Download as pdf or txt
Download as pdf or txt
You are on page 1of 154

ARCHITECTURAL PROJECT SPECIFICATION

FOR
Monash Building H Level 2 Refurbishment

Document Control

Title Version Date Prepared By Approved By


Architectural Specification T1 17.11.22 JH -
Architectural Specification C1 16.02.23 JH

CONSTRUCTION ISSUE (C1)


FEBRUARY 2023
This page is intentionally left blank
MONASH BUILDING H LEVEL 2 CONTENTS 3

CONTENTS

C DEMOLITION .......................................................................................................................... 6
C1 Scope of Works ................................................................................................................ 6
C2 Site Inspection .................................................................................................................. 6
C3 General Notes................................................................................................................... 6
C4 Permits ............................................................................................................................. 6
C5 Demolition and Disposal Methods ..................................................................................... 6
C6 Services ............................................................................................................................ 6
C7 Dilapidation Report ........................................................................................................... 7
C8 Discovery of Hazardous Materials..................................................................................... 7
C9 Registered Demolition Contractor ..................................................................................... 7
C10 Security of Works.............................................................................................................. 7
E CONCRETE............................................................................................................................. 8
E1 General ............................................................................................................................. 8
E2 Construction ................................................................................................................... 10
E3 Concrete Placement ....................................................................................................... 14
E4 Existing Concrete Floors ................................................................................................. 22
F MASONRY ............................................................................................................................ 23
F1 General ........................................................................................................................... 23
F2 Blockwork Materials ........................................................................................................ 23
F3 Blockwork Workmanship ................................................................................................. 24
G CARPENTRY ..................................................................................................................... 26
G1 General ........................................................................................................................... 26
G2 Wall Construction............................................................................................................ 26
G3 Framing .......................................................................................................................... 27
G4 Insulation ........................................................................................................................ 29
G5 Wall & Soffit Linings & Substrates ................................................................................... 30
G6 Ceiling Linings ................................................................................................................ 36
G7 Caulking & Sealing ......................................................................................................... 38
H JOINERY ............................................................................................................................... 40
H1 General ........................................................................................................................... 40
H2 Windows ......................................................................................................................... 40
H3 Doors .............................................................................................................................. 41
H4 Door Schedule ................................................................................................................ 42
H6 Laminated Joinery .......................................................................................................... 44
H7 Joinery Hardware & Accessories .................................................................................... 46
H8 Skirting and Architraves .................................................................................................. 48
J GLASS AND GLAZING ......................................................................................................... 49
J1 General .............................................................................................................................. 49
J2 Glazing Materials................................................................................................................ 50
J3 Glazing and Installation ...................................................................................................... 52
J4 Completion ......................................................................................................................... 52
L ELECTRICAL ........................................................................................................................ 54
L1 Switchplate & GPO Colours ............................................................................................ 54
L2 LED Strip Light – Underside of Overhead Cabinet .......................................................... 54
L3 Whitegoods & Equipment Schedule ................................................................................ 54
L4 Audio Visual .................................................................................................................... 55
L5 Table Boxes .................................................................................................................... 55
L6 Switches and Controls on Accessible path of Travel ....................................................... 55
MONASH BUILDING H LEVEL 2 CONTENTS 4

M PLUMBING............................................................................................................................ 56
M1 General ........................................................................................................................... 56
M2 Schedule of Tapware ...................................................................................................... 57
M3 Schedule of Sanitary Fixtures ......................................................................................... 58
N PLASTERING AND RENDERING ......................................................................................... 59
N1 General ........................................................................................................................... 59
N2 Materials ......................................................................................................................... 59
N3 Accessories and Details.................................................................................................. 61
N4 Plaster Repairs ............................................................................................................... 62
P TILING ................................................................................................................................... 63
P1 General ........................................................................................................................... 63
P2 Materials ......................................................................................................................... 63
P3 Workmanship .................................................................................................................. 64
P4 Completion ..................................................................................................................... 65
Q PAINTING ............................................................................................................................. 66
Q1 General ........................................................................................................................... 66
Q2 Workmanship .................................................................................................................. 66
Q3 Paint Systems ................................................................................................................. 67
Q4 Timber Work - Clear Finishing ........................................................................................ 68
Q5 Completion ..................................................................................................................... 68
R METALWORK ....................................................................................................................... 69
R1 General ........................................................................................................................... 69
R2 Metal Ceiling & Wall Framing .......................................................................................... 70
R3 Window and Door Frames .............................................................................................. 70
R4 Aluminium Components .................................................................................................. 74
R5 Whiteboards & Pinboards ............................................................................................... 75
R6 Stainless Steel ................................................................................................................ 75
R8 Window Blinds ................................................................................................................ 76
R9 Signage .......................................................................................................................... 77
R10 Metalwork & Steelwork for Joinery .................................................................................. 78
R11 Fire Extinguishers ........................................................................................................... 78
S FINISHES SCHEDULE .......................................................................................................... 79
T STRUCTURAL STEELWORK ............................................................................................... 80
T1 Scope of Works .............................................................................................................. 80
T2 Materials ......................................................................................................................... 81
T3 Workmanship .................................................................................................................. 82
T4 Metalwork & Steelwork for Joinery .................................................................................. 85
U MECHANICAL SERVICES .................................................................................................... 86
W FLOOR FINISHES ................................................................................................................. 87
W1 Floor Preparation ............................................................................................................ 87
W2 General & Nominated Installers ...................................................................................... 87
W3 Marmoleum Flooring and Joinery Linings........................................................................ 88
W3 Carpet Flooring and Wall Linings .................................................................................... 89
W4 Tactile Indicators............................................................................................................. 91
W5 Protection upon Completion ............................................................................................ 91
MONASH BUILDING H LEVEL 2 CONTENTS 5

APPENDIX A DOOR HARDWARE SCHEDULE


APPENDIX B JOINERY COLOUR SCHEDULE
APPENDIX C FURNITURE SCHEDULE
APPENDIX D LOTUS GLAZED SLIDING DOOR
APPENDIX E ACOUSTIC REPORT

Note: Please refer also to separate specification documents issued for Electrical,
Mechanical, Fire and Hydraulic Services, and Wayfinding and Room Signage

SEPARATE DOCUMENTS
The following documents are included as separate documents to this Specification for information
to Tenderers:

• Audio Visual Documentation

NOTE:
• Revisions are highlighted in yellow.
MONASH BUILDING H LEVEL 2 DEMOLITION 6

C DEMOLITION
C1 Scope of Works
Drawings A01 shows the existing conditions and demolition works that are required to carry out the
works as documented.

Note that a separate contractor has been engaged to conduct the bulk of the excavation of the
existing fitout on Level 2 of this building.
This includes partitioning, ceilings and floor coverings.

C2 Site Inspection
Tenderers shall inspect the site during the tender period to determine the exact scope of remaining
demolition works, any require floor preparation etc.

C3 General Notes
The word ‘demolish’ means demolish and cart away from site.

Demolition is to be carried out in such a manner as to cause as little inconvenience as possible to


the Proprietor, adjoining owners and the public. The Builder will be held responsible for any claims
which may arise from the disregarding of this clause.

Demolition shall include the redundant services in the vicinity of the works.

No burning off shall be carried out on or adjacent to the site.

C4 Permits
Before commencing work obtain any necessary demolition permits from the local authority.
Arrange and pay for all required protection devices required by the local authority.

C5 Demolition and Disposal Methods


All methods and techniques used for demolition of structural elements shall be such that the
existing structure to be retained is undamaged by the demolition works.

The Builder shall provide all adequate shoring, needling, propping, bracing or other supports
necessary, together with all temporary hoardings, demolitions, alterations and renovations, and
shall make good any damage incurred by the demolition works.

All debris and rubbish shall, during and/or on completion of the demolition works etc, be promptly
removed from the site as it accumulates. Material to be disposed is to be sprinkled with water
where necessary to settle dust.

All rotting timber and timber affected by fungi and mould shall, after demolition, be immediately
removed from the site and burnt.

C6 Services
Support, disconnect, cut back, remove or seal off and/or divert existing services etc, as required
during the demolition works. Services required to be cut and sealed by the demolition must be
carried out to the requirements of the Architect and all Authorities having jurisdiction over the
works.
MONASH BUILDING H LEVEL 2 DEMOLITION 7

Pay all disconnection fees.

Existing services to adjoining parts of the building and other floors of the building are to be
preserved and maintained. Minimise disruption to services affecting any other parts of the building.
Seek approval from Monash facilities management prior to causing any disruption to existing
services to other parts of the building.

C7 Dilapidation Report
The Contractor shall prepare a photographic and written record of the condition of existing adjacent
parts of the building and the parts of the building in the path of travel for removal of materials.
Such record shall be used amongst other things as a means of assessing the responsibility for
damage and/or making good arising out of the performance of the work under this Contract. A
copy of the record shall be kept, and made available for inspection by the Project Manager. All
costs incurred in the preparation of this report shall be included in the tender sum.

C8 Discovery of Hazardous Materials


It is not expected that any hazardous materials will be present in the areas of the building requiring
demolition or alteration. If hazardous materials are identified by the builder as being present in the
works area, notify the Superintendent immediately and await further advice.

If previously unidentified asbestos or other hazardous materials are discovered or suspected while
carrying out the works then works must cease immediately and the Superintendent is to be
notified.

C9 Registered Demolition Contractor


Demolition work of existing buildings is to be carried out by a registered demolition contractor.
Written evidence that the demolisher has the knowledge, experience and storage facilities to
conduct the demolition procedure must be supplied to the Building Surveyor prior to
commencement of demolition work.

Demolition is to be carried out in such a manner as to cause as little inconvenience as possible to


the Proprietor, adjoining owners and the public. The Builder will be held responsible for any claims
which may arise from the disregarding of this clause.

C10 Security of Works


Provide any hoardings necessary to secure the works area at the commencement of this contract.
MONASH BUILDING H LEVEL 2 CONCRETE 8

E CONCRETE

E1 General
E1.1 SCOPE OF WORKS

The work covered by this Section comprises the supplying, forming, reinforcing, transportation,
placing, curing and finishing of all cast in place and pre-cast concrete necessary for the completion
of the structures shown on the drawings.

The Contractor shall supply all materials, plant and labour to construct all new concrete work in
accordance with this specification, the drawings, and the current SAA Code AS 3600-1994
and related supplements including, but not limited to, the following items;

Precast walls, retaining walls, ground floor slabs and beams, first floor slabs & beams, infill slab
areas, plinths, spoon drains, drainage pits, paving slabs, kerbs and concrete bench seats as
shown on the structural, architectural and landscaping drawings.

Ready mixed concrete shall comply with AS 1379-2007.

Concrete work is to be co-ordinated with all other relevant trades, including but not limited to
masonry, steelwork, plumbing, electrical, glazing. Provide data confirming that the tradesmen
engaged for this project have a minimum of 5 years experience in such work as required by this
specification. The nominated experienced foreman is to be present on site at all times work is
being performed.

E1.2 RELATED WORK

Co-ordinate and co-operate with all other trades.

E1.3 DRAWINGS

All work shall be constructed in accordance with the Engineer's details and Architectural details,
specification and /or shown on the drawings. Any discrepancies to be referred to Architect prior to
commencing works.

E1.4 QUALITY ASSURANCE

Supply and install required materials in compliance with Drawings and Specifications which form
part of this Contract and with further details and/or instructions issued during the currency of the
Contract.

The Concreter is to be experienced in all types of concrete work in this project and provide an
appropriately qualified Foremen to supervise requirements. Several concreters may be used if
necessary to obtain the appropriate experience in the various types of work.

E1.5 REFERENCES

(a) Materials for concrete


Materials for concrete shall comply with the requirements of the following as applicable:
AS3972 Portland and Blended Cements
AS2758.1 Concrete Aggregates
AS1478 Chemical Admixtures for Concrete

Water used shall be free from all substances harmful to concrete and steel reinforcement.
MONASH BUILDING H LEVEL 2 CONCRETE 9

(b) Ready Mixed Concrete


The mixing and delivery of ready mixed concrete shall comply with:
AS1379 Specification for the supply of Concrete.

(c) Reinforcement
Reinforcement for concrete shall:
(i) Comply with the requirements of the following as applicable:-
AS1302 Steel Reinforced Bars for Concrete
AS1303 Steel Reinforced Wire for Concrete
AS1304 Welded Wire Reinforcing Fabric for Concrete
(ii) be free from any coating which will reduce or prevent bonding of the concrete to the
steel.

(d) Tilt up and pre-cast concrete


AS 3850 Tilt-up Concrete and Pre-cast Concrete elements for use in Buildings,
Code of Practice: Tilt-up Construction, Occupational Health and Safety Act 1985.

E1.6 DELIVERY AND HANDLING

Deliver materials in the same sequence as they are installed. Avoid double handling at the site.

E1.7 INSPECTION

The Builder shall give a minimum of 48 hours notice to the superintendent, so that he may inspect
the following stages of work: -
a) Formwork ready for Concrete
b) Reinforcement in Position
c) Other items as directed on the job.

Inspection shall not take place if the reinforcement and formwork, over the extent of the pour, has
not been completed and has not been checked by the Builder.

E1.8 MATERIALS

a) Cement
Cement shall be ordinary Portland Cement Type A complying with AS 3972-1991.

b) Aggregates - General
Fine and coarse aggregates shall consist of hard, strong, durable, uncoated rock fragments of
satisfactory size and shape as defined in this Specification. Aggregate shall be delivered to the
batching plant at least 24 hours before batching and each type and size shall be stored separately
in approved bins to prevent intermixing and to permit free drainage. Aggregates shall at all times
be dealt with in such a way that the exact weight of any one size of aggregate may be incorporated
in a batch of concrete in accordance with the approved design of a batch to meet the strength and
density requirements.

c) Fine Aggregate
Fine aggregate shall be clean mineral sand, uniform in quality, complying with the SAA Code AS
1465.

d) Coarse Aggregate
Coarse aggregate shall consist of 20mm maximum size clean, hard and well graded or crushed
stone, and fine aggregate of clean, hard sand, both complying with AS 2758-1985
Dense aggregate shall comply with AS 1465 and shall be graded in accordance with the
requirements of AS 1465 for 14mm and 20mm nominal size of graded aggregate.
MONASH BUILDING H LEVEL 2 CONCRETE 10

e) Water
Water shall be free from any matter harmful to concrete and its reinforcement.

f) Admixtures
No admixtures shall be used in the concrete unless approved by the Engineer. The use of any
admixture that has been approved in no way relieves the responsibility of the Builder in regard to
the quality of the concrete.

g) Reinforcement
The Builder shall prepare schedules of all reinforcement required under the terms of this
Specification and shall supply and incorporate in the work, all such steel reinforcement, including
all wire, support bars, spacer bars, bar chairs and the like, whether shown on the drawings or not,
but which are necessary to complete the work. All steel reinforcement to be used in the work, shall
comply with the appropriate SAA Code as set out below: -

Description of Appropriate Steel Grade Bar Diameter


Reinforcement SAA Code (MPA) Prefix

Hot-rolled plain steel


reinforcing bars AS 1302 230 R

Hard drawn wire reinforcing


fabric AS 1304 450 or 500 F

Hot-rolled deformed bars AS 1302 400 Y

All reinforcement to be used shall be free of kinks or bends not shown on the drawings. Fabric is to
be supplied in flat sheets only. Reinforcement from any section of concrete that has been rejected,
demolished and removed shall only be re-used after inspection and approval by the
superintendent.

All reinforcement shall be bent cold to conform accurately to the shapes and dimensions indicated
on the drawings. Before being placed in position in the work, all loose mill scale, rust, oil, paint,
grease or other deleterious materials shall be removed from the reinforcement. Where there is a
delay in depositing the concrete, after the reinforcement has been placed, the superintendent may
require the Builder to restore the reinforcement to a satisfactory condition.

E2 Construction
E2.1 FORMWORK

The Contractor shall be responsible for the design, construction, safety and adequacy of formwork.

Formwork and finishes shall comply with AS 3610-1995 and relevant supplements. Construct
formwork to give concrete members of shapes and dimensions required by the contract documents
within the specified tolerances, generally in accordance with AS 3600. The materials and methods
of construction of the formwork shall be such that the repetitive use of forms will not reduce the
accuracy of the finished concrete shapes nor vary the quality of the exposed surface. Forms shall
be strong enough to withstand all working stresses including the use of vibrators, and in
accordance with AS 3610, as regards leakage of mortar, maintenance of position and shape,
removal, cleaning and treatment, and inspection openings.

Set out formwork to give the minimum number of joints. An approved release agent may be applied
to forms subject to approval, but no material shall be used which imparts a stain to the concrete.
Release agent shall not come into contact with reinforcing steel.
MONASH BUILDING H LEVEL 2 CONCRETE 11

Surfaces finishes and tolerances to be generally as follows:


Where exposed - Class 2 Formwork
Where exposed, but to be rendered - Class 3 Formwork
Where totally concealed - Class 4 Formwork

In particular internal floor slabs shall be compacted and floated throughout to a tolerance of 3mm in
6 metres. Exposed vertical surfaces are to be within a tolerance of +/- 2mm over 3 metres. Vertical
surfaces to be rendered are to be within a tolerance of +/- 5mm over 3 metres.

Formwork shall conform to shape, lines, grades and dimensions of the concrete as required by the
drawings and shall be constructed in accordance with the requirements of this Specification and
AS 1509 and AS 1510 for the type and grade of concrete surface finishes specified.

Refer to Clause E3.12 Cold Weather Requirements, of this Specification.

Formwork shall be constructed from approved timber or metal. Formwork shall be regularly
replaced to ensure that it remains in good condition and free from surface defects. Formwork that
has been used, shall have all nails withdrawn and be thoroughly cleaned and repaired, prior to re-
use.

Forms shall be close-jointed to prevent leakage of mortar and all joints shall either be horizontal or
vertical, unless otherwise specified or approved.

All debris shall be removed from the interior of the forms before concrete is placed.

The formwork surfaces to be in contact with the concrete shall be thoroughly wetted before
concreting or, alternatively treated with an approved form oil. Any such oil shall be applied before
the placing of the reinforcement bars and care shall be taken to prevent reinforcing bars from
contacting the oil. Should this occur, the reinforcement shall be thoroughly cleaned with solvent,
before placing concrete.

Where the finished surface is to be painted, or to receive any other surface finish treatment, the
form oil used shall be compatible with the type of paint or surfacing to be applied.

Forms shall not be disturbed until the concrete in contact with them has hardened sufficiently to
withstand such action, without damage.

Striking and removal of formwork shall be carried out carefully so that the concrete is not jarred nor
the surface damaged. The builder shall take particular care in such stripping and removal of
formwork from surfaces that will remain exposed in the finished work.

Formwork shall not be removed until the concrete has attained sufficient strength to support its
own weight and the superimposed loads.

The following minimum times shall elapse before stripping of forms is commenced:
Vertical surfaces - 2 days
Slab Soffits - 21 days

Freshly stripped surfaces shall not be touched in any manner before inspection by the
superintendent.

E2.2 MOISTURE BARRIER

A waterproof membrane of 0.2mm thick branded "Fortecon” Super is to be laid under floor slabs on
ground. Polythene shall be laid with a minimum number of joints. Where joints are unavoidable,
they shall be lapped at least 150mm in the direction of the pour and sealed with pressure sensitive
tape.
MONASH BUILDING H LEVEL 2 CONCRETE 12

Allow to turn up membrane to level of top of slab at walls, pedestals, penetrations, etc. Care shall
be taken when pouring slabs to ensure that the polythene remains undamaged.

The edges of the membrane shall be jointed and sealed in the manner and with the pressure
sensitive tape recommended by the manufacturer. Take every care to avoid punctures in the
sealed and jointed membrane. Small tears and punctures in the sealed and jointed membrane
shall be patched strictly in accordance with the manufacturer’s recommendations. More seriously
damaged sheets must be replaced.

The membrane shall be continuous around the fittings and sealed to the service ducts and pits in
floors.

E2.3 GROUND SLABS, FOOTINGS AND FLOORS

Construct ground slabs in accordance with the structural drawings. Provide 12mm bituminous
caneite or Abelflex strip to all edges of slabs for full depth of slab, also turn up waterproof
membrane against wall as previously specified. Monolithic steel trowel finish to true level planes.

Concrete footings and floors shall be formed and poured in accordance with details and positions
as indicated on drawings.

Carefully set finished floor levels and allow for finishing materials. Provide any necessary graded
surfaces concrete plinths and set downs.

Slab thicknesses shown are minimum thickness.

Finish slabs at time of pouring as follows:


* Ceramic tiled area - screed or wood float finish.
* Internal floors - powered steel float.
* Deck and Steps - sponge finish.

E2.4 SURFACE FINISHES TO INTERIOR CONCRETE FLOORS

All surfaces shall be finished first with power floats, then with power trowels and finally with hand
trowels. The first trowelling after power floating shall be done by a power trowel and shall produce
a smooth surface which is relatively free of defects, but which may still be hand finished after the
surface has hardened sufficiently. The final trowelling shall be done when a ringing sound is
produced as the trowel is moved over the surface. The surface shall be thoroughly consolidated by
hand trowelling operations. The finished surface shall be free of any trowel marks, uniform in
texture and appearance and shall be planed to the specified tolerance.

E2.5 EMBEDDED ITEMS

The Builder shall allow for building in all fittings, cast-in plates sumps, bolts and other fixings shown
on the drawings or covered in this Specification.

Such items shall be securely fixed in the formwork and inspected by the superintendent before
concreting.

Where necessary, fixings shall be foam filled when cast in, to prevent concrete penetrating the
fixing.

E2.6 INSERTS, CHASES AND SLEEVES

The Contractor is to allow for building into the concrete as the work proceeds, all inserts, wall ties,
pipe sleeves and other attachments necessary and is to form all chases, rebates and other
MONASH BUILDING H LEVEL 2 CONCRETE 13

recesses necessary for the proper completion of all parts of the works and/or shown on drawings
or specified.

E2.7 PLACING CONCRETE

Steel reinforcement shall be placed accurately in the concrete in strict accordance with the
drawings or as directed by the superintendent and within the tolerances specified in AS 3600.

Reinforcement shall be securely held in position, using spacers or chairs, made of plastic, so as
not to be displaced during concreting. Reinforcement shall not be held in position by metal
supports which extend to the surface of the concrete or wooden blocks.

All bars shall be securely tied together with tie wire or other approved fasteners at every alternative
intersection or as approved by the Superintendent. Tie wire shall be annealed iron wire not less
than 1.6mm diameter.

No welding (including spot welding) will be permitted on hard-drawn steel bars or fabric.

Concrete cover to reinforcement shall be as shown on the drawings and the allowable tolerances
shall be in accordance with AS 3600.

Measurements made in placing reinforcement shall be to the centrelines of bars with the exception
of cover, which shall be to the outside of bars.

After placing concrete, care shall be taken to ensure reinforcement is embedded in, not protruding
from concrete and remains undisturbed for at least 24 hours.

E2.8 REINFORCEMENT

Steel reinforcement to be incorporated in the works shall comply with the requirements of
whichever of the following standard specifications is applicable.

AS 1302 Steel reinforcing bars for concrete


AS 1303 Steel reinforcing wire for concrete
AS 1304 Welded wire reinforcing fabric for concrete

The Contractor shall supply and fix all necessary bar chairs, support and spacer bars to position
reinforcement correctly and securely.

All reinforcement and steel built into concrete shall be free from loose rust, mill scale, dirt or other
substances which might prevent proper adhesion with the concrete.

All reinforcement shall be cut before placement, accurately positioned and securely fastened in
place so as to maintain the required clearance and spacings while concrete is being placed.

Splicing of bars and fabric, where approved shall, unless otherwise shown on drawings, be in
conformity with the following:

Plain Bars 60 diameters


Tempcore Deformed Bars 50 diameters
Fabric 450 minimum, but overlap measured between outermost
wires of each sheet not less than pitch of cross wires.

Bars and fabric at splices shall be securely tied together.

No section of the concrete shall be poured until the placement of reinforcement has been approved
by the Engineer. All reinforcement shall be free of grease, tar, paint, oil and mill scale and loose or
MONASH BUILDING H LEVEL 2 CONCRETE 14

thick rust, and must be stored and placed clear of the ground. Where there is delay in depositing
concrete reinforcement shall be re-inspected and if necessary, cleaned.

Note: No welding of cold worked bars will be permitted.

E2.9 SPLICES IN REINFORCEMENT

Splice reinforcement where shown on the drawings or where directed by the Engineer.

Splices may be made by lapping or electric welding or mechanically joined.

Fabric shall be lapped as described above.

Unless otherwise shown on the drawings, splice lengths shall be as follows: -

i. Deformed bars 38 diameters

ii. Hard-drawn Wire Fabric 250mm minimum overlap measured between


outermost transverse wires but not less than pitch of transverse wires.

Hard-drawn steel bars of fabric shall not be spliced by welding. Wherever possible, bar splices
shall be staggered unless shown otherwise on the drawings. All laps, in bars or fabric, shall be
securely tied together to the satisfaction of the Superintendent.

E3 Concrete Placement
E3.1 GENERAL

Concrete shall be made with Portland cement, fine aggregate, coarse aggregate, water and any
admixtures that may be specified or approved. The Builder shall be wholly responsible for
producing the concrete in accordance with the properties specified.

E3.2 PROPORTIONS

The Contractor shall be entirely responsible for ensuring that the placed concrete has a maximum
practical density, the specified compressive strength at 28 days (F'c) as set out in SAA Code AS
3600-2009 and other properties specified on the engineering drawings.

Where ready mixed concrete is used, the Contractor shall obtain from the supplier a statement in
writing guaranteeing that the concrete supplied conforms with the specified strengths and testing
requirements of SAA Code 3600-2009.

The proportion of materials shall result in a satisfactory workable mixture with a slump of 75mm
(maximum permissible variation 12mm).

No water shall be added to the mix on site.

The concrete strength (F'c) cement content and slump shall be marked on all delivery dockets by
the supplier.

Where a minimum cement content is required in the concrete, the minimum amount per cubic
metre shall be as specified.

Concrete to be placed by pumping methods shall have a minimum percentage of fine aggregate
consistent with the required workability for pumping and placing and the combined fine and coarse
aggregates shall be continuously graded with approved limits.
MONASH BUILDING H LEVEL 2 CONCRETE 15

E3.3 STRENGTH

The characteristic strength of the concrete, as defined in AS 3600 and as required for the various
parts of the work, shall be as shown on the drawings.

E3.4 SLUMP

The slump required for the various parts of the work shall be generally in the range 80mm with a
maximum variation of ±20mm. Design slump for each mix to be determined.

E3.5 REQUIRED DOCUMENTATION AND SUBMISSION TO SUPERINTENDENT

The following information shall be supplied to the superintendent by the Builder at least two (2)
weeks prior to the placement of any concrete, this information is for assessment and approval of
the concrete mix designs.

a) Material
i. The source of the supply of all materials including cement and any admixtures and
the type of cement proposed.
ii. The grading envelope and anticipated nominal grading of each aggregate.
iii. The gross apparent specific gravity of all aggregates.

b) Concrete Properties
The Builder shall submit the following details for every different concrete mix and shall
indicate whether the mix is a pump mix or normal mix.
i. Mix proportions per cubic metre of all constituents, including water and specifying
the range of variation which the Supplier can guarantee will not be exceeded.
ii. Design mean (target) strength at 7 days and 28 days.
iii. Standard deviation allowed for.
iv. Expected average slump at the form and the limit above which rejection of the wet
concrete is acceptable to the Supplier.
v. The anticipated air content of the concrete.
vi. Anticipated average density of hardened concrete in test cylinder form and the
range of variation anticipated.
vii. Shrinkage characteristics of the proposed mix.

E3.6 READY MIX CONCRETE

All concrete for the work shall be ready from a supplying company approved by the Superintendent
and shall be batched, mixed and delivered to the job in accordance with the SAA Code AS 1379,
except as varied by this Specification. Where any discrepancy exists between the SAA Codes AS
1379 and AS 3600, the latter shall prevail.

Site mixed concrete shall not be used for any part of the work unless permission is obtained from
the Superintendent. A separate specification will be supplied by the Engineer for any such work.

When ordering ready mix concrete, the Builder shall give the following information and instructions
to the supplier:-
i. Type and specification for Portland cement.
ii. Slump required at the form.
iii. Type and maximum size of aggregate.
iv. Admixtures (if any).
v. Characteristic compressive strength (F’c)
vi. Quantity.
vii. The building element being poured.
viii. Non-agitating trucks will not be permitted.
MONASH BUILDING H LEVEL 2 CONCRETE 16

Each truck of concrete shall be accompanied by the duplicate delivery dockets bearing the
following information:-
i. The name and location of the Project.
ii. The truck number and the name of the supplier.
iii. The delivery date and time dispatched.
iv. The quantity of concrete contained.
v. The amount of water added to the mix, excluding moisture in aggregate.
vi. The quantity or type of constituents where the approved mix being supplied permits
variation in cement content, admixture type or quantity or other feature.
vii. Where the water content is outside the agreed limits, the dockets shall show the
moisture content of the aggregate or other explanation for the variation.
viii. No truck which is not accompanied by a fully completed docket shall be permitted to
discharge.

