rft. 1.25 10.80 Per Metre 4.05 35.35 38.8
wiring purposes, including insulation cleats, screws, etc.
complete.

10 Supply and erection of single core PVC insulated copper 38.1


conductor cables, in prelaid PVC pipe/M.S. conduit/G.I
pipe/wooden strip batten/wooden casing an capping/G.I.
wire/trenches (rate for cables only):-

a) 250/440 volts, PVC insulated:

i) 3/0.74 mm (3/0.029") Per Rft. 2.50 6.60 Per Metre 8.10 21.70
ii) 3/0.91 mm (3/0.036") Per Rft. 2.50 8.50 Per Metre 8.10 27.90
iii) 7/0.74 mm (7/0.029") Per Rft. 2.50 11.50 Per Metre 8.10 37.80
iv) 7/0.91 mm (7/0.036") Per Rft. 2.75 16.70 Per Metre 9.00 54.75
v) 7/1.12 mm (7/0.044") Per Rft. 3.10 23.45 Per Metre 10.15 76.90
vi) 7/1.63 mm (7/0.064") Per Rft. 3.80 46.00 Per Metre 12.50 150.90
vii) 19/1.32 mm (19/0.052") Per Rft. 8.60 84.35 Per Metre 28.20 276.65
viii) 19/1.63 mm (19/0.064") Per Rft. 10.05 114.50 Per Metre 32.90 375.60

chapter-24(Electric Installation) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) 250/440 volts, PVC insulated cotton braided and


compounded cables:-

i) 3/0.74 mm (3/0.029") Per Rft. 2.75 5.95 Per Metre 9.00 19.55
ii) 3/0.91 mm (3/0.036") Per Rft. 2.75 6.25 Per Metre 9.00 20.45
iii) 7/0.74 mm (7/0.029") Per Rft. 2.75 7.65 Per Metre 9.00 25.10
iv) 7/0.91 mm (7/0.036") Per Rft. 2.90 9.30 Per Metre 9.55 30.55
v) 7/1.12 mm (7/0.044") Per Rft. 3.25 11.90 Per Metre 10.70 39.10
vi) 7/1.63 mm (7/0.064") Per Rft. 3.75 24.50 Per Metre 12.30 80.30

11 Supply and erection of single core PVC insulated, PVC


sheathed copper conductor, 250/440 volts grade cable
(BSS-2004), in prelaid PVC pipes/M.S. conduit/G.I.
pipe/wooden strip batten/wooden casing and
capping/trenches, etc. (rate for cable only):-

i) 3/0.74 mm (3/0.029") Per Rft. 2.50 7.95 Per Metre 8.10 26.05
ii) 3/0.91 mm (3/0.036") Per Rft. 2.50 10.75 Per Metre 8.10 35.30
iii) 7/0.74 mm (7/0.029") Per Rft. 2.50 14.15 Per Metre 8.10 46.45
iv) 7/0.91 mm (7/0.036") Per Rft. 2.75 21.05 Per Metre 9.00 68.95
v) 7/1.12 mm (7/0.044") Per Rft. 3.10 28.70 Per Metre 10.15 94.20
vi) 7/1.63 mm (7/0.064") Per Rft. 3.80 58.45 Per Metre 12.50 191.70

12 Supply and erection of single core PVC insulated, PVC


sheathed copper conductor, 660/1100 volts grade cable, in 38.1 to
prelaid G.I. pipe/M.S. conduits/PVC pipe/G.I. wire/trenches, 38.7
etc (rate for cable only):-
i) 7/1.63 mm (7/0.064") Per Rft. 3.75 63.45 Per Metre 12.30 208.15
ii) 19/1.32 mm (19/0.052") Per Rft. 4.15 69.05 Per Metre 13.55 226.50
iii) 19/1.63 mm (19/0.064") Per Rft. 4.50 93.30 Per Metre 14.75 306.05
iv) 19/2.11 mm (19/0.083") Per Rft. 4.95 178.10 Per Metre 16.25 584.15
v) 37//1.83 mm (37/0.072") Per Rft. 8.55 246.60 Per Metre 28.00 808.90
vi) 37/2.11 mm (37/0.083") Per Rft. 10.30 309.20 Per Metre 33.85 1,014.25
vii) 37/2.62 mm (37/0.103") Per Rft. 14.55 474.30 Per Metre 47.75 1,555.70

13 Supply and erection of copper conductor cables for service ditto


connection, in prelaid pipe/G.I. wire/trenches, etc. (rate for
cable only):-
a) PVC insulated, PVC sheathed twin core, 250/440 volts.
i) 3/0.74 mm (3/0.029") Per Rft. 2.75 7.30 Per Metre 9.00 24.00
ii) 3/0.91 mm (3/0.036") Per Rft. 2.75 20.10 Per Metre 9.00 65.90
iii) 7/0.74 mm (7/0.029") Per Rft. 2.75 27.25 Per Metre 9.00 89.35

chapter-24(Electric Installation) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) 7/0.91 mm (7/0.036") Per Rft. 2.90 39.85 Per Metre 9.55 130.70
v) 7/1.12 mm (7/0.044") Per Rft. 3.25 57.50 Per Metre 10.70 188.65
vi) 7/1.63 mm (7/0.064") Per Rft. 3.75 103.75 Per Metre 12.30 340.35

b) PVC insulated, PVC sheathed 3 core,


660/1100 volt cable:-

i) 3/0.74 mm (3/0.029") Per Rft. 2.90 21.40 Per Metre 9.55 70.10
ii) 3/0.91 mm (3/0.036") Per Rft. 2.90 30.80 Per Metre 9.55 101.00
iii) 7/0.74 mm (7/0.029") Per Rft. 2.90 41.75 Per Metre 9.55 136.85
iv) 7/0.91 mm (7/0.036") Per Rft. 3.25 55.15 Per Metre 10.70 180.80
v) 7/1.12 mm (7/0.044") Per Rft. 3.45 81.45 Per Metre 11.30 267.10
vi) 7/1.63 mm (7/0.064") Per Rft. 3.95 162.55 Per Metre 12.90 533.10

c) PVC insulated, PVC sheathed 4 core,


660/1100 volt non armoured cable:-

i) 3/0.74 mm (3/0.029") Per Rft. 3.10 27.60 Per Metre 10.15 90.50
ii) 3/0.91 mm (3/0.036") Per Rft. 3.10 38.90 Per Metre 10.15 127.55
iii) 7/0.74 mm (7/0.029") Per Rft. 3.25 50.30 Per Metre 10.70 164.90
iv) 7/0.91 mm (7/0.036") Per Rft. 3.25 74.90 Per Metre 10.70 245.70
v) 7/1.12 mm (7/0.044") Per Rft. 3.45 107.55 Per Metre 11.30 352.75
vi) 7/1.63 mm (7/0.064") Per Rft. 3.95 211.80 Per Metre 12.90 694.65
vii) 19/1.32 mm (19/0.052") Per Rft. 5.50 268.20 Per Metre 18.05 879.75

d) PVC insulated, PVC sheathed 4 core 660/1100 volt grade cable, Cost of trenches where necessary
armoured with G.I. wire 16 SWG. is included in the rates.
i) 19/1.32 mm (19/0.052") Per Rft. 5.50 295.45 Per Metre 18.05 969.10
ii) 19/1.63 mm (19/0.064") Per Rft. 5.90 396.25 Per Metre 19.35 1,299.65
iii) 19/1.83 mm (19/0.072") Per Rft. 6.20 536.85 Per Metre 20.30 1,760.80
iv) 19/2.11 mm (19/0.083") Per Rft. 6.70 754.15 Per Metre 21.95 2,473.60
v) 37//1.83 mm (37/0.072") Per Rft. 6.90 1,296.55 Per Metre 22.55 4,252.70
vi) 37/2.11 mm (37/0.083") Per Rft. 8.25 1,441.60 Per Metre 27.05 4,728.45
vii) 37/2.36 mm (37/0.093") Per Rft. 9.90 1,583.55 Per Metre 32.45 5,194.10
viii) 37/2.62 mm (37/0.103") Per Rft. 12.40 2,689.15 Per Metre 40.60 8,820.35

