Backfilling Cost for Unloading TBM -Outfall

Volume
Zones (Between
S Internal Walls) Area Depth Volume

1 1-5 30.9 2.5 77.25


2 5-6 22 3.5 77
3 6-7 24.5 4.5 110.25
4 (7-8)+Ramp 22.7 6 136.2

Total Vol (m3)= 400.7

Cost of Backfilling (Mahmoud Al Obaidi Loader) = 600 JD

Cost of removal Backfilling & spread it in the river bed (Mahmoud Al Obaidi Excavator) = 400 JD

Cost of final cleaning by labors = 350


Total Cost = 1350 JD
Cost of Unloading TBM - Pre-cast Platform Method-Outfall
S Item Cost Details Cost (JD) Remarks
1 Extra Rebar
W4=10.1*2/0.125*1*(2*2*0.617*0.7=280JD
Reinforcement steel 728 development steel
W5=262 JD, W6= 186 JD
Coupler (161+107+151)*6.56+(60 JD logestic) 2808 coupler price = 6.56
Total JD = 3536

2 Platform (Pre-cast Concrete)


Rebar 1283 1283 As per attached design
Concrete (13.2+3) m3*75 1200 slab + wing walls
Installation Around 135 JD 135
De-Installation Around 135 JD 135
Total JD = 2753

3 Crushed Stone
Coarse Aggregate 0.3*8*5*4 + (30 JD Loader) 78
Total JD = 78

Total Cost JD = 6367