The maximum slump loss during transportation from the mixing plant to the site of the work shall
not exceed 25mm. If this limit cannot be met, then the problem shall be referred to the
Superintendent, who may vary this requirement.

The Builder shall organise the delivery of concrete to the site in such quantities as can be
efficiently handled by the labour available at the site without undue delay in the discharging of
concrete from the delivery vehicles.

E3.7 MIXING, TRANSPORTING AND PLACING

The concrete shall be mixed, transported and placed in accordance with AS 3600.

All the concrete constituents for a batch, with the possible exception of water, shall be measured
by weight in an approved type of weight-batcher or similar weighing device. Water for concrete
may be measured by volume and shall discharge directly from an approved water measuring and
discharge device with controls so arranged that only measured water shall flow into the mixer. The
device shall also have a visible indicator showing the quantity of water measured and shall be
provided with a locking arrangement on the volume control so that unauthorised adjustment will be
prevented. Admixtures shall be incorporated into the mixing water in accordance with the
Manufacturer’s recommendations.

Concrete shall be mixed only in the quantities for immediate use. The use of partly hardened
concrete or re-mixing of such concrete with additional cement, aggregate or water, shall not be
permitted.

Concrete shall be mixed in batch mixers of an approved type or types which shall ensure uniform
distribution of the ingredients through the mass. Mixing by hand shall not be permitted except in an
emergency and then only subject to the approval of the Superintendent.

Prior to placing concrete, formwork shall be cleaned of all hardened concrete, free of water and
other foreign matter. Concrete shall not be deposited in wet trenches or in running water.

No concrete shall be placed until the excavations, formwork and reinforcement have been
inspected and approved by the nominated registered Building Surveyor. Notice of intention to pour
must be in writing and submitted at least two days prior to the pour. Any concrete poured without
approval may be rejected.

Before inspection, the Contractor shall check that reinforcement is securely fixed in place, forms
are clean and free from water and debris and that the whole of the work is in strict accordance with
the drawings and this specification.

The Contractor shall have a competent experienced supervisor present throughout the placing of
formwork and reinforcing and the pouring of concrete.
MONASH BUILDING H LEVEL 2 CONCRETE 17

Concrete shall be conveyed and deposited continuously, as close as possible to its final location,
until completion of any section or until an approved construction joint is reached, without
segregation and at a rate which prevents stiffening of the concrete. Approved mechanical vibrators
shall be used by experienced operators to compact the concrete during placing. Concrete shall be
thoroughly worked under and around reinforcement and the finished work shall be a dense,
uniform mass, free from voids, segregation and honeycombing.

Particular attention is drawn to SAA Code AS 3600 regarding hot and cold weather requirements.

Concrete shall be placed in daylight or under approved lighting.

Concrete shall be conveyed from the mixer to the place of final deposit without any delay and by
methods which will not cause segregation and/or loss of materials. Pumped concrete shall be
permitted, subject to the foregone conditions of this Specification.

Each monolithic portion of work shall be placed in one (1) continuous pour, except where the use
of construction joints is permitted. The order of placing shall be as required by the Superintendent
and shall be so arranged that new concrete is continually being placed against unset concrete, so
that a monolithic structure shall result.

Concrete shall be placed as nearly as practicable in its final position. Free dropping of concrete
from a height greater than 1.5m, or placing concrete far from its final position and working it along
forms, shall not be permitted.

Concrete shall not be placed at a rate greater than that which will permit satisfactory compaction
not to a depth greater than 500mm before compaction thereof.

Concrete shall only be placed in the presence of the Superintendent or his duly appointed
representative.

No re-tempered concrete, or concrete that has partially hardened or has been contaminated by
foreign matter shall be deposited in the work.

E3.8 COMPACTION

Unless otherwise approved by the Superintendent, concrete shall be compacted by vibrators and
concreting shall not commence until, in the opinion of the Superintendent, the Builder has sufficient
vibrators, including standby units, available at the site. Vibrators shall be of the internally vibrated
power type with a frequency of not less than 5000 vibrations per minute or vibrating screeds of a
type or types approved by the Superintendent.

The vibrators shall be inserted into the concrete continuously and progressively along the pour for
just sufficient time at each insertion to thoroughly compact the concrete. Over vibration shall be
avoided.

Vibrators shall be uniformly spaced and not further apart than the radius beyond which vibration is
visibly effective. Vibration shall achieve uniform plasticity of the concrete but shall nowhere be
continued to the extent that localised areas or mortar are formed.

The Builder shall ensure that no damage occurs to partially set concrete during compaction of
nearby concrete.

Where practicable and in addition to the vibrators, a suitable tool shall be worked up and down
next to the forms until coarse material is forced back and a mortar layer is brought to the next form.

The finished concrete shall be a dense homogeneous mass, completely filling the forms,
thoroughly embedding the reinforcement, free of stone pockets and compacted to bring only a
MONASH BUILDING H LEVEL 2 CONCRETE 18

slight excess of mortar to the surface.

E3.9 CONSTRUCTION JOINTS

Wherever the concrete has taken its initial set by reason of placing being stopped or delayed
before completion of the portion of the work under construction, the point of stopping shall be
deemed a construction joint. Placing of concrete shall be continued without cessation throughout
the whole of any section of the work between the approved construction joints.

The location of construction joints shall be planned in advance and conform with the Engineers
drawings.

If, due to breakdown or other unforseen contingency, a construction joint becomes necessary at a
point not previously approved, concreting shall be continued by means to a point designated by the
Superintendent or his representative, and a construction joint formed at that location.

Before placing new concrete on or against set concrete, the surface of the set concrete shall be
thoroughly roughened, cleaned of all laitance and loose material and kept damp for not less than 2
hours.

Vertical construction joints shall be formed against a barrier.

Before placing new concrete on or against concrete which has set, the forms shall be tightened
and the surface of the set concrete be thoroughly roughened, cleaned of all laitance and/or loose
materials and kept damp for not less than two (2) hours. Immediately before placing the new
concrete, the set concrete shall be covered with a neat cement slurry finished onto the surface.

For basement walls, slabs and footings immediately before placing new concrete, a continuous
strip of Hydrotite Water Stop shall be placed on the set concrete and the remainder of the surface
shall be covered with a neat cement slurry brushed into the surface.

E3.10 SURFACE FINISHES

After placing of concrete, all exposed surfaces shall be protected by approved means against loss
of moisture for a period of at least seven (7) days and against damage by rain until the concrete
has hardened.

All concrete top surfaces shall be kept continuously wet for the above period by use of an
approved covering, such as good quality hessian, building paper covered with hessian or other
approved means. Soaker hoses or rose sprays shall not be used to apply water to the covering
material to keep the surface of the concrete continuously moist. At no time during the first seven
(7) days shall the surface of the concrete be permitted to dry out.

Sprayed curing compounds will not be permitted on surfaces which are to have a subsequent
surface applied to them. Approved curing compounds may be used on other locations. Curing
compounds with a wax emulsion base are those types which will be approved.

All formed surfaces of concrete which have been placed for not more than fourteen (14) days shall
be cured in a similar manner immediately following stripping.

Wind exposure shall be prevented by the Builder who shall erect breaks to the satisfaction of the
Superintendent to protect concrete during curing.

E3.11 TOLERANCES AND SURFACE FINISHES

Unless otherwise specified, all floors and walls shall be finished to the tolerances specified in
AS3600
MONASH BUILDING H LEVEL 2 CONCRETE 19

E3.12 COLD WEATHER REQUIREMENTS

When concreting in cold weather, precautions shall be taken to prevent the concrete from freezing
at any time during the curing period.

When the temperature of the surrounding air falls below 5ºC, the concrete shall be maintained at a
temperature of at least 5ºC until the expiration of the curing period. Concrete placed when the
temperature of the surrounding air is below 5ºC shall have a temperature not lower than 10ºC
when placed in forms.

Salts or other chemicals shall not be used for the prevention of freezing.

E3.13 HOT WEATHER REQUIREMENTS

In hot weather, precautions shall be taken to avoid premature stiffening of fresh mix and to reduce
water absorption and evaporation losses. When the temperature of surrounding air is higher than
32ºC, the following provisions shall apply:

a) The formwork shall be continuously sprayed with cold water in advance of the concreting.
Excess water shall be removed from the inside of the forms immediately prior to the
concrete placement. The reinforcement and the formwork, if metal forms are used, shall be
protected from the effects of hot winds and direct sunlight.

b) Concrete shall have a temperature not higher than 32ºC when placed, either following the
use of chilled mixing water, or by spraying of the coarse aggregate, or both, and if
necessary by covering the container in which the concrete is transported to the form.

c) The concrete shall be mixed, transported, placed and compacted as rapidly as possible and
the element of structure shall then be covered with an impervious membrane or with wet
sand or wet hessian.

d) Curing compounds may be used as an alternative to the requirements of paragraph c)


above.

E3.14 QUALITY CONTROL

a) Quality Control (Project Control)


All concrete shall be obtained from a Concrete Supplier (to be approved by the Engineer) operating
“Project Control Testing” (as defined in AS 3600 on all concrete mixes).

The Builder shall be responsible for all sampling and testing of concrete at his own expense and
shall supply all labour, materials, equipment, including moulds and other necessary items
therefore.

The Builder shall arrange for the concrete testing to be carried out by an independent established
testing laboratory recognised by N.A.T.A. and approved by the Engineer. Testing laboratories
associated with the concrete supplier will not be approved.

b) Certification of Materials
The Builder shall ensure that the N.A.T.A. endorsed Certificate of Tests of materials incorporated
in the concrete as specified, are available on request.

The Builder shall ensure that the supplier of ready Mixed Concrete will permit inspection of the
plant and materials and, if so required, will permit the taking of samples for testing purposes.

c) Sampling and Job Control of Concrete


MONASH BUILDING H LEVEL 2 CONCRETE 20

Test specimens from any batch of concrete shall be sampled in accordance with AS 1012 Part 1 -
2014 “Method for Sampling Fresh Concrete”.

All samples shall consist of three (3) cylinders of 150mm diameter and 300mm in height. One
cylinder shall be tested at 7 days and the other two at 28 days.

The truck to be tested shall be selected by the Acceptor before he has seen the concrete or the
delivery docket.

To identify samples, the following data must be recorded in the Samplers field book:-
i. Entry point to site.
ii. Date and time of taking the sample.
iii. Name of the Supplier.
iv. Number of the Delivery Docket.
v. Method of sampling.
vi. Location of sampling.
vii. Method of identifying cylinders.
viii. Location of batch of concrete after its placement.
ix. Slump of sample.
x. Characteristic compressive strength.

The Acceptor shall witness the initial discharge of concrete from each truck and shall perform a
slump test after the discharge of 1/3m3 of concrete on any delivery of which he is uncertain that
slump conforms to specification requirements. The first truck in each pour and each truck samples
for compression test cylinders shall in any case be slump tested.
Should the slump of any delivery exceed the maximum acceptable figure, but not exceed the level
at which the Acceptor has instruction to reject the delivery unequivocally, the delivery may be
accepted by the Builder on his responsibility, but a sample shall be taken at the expense of the
Builder for cylinder testing.

Where suspicions of concrete quality are entertained, the Engineer shall be entitled to increase the
frequency of testing and introduce additional tests at his own discretion. If any of the concrete so
tested fails to meet any provision of the specification, then such testing shall be at the Builder’s
expense.

d) Sampling and Testing


Sampling, making and testing of goods shall comply with AS 1012.
(i) The Contractor shall arrange for the carrying out of the standard slump test and
making and testing standard test cylinders, by an independent established
laboratory recognised by N.A.T.A.

Sampling shall be carried out at regular intervals during the placement of concrete
in accordance with AS 3600-2009.

Two test cylinders and one slump test shall be taken from each third delivery.

(ii) The determination of the compressive strength of the concrete shall follow the
standard procedures set out in AS 3600-2009.

(iii) One copy of the result shall be submitted to the Engineer showing the specified
strength and location on the job of the concrete represented by the sample.

Concrete shall not be discharged into formwork whilst slump or other tests are being performed,
which could result in its rejection.

The Builder shall allow for any additional testing he may require to substantiate any construction
procedures he may wish to adopt.
MONASH BUILDING H LEVEL 2 CONCRETE 21

e) Frequency of Sampling and Testing


The sample rate given applies to each particular mix design.

The sampling rate by the Concrete Supplier shall not be less than that given under AS 3600.

The sampling rate shall be one (1) sample every six (6) trucks with a rate of one (1) sample every
five (5) trucks for concrete mixes when used in columns, with a minimum of two (2) samples per
week for that mix design, or if that mix design is produced less frequently than twice per week, then
at least one sample on each day shall be taken.

If the air temperature exceeds 32°C during any part of a pour, then an additional sample shall be
taken during the period of highest temperature.

Where, in an emergency or otherwise, concrete is obtained from a different plant to that which
normally supplies a mix, then full AS 3600 sampling rates shall be employed on all concrete so
obtained.

f) Certificates
The Builder shall provide the Engineer with two (2) copies of the manufacturer’s certificate for each
batch of ready mixed concrete delivered to site, in accordance with AS 1379.

Provide the Engineer with two (2) copies of the Certificates endorsed by the testing laboratory for
all tests carried out in accordance with the specification.

g) Acceptance Basis for Concrete Strength


Acceptance of the concrete shall be primarily based on compliance of the tests with the
requirements of AS 3600 and the reduced frequency of testing shall not be grounds for avoiding
these requirements.

h) Rejection
The superintendent may reject before placement, any batch of concrete which, in his opinion
does not conform with the design approved therefore, or is unsatisfactory in any respect of which
a delivery docket containing full information as specified herein is not immediately available.

Should the concrete fail to comply with the specification then all results and any other relevant
information shall be immediately forwarded to the Engineer such that they shall be analysed in
accordance with AS 3600.

The superintendent may also reject any concrete after placement because of unsatisfactory finish
or because of incorrect positioning or other failure to conform to the requirements of this
specification. Upon such rejections, the Builder may seek the approval of the superintendent to
carry out at his, the Builder’s expense. a load test or other tests on the concrete so rejected and/or
to have core samples taken and tested and the superintendent may, should he consider such to be
advisable, allow the Builder to proceed with the tests. Concrete which is rejected and concrete
which fails the approved tests shall be demolished or removed from the site and replaced with
concrete conforming to the requirements of this specification.

