Professional Documents
Culture Documents
A1-Ped-Paq-008 Empty Box
A1-Ped-Paq-008 Empty Box
EMPTY BOX
MAINTENANCE
PROCEDURE A5
A1-PED-PAQ-008
V1.0
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
Index
1. OPERATIVE / FUNCTIONALITY.................................................................................................................................................. 2
2. PROCEDURE REVISIONS.......................................................................................................................................................... 8
1
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
1. OPERATIVE / FUNCTIONALITY
The purpose of this procedure is to describe the process/route the boxes follow when they arrive to Empty Box Area (.
2
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
☐ STEP 01
Operators lift pallets full of empty boxes from the ground floor to the third floor using one of
the two elevators.
☐ STEP 02
Operators load the new cartons in the Lantech box maker (Id. 20184616) located third floor.
This machine erects boxes automatically, thus feeding the system with new boxes.
☐ STEP 03
Zetes MD1500
A labelling machine (Zetes MD1500) attaches a barcode label to identify each box and then a
scanner reads it to enter the code into the management and control system.
☐ STEP 04 The new empty boxes continue along a single line of the Knapp system (roller and belt
3
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
To lower
level
conveyors) leaving the third floor in the direction of the sorters (first floor).
☐ STEP 05
Before the empty boxes reach the first floor, they circulate through the intermediate platform
located on the first floor.
These come by a single line and this is where they are divided into three different routes
To To To depending on which classifier you have to supply.
Sorter 3 Sorter 2 Sorter 1
☐ STEP 06
New empty boxes are finally lowered into the corresponding sorter on the first floor via two
Knapp belt conveyors.
☐ STEP 07
Once the boxes arrive at the sorter, they circulate in a loop on both sides of the sorter, until
the operators take them manually to place a new empty box at the destination chute.
☐ STEP 01 The empty boxes reach the third floor from the sorting machines (See previously A1-PED-
PAQ-007 DISTRIBUTION SORTER CONNECTION WITH EMPTY BOXES) once they are
4
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
☐ STEP 02
Used empty boxes can be directed to two different checking stations on the third floor.
Both have the same function and are made up of the same equipment.
☐ STEP 03
Boxes arrive at one of the two areas where they receive the first inspection. In each of these
areas there are four checkpoints.
☐ STEP 04
At each inspection station, an operator visually checks the status of each box and decides
where it should be sent by pressing the corresponding button on the control panel:
☐ STEP 05 Boxes that can be reused are sent to the sorters in the same way as new ones.
5
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
☐ STEP 06
The boxes that are not in good condition and cannot be reused are sent to the carton trash
located on the ground floor.
The boxes of the different inspection agencies are united in a single line. This runs a long
distance on the third floor via Knapp roller conveyors.
☐ STEP 07
The boxes are lowered by a belt conveyor from the third floor to the first floor. At this level the
boxes continue on roller conveyors until they take the Nerak box elevator.
☐ STEP 08
The boxes leave the Nerak elevator on the ground floor and circulate on the Knapp
conveyors until they reach the garbage containers.
☐ STEP 09 Boxes that are not damaged but cannot be reused directly are sent to the check stations to
be checked manually by the operators.
6
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
The boxes arrive at each check station via two rollers located at a low level and exit via a
conveyor belt that rises to a high level.
☐ STEP 10
There are two check stations in each empty box management area. There operators check
visually boxes damaged and they repair them if is possible.
Repaired boxes will be joined on the route followed by the reused boxes (See Step 05).
Damaged boxes that cannot be repaired will join the trash route located on the ground floor
(See Step 06).
MAINTENANCE
☐ STEP 01
7
A1-PED-PAQ-008
EMPTY BOX Date: 25/09/2020
Version: 1.0
2. PROCEDURE REVISIONS
REVISIONS
APPROVAL