Slick Line Rig Up
Slick Line Rig Up
Slick Line Rig Up
INS-003679
Rev no. 5.0
Rig Up Drawing
Tree
Location Taqa Bergermeer Well Number BGM-28 Connection 9 1/2" 4ACME
Size & Type
Tree Maximum
Job slickline Date Working
Description Pressure
Hydraulic Stuffing Box c/w 0.125" c/w 6 5/16”bwn 10000 0.00 1.00
Chemical Injection Sub 6 5/16 6 5/16”bwn 3.000 10000 0.50 0.50
Xover 6 5/16" x 9 1/2" Otis 6 5/16” x 9 1/2" 3.000 5000 0.30 0.30
Xover 9 1/2" x 9 7/8" P/C 9 1/2 x 9 7/8 6.375 5000 0.50 0.50
9 7/8" In-Situ test sub 9 7/8" bwn 6.375 5000 0.65 0.65
Xover 9 7/8" x 9 1/2" p/c 9 7/8 x 9 1/2 6.375 5000 0.40 0.40
Deck Height
Ported 8FT Lubricator 9 1/2" 9 1/2" Otis 6.375 5000 2.44 2.44
Total length of riser section between Wireline Valve and Tree Valves = 3.54m
Conflict with Tool-string straddling Wireline
Valve and Xmas Tree Valves
Safety Gap - between Wireline Valve and Tree Valves = -7.46
1000 Kilograms (KG's) = 1 Tonne
1 Tonne = 2204 lbs
Enter Maximum Toolstring Length = 11.00m 1 Metre = 39.36 Inches
1 Metre = 3.2803 Decimal Feet
12 Inches = 1 Foot