Furthermore, the superintendent may have any concrete analysed in accordance with AS 1012 or
may arrange for core samples to be taken and tests carried out in accordance with Clause 4.10 of
AS 3600. Should the results of any such analysis or test not be in accordance with the
requirements of this specification, the concrete represented by such analysis or test may be
rejected and the full cost to the Proprietor, including reasonable allowance for indirect costs, will be
chargeable to the Builder and will be deducted from monies due or becoming due to the Builder,
pursuant to the Contract Terms of Payment.
MONASH BUILDING H LEVEL 2 CONCRETE 22

E3.15 TREATMENT OF DEFECTS ON FORMED SURFACES

No repairs to concrete shall be made until after inspection by the Superintendent, and then only in
strict accordance with his direction.

As soon as forms are removed, all exposed surfaces shall be carefully examined and any
irregularities found in the surface of the concrete shall be immediately rubbed down in a manner
satisfactory to the superintendent so as to secure a smooth uniform and continuous surface.

Plastering or coating of surfaces to be smoothed will not be permitted. Concrete containing voids,
holes, honeycombing or similar depression defects shall be completely removed and replaced,
provided that, where required or approved by the Superintendent, shallow defects shall be repaired
with mortar as hereinafter specified.

In no case will extensive patching of honeycombed concrete be permitted. All repairs and
replacements specified herein shall be promptly executed by the Builder and entirely at his own
expense. If the Builder fails to do so, the Superintendent may forbid him to proceed with some part
of or all of the work until the Builder shall have completed such repairs to the superintendent’s
satisfaction and no extension of time for completion or other compensation shall be made because
of any subsequent delay.

Each defective surface that is to be repaired with mortar shall, unless otherwise directed by the
Engineer, be cut back from the true surface, a minimum of 15mm over the entire area. Feather
edges shall be avoided. After preparation, the surface shall be wet sufficiently in advance, so as to
be quite moist, but not wet, when the mortar is applied.

Mortar for repair purposes shall be proportioned and mixed as specified by the Engineer. All bolts
and tie wires or other appliances passing through the concrete, shall be cut off 25mm below the
surface.

E4 Existing Concrete Floors


E4.1 INSPECTION OF EXISTING CONCRETE FLOOR SUBSTRATES

Tenderers must during the tender period inspect the site and the condition of the existing concrete
floor substrates in order to make the appropriate allowance for floor preparation.

Existing floor finishes and screeds of various thicknesses will have been removed as part of an
early works demolition package and so inspection of the remaining substrates is expected.

E4.2 FLOOR SLABS

Allow for cementitious floor screeds to floor slabs where levelling is required.

Allow for a floor levelling compound such as Ardit to bring all floor areas to a suitable level to
receive floor finishes ensuring that all abutting floor finishes are installed with finished surfaces
flush with each other.

E4.3 CONCRETE PATCHING

Provide patching to concrete floors and columns where repair work is required. Any damaged
concrete work with exposed reinforcement is to be treated with an anti-rust product followed by
concrete repair work.
MONASH BUILDING H LEVEL 2 MASONRY 23

F MASONRY

F1 General
F1.1 SCOPE OF WORKS

The scope of the work shall include but not necessarily be limited to the following:

- Blocking up an existing doorway with concrete blockwork to match existing at North-west


corner of Plant Room.

In addition to the requirements as described herein, all work shall conform to the design intent as
indicated on the architectural documents and the relevant documentation of the associated design
consultants for this project.

F1.2 CODES & REFERENCES

All aspects of Masonry work shall comply with AS 3700 and other relevant current Australian
standards.

F2 Blockwork Materials

F2.1 BLOCKS

Provide solid concrete blocks to match existing

F2.2 MORTAR

a) Materials
Cement shall be Portland cement of Geelong manufacture. Sand shall be clean, washed
sand free from soluble salts inorganic matter. Lime shall be `Limil' from David Mitchell
Estate or equivalent. Water shall be clean and fit for drinking by the foreman bricklayer.
Plasticiser shall be `Nonporite Mortarlox' or similar if required. All materials shall be
delivered to site in branded sealed bags, stored under cover and clear of the ground.

b) Mortar Mix
The mortar for external and internal blockwork in fair face work shall be:
One (1) part cement
One (1) part lime
Six (6) parts sand
Water and plasticiser as necessary

Allow for colour in mortar. Mortar for new brickwork is to be white to match brickwork.

c) Mixing
Mortar shall be mixed in a mechanically operated batch type mixer of adequate capacity. Mortar
materials shall be accurately gauged by volume using clean vessels and gauging boxes. Dry
ingredients shall be mixed until the colour is uniform, then water added, mixed once again until
colour is uniform and for a further 1.5 minutes to achieve a workable plastic consistency.

d) Using
Mortar shall be transported and handled so that no segregation of materials, loss of water or
contamination occurs. Mortar containing cement shall be prepared in quantities only sufficient for
immediate use and shall be used within thirty minutes and shall not be retempered.
MONASH BUILDING H LEVEL 2 MASONRY 24

F3 Blockwork Workmanship
F3.1 GENERAL

Standard: To AS 3700.

Protection: To AS 3700. Brickwork and blockwork materials shall be liable to rejection if damaged
or disfigured during the course of the work under the Contract.

Moisture Content: To AS 3700.

Tolerances: Construct blockwork within the tolerances prescribed in AS 3700.

Cutting: If cutting is required, use a masonry saw. Knapped units shall not be used.

Chases: Do not chase without prior approval.

Penetrations: Cored or sawn.

Disturbance After Placement: If bricks are moved after the initial placement, re-lay in fresh mortar.

Inspection: Any work or materials will be subject to rejection by the Architect if damaged or
disfigured during the course of the work.

F3.2 CLEANING

Standard: To AS 1475 Part 1, Rule 5.11.

Maintain the cleanliness of blockwork as it rises by regular removal of mortar droppings and dirt
from work in progress. Clean off hardened mortar with a stiff scrubbing brush.

Remove any other soiling or staining by first drenching the brickwork with water to kill any suction.
Then apply a 1:20 solution of hydrochloric acid in water (increase strength to 1:10 maximum for
difficult parts) in areas of 1m to 2m using a stiff scrubbing brush, working from top to bottom.
Ensure that the brickwork and blockwork remains wet with water wherever acid solution may touch
and avoid scrubbing solution into mortar joints.

Hose down with water after completing each area and mop or sponge off the excess. Repeat the
treatment on any areas which are still disfigured.

Proprietary treatments such as ‘Noskum’ or ‘Corium 93' or other specialised treatment appropriate
to the task shall be used to remove stains occurring from sources other than mortar.

F3.3 SETTING OUT

Rod and Bond: Set out the work so as to maintain the required rod and bond with bed joints and
vertical joints of equal and uniform width and with the minimum cutting of units.

Trial Set-Out: Makes trial set-out of two courses for each panel of facework and obtain approval
before laying.

F3.4 BONDING

Standard: To AS 3700 clause 3.9.


Bonding Pattern: New areas of face brickwork are to be laid in Stack bond unless otherwise noted
on the drawings.
MONASH BUILDING H LEVEL 2 MASONRY 25

Bonding At Intersections:
Bond walls to intersecting walls either by masonry bonding or by tie bonding, as AB 3700 clause
3.9.

F3.5 JOINTING

Standard: To AS 3700 clauses 3.6.2 and 8.7.2. Full bedding required.

Joints Around Flashings: Point up as necessary.

Facework Joints:
Flush struck to horizontal joints. Rake out perpends of bevelled brickwork back to align with
horizontal joints.

Joints to Structure:
Where masonry walling abuts other structural elements such as concrete columns and the like,
leave a suitable movement joint and seal completely with a non-shrink flexible sealant.
MONASH BUILDING H LEVEL 2 CARPENTRY 26

G CARPENTRY

G1 General
G1.1 SCOPE OF WORKS

Supply and install all carpentry items to those areas described on the drawings.

In addition to the requirements as described herein, all work shall conform to the design intent as
indicated on the architectural documents and the relevant documentation of the associated design
consultants for this project.

G1.2 CODES & REFERENCES

All aspects of Carpentry work shall comply with the relevant current Australian standards and
Building Codes.

G1.3 FIXINGS & FASTENINGS

- Nails generally shall be bullet head steel for carpentry and flat head steel for fixing steel to
timber, all galvanised or stainless steel where exposed to weather or damp situations.
- Screws shall be countersunk head for fixing accessories to timber. Cadmium or chrome
plated in joinery.
- Brass screws shall be chrome plated and countersunk for dome headed as required.
- Coach bolts and coach screws shall be to AS1393 for structural timber fixings.
- Engine bolts shall be hexagonal head for fixing timber to steel.
- Masonry anchors shall be of expanding screw type.
- Explosive powered steel pins into concrete or steel may be used only if specifically
approved by the Superintendent.
- Bolts and screws shall be complete with nuts and washers as appropriate.
- Adhesives - contact, waterproof, of type recommended by manufacturer for sheeting being
fixed.
- Grounds, plugs, fillets, etc., to be dry softwood plugs, dry straight Oregon grounds, patent
fibre plugs or patent plastic plugs.
- Bolt size shall be 10mm diam unless otherwise noted.

G2 Wall Construction
G2.1 FRAMED WALL TYPES

Refer Architectural Drawings, Floor Plan for wall types, and as described below:
Insulation to external walls must comply with non-combustibility requirements of AS1530.1.

Wall Type WT/A (Yellow on floor plan) – Rw35 dB


▪ 92mm metal studs
▪ 13mm standard plasterboard to each side
▪ 50mm thick, 10kg/m3 glasswool in the partition cavity
▪ Acoustically seal around all service penetrations.
▪ Partition and all plasterboard layers to extend past the ceiling to the underside of the slab
above, OR in the instance that full height partition is not possible:
▪ Partition and plasterboard layers to penetrate the ceiling line by at least 100mm, lay 75mm
thick Bradford Acoustigard Partition insulation with minimum 11kg/m3 density over ceiling
for a minimum of 1200mm wide each side of wall.

Refer to Appendix E – Acoustic Report for alternative detailing to minimise flanking path of wall
partition and ceiling junction
MONASH BUILDING H LEVEL 2 CARPENTRY 27

Wall Type WT/B (Blue on plans) – Rw45 dB


▪ 92mm metal studs
▪ 13mm standard plasterboard to each side
▪ 2 no layers of 13mm standard plasterboard on the other side
▪ 50mm, 10kg/m3 glasswool insulation in the partition cavity
▪ Acoustically seal around all service penetrations.
▪ Partition and all plasterboard layers to extend past the ceiling to the underside of the slab
above, OR in the instance that full height partition is not possible:
▪ Partition and plasterboard layers to penetrate the ceiling line by at least 100mm, lay 75mm
thick Bradford Acoustigard Partition insulation with minimum 11kg/m3 density over ceiling
for a minimum of 1200mm wide each side of wall.

Refer to Appendix E – Acoustic Report for alternative detailing to minimise flanking path of wall
partition and ceiling junction

Wall Type WT/ C (Red on plans) – Rw 55 dB and FRL 120/120/120


▪ Blockwork masonry wall to match existing plant room wall. Blockwork to continue to
underside of slab above.
▪ 1 layer of 13mm standard plasterboard on both sides packed to finish flush with adjacent
linings.
▪ Acoustically seal around all service penetrations.
▪ Blockwork wall to achieve fire rating of 120/120/120 FRL to match existing

G2.2 FRAMED WALLS GENERALLY

Framed walls generally, unless indicated on the drawings to be one of the acoustic wall types as
detailed above, shall be constructed as follows:
▪ 92mm x 0.55BMT steel studs at max 600mm cts
▪ 13mm standard plasterboard to each side

G2.3 CONTINUOUS ELEMENTS

Where possible, lightweight elements (e.g. layers of plasterboard) should not span across two
rooms where there is a separating partition with an acoustic rating. A continuous lightweight
element can degrade the performance of the adjacent partition. This concept applied to wall
linings, perimeter cladding, bulkheads, and ceiling plasterboard margins.

If there is a continuous lightweight element across an acoustically rated partition, a saw cut must
be provided to remove the noise flanking path. Further advice to be sought from architect.

G3 Framing
G3.1 METAL STUDWORK

To walls that are to be framed as metal stud walls provide steel stud steel wall systems by
Rondo or equivalent in stud sizes as noted above in clause G2.1. Unless specified
otherwise provide 92mm wide stud wall construction as follows for all internal partition walls.

Stud Configuration: 92 x 0.55 bmt lipped studs at max 600 cts


2 rows of nogging equally spaced over wall height

Head Track: 92 x 50 x 1.15 bmt Deflection Head Track


1 row of nogging 100mm below head track
MONASH BUILDING H LEVEL 2 CARPENTRY 28

Base Track: 92 x 32 x 1.15 bmt Track


1/#8 tek screw both sides per stud

Wall Linings: Refer Section G Carpentry and Section S - Finishes Schedule

Wall Height: Refer to drawings.

Wall framing that extends to the underside of the floor structure above
shall include deflection head details in the framing to prevent the wall
frame bearing any floor loads from above.

Stud configuration to be in accordance with manufacturer’s guidelines to suit maximum heights and
to match existing wall thicknesses where relevant.

General Notes and Limitations:


- All stud and track sections are manufactured by Rondo Buildings Services Pty Ltd.
- Supplied wind loading has not been checked, and has been taken as the net design
pressure including all local factors in accordance with AS1170.2.
- Design assumes stud and track have been installed in accordance with Rondo Building
Services Pty Ltd standard details.
- All walls are non-load bearing, except for self weight unless noted otherwise.
- Provide additional framing across full height doors for support of door heads and pivot door
operating mechanisms.
- Provide all necessary bracing and support to top of walls to the underside of slab where
walls do not continue to the underside of the slab.

Manufacturer: Rondo Building Services, 12-14 Dunlop Road Mulgrave 3170. Tel: 8561 2222. Fax:
8561 2266.

G3.2 DOOR JAMB STUDS

Provide 90x45 MGP10 timber studs beside metal studs or instead of metal studs each side of door
jambs for additional rigidity.

G3.3 METAL BATTEN FRAMING

Provide metal battens where necessary to support linings and for reticulation of services against
masonry wall. Provide any metal furring channels, clips, and timber packing strips necessary to
bring finishes to the levels indicated on the drawings.

G3.4 TIMBER STUDWORK

a) Timber Lined Walls


Provide 90 x 45 MGP10 pine timber framing or timber battens wherever there are to be
timber or plywood linings to enable nail fixing of linings. Timber and plywood linings can
then be nail fixed into timber framing. Nail holes can be punched and filled.

b) Door Jamb Framing


Studs beside door openings are to be timber as per Clause G3.2 above and are to continue
to the underside of the structure above and be secured to the slab to ensure rigidity at door
frames.