14 Supply and erection of M.S. sheet box of 16 SWG, 10 cm (4") 38.1


deep, with 4.75 mm thick (3/16") bakelite sheet top, for to
recessed wiring, including making holes for regulators, 38.7
switches, plugs, etc.
i) 10 x 10 cm (4"x4") Each 40.60 91.70 Each 40.60 91.70
ii) 17.5 x 10 cm (7"x4") Each 50.75 127.95 Each 50.75 127.95
iii) 22.5 x 10 cm (9"x4") Each 67.65 159.10 Each 67.65 159.10

chapter-24(Electric Installation) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) 20 x 25 cm (8"x10") Each 81.20 240.90 Each 81.20 240.90


v) 25 x 30 cm (10"x12") Each 101.50 325.60 Each 101.50 325.60
vi) 30 x 35 cm (12"x14") Each 135.30 427.65 Each 135.30 427.65

15 Supply and erection of round block of Sahl wood, 10x4 cm Each 11.60 25.55 Each 11.60 25.55 38.1
(4"x1½") thick.

16 Supply and erection of teak wood board, 4.5 cm (1¾") thick. 38.1

i) 17.5 x 10 cm (7"x4") Each 16.25 67.85 Each 16.25 67.85


ii) 22.5 x 10 cm (9"x4") Each 16.25 79.85 Each 16.25 79.85
iii) 20 x 25 cm (8"x10") Each 18.05 93.65 Each 18.05 93.65
iv) 25 x 30 cm (10"x12") Each 20.30 125.90 Each 20.30 125.90
v) 30 x 35 cm (12"x14") Each 23.20 176.80 Each 23.20 176.80

17 Supply and erection of Sahl wood board, 4.5 cm (1¾") thick.

i) 17.5 x 10 cm (7"x4") Each 16.25 47.45 Each 16.25 47.45


ii) 22.5 x 10 cm (9"x4") Each 16.25 64.25 Each 16.25 64.25
iii) 20 x 25 cm (8"x10") Each 18.05 79.25 Each 18.05 79.25
iv) 25 x 30 cm (10"x12") Each 20.30 95.90 Each 20.30 95.90
v) 30 x 35 cm (12"x14") Each 23.20 112.00 Each 23.20 112.00

18 Supply and erection of iron/aluminum clad, 500 volts main 38.1 When the base frame is already
switches with kitkat fuses, on angle iron board with 3 mm installed, the labour and composite
(1/8") thick M.S. sheet covering, including bonding to earth rates will be reduced as follows:- For
with necessary flexible pipe and thimbles, etc. 15 to 35 Amps. by Rs. 21.20 and Rs.
145.50. For 60 to 65 Amps. by Rs.
a) double pole: 38.80 and Rs. 252.60. For 100 Amps.
by Rs. 38.80 and Rs. 350.80.
i) 15/20 Amp. Each 270.60 1,070.05 Each 270.60 1,070.05
ii) 30/35 Amp. Each 270.60 1,334.05 Each 270.60 1,334.05
iii) 60/65 Amp. Each 405.90 1,787.35 Each 405.90 1,787.35
iv) 100 Amp. Each 405.90 2,358.55 Each 405.90 2,358.55

b) triple pole:
i) 15/20 Amp. Each 405.90 1,506.55 Each 405.90 1,506.55
ii) 30/35 Amp. Each 270.60 1,748.05 Each 270.60 1,748.05

c) triple pole with neutral link:


i) 30/35 Amp. Each 270.60 1,868.05 Each 270.60 1,868.05
ii) 60/65 Amp. Each 405.90 2,380.70 Each 405.90 2,380.70
iii) 100 Amp. Each 514.35 2,993.10 Each 514.35 2,993.10

chapter-24(Electric Installation) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

19 Supply and erection of iron/aluminum clad, 500 volts main When the base frame is already
switches with triple pole and neutral link and HRC fuses, on 38.1 installed, the labour & composite
angle iron board with 3 mm (1/8") thick M.S. sheet covering, rates will be reduced as follows:-
including bonding to earth with necessary flexible pipe and
thimbles. i) For 60/65 Amp. by Rs. 21.20 and
Rs. 145.50.
60/65 Amp Each 405.90 2,450.70 Each 405.90 2,450.70 ii) For 100 to 300 Amp. by Rs. 21.20
100 Amp Each 514.35 3,508.35 Each 514.35 3,508.35 and Rs. 350.80
150 Amp Each 514.35 4,948.35 Each 514.35 4,948.35 iii) For 400 to 500 Amp. by Rs. 42.20
200 Amp Each 1,161.60 7,806.00 Each 1,161.60 7,806.00 and Rs. 526.20
300 Amp Each 1,161.60 9,058.80 Each 1,161.60 9,058.80
400 Amp Each 1,626.90 12,132.30 Each 1,626.90 12,132.30
500 Amp Each 1,742.40 15,500.60 Each 1,742.40 15,500.60

20 Supply and erection of iron/aluminum clad, branch ditto When the base frame is already
distribution board, 250 volt, on angle iron frame of suitable installed the labour and composite
size with 3 mm (1/8") M.S. sheet covering: rates will be reduced by Rs. 19.50 &
Rs. 152.20 respectively.
i) 2 way, 15 Amp per way Each 135.30 455.70 Each 135.30 455.70
ii) 3 way, 15 Amp per way Each 135.30 455.70 Each 135.30 455.70
iii) 4 way, 15 Amp per way Each 135.30 521.70 Each 135.30 521.70
iv) 5 way, 15 Amp per way Each 135.30 575.70 Each 135.30 575.70
v) 6 way, 15 Amp per way Each 135.30 617.70 Each 135.30 617.70
vi) 7 way, 15 Amp per way Each 135.30 665.70 Each 135.30 665.70
vii) 8 way, 15 Amp per way Each 135.30 713.70 Each 135.30 713.70
viii) 9 way, 15 Amp per way Each 135.30 761.70 Each 135.30 761.70
ix) 10 way, 15 Amp per way Each 135.30 833.70 Each 135.30 833.70
x) 11 way, 15 Amp per way Each 135.30 881.70 Each 135.30 881.70
xi) 12 way, 15 Amp per way Each 135.30 935.70 Each 135.30 935.70
xii) 2 way, 30 Amp per way Each 202.95 523.35 Each 202.95 523.35
xiii) 3 way, 30 Amp per way Each 202.95 529.35 Each 202.95 529.35
xiv) 4 way, 30 Amp per way Each 202.95 583.35 Each 202.95 583.35
xv) 5 way, 30 Amp per way Each 202.95 643.35 Each 202.95 643.35
xvi) 6 way, 30 Amp per way Each 202.95 685.35 Each 202.95 685.35
xvii) 7 way, 30 Amp per way Each 202.95 745.35 Each 202.95 745.35
xviii)8 way, 30 Amp per way Each 202.95 793.35 Each 202.95 793.35
xix) 9 way, 30 Amp per way Each 202.95 841.35 Each 202.95 841.35
xx) 10 way, 30 Amp per way Each 202.95 913.35 Each 202.95 913.35

chapter-24(Electric Installation) Page 7


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

21 Supply and erection of bus bars, for 500 volts 3 phase A.C. When the base frame is already
supply with four copper bars, including glazed porcelain 38.1 installed the labour and composite
bridges, on angle iron board, fixed with rag bolts and M.S. rates will be reduced by Rs. 21.20 and
sheet box 1.5 mm thick, etc. complete:- Rs. 145.50 respectively.

