SCHEDULE DRAWING

NAME PROJECT : JCI BALI


LOCATION : JL. GATOT SOEBROTO – DENPASAR

Estimated Actual
Actual Start
NO DRAWING NAME KODE Completion Completion Comments
Date
Date Date

1 PETA LOKASI LCP 001


2 SITE PLAN LCP 002
3 DENAH LANTAI 1 AR 001
4 DENAH LANTAI 2 AR 002
5 DENAH LANTAI 3 AR 003
6 DENAH LANTAI 4 AR 004
7 DENAH ROOF GARDEN & MEZZANINE AR 005
8 DENAH ROOF & HELIPAD AR 006
9 TAMPAK A AR 007
10 TAMPAK B AR 008
11 TAMPAK C AR 009
12 TAMPAK D AR 010
13 POTONGAN A-A AR 011
14 POTONGAN B-B AR 012
15 POTONGAN C-C AR 013
16 POTONGAN D-D AR 014
17 POTONGAN E-E AR 015
18 POTONGAN F-F AR 016
19 POTONGAN G-G AR 017
20 POTONGAN H-H AR 018
21 POTONGAN I-I AR 019
22 DENAH FINISHING LANTAI 1 AR 020
23 DENAH FINISHING LANTAI 2 AR 021
24 DENAH FINISHING LANTAI 3 AR 022
25 DENAH FINISHING LANTAI 4 AR 023
26 DENAH FINISHING ROOF GARDEN & MEZZANINE AR 024
27 DENAH FINISHING ROOF & HELIPAD AR 025
28 DENAH PLAFON LANTAI 1 AR 026
29 DENAH PLAFON LANTAI 2 AR 027
30 DENAH PLAFON LANTAI 3 AR 028
31 DENAH PLAFON LANTAI 4 AR 029

DETAIL LANTAI 1
33 DETAIL LOBBY LIFT AR 030
34 DETAIL TOILET DAN MUSHOLLA AR 031
35 LAYOUT AKSES MASUK DEPAN AR 032
36 DETAIL PARKIR MOTOR SISI BARAT & TIMUR AR 033
37 DETAIL PAGAR SISI SELATAN, BARAT & TIMUR AR 034

DETAIL LANTAI 2
37 DETAIL LOBBY LIFT AR 035
38 LAYOUT AKSES MASUK BELAKANG & ROOF GARDEN AR 036
39 DETAIL PAGAR BELAKANG (SISI UTARA) AR 037

DETAIL LANTAI 3
40 DETAIL TOILET LT.3 AR 038

DETAIL LANTAI 4
41 DETAIL TOILET LT.4 AR 039
42 DETAIL RUANG LAKTASI AR 040