G3.5 TIMBER BLOCKING

Provide all noggings, timber blocking and/or plywood blocking behind plasterboard linings to
provide secure fixing for all items to be fixed to walls.
MONASH BUILDING H LEVEL 2 CARPENTRY 29

Blocking is required for all wall mounted items including, but not limited to:
• Toilet & Washroom fittings, grab rails etc
• AV equipment including LCD Screens.

G3.6 TIMBER BATTEN FRAMING

Provide pine timber battens where necessary to support linings. Provide any battens or packing
strips necessary to bring finishes to the levels indicated on the drawings.

G3.7 TIMBER TRIMS

Provide KDHW trims as shown on the Drawings.

KDHW shall be Vic Ash or Tas Oak in 19mm and 32mm thick as noted on the drawings.

Timber finish stain refer Section Q - Painting

G4 Insulation
G4.1 INTERNAL ACOUSTIC WALL CAVITY INSULATION
Provide Bradford Acoustigard / equivalent 50mm thick black 10kg/m3 glasswool or 10kg/m3
polyester wall batts behind.

Refer Section G2.1 Wall Construction.

G4.2 ACOUSTIC INSULATION BEHIND BATTEN SCREEN WALLS

To wall areas denoted as having timber batten finish TB provide Sculptform timber
battens achieving min 25% open area on 7mm black acoustic backing.

G4.3 CEILING INSULATION

a) Acoustic Insulation Above Perforated Plasterboard Ceilings & Perforated Timber


veneered panel soffits
Provide 100mm thick sound absorptive insulation in black “Martini Absorb XHD100” above
all areas of perforated plasterboard ceiling linings and perforated timber veneered soffit
linings.

Batt insulation is to comply with AS1530.3 fire testing. Provide all necessary
blocking/tape/brackets to secure insulation into place.

b) Acoustic Ceiling Panels


Refer Clause G6.4.

c) Acoustic Wavebar
Provide Pyrotek Wavebar 5mm thick 10kg/m2 high performance flexible vinyl acoustic
noise barrier over wall partitions in ceiling space where shown on the drawings.

G4.4 ACOUSTIC TREATMENT AND INSULATION AT SERVICES PENETRATIONS

For services penetrations running through acoustic rated full height walls, the following must be
ensured:
• Penetrations for cable trays and conduits to be made as small as practical
• The gap around the cable tray, within the cable tray and within the conduit is to be filled
with tightly packed acoustic insulation with a minimum density of 32 kg/m3
• The penetration around a conduit is to be sealed airtight with backing rods and flexible
caulking compound
MONASH BUILDING H LEVEL 2 CARPENTRY 30

• Pipes are to be acoustically lagged


• Avoid back-to-back electrical outlets on wall partitions between spaces to minimise noise
transfer between spaces.
• Back-to-back electrical outlets are to be installed with acoustic rated switch boxes; suitable
products are those manufactured by Promat, Clipsal or HPM; suitable products include type
435 by HPM, type 157/1F or similar by Clipsal

Refer also Services Engineer’s Specification on acoustic treatment for Mechanical Services

G4.5 SEALING - ACOUSTIC RATED BUILDING ELEMENTS

An airtight seal should be provided between all acoustically rated elements and other adjacent
building elements by means of a flexible caulking compound.

All acoustically rated walls should be sealed at the head and base with flexible caulking compound
and backing rods as required.

The flexible caulking compound may be acrylic, polyurethane or silicone. Any other proposed
acoustic sealant should be first approved by the acoustic consultant.

G5 Wall & Soffit Linings & Substrates


G5.1 PLASTERBOARD WALL LININGS
Refer to Section N Plastering of this specification.

G5.2 TIMBER VENEERED BOARD LININGS

Product Colour / Image Location Legend


Timber Veneered MDF External Wall Lining TBV1
(Public Area Side):
Manufacturer: Plyco • Tutorial 1 / West
Corridor 1
Sheet Size: 2700 x 1200 • Tutorial 2 / West
Special Order Corridor 1
• North Corridor
Thickness: Joinery JU.08A
• Straight wall sections - 6mm
thick veneered MDF
• Curved wall sections - 3mm
thick veneered MDF over 1
layer of 3mm plain MDF.

Colour: American Walnut


American Walnut Timber
Veneered
MONASH BUILDING H LEVEL 2 CARPENTRY 31

Product Colour / Image Location Legend


Timber Veneered MDF External Wall Lining TBV2
(Public Area Side):
Manufacturer: • Tutorial 3 / West
Plyco Corridor 2
• Tutorial 4 External
Sheet Size: 2700 x 1200 Wall Face / West
Special Order Corridor 2

Thickness:
• Straight wall sections - 6mm Joinery:
thick veneered MDF • North Corridor
• Curved wall sections - 3mm Joinery JU.08B,
thick veneered MDF over 1 JU.08C, and JU.08D
layer of 3mm plain MDF. • South Corridor
American Cherry Screen Partition SC
Colour:
American Cherry Timber
Veneered
Timber Veneered MDF East Corridor Column TBV3
Wall Lining
Manufacturer:
Plyco External Wall Lining
(Public Area Side):
Sheet Size: 2700 x 1200 • Tutorial 8 / East
Special Order Corridor
• Tutorial 9 / East
Thickness: Corridor 2
• Straight wall sections - 6mm
thick veneered MDF Joinery:
• Curved wall sections - 3mm • South Corridor
thick veneered MDF over 1 Screen Partition SC
layer of 3mm plain MDF.
Tasmanian Oak
Colour:
Tasmanian Oak Timber
Veneered
Perforated Timber Veneered Soffit Lining PTV1
MDF • North Corridor
Joinery JU.08A
Manufacturer: Plyco / Atkar

Sheet Size: 2400 x 1200


Special Order

Thickness:
• 12mm thick veneered MDF

Colour:
American Walnut Timber
Veneered
Perforated American
Perforation : Atkar – 10mm dia Walnut
holes in Perforation Pattern
Type AP250D
MONASH BUILDING H LEVEL 2 CARPENTRY 32

Product Colour / Image Location Legend


Perforated Timber Veneered Soffit Lining PTV2
MDF • North Corridor
Joinery JU.08B,
Manufacturer: JU.08C, and JU.08D
Plyco

Sheet Size: 2400 x 1200


Special Order

Thickness:
• 12mm thick veneered MDF

Colour:
American Cherry Timber Perforated American
Veneered Cherry

Perforation : Atkar – 10mm dia


holes in Perforation Pattern
Type AP250D

Special Order – 2700 long sheets:


Please note that 2700 long sheets of veneered board material are available by Special Order. The
builder is to confirm the lead time for delivery of this material and make sufficient allowance in the
program accordingly.

G5.3 SCULPTFORM TIMBER CLICK-ON BATTENS

To areas denoted on the drawings with TB provide vertical dressed timber battens on metal clip
system backed with acoustic insulation to the extent as shown on the drawings.

Product Colour / Image Location Legend


Manufacturer: • Lift Lobby TB
Sculptform • North Corridor
• East Corridor 1
Range: • West Corridor 3
Timber Click-On Battens
with Autex Acoustic

Colour:
American Oak

Stain:
Prefinished Clear Stain

Timber battens and fixing system shall be as follows:

Wall areas denoted as TB


Framing System: Sculptform
Feature battens: 19mm thick Block profile batten in American Oak as detailed on the drawings
Finish on battens: Clear Finish. Provide sample for approval.
Fixing Batten system: Ontrax Acoustic Integration 73mm x 12mm at 600 centres
MONASH BUILDING H LEVEL 2 CARPENTRY 33

Acoustic backing: To be included. Ref Clause G4.2.

Cap all vertical edges in 19mm thick dressed Victorian Ash in width to suit thickness of wall
that battens system is being fixed to.

Manufacturer: Sculptform.
Contact. Kalani Walerys
Tel: 5446 0100.
Email: kalani.w@sculptform.com.au

G5.4 PAINTED MDF LININGS

Provide painted MDF linings to areas as detailed on the drawings.

G5.5 WALL TILES

Provide ceramic tile wall linings over wall areas as shown on the drawings. Wall tiles are to be
installed on flush jointed 9mm Villaboard wall lining substrate.

Refer to Section P Tiling.

G5.6 PINBOARD WALL LININGS

Provide pin board wall linings to the extent described in Clause G5.7 Schedule of Pinboard Colours
and as shown on the drawings.

PIN1 Woven Image EchoPanel 12mm thick in colour to be selected. Butt join panels at
joins in sheets. Trim perimeter edge with reverse black anodised aluminium angle such that
angle covers edge of EchoPanel but not the face of the panel.

PIN2 Woven Image EchoPanel Longitude 12mm thick in colour to be selected. Butt join panels
at joins in sheets. Trim perimeter edge with reverse black anodised aluminium angle such
that angle covers edge of EchoPanel but not the face of the panel.
Ribs in EchoPanel Longitude material are to run vertically.

Refer also to Section R5 Whiteboard & Pinboard.

G5.7 SCHEDULE OF PIN BOARD COLOURS

Legend on Location Colour Product &


Drawings Manufacturer
PIN1A Wall Lining: Manufacturer:
• Tutorial 1 Woven Image
• Tutorial 2
• Tutorial 5 Range:
• Group Study A-1 EchoPanel 12mm
• Group Study A-3

Colour: 269-Wine
MONASH BUILDING H LEVEL 2 CARPENTRY 34

Legend on Location Colour Product &


Drawings Manufacturer
PIN1B Wall Lining: Manufacturer:
• Tutorial 3 Woven Image
• Tutorial 4
• Tutorial 6 Range:
• Tutorial 8 EchoPanel 12mm
• Industry
Engagement
Space

Colour: 908-Cream

PIN1C Wall Lining: Manufacturer:


• Tutorial 7 Woven Image
• Group Study A-5
• Group Study C-1 Range:
EchoPanel 12mm

Colour: 580-Sage

PIN2A Wall Lining: Manufacturer:


• Tutorial 1 Woven Image
• Tutorial 2
• Tutorial 5 Range:
EchoPanel Longitude

Colour: 269-Wine
PIN2B • Tutorial 3 Manufacturer:
• Tutorial 4 Woven Image
• Tutorial 6
• Tutorial 8 Range:
• Industry EchoPanel Longitude
Engagement
Space

Colour: 908-Cream
MONASH BUILDING H LEVEL 2 CARPENTRY 35

Legend on Location Colour Product &


Drawings Manufacturer
PIN2C Internal Wall Lining: Manufacturer:
• Tutorial 7 Woven Image
• Group Study A-5
• Group Study C-1 Range:
EchoPanel Longitude

Colour: 580-Sage

G5.8 CARPET WALL LININGS

Refer also to Floor Finishes - Section W of this specification.

G5.9 STUDDED RUBBER WALL LININGS

Product Colour / Image Location Legend

Studded Rubber • Group Study B-1 RB1


• Group Study B-2
Manufacturer: Spectrum Semi Open Wall
Partition
Range: • Group Study A-5
Studded Classic Rubber • Group Study C-1
Flooring • Group Study C-2
• Kitchen Joinery
Colour: JU.01C Table Base
Studded Rubber / G816 Lining
Glacier • Arrival and Catchup
Zone Joinery JU.01A
Tile Size: Table Base and
G816 Glacier
500 x 500 x 2.7mmm Bulkhead Lining
• South Corridor 2
JU.01B Table Base
Lining

G5.10 CORK WALL LININGS

Product Colour / Image Location Legend

Cork Wall Lining External Wall Lining CRK1


Manufacturer: (Public Area Side):
Market Timbers • Tutorial 6
• Group Study / A-4
Range: Cork Dekwall

Colour: Cayman

Tile Size: 600 x 300 x 3mm


Cayman
NRC: 0.10 direct fix
MONASH BUILDING H LEVEL 2 CARPENTRY 36

Cork Wall Lining Internal Wall Lining: CRK2


• Group Study / A-1
Manufacturer: • Group Study / A-2
Market Timbers • Group Study / A-3
• Group Study / A-4
Range: CORK PURE • Group Study / B-1
• Group Study / C-1
Colour: Dark • Group Study / C-2
• Group Study / C-3
Tile Size: Dark
600 x 300 x 4mm

Method of Installation: Cork Wall Tiles to be installed in horizontal 2/3 stretcherbond pattern

G5.11 PLYWOOD SUBSTRATES

Generally it is expected that the specified plasterboard linings will provide a suitable substrate for
wall finishes such as timber veneered MDF, carpet and rubber wall linings.

Plasterboard must be used where an acoustic rating is required as scheduled on the drawings and
in Clause G2.

In other cases, plywood may be used as an alternative to plasterboard as a substrate material.

Curved wall linings can be achieved with a substrate of multiple layers of 6mm Bendy plywood.
Plywood substrate is to receive wall linings as schedules and shown on the drawings.

Bendy plywood is available from Austral Plywood or approved equivalent


http://www.australply.com.au/austral-bendy
Ph: 07 3426 8666

G6 Ceiling Linings
G6.1 PLASTERBOARD CEILING LININGS

Refer to Section N Plastering of this specification.

G6.2 TIMBER CEILING LININGS

Refer to Clause G5 of this specification for perforated timber veneered board soffit linings.

To the Lift Lobby & Stairwell area provide 19mm thick KDHW timber strip trims to divide panels of
acoustic ceiling panels as shown on the Reflected Ceiling Plan.

G6.3 LAMINATED BOARD CEILING STRIPS

Refer to Ceiling Plan for strips of 24mm thick laminated particleboard that are to accommodate
ceiling mounted services. Laminated ceiling strips also form edge strips for acoustic ceiling panels.
MONASH BUILDING H LEVEL 2 CARPENTRY 37

G6.4 ACOUSTIC CEILING PANELS

Legend on Location Colour Product &


Drawings Manufacturer
AP1 Group Study A-1 Manufacturer:
Group Study A-2 Autex Quiet Space
Group Study A-3
Group Study A-5 Range:
Tutorial 5 Quiet Space 100mm
Tutorial 7 thick with Vertiface
Group Study B-1
Group Study C-1 Colour:
Group Study C-2 Vertiface Fawn

Installation:
Fawn Direct Stick

AP2 Group Study A-4 Manufacturer:


Tutorial 6 Autex Quiet Space
Group Study B-2
Range:
Quiet Space 100mm
thick with Vertiface

Colour:
Vertiface Civic

Installation:
Civic Direct Stick

AP3 North Stair Well Manufacturer:


South Stair Well Autex Quiet Space
Lift Lobby
Range:
Quiet Space 50mm thick

Colour:
Nude Black

Installation:
Direct Stick and as
Nude Black detailed

Stainless Steel Mesh:


This panelling is to be
covered with Woven
Wire stainless steel
mesh. Ref Section R -
Metalwork
MONASH BUILDING H LEVEL 2 CARPENTRY 38

Edge trims to Acoustic Ceiling Panels

Where acoustic ceiling panels AP1, AP2 & AP3 are not edged by meeting a wall surface or
laminated ceiling strip the following aluminium edge details area required:

• Provide 100 x 50 x 3mm thick powdercoated aluminium angle trim to the free edge of all
100mm thick acoustic insulation panels with 50mm leg fixed to plasterboard under the
acoustic panel.

