1ST June 2023 Onsite Offsite Activities Report
1ST June 2023 Onsite Offsite Activities Report
2. ENGINEERING
A.
B. Equipment maintenance:
A. TCF
B. DISMANTLING/REMOVAL ACTIVITIES
Marking of floor cutouts in SS1continued.
Demolition/cutting of floor cutouts in SS1 continued
Protection of cables in cable cellar continued
Tracing, Retrieving and removal of electrical cable in control room continued
Demolition of wall tiles in SS1 continued
Dismantling of HVAC in 2nd floor continued.
Lighting fittings dismantling and retrieving of cables in SS10 continued.
General house keeping in SS10.
5. PROCUREMENT ACTIVITIES
A. Sourcing of Materials
Continuation of contacting vendors for availability and supply of
materials.
Procurement of tools and equipment continued.
6. QA/ QC
Nil
7. EQUIPMENT
Grinding machine = 3 number
Compressor = 1
Jack hammer = 1
Drilling machine = 1
Ladder = 5
16KVA diesel generator = 1
Expeller = 3
Floodlight = 9
Industrial fan = 3
Nissan bus = 1
Concrete cutting machine = 2
Toyota Sequoia SUV = 1
8. WORKING TOOLS
Head pan = 4 number
Hammers = 3 numbers
7.5-meter measurement Tape = 3 numbers
Screw drivers
Pincers
Spanners
Set of electrical tools
Hacksaw 1
Shovel = 2
Builder’s square
Blue line
9. LOOK AHEAD
Dismantling of HVAC
Dismantling and demolition in SS10 and SS10E
Cutting/demolition of floor cutouts
Evacuation of dismantled materials and demolished debris to dump site
Sourcing of personnel and materials for mobilization to PHRC building works.
Conveying of more equipment to site.
Production of documents for submission.
10. CHALLENGES
Panels not moved out of SS1 RACK ROOM by SPIE.
Revised floor cutout project drawings for Substation 10E not yet received.