i) 60 Amp. with 4 copper bars Each 511.50 2,326.25 Each 511.50 2,326.25
size 1½"x1/8" (40 x 3 mm)
ii) 100 Amp. with 4 copper bars Each 511.50 2,326.25 Each 511.50 2,326.25
size 1½"x1/8" (40 x 3 mm)
iii) 200 Amp with 4 copper bars Each 792.00 2,726.75 Each 792.00 2,726.75
size 2"x1/8" (50x 3 mm)
iv) 300 Amp with 4 copper bars Each 927.30 2,862.05 Each 927.30 2,862.05
size 2"x3/16" (50x 5 mm)
v) 500 Amp with 4 copper Each 627.00 3,074.65 Each 627.00 3,074.65
size 2"x1/4" (50x 6 mm)

22 i) Supply and erection of plain pendent lamp holder, Each 9.65 43.25 Each 9.65 43.25 38.1
complete with bakelite lamp holder and flexible twin wire
23/0.0076" upto 2 metre length (without bulb and shade).

ii) Extra for additional length of flexible wire, beyond Per Rft. -- 1.65 Per Metre -- 5.45
2 metres.

23 Supply and erection of counter weight pedent with porcelain Each 19.25 136.85 Each 19.25 136.85 38.1
counter weight, and fitting on bakelite lamp holder, with
flexible twin wire 23/0.0076" complete (without bulb and
shade).

24 Supply and erection of stiff pedent with brass/metal pipe 6.3 Each 26.40 212.40 Each 26.40 212.40 ditto
cm (2.5") long, and 15 mm (½") dia brass oxidised or painted,
along with brass lamp holder with VIR/PVC cable 3/0.74 mm
(3/0.029").

25 Supply and erection of 22.5 cm (9") long swan neck plain Each 27.30 64.50 Each 27.30 64.50 ditto
brass/steel brass oxidised bracket lamp holder, complete.

26 Supply and erection of wall type/pole type bracket, with double Each 37.70 351.50 Each 37.70 351.50 ditto
cover water tight reflector, flexible wire and brass bolder.

27 Supply and erection of bakelite button holder shade, large Each 6.25 25.10 Each 6.25 25.10 ditto
size.

28 Supply and erection of call bell 220/250 volts, fixed on teak Each 26.40 180.85 Each 26.40 180.85 38.1
wood board 17.5x10 cm (7"x4").

chapter-24(Electric Installation) Page 8


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

29 Supply and erection of bell push or bed switch, with 5 metres Each 5.80 75.40 Each 5.80 75.40 38.1
twin flexible wire 23/0.0076".

30 Supply and erection of ceiling rose, bakelite. Each 9.65 19.55 Each 9.65 19.55 ditto

31 Supply and erection of switches 5 Amp.

i) open type Each 9.25 21.55 Each 9.25 21.55 ditto


ii) piano type Each 9.25 20.35 Each 9.25 20.35
iii) ring type, recessed Each 9.25 16.45 Each 9.25 16.45
iv) plate type, recessed Each 9.25 40.75 Each 9.25 40.75
v) double control, open type Each 12.40 29.60 Each 12.40 29.60
vi) double control, ring type recessed Each 12.40 30.80 Each 12.40 30.80
vii) double control, piano type Each 12.40 27.05 Each 12.40 27.05

32 Supply and erection of switches 10/15 Amp. ditto

i) open type Each 9.25 31.25 Each 9.25 31.25


ii) recessed type Each 9.25 39.65 Each 9.25 39.65

33 Supply and erection of wall socket with 3 pin 5 Amp, shoe. Each 9.25 61.25 Each 9.25 61.25 ditto

34 Supply and erection of 3 pin. 5 Amp wall socket. Each 9.25 45.65 Each 9.25 45.65 ditto

35 Supply and erection of 3 pin, 10/15 Amp. wall socket. ditto

i) open type Each 9.25 39.65 Each 9.25 39.65


ii) recessed type Each 9.25 75.65 Each 9.25 75.65

36 Supply and erection of 3 pin switch and plug combined, ditto


recessed type.

i) 5 Amp Each 9.25 58.05 Each 9.25 58.05


ii) 10/15 Amp Each 9.25 82.25 Each 9.25 82.25

37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe, Each 9.25 118.85 Each 9.25 118.85 ditto
open type.

38 Supply and erection of cut out, bakelite. ditto


i) open type Each 5.15 23.55 Each 5.15 23.55
ii) recessed type Each 5.15 29.55 Each 5.15 29.55

chapter-24(Electric Installation) Page 9


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

39 Supply and erection of button holder. 38.1

i) bakelite large size Each 5.80 13.85 Each 5.80 13.85


ii) brass Each 5.80 20.60 Each 5.80 20.60

40 Supply and erection of brass bracket with holder. Each 7.70 22.50 Each 7.70 22.50 ditto

41 Supply and erection of bell push open/recessed type Each 5.15 15.15 Each 5.15 15.15 ditto
(without flexible wire).

42 Supply and erection of kitkat, 500 volt: ditto

i) 15/20 Amp Each 9.10 34.30 Each 9.10 34.30


ii) 30/35 Amp Each 9.90 35.10 Each 9.90 35.10
iii) 60/65 Amp Each 15.15 55.35 Each 15.15 55.35
iv) 100 Amp Each 17.00 90.80 Each 17.00 90.80
v) 200 Amp Each 19.45 131.65 Each 19.45 131.65
vi) 300 Amp Each 19.45 279.25 Each 19.45 279.25
vii) 400 Amp Each 25.10 349.70 Each 25.10 349.70
viii) 500 Amp Each 25.10 499.10 Each 25.10 499.10

43 Supply and erection of tube light, including rod, choke, starter 38.1
with frame, flexible wire, including connection from ceiling
rose, etc., complete.

i) double rod (80 watts) with two chokes and 2 starters. Per set 156.75 951.15 Per set 156.75 951.15

ii) single rod (40 watts) with one choke and one starter. ditto 125.40 481.80 ditto 125.40 481.80

iii) round tube, 32 watt, with one choke and one starter, Each 125.40 544.20 Each 125.40 544.20
without cover.

iv) round tube, 32 watt with one chock and one starter, with ditto 104.50 643.30 ditto 104.50 643.30
cover.

44 Providing and fixing M.S. iron box for housing main switches, ditto
made of 1.5 mm (1/16") thick M.S. sheet, with locking
arrangement, including painting:-
i) 60x35x15 cm (24"x14"x6") Each 131.95 1,938.30 Each 131.95 1,938.30
ii) 95x40x20 cm (38"x16"x8") Each 474.40 2,685.55 Each 474.40 2,685.55
iii) 105x52.5x22.5 cm (42"x21"x9") Each 721.20 3,698.05 Each 721.20 3,698.05
iv) 135x70x27.5 cm (54"x28"x11") Each 796.15 5,518.05 Each 796.15 5,518.05

chapter-24(Electric Installation) Page 10


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

45 Supply and erection of girder clamp hook, 16 mm (5/8") with Each 20.90 126.50 Each 20.90 126.50 38.1
M.S. plate 25x6 mm (1"x¼"), with bolts and nuts for hanging &
ceiling fans. 38.10

46 Supply and erection of girder strut, of M.S. tee section Each 26.40 688.00 Each 26.40 688.00 ditto
40x40x6 mm (1½"1½"x ¼"), complete with clamp, bolts and
nuts, etc., including fixing with cement concrete 1:3:6.