• Provide 50 x 50 x 3mm thick powdercoated aluminium angle trim to the free edge of all
50mm thick acoustic insulation panels with 50mm leg fixed to plasterboard under the
acoustic panel.

Check lead times on stock and ensure orders are placed to allow for lead times.

STAINLESS STEEL WOVEN MESH


Provide Locker Woven Wire 4/16 – 4.75mm aperture x 1.6mm diameter wire in 316 grade stainless
steel.

G6.5 ACOUSTIC LAY-IN CEILING TILES

To the areas scheduled on the table below and as shown on the Reflected Ceiling Plan, provide
24mm thick Echopanel ceiling tiles laid into suspended metal ceiling tile framing system as follows:

Legend on Location Colour Product &


Drawings Manufacturer
ACT Wall Lining: Manufacturer:
• Tutorial 1 Woven Image
• Tutorial 2
• Tutorial 3 Range:
• Tutorial 4 EchoPanel 24mm
• Tutorial 6
• Tutorial 8 Sheet Size:
2400 x 1800

Cut into 6 panels of 1200


x 600 Tiles to be laid into
Colour: 908-Cream
ceiling grid

G7 Caulking & Sealing

G7.1 CAULKING AND SEALING

All junctions and gaps between abutting materials and finishes are to be fully caulked and or
sealed with the appropriate interior or wet area grade caulking or sealing compounds. Provide
continuous polyethylene backing rods, closed cell foam expansion joint fillers and pipe sleeves to
provide for consistent depth of all sealant joints.

This shall include but is not limited to the following;


• Window and door reveal frames to abutting surfaces.
• Expansion joints
• Plasterboard stopping angles to abutting surfaces that do not ‘butt’ tightly and finish flush.
• Services penetrations
MONASH BUILDING H LEVEL 2 CARPENTRY 39

Colour of sealants to be selected by the Architect.

It is the builder’s responsibility to fully seal the building in accordance with the requirements of the
Building Code of Australia and to ensure the building is vermin, insect and waterproof at the
completion of the works.

Refer also to the drawings for further extent and sealing requirements.
MONASH BUILDING H LEVEL 2 JOINERY 40

H JOINERY

H1 General
H1.1 SCOPE OF WORKS
Supply and install all joinery items to those areas described on the drawings.

In addition to the requirements as described herein, all work shall conform to the design intent as
indicated on the architectural documents and the relevant documentation of the associated design
consultants for this project.

H1.2 CODES AND REFERENCES

All materials and workmanship shall conform to the requirements of the following SAA codes:
AS 2688 Timber Doors
AS 2689 Timber Doorsets
AS 1909 Code of Practice for Installation of Timber Doorsets
AS 2146 Performance of Timber Window Assemblies
AS 2147 Code of Practice for the Installation of Timber Windows
AS 1540 1974 Timber Frames and Sashes for Windows

H1.3 OTHER- GENERAL

Joinery work generally is shown in the various detail drawings. Materials, sizes, types of fixings etc
are not necessarily described in the specification when on the drawings.

All works associated with the manufacture and installation of joinery items shall be carried out by
approved firms specialising in the types and standard of the specified works.

All dressed timber surfaces shall be finished smooth, even, free from machine marks and finally
hand sanded. Timbers shall be grained and colour matched throughout.

Joinery shall not be fixed until associated wet trades have cured and dried.

The Contractor shall replace any damaged components and make good joinery affected by
dampness, shrinkage or distortion of timbers.

All joinery work shall be fine sanded, fixings punched or recessed and puttied ready for paint finish
as scheduled.

Prime paint concealed faces of all joinery prior to installation.

H2 Windows
H2.1 ALUMINIUM FRAMED WINDOWS & DOORS
Refer section R Metalwork for aluminium windows and doors.

H2.2 TIMBER FRAMED WINDOWS

Timber framed windows, where shown on the drawings shall be fabricated from 32mm thick
rebated KDHW.
MONASH BUILDING H LEVEL 2 JOINERY 41

H3 Doors
H3.1 DOOR TYPES
Provide and fit doors and door furniture as shown on the Door Schedule and as follows:

a) Hollow Core Doors


Where hollow core doors are called for on the Door Schedule, they shall be flush panel,
constructed with cores of Cemac or equivalent first quality manufacture. Doors shall have
10mm thick kiln dried hardwood edge strips on both vertical edges. Doors shall be of the
sizes scheduled on the drawings and shall be a minimum thickness of 32mm. Facing shall
be "Redicote" hardboard suitable for painting.

b) Semi Solid Core Doors


Face doors with MDF suitable for painting and provide 10mm thick kiln dried hardwood
edge strips to both long edges. Door thickness minimum 35mm.

c) Solid Core Doors


Solid core doors shall comply with AS 1908 and AS 2688-1984 Section 5 with blockboard
or particleboard infill. Provide 10mm thick KDHW edge strips to both long edges. Doors
shall have a minimum overall thickness of 40mm.

d) Solid Core Doors with Vision Panels


Provide 10mm thick laminated glass vision panels to solid core doors nominated to have
vision panels. Provide KDHW glazing beads finishing flush with the face of the door. Doors
to be painted. Where scheduled, doors are also to have stainless steel panels and/or timber
veneered finish as detailed on the drawings.

e) Glazed Sliding Aluminium Framed doors


Refer Clause R3.1

f) Fire Rated Door


To plant room H2-Pl01 provide a fire rated door with pressed metal door frame as called on
the Door Schedule. Door is to achieve a -/120/30 FRL.

H3.2 DOOR FRAMES


Unless detailed otherwise, internal door openings shall be fitted with reveal linings of kiln dried
hardwood, 19mm thick to suit wall thickness, together with 30mm x 12mm door stops planted on
where necessary.

Refer to Section R METALWORK of this specification for details of aluminium door frames.

H3.3 ACOUSTIC SLIDING DOOR SYSTEM

Doors D16 shall be Lotus Acoustic Sliding Glazed Doors System with Rw37 rating as specified in
clause R3.1. Refer to Lotus specification - Appendix D

H3.4 AUTOMATIC SLIDING DOOR SYSTEM

Doors D09, D13, D14, D15, and D21 are to be provided with an automatic sliding door headbox
operator system as specified in Door hardware Schedule – Appendix A

H3.5 MASTERKEYING

Refer Door Hardware Schedule – Refer Appendix A.

Master-keying shall be undertaken by the proprietor.


MONASH BUILDING H LEVEL 2 JOINERY 42

Allow to provide construction lock cylinder as required to maintain security to new works until such
time master-keyed locks are supplied and installed by the proprietor.

H3.6 DOOR HINGES

All hinged doors to have a minimum of 3 No 100mm stainless steel heavy duty butt hinges as
specified in the Door Hardware Schedule – Appendix A.

Do not paint hinges.

H4 Door Schedule
The following Door Schedule provides a general guide to doors sizes, construction type of doors
and frames, paint finishes and types of hardware proposed.

Refer to Assa Abloy Door Hardware Schedule - Appendix A of this specification for specific
hardware details to be provided.

Note: All door sizes are approximate and shall be check measured on site.

Size Width x Other Refer


Door Frame
No Height Location also Hardware Finish
Type Type
(approx.) Schedule
AS, ELS, DC, SS1,
D01 920 x 2640 Tutorial 1 SC1 AF1
VP TBV1
SC1 AF1 AS, ELS, DC, SS1,
D02 920 x 2640 Tutorial 2
VP TBV1
920 x 2640 SC1 AF1 AS, ELS, DC, SS1,
D03 Tutorial 3
VP TBV2
920 x 2640 SC1 AF1 AS, ELS, DC, SS1,
D04 Tutorial 4
VP TBV2
D05 920 x 2340 Plant Room FR PM DC P
AF1 AS, ELS, DC, SS1,
D06 920 x 2640 Tutorial 5 SC1
VP TBV1
AF1 AS, ELS, DC, SS1,
D07 920 x 2640 Group Study A-1 SC1
VP TBV1
AF1 AS, ELS, DC,
D08 920 x 2640 Group Study A-3 GT CS
VP
D09 1500 x 2640 Group Study A-4 SL2 TF AUTO CS
AS, ELS, DC, SS1,
D10 920 x 2640 Tutorial 6 SC1 AF1
VP TBV2
Arrival and
D11 920 x 2640 Catchup Zone / HC TF P
Fire Hose Reel
North Corridor 2 /
D12 920 x 2340 HC TF P
Fire Hose Reel
D13 1500 x 2640 Group Study C-1 SL2 TF AUTO CA
D14 1500 x 2640 Group Study C-2 SL2 TF AUTO CS
D15 1500 x 2640 Group Study A-5 SL2 TF AUTO CS
Industry
2No AS, Hardware
D16 Engagement SL1 AF2
1350 x 2640 by Lotus
Space (IES)
920 x 2640 AF2 AS, ELS, DC, SS2,
D17 IES SC1
VP TBV3
MONASH BUILDING H LEVEL 2 JOINERY 43

Size Width x Other Refer


Door Frame
No Height Location also Hardware Finish
Type Type
(approx.) Schedule
AF2 AS, ELS, DC, SS2,
D18 920 x 2640 Tutorial 8 SC1
VP TBV3
AF2 AS, ELS, DC, SS2,
D19 920 x 2640 Tutorial 8 SC1
VP TBV3
AS, ELS, DC, SS1,
D20 920 x 2640 Tutorial 7 SC1 AF1
VP TBV1
D21 1500 x 2640 Group Study B-1 SL2 TF AUTO CS

DOOR TYPE
AL Aluminium door fully glazed to comply with AS1288
ESD Existing Door. Make good and allow for new paint finish to existing door
GT Glazed timber framed door
HC Hollow-core door with paint finish
SSC 40mm Semi-Solid core door with paint finish.
SC1 40mm Solid core door with Plywood timber veneer finish and Stainless-steel panel
as detailed on the drawings.
SC2 40mm Solid core door with paint finish
SL1 Acoustic Lotus Sliding Glazed Doors. Refer to Appendix D
SL2 Glazed timber framed auto sliding door with timber sidelight window as shown on
the drawings. Refer also to Appendix A
FR Fire Rated Door Panel with a -/120/30 fire rating with paint finish

FRAME TYPE
AF1 Aluminium frame with powdercoat finish
AF2 Aluminium frame with silver anodised finish
PM Pressed metal steel frame with paint finish
TF Timber door frame – 19mm with planted stop or 32mm rebated KDHW as detailed.

Note: Refer to Door Hardware Schedule – Appendix A for specification of all locks,
handles, door furniture & accessories.

DOOR STOPS
Allow to provide Dalco 13004 skirting mounted door stops or Dalco 12801 floor mounted door
stops to all doors. All door stops to be in satin chrome finish.

OTHER
AUTO Automatic Sliding Door with Slim Operator and Card Reader. Refer to clause
Appendix A and also Services Drawings
AS Acoustic Door Seals to achieve Rw>30
DC Door closer. Refer to Door Hardware Schedule
SM Smoke seals. Refer to Door Hardware Schedule
VP Glass Vision Panel to door
ELS ES2000 Electronic Strike with Reed Switch and Card Reader. Refer also Services
Drawings.

DOOR FINISH
P Paint finish – High Gloss Water based
SS1 Stainless Steel Panel – Rimex 2mm thick Stainless Steel Copper Satin. Refer clause
R7.3
SS2 Stainless Steel Panel – Rimex 2mm thick Stainless Steel Champagne Satin. Refer
clause R7.3
MONASH BUILDING H LEVEL 2 JOINERY 44

TBV Timber Veneered to match adjacent timber veneered board lining with Clear Stain
finish.
CS Clear Stain finish

NOTES
- Install door furniture at height 1000 AFL.
- A door in a required exit must be readily openable without a key by a single hand
downward action or pushing action on a single device which is located between 900mm
and 1100mm from the floor.
- Allow for several different colour paints to be used on doors. Final paint colour schedule to
be confirmed by architects.

H6 Laminated Joinery
H6.1 GENERAL

a) Fabrication of Joinery (Shop Fabrication)


Construction generally shall be screwed and glued, or other approved system. Dry, stapled
assembly will not be approved. Fabricate bench tops in a manner as recommended by materials
manufacturer. Fabricate units without joints unless counter length exceeds maximum available
length of materials.

Fabricate joinery with pre-cut openings, wherever possible, to receive hardware, appliances,
plumbing fixtures, electrical work, and similar items. Locate openings accurately and use templates
or roughing-in diagrams for proper size and shape. Smooth edges of cut-outs and, where located
in bench tops and similar exposures, seal edges or cut-outs with a water resistant coating.

Provide screw caps cover plugs to all visible fixings in carcase frame in colour to match selected
laminate colour.

b) Preparation of Joinery installation


Condition joinery to average prevailing humidity conditions in installation areas prior to installing.

Deliver inserts and similar anchoring devices to be built into substrates well in advance prior to
fittings being built in.

Prior to installation, examine shop fabricated work for completion, and complete work as required,
including back priming and removal of packing.

Thoroughly clean floor and walls of all areas to be permanently concealed by joinery. Effectively
seal-off all openings in flooring or walls against rodents prior to building in.

c) Installation of Joinery

Install the work plumb, level, true and straight with no distortions.

Shim as required using concealed shims. Install to a tolerance of 3mm in 2400mm for plumb and
level (including benchtops) and with 0.5mm maximum offset in flush adjoining surfaces, 2mm
maximum offsets in revealed adjoining surfaces. Scribe and cut work to fit adjoining work, and
refinish cut surfaces or repair damaged finish at cuts.

d) Delivery, Storage and Handling

Protect joinery during transit, delivery, storage and handling to prevent damage, soiling and
deterioration. Do not deliver joinery until painting, wet work, grinding and similar operations which
would damage, soil or deteriorate joinery have been completed in installation areas. If, due to
unforeseen circumstances, joinery must be stored in other than installation areas, store only in
MONASH BUILDING H LEVEL 2 JOINERY 45

areas meeting requirements specified for installation areas.

Once on site, all joinery must be fully covered and protected from damage and contact. Do not
place any items on or work from joinery units.

