SDGM-Look Ahead

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Date: From To

1-Jul-23 3-Jul-23
WORK PERMIT SCHEDULE FOR SDGM FIELD

SI.N Counter Sign WP Received


O AREA WELL ACTIVITY (Mech/ E&I/CP) WP TYPE Yes or No PMT Site Eng. PMT Safety Eng. Time (Date
……………. )

1 GOSP-5 SDGM-601 (FL) 1-Manual Excavation for Pipe and FOC line Cold Gas Hajri, Faisal Alshahrani, Jarallah A

2 GOSP SDGM-272 ROW + Excavation Cold Gas Hajri, Faisal Alshahrani, Jarallah A

3 GOSP SDGM-165 Commissioning of VSAT Cold No Hajri, Faisal Alshahrani, Jarallah A

4 GOSP SDGM-539 Commissioning of VSAT Cold No Hajri, Faisal Alshahrani, Jarallah A

Classification | Saudi Aramco


REMARKS

Classification | Saudi Aramco