47 Supply and erection of roof suspension hook, 16 mm (5/8") Each 28.30 1,157.35 Each 28.30 1,157.35 38.1
dia rod with 75x40x3 mm (3"x1½"x1/8") M.S. steel channel,
with clamp, bolts and nuts, etc., including fixing with cement
concrete 1:3:6.

48 Supply and erection of roof suspension hook of M.S plate Each 37.70 452.15 Each 37.70 452.15
75x40x12.7mm (3"x1½"x½") with 16 mm (5/8") hook complete
with bolts, nuts and fixing with cement concrete 1:3:6

49 Supply and erection of 3/8" (10 mm) dia M.S. bar fan hook, Each 11.85 26.25 Each 11.85 26.25 ditto
placed at the time of casting of slab.

50 Erection of circular L.T. pole in cement concrete 1:3:6 one Each 284.45 856.60 Each 284.45 856.60 38.12
metre below ground level (excluding the cost of pole),
including cement concrete collar (1:2:4) excavation of
foundation, and finishing surface.

51 Supply and erection of bracket of M.S. channel 75x40x6 mm


(3"x1½"x¼") section:-
i) 0.60 metre (2') long for 2 lines. Each 82.50 513.75 Each 82.50 513.75
ii) 1.200 metre (4') long for 4 lines. Each 96.25 1,023.30 Each 96.25 1,023.30

52 Supply and erection of anchor rod Henley type for pole, Per Rft. 4.90 16.65 Per Metre 16.05 54.55 38.14
including necessary clamps and 7/12" stay wire, straining
screws, etc., erected in cement concrete 1:3:6 and collar of
cement concrete.

43 Supply and erection of stay for house service pipe, erected Per Rft. 7.05 25.65 Per Metre 23.20 84.20 ditto
with straining screws and 7/14" stay wire, complete.

54 Supply and erection of house service pipe Henley (G.I. pipe Per Rft. 29.50 93.55 Per Metre 96.80 306.90
water quality) or pole type, 50 mm (2") dia, erected to instal
insulated overhead line,include shackle insulator for holding
insulated wire and straining devices for bearer wire and other
accessories etc., complete.

chapter-24(Electric Installation) Page 11


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

55 Supply and erection of house service pipe 50 mm (2") dia G.I. Per Rft. 28.50 200.10 Per Metre 93.50 656.30
pipe Henley or pole type for bare copper wire overhead line,
including shackle insulator, straining devices and other
accessories etc.

56 Supply and erection of lightning arrestor horn type, complete. Each 158.40 2,078.40 Each 158.40 2,078.40

57 Supply and erection of shackle insulator, medium size. Each 21.80 171.80 Each 21.80 171.80 38.12

58 Supply and erection of pin insulator, green medium size. Each 21.80 63.80 Each 21.80 63.80 ditto

59 Supply and erection of bare copper conductor wire No. 2 to Per Kg 11.30 494.10 Per Kg 11.30 494.10 38.1
No. 10 SWG, including binding wire No. 16 SWG.

60 Supply and erection of G.I. wire of all sizes, including binding Per Kg 11.30 98.10 Per Kg 11.30 98.10 ditto
wire No. 16 SWG for support of rubber wire or earthing wire,
pole to pole etc.

61 Wiring overhead line in 2 single core, PVC/weather proof 38.12


cable, on G.I. wire No. 8 SWG bearer wire and in house
service pipe, including connection through joint box.

i) 3/0.74 mm (3/0.029") Per Rft. 2.70 4.75 Per Metre 8.80 15.50
ii) 7/0.74 mm (7/0.029") ditto 2.70 10.40 ditto 8.80 34.05
iii) 7/0.91 mm (7/0.036") ditto 2.70 12.95 ditto 8.80 42.40
iv) 7/1.12 mm (7/0.044") ditto 2.70 10.45 ditto 8.80 34.30

62 Supply and erection of all aluminum stranded hard drawn bare Per Rft. 5.40 17.15 Per Metre 17.75 56.15 38.1
conductor, of size 7/3.099 mm (7/0.122").

63 Supply and erection of street light pole bracket 30 mm (1¼") Each 132.00 763.40 Each 132.00 763.40
G.I. pipe 2 metre long, complete with 2 No. pole clamp.
64 Supply and erection of pole mounted street light, holders,
shade and glass, etc., for fitting 125/250 watts mercury vapour
lamp (excluding cost of lamps):
i) G.E.C. design Each 264.00 2,508.00 Each 264.00 2,508.00
ii) Philips design ditto 264.00 2,934.00 ditto 264.00 2,934.00

65 Supply and fitting of mercury vapour lamp, complete with


choke set.
i) 125 watt lamp Each 104.50 944.50 Each 104.50 944.50
ii) 250 watt lamp ditto 125.40 1,745.40 ditto 125.40 1,745.40

chapter-24(Electric Installation) Page 12


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

66 Manufacture and erection of angle iron lattice steel structure Each 4,765.15 19,590.75 Each 4,765.15 19,590.75 38.13 The composite rate will be reduced
pole (36.0') 10,923 mm long 9348 mm (30.5') above ground or increased by Rs. 36.50 for each
level) 355 mm (14") square at base and 204 mm (8") square at (100 mm) of reduction or addition in
top for electric distribution line, using 1¼"x1¼"x3/16" (30x30x5 the height of the pole above ground
mm) angle iron legs and ¾"x¾"1/8" (20x20x3 mm) angle iron level.
bracing 420 mm (17") long fixed between legs on all the four
sides in diagonal position, and 1¾"x1¾"x3/16"(45x45x5 mm)
angle iron on top and 4 bands of M.S. flat iron 2"x¼" (50x6 mm)
305 mm (12") centre to centre, as per standard drawing
including silver painting of pole 3 coats, excavation and refilling
of foundation cement concrete 1:2:4. 6'-0"x1'-8"x1'-8"
(1807x500x500 mm) for foundation, etc, complete in all
respects.

67 Manufacture and erection of galvanized angle iron lattice steel Each 1,801.85 28,101.90 Each 1,801.85 28,101.90 38.13 The composite rate will be reduced
structure pole 37 ft. (11.25 m) long 30 ft. (9 m) above ground or increased by Rs. 237.00 for each
level), 34" square (850 mm) at base, 13.75" (35 mm) square at foot (300 mm) of reduction or
top, for electric distribution line, using 2"x2"x5/32" addition in the height of the pole
(50x50x4mm) high tensile steel angle iron legs, and 1-3/8"x above ground level.
1-3/8"x1/8" (35x35x3 mm) M.S. angle iron bracings fixed
between legs on all the four sides in diagonal position as per
standard drawing including silver painting of pole, excavation
and refilling of foundation, one ft. (300 mm) thick cement
concrete 1:3:6 foundation of outer size 8'x3½'x3½'
(2400x1050x1050 mm), etc. complete in all respects.

68 Earthing of iron clad/aluminum switches, etc. with G.I. wire No. Job 561.00 2,846.30 Job 561.00 2,846.30
8 SWG in G.I. pipe 15 mm (½") dia, recessed or on surface of
wall and floor, complete with 1.5 metre long G.I. pipe, 50 mm
(2") dia with reducing socket 4 to 5 metre below ground level,
and 2 metre away from building plinth.

