Appendix Y-PR - ltd.003-OvertCovert Security Test
Appendix Y-PR - ltd.003-OvertCovert Security Test
Document Title:
Appendix “Y” - PROCEDURE ON LAND TRANSPORTATION SYSTEM SECURITY TEST
(COVERT/OVERT)
Prepared by: Recommending Approval: Approved by:
To provide guidance to OTS National Land Security (LANDSEC) Auditors for the standard preparation
and conduct of a security test.
2.0 Department/ Unit:
Land Transport Security Division - Transport Security Oversight & Compliance Service (LTSD-TSOCS)
3.0 Definitions:
Compliance Monitoring Activities (CMA) – the conduct of security audit, inspection, testing, drills, and
exercises, to ensure implementation of the prescribed security standards and policies by OTS.
Corrective Action Plan (CAP) – refers to the plan of action that will be carried out to immediately rectify
the deficiencies or identified non-compliances.
Interim Findings Report (IFR) – a summarized audit findings and recommendations shared with the
stakeholder during the post-inspection meeting. IFR is the basis of the final audit report.
Land Transportation Security Plan (LTSP) – a plan developed to describe and ensure the application
of measures designed to protect the land transportation system from acts of terrorism and acts of
unlawful interference. LTSP may refer to any of the following: Bus Operator Security Plan (BOSP), Bus
Terminal Security Plan (BTSP), Integrated Terminal Exchange Security Plan (ITXSP), Rail Security Plan
(RSP), Tollway Security Plan (TSP)
Security Test – a simulated act of unlawful interference against existing security measures
carried out covertly or overtly to demonstrate whether the security controls were effective as it
were being applied at the place and time of the test .
4.0 Reference: (Organization Knowledge)
5. Revision History:
Process Map
Yes
Coordinate with target stakeholders Testing Team Letters Approved Security Test None
if overt testing (4 hours) Deployment Plan
Conduct Exit Brief (30 minutes) Team Leader; Standard Testing IFR; Testing Materials Availability of
Testing Team; Report Matrix stakeholder;
Stakeholder Availability of venue
Prepare Security Test Report and Testing Team Testing Final Approved Memo; Travel None
Report and Order; Mission Order;
Mission Report (2 hours)
Mission Report; Testing Deployment
CAP Template Plan; IFR;
CMA Database;
Testing Materials
Review the submitted Corrective Testing Team; None Submitted CAP Stakeholder delays
Action Plan (2 hours) Section Chief submission of CAP
Refer to PR.LTD.2019.002
Conducts on-site
TOTAL: 5 days: 17 briefing
hours (1 day)