H6.2 LAMINATED BOARD MATERIALS

a) Laminated Benchtops
To all laminated benchtops as shown on the drawings provide bench grade Laminex
Redback laminated benchtops on 33mm thick Laminex Aquaban moisture resistant board
with white melamine underside:

Provide post formed coves and rounded edge profiles as detailed on the drawings.

Laminate colours as selected. Refer also Appendix B Colour Schedule

b) ABS Benchtop Edging


To front edges of benchtop, unless shown to be post formed in bench grade laminate,
provide ABS edging to match benchtop colour.

c) KDHW Trims & Benchtop Edging


Where shown on the drawings provide 19mm Vic Ash edge strips. Provide 3mm aris to
exposed edges. Vic Ash to be clear finished with a water based finish.

d) Cupboards - Generally
Outer carcase and cupboard doors shall be Laminex Industries 18mm thick Lamiwood MR
MDF of selected colour. All edges to cupboard doors and drawer fronts shall be edge
banded in 2mm thick ABS edging in colour to match selected laminate.

Internal shelves to underbench and overhead cupboards shall be 18mm thick white
melamine board and shall be height adjustable.

Note in some cases 25mm thick shelves are required as noted on the drawings.

e) Open Overhead Shelf / Cupboard Unit


Open laminated board shelf unit shall be Laminex Industries 18mm thick Lamiwood MR
MDF, unless noted otherwise, in colour to be selected in Natural Finish.

Note in some cases 25mm thick carcass are required as noted on the drawings.

f) MDF Board Materials


Provide MDF board in thicknesses as shown on the Drawings provide 3mm pencil round
edging. Provide paint finish, refer Section Q Painting.

g) AV Backing Board
As shown on the drawings in Tutorial Rooms provide laminated panel backing board to
Audio Visual ceiling mounted microphone.

Backing board shall be Laminex Industries 18mm thick Lamiwood MR MDF of selected
colour with 2mm thick ABS edging in colour to match selected laminate.

h) Laminated Board Ceiling Linings


As shown on the drawings in Group Study Rooms provide laminated board panel ceiling
linings for mounting of ceiling mounted fixtures.

Backing board shall be Laminex Industries 18mm thick Lamiwood MR MDF of selected
colour with 2mm thick ABS edging in colour to match selected laminate.
MONASH BUILDING H LEVEL 2 JOINERY 46

H6.3 TIMBER VENEERED BOARD MATERIALS

a) Timber Veneered MDF


Refer to clause G5.2

b) Perforated Timber Veneered MDF


Refer to clause G5.2

c) Screen Partition - Timber Veneered Divider Panels


Refer to clause G5.2

H6.4 ENGINEERED STONE BENCH & SPLASHBACK


To joinery unit JU.02A provide 20mm thick Caesarstone bench top and splashback.
o Caesarstone Colour in 5003 Piatra Grey
o Benchtop edge to be with pencil rounding to top and bottom edges.
o Refer also Joinery Colour Schedule.

Sink to be black composite Nanogranite sink – refer to Schedule of Sanitary Fixtures –


Clause M3.

H6.5 OTHER LININGS & BOARD MATERIALS

a) Marmoleum Benchtop

Provide benchtop substrate as 33mm thick Aquapanel.


Benchtop material to be marmoleum as shown on the drawings.
Underside of benchtop also to be lined with Marmoleum.
Provide marmoleum as specified in clause W3

Provide 10mm compact laminate edge

b) Studded Rubber Linings


Refer to clause G5.9

H7 Joinery Hardware & Accessories


H7.1 HIDEAWAY PULL OUT WASTE BIN

Provide hideaway pull out bin behind laminated door front to kitchenette cabinetry as shown
on the drawings as follows:

Hafele Hideaway Waste Bin – 2 x 40 litre capacity with soft closer

H7.2 CABLE SLEEVES

Provide black plastic cable outlet sleeves to bench tops as shown on the drawings confirm
location. Cable sleeves to be approx. 60mm diameter by Hafele or similar.

H7.3 DESK LEG

Provide 60mm diameter black adjustable desk leg to JU.07A & JU.07B where shown on the
drawings. Hafele Rondella or equivalent.

H7.4 CUPBOARD HINGES

All laminated cupboard door hinges shall be heavy duty 110 degree soft-closing overlay
hinges as manufactured by Blum or equivalent approved.
MONASH BUILDING H LEVEL 2 JOINERY 47

H7.5 OVERHEAD LAMINATED SLIDING DOOR TRACK

To all overhead cupboard laminated sliding doors provide the following sliding door track
Hafele EKU Clipo 15 SH – infront sliding door fitting or similar approved.

H7.6 DRAWER RUNNERS – UNDER BENCH DRAWERS

Drawer runners, sides and brackets are to be:


Blum Tandembox Antaro or approved equivalent

Drawer sides are powdercoated metal in colour to be selected.

Soft closing runners are concealed. Runners and sides are ordered as part of a set for each
drawer. Drawers to be to sizes as shown on the drawings. Length (front to back) of drawers
is to be the maximum that will fit in the cabinet.

Blum cabinet hardware is available from:


Wilson & Bradley
94 Bell Street, Preston
Tel: 03 9495 8900

H7.6 CABINET DOOR HANDLES

Door and Drawer Image Product


Handles

Below Bench To the top edge of all under bench


Cupboards and cupboard doors and drawer fronts
Drawers provide 35mm high powder coated
aluminium finger pull handles in colour
to be selected, as follows:

Hafele Cat No 126.27.904

Overhead Sliding Style Finish GOM Knob NB5 – black


Door Knobs rubber 40mm diameter.

Tall Cupboards To tall cupboards doors provide


FER300 Ferrara Lip Pull Handle with
rounded corners or approved
equivalent.

Size: 300mm door handles to be


installed vertical as shown on the
drawings colour in matt black.

Cupboard door handles can be


supplied from momohandles

www.momohandles.com.au
P: 1300 222 600
MONASH BUILDING H LEVEL 2 JOINERY 48

H7.6 CABINET DOOR LOCKS

Provide cabinet door locks and keys to data rack cupboards and laminated access panels
under group study tables.

H7.7 LED LIGHT STRIP – TO UNDERSIDE OF OVERHEAD CABINET

Provide LED light strip to underside of overhead cabinet as shown on the drawings. Refer
also Section L2

H7.8 TABLE BOXES – POWER AND AUDIO VISUAL

Allow to coordinate with AV contractor for installation of table boxes

H7.9 ACCESS PANELS TO GROUP STUDY TABLES

Provide lockable access panels in laminated plinth of Group Study tables.

H8 Skirting and Architraves


H8.1 ALUMINIUM SKIRTINGS

To all areas unless shown otherwise where plasterboard wall linings meet the floor provide
100mm high aluminium skirting in satin black powdercoat and/or natural anodised finish as
shown on the drawings.

H8.2 ARCHITRAVES

No architraves are to be used to cover the junction of door/window frames and wall linings.
Note also the use of plaster stopping angles to edges of plasterboard linings at all windows
and doors as detailed on the drawings. Refer Section N - Plastering.
MONASH BUILDING H LEVEL 2 GLASS AND GLAZING 49

J GLASS AND GLAZING

J1 General
J 1.1 SCOPE OF WORK

Generally provide window and door glazing as shown on the drawings.

J 1.2 STANDARDS AND CODES

Where applicable, current editions of the following Australian Standards shall be deemed to
govern requirements for relevant materials and workmanship under the contract.
AS 1170 SAA Loading Code, Part 2 - Wind Forces
AS 1263 Oil-based Putty
AS 1288 SAA Glass Installation Code
AS 1905 SAA Fire Door Code
Part 1 - Fire Resistant Doorsets
AS 2047 Aluminium Windows in Buildings
AS 2048 Code of Practice for the Installation and Maintenance of Aluminium
Windows in Buildings
AS 2208 Safety Glazing Materials for Use in Buildings (Human Impact
Considerations)

It is the Contractor's responsibility to determine the best glazing methods and techniques to
be adopted for each type of glass and glazing required under this contract.

The glazing installations in external walls and other areas exposed to weather and/or
differential air pressures and/or wet conditions and/or variable temperatures shall include
provision for the following essential requirements:

a) Thermal and settlement movements


b) Prevention of air leakage
c) Prevention of water penetration
d) Prevention of discolouration and/or etching of glass due to contamination by
other materials
e) Design for withstanding the effects of horizontal wind forces predictable for
the location and Terrain Category of the site (calculated in accordance with
AS 1170 Part 2).

J 1.3 SUBCONTRACTS

It is the Contractor's responsibility to ensure that all subcontractors (including nominated


subcontractors) are fully informed of the conditions and requirements which govern
subcontracts under this contract.

J 1.4 SPECIALIST SUBCONTRACTORS

All glass, glazing materials and glazing sealants shall be supplied and installed by an
approved competent specialist glazing subcontractor who is skilled in the type of work
required under the contract and who will accept responsibility for accurate fitting and correct
fixing and sealing of glass.
MONASH BUILDING H LEVEL 2 GLASS AND GLAZING 50

J2 Glazing Materials
J 2.1 GLASS TYPE AND THICKNESS

Refer to Window Schedule – clause R3.2 for glass types and thicknesses including U and
SHGC performance values.

To door vision panels and internal glazed doors provide 10.38mm thick laminated clear glass
to AS1288.

Glass type and thickness must comply with the relevant Glass Installation Codes and is to
be nominated on the glass manufacturer’s shop drawings.

J 2.2 GLASS GENERALLY

All glass used in the works shall be of best quality of the type or types specified.
All glass supplied for use under the Contract shall be warranted by the manufacturer and/or
the supplier to be free from air bubbles, crazing, distortion, cracks, scratches, chipped
surfaces and arises, discolouration, and similar defects and damage.

Glass with unacceptable defects will be rejected. All rejected glass shall be removed from
the site and new glass of the required type and quality supplied and installed at the
Contractor's expense.

J 2.3 GLAZING MATERIALS

All glazing materials used in the works, including as applicable, all setting blocks, spacers,
tapes, strips, gaskets, sealants, putty and other materials as required, shall be of approved
manufacture conforming with the description in AS 1288, and of the types suitable for the
glazing methods and techniques adopted.

J 2.4 EXTERNAL GLAZING UPGRADE

Refer to clause R3

J 2.5 SPECIAL GLASS MATERIALS

a) Acoustic rated glazing


To all windows as scheduled in clause R3 provide Viridian Vlam Hush glazing in
minimum 6.5mm thickness and also in thickness to comply with requirements of SAA
Code 1288.

b) Textured glazing
To the South Corridors Breakout Screen (SC) partition units provide panels of
textured glass infills as follows:

Item / Legend Product Image / Texture &


Privacy Level
Textured Glass Textured Glass
Infill / (TG1) 5 or 6mm thick toughened glass
Texture: Gluechip Glass

Supplier: Alltrade Aluminium Glass &


Stainless Steel Pty Ltd
Tel: 03 9706 4978
MONASH BUILDING H LEVEL 2 GLASS AND GLAZING 51

Item / Legend Product Image / Texture &


Privacy Level
Textured Glass Textured Glass
Infill / (TG2) 5 or 6mm thick toughened glass
Texture: Drift Glass

Supplier:
Alltrade Aluminium Glass & Stainless
Steel Pty Ltd

Textured Glass Textured Glass


Infill / (TG3) 5 or 6mm thick toughened glass
Texture: Broadline Reeded Glass
(20mm centred gaps)

Supplier:
Alltrade Aluminium Glass & Stainless
Steel Pty Ltd

c) Mirror Coloured Back Glass


To the Group Study A-2 Screen Wall partition

Item / Legend Material / Product Image / Texture & Privacy


Level
Toughened Tinted Manufacturer:
Mirror Glass / (MG) Aus Tuff

4mm thick Toughened Mirrors

Colour:
Bronze

Provide min 4mm thick toughened mirror glass as specified above or approved
equivalent to areas shown on the drawings.

Mirror Glass to Group Study A-2 Screen Wall partition to be oval shape as shown on
the drawings and shall have polished edges.

Adhere mirrors to substrate using heavy-duty double-sided mirror tape and neutral
curing strong bond silicone.

J2.6 SILICONE BEADING COLOUR

Silicone beading shall be in colour BLACK.

J2.7 GLAZING FILMS

Provide 3M brand glazing films to windows as follows:

a) Glazing Decals - DC
Provide single colour solid band vinyl decals to new glazed doors and windows as
MONASH BUILDING H LEVEL 2 GLASS AND GLAZING 52

shown on the Drawings.

Band to be minimum 75mm thick and 900-1100mm above floor level to the
underside.

Refer to drawings and provide artwork and samples for film design prior to
manufacture for the approval of the architect

J3 Glazing and Installation


J3.1 GLAZING PERFORMANCE

Refer to Window Schedule – clause R3.2 for glass types and thicknesses including U and
SHGC performance values.

Glazier to confirm all glass types and colours with Architect prior to manufacturing the
windows.

J3.2 WORKMANSHIP

A high standard of workmanship is required for the installation of all glass and glazing
materials under this contract.

All glazing methods, techniques and workmanship shall conform with the requirements of AS
1288. The installation of proprietary manufactured materials shall also conform with the
relevant manufacturer's recommendations and instructions.

Sealants shall be applied by approved skilled applicators who are experienced in the correct
use of sealants and recommended by the sealant manufacturer and/or supplier. Correct
primers and/or backing strips shall be used where required and where recommended by the
sealant manufacturer.

It is the contractor's responsibility to ensure that particular attention is taken in:


a) Accurate cutting and fitting of glass with adequate provision for thermal, structural
and settlement movements
b) Correct use of glazing materials
c) Weatherproofing of all external glazing
d) Protection of glass and glazing from damage at any time before the date of Practical
Completion of the Contract
e) Protection of all persons on or adjacent to the site from injury due to any works under
this

J3.3 ACCEPTANCE

The commencement of glazing shall be taken as the Contractor's acceptance of the quality
of frames to be glazed and specification for glazing.

Report any unsatisfactory conditions to the Architect prior to commencement.

J4 Completion
J4.1 CLEANING
During the progress of the works, keep the glass clean by prompt removal of foreign matter,
particularly cement products.
MONASH BUILDING H LEVEL 2 GLASS AND GLAZING 53

Carefully trim and clean off all glazing compound, take out and renew all defective glass and
leave in sound and perfect condition on completion.

Clean all new glass externally and internally.

All exposed surfaces and unframed edges shall be ground off to a smooth finish, arrised,
rounded and polished.

J4.2 WARRANTY

The Contractor, in conjunction with the glass supplier and glazing subcontractor, shall
provide a written warranty which guarantees the safety, adequacy and correct performance
of the glazing installation for an effective period of at least five (5) years after the date of
Practical Completion of the Contract.