69 Earthing of Metallic cases, etc. with G.I. wire No. 8 SWG, in 38.11
15 mm (½") dia G.I. pipe, best quality:-
i) on surface, including clamps, etc. Per Rft. 6.05 46.25 Per Metre 19.80 151.75
ii) recessed in wall, including hooks, ditto 13.70 53.05 ditto 44.90 174.00
jharries and making good surface.

70 Bonding to earth with wire on surface, including cost of wire, ditto


clamps, thimbles, etc.
a) G.I. wire:
i) 8 SWG Per Rft. 2.80 7.75 Per Metre 9.25 25.45
ii) 16 SWG ditto 2.80 4.15 ditto 9.25 13.55

chapter-24(Electric Installation) Page 13


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) Copper wire:

i) 16 SWG Per Rft. 2.80 6.50 Per Metre 9.25 21.40


ii) 20 SWG ditto 2.80 4.35 ditto 9.25 14.35

71 Erection only, of lightning conductor of copper tape, including Per Rft. 9.65 13.20 Per Metre 31.70 43.25 38.11 Rate includes all materials required
supply of copper staple and copper nails and cement, sand in erection (excluding copper tape
mortar. lightning conductor).

72 Supply and erection of 600x600x3 mm (2'x2'x1/8") copper Each 374.00 3,596.70 Each 374.00 3,596.70 ditto
plate, including revitting to copper tape and placing in mixture
of salt and charcoal, etc.

73 Supply and erection of copper tape, including copper staple


copper nails, cement, sand, etc.

i) tape 40x3 mm (1½"x1/8") Per Rft. 13.70 108.25 Per Metre 44.90 355.10
ii) tape 50x3 mm (2"x1/8") ditto 13.70 126.55 ditto 44.90 415.10

74 Supply and erection of 25 mm (1") dia and one metre long Job 264.00 2,154.00 Job 264.00 2,154.00
lightning conductor copper rod with 5 spikes on ball and base,
etc. complete.

75 Supply and erection of electric energy meter, including meter 38.1


testing fee, etc.

a) single phase:

i) 1x10 Amp, 250 volts Each 115.50 1,879.50 Each 115.50 1,879.50
ii) 1x30 Amp, 250 volts ditto 115.50 1,879.50 ditto 115.50 1,879.50

b) three phase, 4 wires:

i) 3x15 Amp, 400 volts Each 231.00 5,349.00 Each 231.00 5,349.00
ii) 3x50 Amp, 400 volts ditto 313.50 5,431.50 ditto 313.50 5,431.50
iii) 3x80 Amp, 400 volts ditto 313.50 5,431.50 ditto 313.50 5,431.50

76 Rewinding of A.C. ceiling fan, capacitor type, including cost of The credit of out turn of dismantled
wire, leatheride paper cotton tape, soldering, etc. material has been accounted for in
the rate.
i) 1200 mm (48") sweep, 275-300 RPM. Each 214.50 654.00 Each 214.50 654.00
ii) 1400 mm (56") sweep, 250-275 RPM. ditto 235.15 643.70 ditto 235.15 643.70

chapter-24(Electric Installation) Page 14


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

77 Rewinding of A.C. exhaust fan, including cost of wire, The credit of out turn of dismantled
leatheride paper, cotton tape, soldering, etc. material has been accounted for in
the rate.
i) 375 mm (15") sweep, and 1300-1500 RPM Each 154.00 421.05 Each 154.00 421.05
ii) 450 mm (18") sweep, and 1300-1500 RPM ditto 154.00 457.80 ditto 154.00 457.80

78 Rewinding of pedestal fan 600 mm (24") sweep, and 900-950 Each 184.80 523.45 Each 184.80 523.45 The credit of out turn of dismantled
RPM, including wire, leatheride paper, cotton, tape, etc. material has been accounted for in
the rate.
79 Supply and fitting of regulator knob with shaft Each 28.90 88.90 Each 28.90 88.90 38.1
and plate of electric fan regulator.

80 Supply and fitting of capacitor 2.2 uF, for ceiling fans. Each 23.10 59.10 Each 23.10 59.10 ditto

81 Supply and fitting of ball bearing of size Each 28.90 136.90 Each 28.90 136.90 ditto
6201, 6202 or 6203 for ceiling fans.

82 Rewinding regulator of ceiling fan 48"/56" (1200/1400 mm) Each 57.75 122.00 Each 57.75 122.00 The credit out turn of dismantled
sweep, to control 3/4 speeds. material has been accounted for in
the rate.
83 Erection of ceiling fan alongwith regulator (all sizes), including Each 104.00 117.60 Each 104.00 117.60
carriage from local Railway Station/Store to site of work,
electric wire/cable for suspension rod and board connection,
and cutting, threading on the rod, where necessary.

chapter-24(Electric Installation) Page 15


IRON WORK
The Rates for all finished works include the removal of surplus debris, unused material and byproduct

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Railway Track, etc.

1 Laying, linking and packing tramway line. 100Lft. 805.20 Metre 26.40

2 Dismantling tramway track. 100Lft. 272.00 Metre 8.90

3 Laying, linking of B.G. track, including packing, 100Lft. 2073.50 Metre 68.00
straightening and leveling.

4 Linking points and crossings, complete with fastenings. Each 2069.10 Each 2069.10

5 Bending or strainghtening B.G. rail with Jim Each 257.40 Each 257.40
Crow. Point Point

6 Fixing street lamp posts. Each 280.50 Each 280.50

7 Binding ends of sleepers and timber of all sizes and kinds, 100 Nos 2471.70 100 Nos 2471.70
including spreading and restacking.

8 Opening stacks of sleepers and timber of all kinds and 100 Nos 318.55 100 Nos 318.55
sizes, including spreading for inspection and restacking
within one chain lead.

IRON WORK

9 Small iron work, such as gusset plates, knees, bends, Per Cwt 1518.00 6570.95 100 Kg 2988.20 12935.00
stirrups, straps, rings, etc. including cutting, drilling,
riveting, handling, assembling and fixing; but excluding
erection in position.

10 Fabrication of heavy steel work, with angle, tees, flat iron Per Cwt 421.10 5232.05 100 Kg 828.90 10299.35
round iron and sheet iron for making trusses, girders,
tanks, etc., including cutting, drilling, revitting, handling,
assembling and fixing, but excluding erection in position.

11 Erection and fitting in position iron trusses, staging of Per Cwt 146.65 100 Kg 288.70
water tanks, etc.

chapter-25(Iron work) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

12 Fixing corrugated iron sheet, including revitting, etc. 100 Sft. 633.60 sq.m 68.20

13 Erecting corrugated iron sheet tanks, upto 20' Per Cwt 284.85 100 Kg 560.70
(6 m) height.

14 Erecting rolled steel beams or old rails, in roofs, etc., Per Cwt 167.20 100 Kg 329.15
erection and fixing in position.

