(Standards Cutoff Date -May, 31, 2016) Rev 1

SAC TYPICAL INSPECTION PLAN SACTIP No. APPROVED DATE DISCIPLINE:

Precast Concrete at Fabrication Yards SACTIP-Q-001-05 7-Jan-20 CIVIL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES 25-00053,0004,0005, 0006, CONSORTIUM of BRANCH OF SINO HYDRO CORPORATION COMPANY
AND SERVICES (MYP) PACKAGE # 4, 5 & 6 0007/6600042823 (IK) LTD. and SEPCO ARABIA COMPANY

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CONTRACTOR
ARAMCO

1.0 DOCUMENT REVIEW

Contractor - "RH" of Documents and "H" for Material


Sampling and Testing during mix design preparation
stage.
Raw Materials Sampling Testing and
1.1
Concrete Mix Design Approval
SACIC-Q-1006 SACIC-Q-1006 RH/ H RH/ H S.ARAMCO - "RH" of Documents and "H" for Material
Sampling and Testing for Mega Projects during mix design
preparation stage and "W" on other Projects.
Refer to SACTIP-Q-001-02

Project
The 3rd Party Civil Testing Lab & personnel’s shall be
Approval of 3rd Party Civil Testing Lab & Specification
1.2
its personnel’s
SAEP 383
RE-614005 RH RH approved to comply the requirements of SAEP-383 (Sec.
7.1, 8.1)
Rev. 0

Project
Approved Project Specifications, Project
Specification
1.3 Scope of Works and IFC Drawings/Shop Schedule Q
RE-614005 RH/H R
Drawings.
Rev. 0

Special
Approved Special Process Procedure for Process
1.4
Precast Works
Schedule Q
Procedure for RH RH
Precast Works

RECEIVING
2.0
INSPECTION

FBE Rebar & Embedments Receiving


2.1
Inspection
SACIC-Q-1007 SACIC-Q-1007 H W Refer to SACTIP-Q-001-02

Contractor QC - Witness every inspection request. S.


Handling, Storage & Preservation of FBE ARAMCO - Witness first delivery and once every 5
2.2
Steel Bars Inspection
SACIC-Q-1008 SACIC-Q-1008 I S occurrences.
Refer to SACTIP-Q-001-02

Contractor QC - Witness every inspection request.


S. ARAMCO - Witness first two deliveries and once every
2.3 Concrete Pump/Transit Mixer Inspection SACIC-Q-1010 SACIC-Q-1010 I S 5 occurrences.
Refer to SACTIP-Q-001-02

Saudi Aramco: Company General Use


Page 2

(Standards Cutoff Date -May, 31, 2016) Rev 1

SAC TYPICAL INSPECTION PLAN SACTIP No. APPROVED DATE DISCIPLINE:

Precast Concrete at Fabrication Yards SACTIP-Q-001-05 7-Jan-20 CIVIL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES 25-00053,0004,0005, 0006, CONSORTIUM of BRANCH OF SINO HYDRO CORPORATION COMPANY
AND SERVICES (MYP) PACKAGE # 4, 5 & 6 0007/6600042823 (IK) LTD. and SEPCO ARABIA COMPANY

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CONTRACTOR
ARAMCO

2.4 Receiving Inspection - Anchor Bolts SACIC-Q-1018 SACIC-Q-1018 H W Refer to SACTIP-Q-001-02

Precast Ready Mix Concrete Receiving


2.5
Inspection
SACIC-Q-1019 SACIC-Q-1019 I W

3.0 INSTALLATION

Precast Concrete Formwork and Mould


3.1
Inspection
SACIC-Q-1020 SACIC-Q-1020 H H

All other trades embedded items shall be inspected and


accepted by respective discipline. Clearances shall be
Precast Concrete FBE Reinforcing Steel,
provided to Civil Inspector and attached in the RFI for
3.2 Embedded Items, and Form Closure SACIC-Q-1021 SACIC-Q-1021 H H Project Inspection to proceed his inspection to ensure all
Inspection
embedded items are acceptable for the next level of
activities and inspection

All other trades embedded items shall be inspected and


accepted by respective discipline. Clearances shall be
Precast Concrete Sampling, Testing & provided to Civil Inspector and attached in the RFI for
3.3
Placement Inspection
SACIC-Q-1022 SACIC-Q-1022 I W Project Inspection to proceed his inspection to ensure all
embedded items are acceptable for the next level of
activities and inspection

Precast Concrete Finishing and Curing


3.4
Inspection
SACIC-Q-1023 SACIC-Q-1023 I S

Precast Concrete Formwork Stripping


3.5
Inspection
SACIC-Q-1024 SACIC-Q-1024 I W

Visual Inspection of Pre-cast Concrete for


3.6
Verification of Repair
SACIC-Q-1025 SACIC-Q-1025 I W

Contractor - "H" for Final Inspection & Material Testing.


S.ARAMCO - "H" for Final Inspection & Material Testing
Precast Concrete Compressive Strength
3.7
Testing Inspection
SACIC-Q-1026 SACIC-Q-1026 H H/ W for the first 2 batches and once every 5 batches thereafter
on Mega Projects. "W" for Final Inspection and Testing for
other Projects.

Saudi Aramco: Company General Use


Page 3

(Standards Cutoff Date -May, 31, 2016) Rev 1

SAC TYPICAL INSPECTION PLAN SACTIP No. APPROVED DATE DISCIPLINE:

Precast Concrete at Fabrication Yards SACTIP-Q-001-05 7-Jan-20 CIVIL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES 25-00053,0004,0005, 0006, CONSORTIUM of BRANCH OF SINO HYDRO CORPORATION COMPANY
AND SERVICES (MYP) PACKAGE # 4, 5 & 6 0007/6600042823 (IK) LTD. and SEPCO ARABIA COMPANY

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CONTRACTOR
ARAMCO

Precast Concrete Final Acceptance


3.8
Inspection
SACIC-Q-1027 SACIC-Q-1027 H H/ W

Contractor - "RH" of Documents and "H" for quality control


during implementation.
3.9 Repair of Major Defects Inspection SACIC-Q-1028 SACIC-Q-1028 RH/H RH/H S.ARAMCO - "RH" of Documents and "H" for inspection
during implementation.

Precast Post Concreting and Final


3.10 Inspection Prior to Release from SACIC-Q-1029 SACIC-Q-1029 I W
Fabrication Yard/Plant

4.0 PRE-COMMISSIONING

4.1 Not applicable

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of
1 Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3 I : 100% participation by Contractor QC Inspector for Inspection/Test
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not
4 present.

5 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

6 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection