SUBSTATION READY FOR

PRE-COM ACTIVITY SCHEDULED MANDATORY REQUIREMENT FOR FIRST ENRGIZATION


CURRENT STATUS DATE OF
TAG PRE-COM
START DATE END DATE ENERGIZATION CABLE TERMINATION BATTERY ROOM LIGHTING HVAC F&G DOORS & ROOF

SS01 UNDER CIVIL NO NIL NIL 31-Aug-23 24-Aug-23 31-Jul-23 21-Aug-23 24-Aug-23 21-Aug-23

SS10 UNDER CIVIL NO NIL NIL 11-Sep-23 4-Sep-23 11-Aug-23 1-Sep-23 4-Sep-23 1-Sep-23

SS10E UNDER CIVIL NO NIL NIL 11-Sep-23 4-Sep-23 11-Aug-23 1-Sep-23 4-Sep-23 1-Sep-23

SSA READY TO START PRE-COMM YES 18-Jul-23 28-Jul-23 16-Sep-23 9-Sep-23 16-Aug-23 6-Sep-23 9-Sep-23 6-Sep-23

SSB READY TO START PRE-COMM YES 26-Jun-23 21-Jul-23 15-Sep-23 8-Sep-23 15-Aug-23 5-Sep-23 8-Sep-23 5-Sep-23

SSC READY TO START PRE-COMM YES 26-Jun-23 11-Jul-23 18-Sep-23 11-Sep-23 18-Aug-23 8-Sep-23 11-Sep-23 8-Sep-23

SSD READY TO START PRE-COMM YES 26-Jun-23 16-Jul-23 17-Sep-23 10-Sep-23 17-Aug-23 7-Sep-23 10-Sep-23 7-Sep-23

SSE READY TO START PRE-COMM YES 22-Jul-23 1-Aug-23 19-Sep-23 12-Sep-23 19-Aug-23 9-Sep-23 12-Sep-23 9-Sep-23

SSF READY TO START PRE-COMM YES 12-Jul-23 27-Jul-23 20-Sep-23 13-Sep-23 20-Aug-23 10-Sep-23 13-Sep-23 10-Sep-23 NOT APPLICABLE

Page 1 of 1