15 Erecting rolled steel beams or rails, erection for posts etc. Per Cwt 81.95 100 Kg 161.30
(other than in roofs).

16 Making bolts and nuts of iron rods. Per Cwt 1098.90 6722.60 100 Kg 2163.20 13233.45

17 Cutting rails, rolled steel joists and beams, with hacksaw:-

a) upto 6" size (150 mm) Per Cut 99.00 Per Cut 99.00
b) above 6" size (150 mm) Per Cut 145.20 Per Cut 145.20

18 Cutting rails or rolled steel beams of size below 6" Per 47.15 Per Cwt 47.15
(150 mm), with jim. Cut Cut

19 Bending rolled steel beams or rails. Per 50.50 252.00 Per 50.50 252.00
Bend Bend

20 Drilling holes, in plates upto ½" (13 mm) thick, per inch Per 20.65 Per 20.65
dia, (25mm) or part thereof. Hole Hole

21 Extra for drilling holes in plates over ½" (13 mm) thick, per Per 11.70 Per 11.70
inch dia, (25 mm) or part thereof. Hole Hole

22 Rivetting 1/8" dia (3 mm). 100 Nos 217.25 100 Nos 217.25

23 Cutting out Rivets, all sizes. 100 Nos 676.50 100 Nos 676.50

24 Fitting and erection of gutters of sheet iron. Per Lft. 36.75 Metre 120.50

25 Cutting and fixing iron bars, for barred windows. Per bar 20.75 Per bar 20.75

26 Cutting G.I. sheets. Each 8.35 Each 8.35


Cut Cut

27 Notching web or foot of rail posts, for housing rail beams Per 224.40 358.80 Per 224.40 358.80
Notch Notch

chapter-25(Iron work) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

28 Hoop iron netted trellis work fixed with nails Per Sft. 13.20 sq.m 142.05

29 Fixing zinc iron or G.I. sheet on table tops Per Sft. 9.30 sq.m 100.25

30 Making and fixing steel grated doors, complete wit Per Sft. 70.70 595.65 sq.m 760.90 6409.35
locking arrangement, angle iron frame 2"x2"x3/8
(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)
centre to centre.

31 Making and fixing steel grated door with 1/16" thic Per Sft. 74.85 731.30 sq.m 805.25 7868.65
(1.5mm) sheeting, including angle iron frame 2"x2"x3/8
(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)
centre to centre, with locking arrangement

32 Making and fixing grating in opening, including fixing Per Sft. 28.95 299.95 sq.m 311.60 3227.40
site with flat iron 2"x3/8" (50x10 mm) and ¾" (19 mm)
square bars, at 4" (100 mm) centre to centre.

33 Providing and fixing stair railing (all types and designs) o Per Rft. 211.05 668.65 Metre 692.40 2193.75 The composite rate shall be
hard wood, including bends and corners, screwed to reduced or increased by Rs. 31.90
5/8"x5/8" (16x16 mm) M.S. square bars 2.75 ft. (838 mm) for each foot of reduction or
high, at 5.5 inch (137 mm) inch centre to centre, fixed in addition in the height of the square
steps of stairs, M.S. flat 1"x1/8" (25x3 mm) welded to bars.
bars, painting/polishing 3 coats, etc. complete

34 Providing/fixing stair railing consisting of M.S. Box sectio Per Rft. 107.05 286.95 Metre 351.25 941.40
size 1-1/2"x3" of 16 SWG welded with M.S. flat 1"x1/8"
continuously and welded over M.S. square bars 5/8"x5/8"
punched in M.S. flat 2 ¾' high @ 5½" c/c fixed in steps of
stair I/C painting 3 coats complete

35 Providing and fixing terrace railing of 2" (50 mm) i/ Per Rft. 77.75 508.40 Metre 255.09 1667.98 -do-
conduit pipe 16 SWG, welded with 5/8"x5/8" (16x16 mm)
square bar 2.75 ft. (838 mm) high fixed at 5" (125 mm)
centre to centre, in reinforced cement concrete slab with
suitable arrangement, complete in all respects, as pe
design and drawing

36 Providing and fixing collapsible gate made of 2"x2"x"¼ Per Sft. 131.80 529.65 sq.m 1417.90 5699.05
(50x50x6 mm) tee iron at top and bottom, channel iron
verticals ¾"x¼"x¼"x1/8" (20x6x6x3 mm) at 3" (75 mm) to
5" (125 mm) centre to centre (approximate) and flat iron
crosses 3"x3/16" (75x5 mm), and best quality rollers a
bottom of 3" (75 mm) diameter including holdfasts
handles 12" (300 mm) long of ¾"x¼"x¼"x1/8" (20x6x6x3
mm) channel iron, locking arrangement inside and
outside, painting 3 coats of black Japan enameled
complete in working order

chapter-25(Iron work) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

37 Providing and fixing 24 SWG G.I. sheet rolling shutter, Per Sft. 32.05 184.65 sq.m 344.70 1987.00
consisting of steel frame of M.S. channel 2"x1¼"x1/8"
(50x30x3 mm), angle iron 1½"x1½"x1/8" (40x40x3 mm),
M.S. plate 1'x1'x1/8" (300x300x3 mm), G.I. pipe 1½" (37
mm) dia, springs 2' (600 mm) centre to centre, rollers, 24
SWG G.I. covering 1 ft. x 1 ft. (300x300 mm), handles,
holdfast, and painting three coats, complete in all
respects.

38 Providing and fixing M.S. angle iron 1½"x1½"x¼" Per Rft. 16.30 122.55 Metre 53.50 402.00
(40x40x6 mm) edge protector nozing of steps of stairs,
having holdfast or 3/8" (10 mm) dia M.S. bars 8" (200 mm)
long welded at 2' (600 mm) centre to centre and
embedded in cement concrete on steps, complete in all
respects.

39 Providing and fixing stair railing of 2½" (63 mm) i/d G.I. Per Rft. 92.75 475.05 Metre 304.35 1558.50 The composite rate shall be
pipe, welded with 5/8"x5/8" (16x16 mm) square M.S. bars reduced or increased by Rs. 31.90
2'-9" (838 mm) high, fixed in each step, complete in all for each foot of reduction or
respects, including painting, polishing three coats. addition in the height of the square
bars.
40 Providing and fixing G.I. wire gauze 24 SWG, 12x12 Per Sft. 15.40 52.55 sq.m 165.70 565.25
meshes per square inch, fixed to steel windows or doors,
etc., complete in all respects.

41 Providing and fixing steel windows with openable glazed


panels, using beam section for frame 1½"x1"x5/8"x1/8" For fixed pannels, the composite
(40x25x16x3 mm), Z-section for leaves ¾"x1"x¾"x1/8" rate will be reduced by Rs.30.00
(20x25x20x3 mm), T-section sashes 1"x1"x1/8" (25x25x3 per Sft. or Rs. 305.00 per Sq.
mm), glass panes, wooden screed for glazing embedded metre.
over a thin layer of putty duly screwed with leaves, brass
fittings, holdfast, duly painted, complete in all respects,
including all cost of material and labour, etc. as per
approved design and as directed by the
Engineer-in-charge:-

a) without wire gauze:

i) glass pane 2 mm thick Per Sft. 38.90 117.60 sq.m 418.55 1265.30
ii) glass pane 2.5 mm thick ditto 38.90 250.05 ditto 418.55 2690.70
iii) glass pane 3 mm thick ditto 38.90 254.85 ditto 418.55 2742.35
iv) glass pane 4 mm thick ditto 38.90 257.25 ditto 418.55 2768.15
v) glass pane 5 mm thick ditto 38.90 259.65 ditto 418.55 2794.00

chapter-25(Iron work) Page 4


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) fixed with wire gauze, 22 SWG

i) glass pane 2 mm thick Per Sft. 50.25 283.60 sq.m 540.90 3051.65
ii) glass pane 2.5 mm thick ditto 50.25 286.00 ditto 540.90 3077.50
iii) glass pane 3 mm thick ditto 50.25 290.80 ditto 540.90 3129.15
iv) glass pane 4 mm thick ditto 50.25 293.20 ditto 540.90 3154.95
v) glass pane 5 mm thick ditto 50.25 295.60 ditto 540.90 3180.80

