Professional Documents
Culture Documents
Clarification To Blue Matrix
Clarification To Blue Matrix
1)Could you also please verify if Mr Fetene if he has some experience in water harvesting?
Water Harvesting
Construction of Kobo sand dam construction at Fentalle woreda about 4km from
Metehara town Designed by MS Consultancy. The scheme is to designed to collect
flood by series of four sand dam and collected at 50 m3 sandwich masonry
reservoir located at downstream of the dams by gravity. By chance I have
presented the physical model of the project on international conference on ground
water in Ethiopia held at Economic Commission of Africa by that time.
Additionally, I have managed different small scale roof water harvesting schemes,
when I was at Gudina Tumsa Foundation.
The other one is I have designed and supervised Kori small scale rock fill dam
(Cyclopean Concrete) located at Afar Region Zone one Kori Woreda, as the
project was turnkey Project. The project is to harvest the seasonal flood for the
cattle of the pastoralist.
Question #2
Especially the latest position is very brief – it would be helpful if Mr Fetene could specify his
responsibilities and personal contributions to the listed points. In particular the Tender
documents: what was he designing, revising? What kind of tender documents – what is being
tenderd, what was his task, what was the reques/result of this task and was it the only time he has
elaborated tender documents, if not, kindly ask him to mention when else he was involved in the
elaboration of tender documents.
When I was at Afar Water Works Construction Enterprises I have participated and managed
different procurement works which includes procurement for goods and works. As there was a
multiple construction project, we were working on subletting part or whole of our projects to
different sub-contractors. Being as chief engineer and later as head of Construction Department I
have been engaged on different tender and bid process of works.
Question #3
When he states Capacity Building: what is his task? Who did he train? For which purpose, how
long, who participated, how many people participated, what were the topics, which were the
methods that he applied, has he produced didactic material, where were the Capacity building
activities held? This logic would need to be followed for anything stated in the CV.
At different level of Experience and working environment (Design and Or Construction) I have
been working on Knowledge transferring and Backing up Junior engineers so that they had
confidence professionally. Basically, when you are a team leader or works as the most
responsible person for specific work you need to capacitate your works because it is their
contribution that is summed together for your achievement. To get the ultimate achievement the
shortest way is to train inform backup the by your self if you have the skill and time the second
one is to make them trained by certified institutes or professionals. But most of the time it is
difficult to train construction professionals on duty which will hinder the site work and other
other hand it is also difficult certified professionals to site camps since they are not welling to
take the challenge. So I most of the time do the training by my self specially on contract
management and construction supervision areas. Here under I describes some of my experience
on the issue
1) At Design Environment
When I was working for Afar Design and Supervision Works, I had a commitment on my job
description to train support backup and supervise Junior Engineers. During that time, I have been
doing all formal and non-formal training and capacity building on design process of water
supply, Irrigation Design, Road Design theories and concepts, practical design works flow in
combination with different appropriate design software’s out of which
Bentley Water GEMS/CAD Water Hammer
Network Building
Drawing Elements
Loading Elevation Data
Alternative and Scenario Creation
Running Model
Reviewing and Analysis
Publishing Result
AutoCAD Civil 3D
Importing Surveyed Points
Creating Surface Model
Creating Alignment
Creating Surface Profile
Creating Design Profile
Creating Typical Cros section/ Sub Assembly
Creating Sample Line
Creating Corridor model (Bringing together the Horizontal Alignment, the Vertical
Alignment (Profiles Surface and Design) and the typical Cros section the creating the 3D
model
Creating Cros section Sheet
Creating Quantity take off
Plan Production (Publishing Plan Profile and Cros section Sheet)
2) At Construction Environment
Capacity Building for professional engaged in construction site works,
Process from site taking over on
Construction planning material breakdown, scheduling
Surveying work,
Method statement preparation,
Take off preparation,
Construction time management,
Construction time management,
Construction Claim Management
Construction Change Management ( Variation )
Contract administration,
Payment preparation and overall project management
Project Clause out Preparation
Question #4
When he stated Contract management and Construction supervision: please say which sort of
contracts he managed, I suppose it was the contracts with service providers? If yes, please say
which services. If is was for goods, please name the goods, and also the contract volume. When
Construction supervision is a key task, then it is interesting to know how many people were
working on the construction site, is it possible to state specific sub-tasks, what is being
supervised?
About Types of Contracts
As I have stated above in the previous question related to tender, I have managed contract related
to goods and works too. Contracts related to goods are mainly procurement for construction
materials and Electro Mechanical equipment’s like cement, rebars, Pumps (Surface and
Submersible), Generators, and other building materials. When I was at Pastoral Community
Development Project (PCDP) I also engaged on procurements of Heelpost Materials and Tools,
Schools furniture’s and tools.
On the other hand, I have worked on Contract related to works specially when I have worked for
Afar Water Works, by subletting different construction projects to different sub-contractors in
the area.
Number of Staffs I have Supervised
At different levels of experience, I have managed and supervised different size of works. For
instance, when I was working as
Site Engineer I managed from 10 to 20 Skilled and Semi-skilled personnel
Project Manager I managed about 50 personnel’s out of which about 10 are skilled
professionals
As Head of Construction Division more than 200 works were during under my
department out of which more than 10 highly professional Engineers, about 30 juniors to
graduate engineers, about 30 professionals on Administration and Finance area working
at different construction Sites. This number may not include temporary workers hired at
site level.
1) At Design Environment
Completed Design and Supervision of construction of Gewane Town Water Supply
Projects which is owned by the Afar National Regional State (SDG ) and AfWWCE as a
contractor . Located at Zone 3, Afar NRS, whose first Phase Project Cost is about
375,000,000 Birr Three hundred seventy-five Million Birr after expansion the
overall project cost goes up 500,000,000 Birr.
Completed Design and Supervision of construction of Genu Multi Village Water Supply
Projects which is owned by the Afar National Regional State (SDG) and AfWWCE as a
contractor. Located at Zone 4, Afar NRS. Whose Project Cost is about 41,000,000 Birr
Forty-One Million Birr
Completed Design and Supervision of construction of Ayshet Multi Village Water
Supply Projects which is owned by the Afar National Regional State (SDG) and
AfWWCE as a contractor. Located at Zone 2, Afar NRS. Whose Project Cost is about
67,000,000 Birr sixty-seven Million Birr
Completed Geometric Design of DC 1 ERA Design standard one road from Afar
National Region State Palaces to Semera Air Port.
2) At Construction Environment
As a Project Manager Completed Construction of 530 Ha Pasture Irrigation Land
Development Projects which is owned by the Ministry of Water Resource and AfWWCE
as a contractor. Located at Zone 1, Afar NRS. Whose Project Cost is about 78 ,000,000
Birr Seventy Eight Million Birr.
As a Project Manager Completed Construction of 1521 Ha Pasture Irrigation Land
Development Projects which is owned by the Ministry of Water Resource and AfWWCE
as a contractor. Located at Zone 1, Afar NRS. Whose Project Cost is about
156 ,000,000 Birr One hundred fifty six Million Birr
The mentioned ESIA study, did he conduct it by himself? With who did he
collaborate, what was the result, what was his specific taks, any prior assessments,
which regulations were being followed/monitored, … more details will strengthen
the list of tasks of the first position.
All projects should take the following in environmentally sensitive areas activities
irrespective of the nature of the project. Sensitive areas may include: