Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

BRIDGSITE NIGERIA LTD

PHRC TECHNICAL BUILDINGS REFURBISHMENT WORKS


REPORT OF ONSITE/OFFSITE ACTIVITIES (_1/6/2023)
1. HSSE
Daily Tool box meetings was carried out by each work group for their personnel prior to
commencement of any work on site on the topic “TEAM WORK”.
 Daily Man-hour = 290hrs
 POB = 29 persons worked for 10 hours
 Cumulative Man-hours = 7,170hrs.

2. ENGINEERING

 Development of Method Statements and deliverables ongoing


 Submission of Method Statements and deliverables ongoing

3. MOBILIZATION/OFFSITE CONSTRUCTION ACTIVITIES

A.

B. Equipment maintenance:

4. ONSITE CONSTRUCTION ACTIVITIES

A. TCF

B. DISMANTLING/REMOVAL ACTIVITIES
 Marking of floor cutouts in SS1continued.
 Demolition/cutting of floor cutouts in SS1 continued
 Protection of cables in cable cellar continued
 Tracing, Retrieving and removal of electrical cable in control room continued
 Demolition of wall tiles in SS1 continued
 Dismantling of HVAC in 2nd floor continued.
 Lighting fittings dismantling and retrieving of cables in SS10 continued.
 General house keeping in SS10.

5. PROCUREMENT ACTIVITIES

A. Sourcing of Materials
 Continuation of contacting vendors for availability and supply of
materials.
 Procurement of tools and equipment continued.

6. QA/ QC

Nil

7. EQUIPMENT
 Grinding machine = 3 number
 Compressor = 1
 Jack hammer = 1
 Drilling machine = 1
 Ladder = 5
 16KVA diesel generator = 1
 Expeller = 3
 Floodlight = 9
 Industrial fan = 3
 Nissan bus = 1
 Concrete cutting machine = 2
 Toyota Sequoia SUV = 1

8. WORKING TOOLS
 Head pan = 4 number
 Hammers = 3 numbers
 7.5-meter measurement Tape = 3 numbers
 Screw drivers
 Pincers
 Spanners
 Set of electrical tools
 Hacksaw 1
 Shovel = 2
 Builder’s square
 Blue line

9. LOOK AHEAD
 Dismantling of HVAC
 Dismantling and demolition in SS10 and SS10E
 Cutting/demolition of floor cutouts
 Evacuation of dismantled materials and demolished debris to dump site
 Sourcing of personnel and materials for mobilization to PHRC building works.
 Conveying of more equipment to site.
 Production of documents for submission.

10. CHALLENGES
 Panels not moved out of SS1 RACK ROOM by SPIE.
 Revised floor cutout project drawings for Substation 10E not yet received.

11. ON SITE ACTIVITY.


Nil.
12. PROGRESS PICTURS

Floor cutting/Demolition in SS1

Demolition of wall tiles in 1st floor.


Floor cutting/Demolition in SS1
Floor cutting/Demolition in SS1
Retrieving of cables in SS10
General housekeeping in SS10
Dismantling of lighting fittings in transformation bay in SS10

You might also like