42 Providing and fixing steel windows using M.S. sheet (16


SWG) moulded tubular pipe 1½"x1½" (40x40mm) for
frame and 1¼"x1¼" (30x30mm) for leaves including M.S.
square bars ¼"x¼" (6x6 mm) welded around each panel
of frame, 5 mm thick glass panes fixed with double M.S.
square tubular pipe 3/8"x3/8" (10x10mm) (22 SWG)
beading with U' shaped rubber lining, brass fitting,
holdfast, including painting three coats complete in all
respects.
a) For openable panels fixed with wire Per Sft. 28.05 221.70 Sq.m 302.00 2385.75
gauze 24 SWG, 12x12 mesh and glass
panes ¼" (6 mm) thick.
b) For fixed panels without wire gauze. ditto 27.00 118.00 ditto 290.50 1269.55

43 Providing and fixing windows consisting of M.S. box Per Sft. 38.50 310.15 Sq.m 414.40 3337.35
section frame 2"x1½" (50x40mm), leaves frame 1-½"x1"
(40x25mm) box section frame for glazing 3/8"x3/8"
(10x10mm) using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" (25x3mm) M.S. flat for fixing 3/16"
(5 mm) thick glass panes M.S. box section ½"x½"
(13x13mm) of 16 SWG for fixing 24 SWG wire gauze on
outer side by means of ¾"x1/8" (20x3mm) M.S. flat and
screws I/C all C.P. fitting and painting 3 coats complete in
all respect.

44 Providing and fixing windows consisting of M.S. box Per Sft. 47.45 361.95 Per Sft. 510.70 3894.40
section frame 2"x1½", (50x40mm) leaves frame 1½"x1"
(40x25mm) box section frame for glazing 3/8"x3/8"
(10x10mm) using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" (25x3mm) M.S. flat for fixing 3/16"
(5 mm) thick glass panes M.S. box section ½"x½"
(13x13mm) of 16 SWG for fixing 24 SWG wire gauze on
outer side by means of ¾"x1/8" (20x3mm) M.S. flat and
screws including grill of M.S. flat ½"x1/8" (13x3mm) or
¼"x¼" (6x6mm) square bar with independent frame of
½"x½" (13x13mm) box section of 16 SWG i/c all C.P.
fitting and painting 3 coats complete in all respect.

chapter-25(Iron work) Page 5


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

45 Flapping G.I. pipes for bath room drains. Each 247.50 281.10 Each 247.50 281.10

46 Supply and fixing iron grating for fire place. Per Sft. 75.90 171.90 sq.m 816.70 1849.65

47 Fixing copper flashing, including cutting of sheets, Per Lft. 26.40 Metre 86.60
grooving and rivetting.

48 Providing and fixing angle iron railing, using 2½"x2½"x3/8" Per Rft. 39.00 719.35 Metre 128.00 2360.00
(63x63x10 mm) angle iron post 4½" (113 mm) long, 5' to
6' (1500 to 1800 mm) apart, with 2½"x2½"x3/8" (63x63x10
mm) angle iron top rail, and two rows of M.S. flat 2½"x¼"
(63x6 mm) including fixing to side of Bridge/structure with
U.bolt 1½' (450 mm) long ¾" (20 mm) dia, painting posts,
etc. complete in all respects.

49 Providing and fixing barbed wire fencing on compound 100Rft. 946.70 7805.65 Metre 31.05 256.10
wall, consisting of 1½"x1½"x3/16" (40x40x5 mm), angle
iron post 3¼ ft. (990 mm) long, 5 to 6 ft. (1500 to 1800
mm) centre to centre, embedded in cement concrete
1:4:8, base of size 9"x9"x12" (225x225x300 mm), and
three rows of barbed wire, painting posts, etc. complete in
all respects.

50 Providing and fixing barbed wire fencing on compound 100Rft. 1595.75 9933.65 Metre 52.35 325.90
wall, consisting of 1½"x1½"x3/16" (40x40x5mm) angle
iron post 3' (900 mm) long, 4' (1200 mm) apart embedded
in cement concrete 1:4:8 base of size 6"x6"x9"
(150x150x225 mm) and 4 rows of barbed wire, including
binding wire, painting posts, etc. complete in all respects.

51 Providing and fixing all types of partly fixed and partly (1) Increase rate by Rs. 30.00 per
openable glazed anodised bronze colour aluminium Sft or Rs.322.80 per Sq-metre if
doors, using delux section of M/s Al-Cop or Pakistan sections thickness is 2 mm.
Cables, having chowkat frame of size 40 x 100 mm (1½" x (2) Reduce rate by Rs.20.00 per Sft
4") and leaf frame of 60x40mm (2½"x1½") wide sections or Rs.215.20 per Sq-metre if
including the cost of ¼" (5 mm) thick imported tinted sections are of dull aluminimum
glass with aluminium triangular gola and rubber gasket to Per Sft 48.50 330.55 sq. m 521.85 3556.70 shade.
support the glass and leaf edging, using approved (3) Reduce rate by Rs.20.00 per
standard fittings, locks, 3" (75 mm) wide long handles Sft or Rs.215.20 per Sq-metre if
etc., and hardware any required as approved by the local glass is used.
engineer in-charge.

chapter-25(Iron work) Page 6


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

52 Providing and fitting all types of glazed aluminium Per Sft 65.06 283.91 sq. m 700.05 3054.85 (1) Reduce rate by Rs.20.00 per Sft
windows of anodised bronze colour partly fixed and partly or Rs.215.20 per Sq-metre if
sliding using delux sections of M/s Al-Cop or Pakistan section thickness is 1.2 mm.
Cables having frame size of 100 x 20 mm (4"x¾") and
leaf frame sections of 50 x 20 mm (2"x¾"), all of 1.6mm (2) Reduce rate by Rs.20.00 per Sft
thickness including 5 mm thick imported tinted glass with or Rs.215.20 per Sq-metre if
rubber gasket using approved standard latches, hardware sections are of dull aluminium
etc., as approved by the Engineer in-charge. shade.
(3) Reduce rate by Rs.20.00 per Sft
or Rs.215.20 per sq-metre if local
glass is used.

chapter-25(Iron work) Page 7


MISCELLANEOUS
Rates for all finished works include the removal of surplus debris, unused material and byproduc

MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Notice board made of cement, sand mortar 1:3. Per Sft. 38.80 45.30 Per 417.20 487.55 The board is to be of cement
sq.m plaster ½" (13 mm) thick, with 2"
(50 mm) wide and 1" (25 mm) thick
beading.
2 Fixing handles to iron hammers. Each 48.15 - Each 48.15 -

3 Providing and fixing barbed wire fencing, with 4 horizontal 100Lft. 3,404.30 17,381.95 L.m. 111.70 570.30 Vertical bars in straining and
and 2 number cross wires fixed with posts of R.C.C., 1:2:4 stiffening posts to be 4 No. each by
(straining posts 7'x9"x9" (2.13 mx225x225 mm) at 100' ½" (13 mm) dia and for
(30 m) centre to centre, stiffening posts 7'x6"x6" (2.13 intermediate posts to be 4 No. of
mx150x150 mm) at 50 ft. (15 m) interval and intermediate 3/8" (10 mm) dia Stirrups for all
post 7'x5"x5" (2.13 mx125x125 mm) at 8 ft.(2.4 m) centre posts to be ¼" (6 mm) dia. at 12"
to centre), including cost of steel, its fabrication and (300 mm) centre to centre.
placing of steel reinforcement, eye bolts, washers, etc.
complete.
Surveying

4 Supplying Bamboo Jhandies 10' to 12' (3.00 to 3.65 m) with Each 26.40 118.80 Each 26.40 118.80
iron shoes, and flags 15" (375mm) square.

5 Supplying wooden pegs for levelling, 1½" (40 mm) dia, 6" 100Nos. 77.00 92.60 100Nos. 77.00 92.60
(150mm) long.

6 Supplying wooden pegs for alignment, 2" to 3" dia (50 to 100Nos. 184.80 364.80 100Nos. 184.80 364.80
75 mm), 9" (225 mm) long.

7 Fixing enamalled iron gauges flush with masonry, including Per Lft. 46.20 53.40 Per 151.60 175.20
cost of hooks. L.M.

8 Placing boundary pillars in position, including digging pits. Each 30.80 - Each 30.80 -

9 Fixing main line type distance mark in position, including Each 125.40 232.50 Each 125.40 232.50 Composite rate does not include
making 1:3:6 cement concrete base block, size cost of iron distance marks.
14"x10"x15" (350x250x375 mm).

chapter-26( Misc) Page 1


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Hand Pumps & Pressure Pipes

10 Cutting pipes, upto 2" (50 mm) dia. Per cut 26.40 - Per cut 26.40 -

11 Cutting pipe, above 2" (50 mm) dia. Per cut 48.85 - Per cut 48.85 -

12 Threading pipe ends, 1½" (40 mm) to 4" (100 mm) dia. Each 34.10 - Each 34.10 -
End End

13 Assembling 1½" (40 mm) dia pressure pipe. 100Lft. 103.15 - Per Metre 3.40 -

14 Boring and fixing 1½" (40 mm) dia pressure pipe:

a) in ordinary soil Per Lft. 37.15 - Per Metre 121.80 -


b) in clay Per Lft. 25.40 - Per Metre 83.35 -
c) in shingle Per Lft. 36.55 - Per Metre 119.90 -

15 Repairs to hand pump, pulling out and refitting. Per Lft. 17.80 - Per Metre 58.45 -

16 Fixing hand pump (Machine only) Each 92.40 - Each 92.40 -

Rest House Furniture & Fuel, etc.

17 Washing Niwar of bed. Per bed 247.50 267.65 Per bed 247.50 267.65

18 Washing Durries. 100Sft. 330.00 378.00 sq.m 35.50 40.70

19 Recaning chairs:

i) office chairs, single caning seat only. Each 115.50 146.10 Each 115.50 146.10
ii) office chairs, double canning seat only. Each 148.50 191.70 Each 148.50 191.70
iii) office chairs, single caning back only. Each 82.50 84.45 Each 82.50 84.45
iv) office chairs, double caning back only. Each 132.00 148.55 Each 132.00 148.55
v) easy chairs, single caning seat only. Each 82.50 123.55 Each 82.50 123.55
vi) easy chairs, double caning seat only. Each 231.00 292.20 Each 231.00 292.20
vii) easy chairs, single caning only, back and seat in one Each 330.00 582.00 Each 330.00 582.00
piece.
viii) easy chairs, double caning back & seat in one piece Each 495.00 1,107.00 Each 495.00 1,107.00
or couches with caned area about 16 Sft (1.5 Sqm).

20 Making and fixing Hat pegs ordinary. Each 83.15 171.95 Each 83.15 171.95
21 Weaving charpoy. Each 227.35 - Each 227.35 -

chapter-26( Misc) Page 2


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

22 Sweeping chimney Each 55.00 56.20 Each 55.00 56.20

23 Picture railing, including making, fixing and painting Per Lft. 23.75 55.00 Per LM 77.90 180.40

24 Cutting fuel wood, from plantation 100Kg 73.65 - 100Kg 73.65 -

25 Splitting fuel wood 100Kg 154.30 - 100Kg 154.30 -

26 Burning charcoal, including loading, unloading and 100Kg of 250.05 - 100Kg of 250.05 -
repairing kilns. Char- Char-
coal coal

27 Filling cement bags with coal and sewing (including cos 100Cft. 676.50 679.40 cu.m 238.95 239.95
of strings).

28 Supplying manure. Cart 39.60 159.60 Cart 39.60 159.60 Capacity of cart, 20 Cft. (0.57
Load Load cu.m).

29 Washing punkha frills. Each 69.95 - Each 69.95 -

30 Washing:-

a) table cloth Each 17.50 - Each 17.50 -


b) napkins, dusters, etc Each 11.65 - Each 11.65 -

31 Hoisting and placing sleepers for centring, includin Each 32.20 - Each 32.20 -
carriage within one chain No. No.

32 Dismantling sleepers from centring, including stackin Each 33.25 - Each 33.25 -
within one chain No. No.

33 Dredging Sumps. Per 1,237.50 - Per 1,237.50 - Not less than five gangmen to be
Shift Shift employed for each shift to ensur
effective dredging

34 Fixing `U' bolt in masonry or concrete, including levellin Each 115.50 - Each 115.50 -
and tying for fixing angle iron post

35 Bailing out water:-

a) by hand 1000 Cft. 990.00 - cu.m 34.95 - Rate includes cost of providing
b) by pump 1000 Cft. 103.15 194.90 ditto 3.65 6.90 pump, POL and operation charges
etc.

36 Drilling holes in R.C. Trough Per Nos. 66.00 - Per Nos. 66.00 -

chapter-26( Misc) Page 3


MRS, 3rd QUARTER OF 2008 (July to September) DISTRICT FAISALABAD

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

37 Supplying and laying polythene sheet over D.P.C. unde The rate includes overlaps
floors and on roofs, etc

i) 300 gauge (.003" thick) Per Sft. 0.55 1.15 sq.m 5.65 12.50
ii) 500 gauge (.005" thick) Per Sft. 1.05 2.00 sq.m 11.30 21.35

38 Laying 2" (50 mm) thick sand and bitumen carpet, on top 100Sft. 758.05 4,032.55 sq.m 81.55 433.90
of foundation of oil tank.

39 Cutting hole 4"x6" (100x150 mm) in stone masonry or Per 132.00 - Per 132.00 - Same rate to be paid for other type
brick wall with chisel, repairing masonry and removing Hole Hole of masonry and R.C.C. work.
debris within one chain lead.

40 Making 1½"x1½" (40x40 mm) groove in wall of stone or Per 115.50 - Per 115.50 -
brick masonry in cement for fixing planks upto 9" (225 Plank Plank
mm) deep.

41 Drilling holes in stone or brick masonry upto 2" (50 mm) Per hole 33.00 Per hole 13.20
dia, per inch (25 mm) depth. per inch per c.m
depth depth

42 Spraying anti-termite liquid mixed with water in the ratio of 100Sft. of 11.20 92.70 sq.m of 1.20 10.00
1:40. each each
spray spray

43 Providing and fixing barbed wire fencing, with 4 horizontal


and two cross wires, with R.C.C. 1:2:4 posts, 5.5'x6"x9"
(1.68mx150mmx225 mm) at 8 ft. (2.45 m) centre to
centre, reinforced with 4 No. 3/8" (10 mm) dia vertical bars
and 1/8" (3 mm) dia stirrups 12" (300 mm) centre to
centre, complete in all respects.

i) without cement concrete base. 100Rft. 3,913.40 16,433.30 Per Metre 128.35 539.00
ii) in cement concrete 1:4:8 base of size 12"x12"x21" 100Rft. 4,294.40 17,848.10 Per Metre 140.85 585.40
(300x300x525 mm).

chapter-26( Misc) Page 4