Professional Documents
Culture Documents
Well Sinking
Well Sinking
0 Cross References:
. MoRT&H Specification for Road and Bridge Works ( Sth Revision)
.r Contractspecifications.
The initial survey will be carried out in the area of bridge, and controls
carried out at the well location as per the available soil profile data.
Steel formwork shall be made at the fabrication yard as per concrete section
used for two adjacent wells for well stening. Wherever three wells are tackled
by one crane, 2sets of shuttering will be provided.
Curb casting is followed after cutting edge placing. After curb ca$ting, curb will
be sunk upto it's partial height. Stening & sinking will be alternately carried out
drawing wherever required. Bottom plug will be done only after final checking
of tilt and shift. When the bottom plug of concrete has attained the required
strength, sand filling will be done. lntermediate plug with water filling will be
done as per drawing.
3.2 Detailedmethodology:
r Setting Out
. Cutting Edge
. Preparation of Area
. Well curb
r Well Stening and Sinking
. Plugging Of Well And Well Cap
Necessary reference points shall be fixed by total station from control points.
The distance, whenever practicable, shall be checked with the help of
accurate tapes and precision Distomat. Reference points shall also be fixed to
mark X-X axis (usually traffic direction) and Y-Y axis (normal to X-X axis)
accurately. A temporary bench mark shall also be established near the bridge
site. The bench mark shall be checked regularly with respect to the
. Well on land: - lf the wells are to be constructed on land, the area will be
a Wells in water (Above 3m): - Area will be filled with sand forrning island
including approaches to the well with the support of ballies piling and sand
bags protection to avoid the erosion of filled soil.
. Accurate survey shall be carried out by Total Station for fixing the well
locations.
. Fermanent reference pillars are to be provided at the four sides i.e. along
trailer.
. Cutting edge is placed over wooden sleepers using crane aligned and
. Level and alignment of cutting edge shall be checked finally using the
established horizontal controls. lf required minor rigid bracings are
r Dowel bars shall be fixed to cutting edge and as per approved drawing.
. lnner form panels are first cleaned and standard form releasing agent is
applied on form surface.
To make the shutter joints leak proof suitable foam sheets between
shuttering joints and/or masking tape at joints are used to seal the joints.
a lnner formwork shall be erected and all the form panels shall be joined to
form the true shape as per the concrete profile, horizontal and diagonal
supports erected
to maintain cover along ihe periphery of formwork and also at the bottom
r Outer vertical bars shall be welded with angle. All other reinforcement bars
along with any stiffeners / spacers are fixed in position as per the drawing
and approved bar bending schedule.
. The rebar shall be checked by section-in-charge (structures) of Epc.
. Acces's platform using landing mats are provided for inspection and
concrete purpose.
3.2.4.3 Concreting:
. concrete shall be done by crane and bucket or pump as per the
availability.
the laitance) using hard steel and/or nylon brushes before the final setting
is over at each joint to receive the succeeding lift of concrete.
3.2.4.4 Curing:
r Curing will be done by spraying water on surface covered with Hessian
cloth.
. After removal of inner form panel, gunny bags filled with sand shall be
cutting edge.
. Grounding of the curb will be done after removing the inner forms. lnner
r The curb shall be sunk to the ground keeping curb top approximately one
meter above the ground level by dredging using crane and bucket.
. 3.0 mm thick foam sheet adhesive tape at the location of joints are used to
r Form releasing agent shall be applied on the inner face of the panels
. Coil anchorslnuts, which are to be embedded in concrete for erection of
. The inner form panels are erected. For the subsequent lifts, the formwork
is supported on the coil nut arrangement with the bottom lift concrete. The
re-bars are fixed in position followed by fixing of outer formwork. Over the
mats.
(structures) of EPC
. Re'bars are cut and bent at the central rebar yard as per the approved bar
. Re-bars are fixed as per the drawings and bar bending schedule
. Adequate cement concrete cover blocks shall be provided along the
3.2.5.3 Concreting:
3.2.5.4 De-shuttering:
The inner and outer form panels are removed after setting of the concrete
finished time.
3.2.5.5 Sinking:
Following the de-shuttering of stening lift, gauge marking is carried out at both
axes in line with well curb marking and reference height is marked on the wall
surfaee. Sinking of wells will be carried out by the dredge hole method by
using either of following methods:-
dredge hole.
. Plate grab shall be used in case of soft strata like sandy silt, soft clay,
sinking to observe the tilt and shift of the well at closer intervals if the
r Sinking operation shall preferably carry out round the clock under skilled
supervision.
The above cycle of well stening and sinking shall be repeated up to the last lift
of the well until well reaches to the founding level.
. Very deep sump shall not be made below the well curb. The depth of
sump shall not exceed 2.0m below the level of cutting edge unless
r The dredging operation will be carried out uniformly over the dredge hole
area. When the minor tilt and / or shift occurs, the same shall be corrected
ln this method, wooden sleepers are kept under lower side of well from inside
and dredging is done on higher side of the well.bringing again well to it's
verticality. For further sinking, the wooden sleepers are to be removed. This
method can be applied only in the very initial stage of the well.
ln this method, hooks are provided for holding the wire rope of winches on the
tilted face of stening. Winches are anchored on opposite direction of tilt. The
winch pulls the well and simultaneous dredging at the other side of the tilt is
carried out.
Tilt and shift shall be monitored by checking the levels at fixed gauge mark on
both of the opposite faces along axes of the well. Levels are checked from the
reference pillars along the axes established in advance for this purpose. fhe
difference in level will establish the tilt along the axis. lt is designated as ratio
of difference in level to dia of well. Such checking and recording of tilts and
shifts are done at regular intervals depending upon the rate of sinking but at
least onoe a day, provided there has been sinking of the well
. False Stening
. Bottom Plug
. $and Filling
. lntermediate Plug
. Water Filling
. Well Cap
When the well reaches to the founding level bottom will be cleaned and
sludge / loose material will be removed. Bottom plug concreting will be done
After the bottom plugging and waiting period, sand filling will be started. Sand
from the Teesta river will be filled in dredge hole after 3 days of bottom plug
concrete up to required level.
3.2.6.4 lntermediate plug:
lntermediate plugging , if any, will be carried out after sand filling as per
drawing.
3.2.6.s Water filling:
documents.
7.0 Distribution:
The document shall be distributed to allthe concerned users.