The warranty shall obligate the warrantors to remedy without delay all defects which are
discovered during the warranty period, including, as applicable, removal of defective
materials and supply and installation of new materials without cost to the Principal.

Such defects shall include:


a) Water penetration through seals
b) Air leakage through seals
c) Cracking or breakage of glass due to thermal, structural or settlement movements, or
due to defects in the glass
d) Accidental breakage of glass by any persons employed by the Contractor or
Subcontractors and/or suppliers.
e) Etching or discolouration of glass, glazing materials or frames due to the effect of
contaminating materials used in the works.

J4.3 CERTIFICATES

The contractor, in conjunction with the glass supplier and glazing sub contractor, shall
provide a written certificate which states compliance of the installation and materials used
with AS1288.

In addition provide four (4) copies of plans showing the elevational area of all glazed window
panels (including skylights) fixing and support framing together with thickness of glass
pursuant to AS1288 and a Certificate of Compliance (Form 13) pursuant to regulation
15.7(2) of the Building Regulations . (This aspect is only applicable if the glazing
specification cannot readily be covered by AS1288).

These certificates shall be required to be submitted to the Building Surveyor for the purposes
of obtaining a Certificate of Compliance.
MONASH BUILDING H LEVEL 2 ELECTRICAL 54

L ELECTRICAL
Refer to separate documents issued by services engineers Lucid Consulting Australia

L1 Switchplate & GPO Colours


Provide black switch plates and GPO covers to all plates on laminated surfaces, timber
linings, studded rubber, echopanel pinboard, and carpet.

All other switch plate and GPO covers mounted on white painted plasterboard linings are to
be white.

L2 LED Strip Light – Underside of Overhead Cabinet


Provide LED Strip lighting underneath overhead cupboard as shown on the drawings.

LED light strip shall be routed to underside of cupboard carcass to finish flush as detailed.

LED Light Switch Double GPO


Provide two gang switch socket with extra light switch to operate LED light strip under
overhead cupboards in kitchen as shown on the drawings.

L3 Whitegoods & Equipment Schedule


Supply and install the following items of electrical equipment:

Item / Product Image Qty Comments


Location
Fridge / Top Mount Fridge 2 Allow for 50mm
Kitchen in Silver Finish clearances each side
LG375 GT-5S

700W x 680D x
1720H

Microwave / Samsung 32L 8 Allow 30mm


Kitchen 1000W Microwave - clearances each side
Black Mirror Finish

Code:
MS32J5133BM

517W x 384D x
297H
MONASH BUILDING H LEVEL 2 ELECTRICAL 55

Item / Product Image Qty Comments


Location
Dishwasher / Fisher and Paykel 1 Built into kitchen
Kitchen Built-under joinery as shown on
Dishwasher, drawings
Sanitise Series 7
DW60UC6X

Stainless Steel
finish

598W x 570D x 820-


880H

L4 Audio Visual
Allow for the coordination and builders work in connection with the installation of all Audio-
Visual equipment as shown on the Audio-Visual drawings issued separately by Norman
Disney & Young engineers.

Refer also Section G carpentry on the provision of noggings, timber blocking and/or
plywood blocking behind plasterboard linings to provide secure fixing for all items to be
fixed to walls.

L5 Table Boxes
Allow for the installation of table boxes in joinery items where table boxes are specified by
as part of the Audio-Visual scope.

Refer also to the Audio-Visual drawings issued separately by Norman Disney & Young
engineers.

L6 Switches and Controls on Accessible path of Travel


All switches and controls on an accessible path of travel, other than general purpose
outlets, shall be located not less than 900mm nor more than 1100mm above the plane of
the finished floor and not less than 500mm from internal corners.

Confirm final position on site and seek clarification from architect on switches and outlet
position if not shown on the internal elevation drawings.
MONASH BUILDING H LEVEL 2 PLUMBING 56

M PLUMBING
Refer also to separate documents issued by services engineers Lucid Consulting Australia.

M1 General
M1.1 SCOPE

Design, supply, installation, test, commission and maintain the Hydraulic Services as shown on the
accompanying drawings and as specified including all equipment and minor or incidental works
necessary for the complete Hydraulic Services Installation.
The Hydraulic Services shall be complete in every aspect to ensure proper operation of the
system.
Equipment shall be installed in accordance with the various Manufacturer's recommendations,
including type of controls, valves, fittings, taps, outlets etc., to ensure proper operation of the
system, and to suit the environment where equipment is installed.

M1.2 WORKS BY OTHER TRADES

The Hydraulic Trade Contractor shall resolve all works to be carried out by others with the
Contractor.

The list below is to assist in the design co-ordination of the Project and therefore not to be
considered as final.

In providing this guide, the Consulting Engineer takes no responsibility for demarcation between
trades or the resolution of inclusions and/or exclusions between trades.

1. Provision of electrical supply to the central hot water system control cubicle. All interface,
power and wiring associated with the system installation shall be carried out by this
Contractor.

2. Provision of power for cooktop and dishwasher within kitchen.

3. Dropped ceilings, bulkheads above and within cupboards to conceal pipework, modification,
trimming, etc. of studs to suit the passage of pipework by Contractor.

4. Ceiling access panels for access.

5. Grading of floors to suit the respective floor waste throughout the project.

6. Installation of roofing systems including roof gutter sumps, overflows, DP pops,


weatherproofing and grading of roof plant room slab into grated drainage outlets inclusive of all
associated flashings, etc. and below ground stormwater reticulation documented by Civil
Consultant.

7. Permanent access to roof and plant via suitable weatherproof access hatch within stairway to
OH&S requirements, etc.

8. Condensate and other drains from air conditioning equipment to tundish. Tundishes and drain
connections to waste for condensate collection shall form part of the Hydraulics Services
Contract.

9. Making good, including Fire Rating, all penetrations not used.


MONASH BUILDING H LEVEL 2 PLUMBING 57

10. Making good of all roadways, footpaths, etc. damaged by excavation and backfill by the
Hydraulic Contractor.

11. Provision of Grease Interceptor Trap of approximately 2000 litres to be constructed by this
Contractor as part of the building structure with rebates to suit HD Cover, inlets, outlets and
vent connections.

12. Provision of power to the hot water package.

M2 Schedule of Tapware
Provide tapware as specified below. All tapware generally shall be 3/4 turn ceramic dish washer
with chrome plated handles, unless other finishes are specified.

Taps shall be fitted with red and green (or blue) hot and cold indicators. The hot tap shall be on the
left. Taps shall be as follows:

M2.1 TAPWARE GENERALLY

Item Product Image Quantity


Room Qty
Kitchen Caroma Vivas Sink Kitchen 2
Sink Mixer Mixer in Chrome finish
Tap
WELS 4 Star Rating

Model No. 80102C4A

Kitchenette Caroma Urbane II Sink Arrival and 1


Sink Mixer Mixer in Black Catchup Zone
Tap
WELS 6 Star Rating

Model No. 99671C56A

Provide all other tapware to service mechanical and hydraulic plant as indicated on the services
drawings.

All tapware available through the following manufacturers;

Caroma Industries Ltd: Tel: 9926 5400


MONASH BUILDING H LEVEL 2 PLUMBING 58

M3 Schedule of Sanitary Fixtures

Item Product Image Quantity


Room Qty
Kitchen Clark Benchmark Single Kitchen 2
Sinks End Bowl, LHB, 1
Taphole, Stainless Steel
Model No. 1003.1

Kitchenette Abey, Cristadur - Arrival and Catchup 1


Sink Schock Mono Single Zone
Bowl with Drainer
Magma (Black)
Composite Nanogranite
Sink
Left-hand bowl
MONASH BUILDING H LEVEL 2 PLASTERING & RENDERING 59

N PLASTERING AND RENDERING

N1 General
N 1.1 SCOPE OF WORKS

The work shall be generally as described on the drawings and in the Finishes Schedule Section S
of this specification.

To all areas to receive plasterboard linings provide framing (studwork, furring channels or battens)
at maximum 600 centres unless noted otherwise on the drawings.

Provide all necessary approved staging and free-standing scaffold for safe and proper execution of
the plastering and rendering work.

N 1.2 STANDARDS

Comply with the following standards unless otherwise specified:


AS CA27 Code of Recommended Practice for Internal Plastering on Solid
Backgrounds
AS 1315 Specification and Methods of Test for Portland Cement (metric units)
AS 2592 1983 Gypsum Plaster for Building Purposes
AS 2185 Fibrous Plaster Products
AS 2186 Code of Practice for the Erection and Fixing of Fibrous Plaster Products
AS 2588 1983 Gypsum Plasterboard
BS 5262 External Rendered Finishes
BS 405 Expanded Metal (steel) for General Purposes

N2 Materials

N 2.1 PLASTERBOARD

Note various thicknesses and types of plasterboard as shown Section G2.1 Wall Types, including;

▪ 13mm plasterboard
▪ 13mm wet area plasterboard
▪ 12mm perforated plasterboard
▪ 6.5mm Gyprock Flexible

Plasterboard shall be standard 'Gyprock' as manufactured by C S R Building Materials or regular


'Victorboard' as manufactured by Australian Gypsum Ltd., with recessed edges.

Corner guards, casing beads, stopping beads, etc, shall be 'exangle' or equivalent approved
galvanised metal beads, fixed in unbroken lengths in each run.

Plasterboard sheets shall be stacked flat, protected from weather and cracked or otherwise
damaged sheets shall not be used. Plasterboard sheets shall be of lengths and widths to ensure
the least amount of jointing. Sheets joined clear of framing timbers shall have butt joints back
blocked.

Supply and fit plasterboard to bulkheads, ceilings and walls and line the interior of all cupboards.

Fix boards horizontally across the timber studding, with special countersunk head galvanised nails
32mm long, and punch slightly below the surface. Where applicable fix sheets to brick walls with
cornice adhesive to manufacturer's recommendations.
MONASH BUILDING H LEVEL 2 PLASTERING & RENDERING 60

The installation of ceiling linings shall conform strictly with the relevant Australian Gypsum
Technical Bulletins. In all cases, nails must not be less than 10mm in from the edge of the sheets.
Reinforce all flush joints with an approved 50mm wide cotton jointing tape embedded in plaster.
Likewise, reinforce the faces of boards at internal and external angles with cotton tape and metal
corner beads respectively.

Do all stopping and finishing with plaster compound recommended by the manufacturer to form
flush joints. All joints shall be flush jointed including vertical internal and external angles. Stop up
all holes, angles, nail and screw holes and elsewhere as required. Finish with flush even surfaces,
remove all blemishes, sand all joints and leave in a satisfactory condition ready for painting.

N 2.2 CURVED PLASTERBOARD WALLS

To curved sections of walls that are to receive plasterboard linings/substrates, provide 2No layers
6.5mm thick Gyprock Flexible plasterboard. This is to marry in with the single layer of 13mm
plasterboard that will be lining the adjacent straight sections of wall.

Both layers of Gyprock Flexible are to be stopped up to maintain acoustic attenuation.

N 2.3 PERFORATED PLASTERBOARD

To the ceilings as scheduled provide and install Rigitone Astral (12-20/66) perforated plasterboard
supported on metal suspensions system and acoustic insulation above.

Product Colour / Image Location Legend


Perforated Plasterboard with • West Corridor PP
Paint Finish • East Corridor
• South Corridor
Manufacturer: • Kitchen
Gyprock • Industry
Engagement
Range: Space
Astral Rigitone

NRC:
0.85 with 200mm air gap and
acoustic ceiling batts

Acoustic ceiling insulation above perforated plasterboard to be 100mm thick sound absorptive
insulation in black “Martini Absorb XHD100”. Refer to Clause G4.3

N 2.4 WET AREA PLASTERBOARD

Provide "Victorboard WR" sheets as supplied by Australian Gypsum Ltd or "Gyprock Aquacheck"
to walls as indicated on the Finishes Schedule Sections. DO NOT USE ON CEILINGS. Fix sheets
as follows:

Victorboard WR is fixed horizontally in all wet area rooms. Cut WR sheet to required sizes and
make all necessary cutouts. Cutouts for pipe penetrations to be made neatly using an appropriate
cutting knife or keyhole saw, leaving as small a gap as possible between the cut edges and the
pipe. This gap is to be sealed with Victorboard WR sealant. Edges of Victorboard WR sheets
adjoining floor to all areas, except shower recess, to be 10mm clear of finished floor levels.

Victorboard WR when used as a substrate for wall tiling in wet areas must be fixed with either
MONASH BUILDING H LEVEL 2 PLASTERING & RENDERING 61

Victorboard nails or screws. Adhesive is not to be used in these locations.

For wall tiles 6.5mm thick or less space Victorboard nails and screws at 200mm maximum centres
on intermediate studs and at 150mm centres on internal and external angles, and butt joints. For
wall tiles more than 6.5mm thick refer to Australian Gypsum for nail and screw fastening centres.
All joints and angles in areas to be tiled are sealed with Victorboard WR self adhesive tape.

N 2.5 VILLABOARD SUBSTRATE

To all areas to receive wall tiles provide 9mm thick Villaboard substrate as manufactured by
Hardie Bondor Building Systems.

Install strictly as per manufacturer’s technical design manual. Note different fixing requirements for
tiled and untiled walls.

Adhesive fixing shall not be used in tiled wall areas.

N 2.6 ACOUSTIC LAY IN CEILING PANELS

Acoustic ceiling panels are to be in 24mm thick Echopanel by Woven Image as specified at Clause
G6.5.

N3 Accessories and Details


N 3.1 PLASTERBOARD EDGING

To all plasterboard edges at windows and door frames etc, provide Rondo metal stopping angles.
Use Rondo P25, P26 to suit plasterboard thickness. Provide P50 and P60 shadowline stopping
angles where shown on the drawings.

N 3.2 CORNICE AND STOPPING ANGLES

Provide square set corners at all plasterboard ceiling to wall junctions and bulkheads unless
otherwise noted.

Provide galvanised metal Rondo Exangle Building Board Sections including corner beads, arch
beads, stopping angles and P35 control joints to all corners and edges of plasterboard.

N 3.3 PLASTERBOARD AND VILLABOARD EXPANSION JOINTS

Provide Rondo P35 control joints in plasterboard ceilings at maximum 12 metre centres in both
directions as recommended by plasterboard manufacturer. Provide Rondo P35 control joints in
Villaboard soffit linings at centres in accordance with the manufacturer’s instructions.

N 3.4 INSULATION

Refer to Section G CARPENTRY of this specification for details of wall and ceiling insulation.
MONASH BUILDING H LEVEL 2 PLASTERING & RENDERING 62

N 3.5 CEILING ACCESS PANELS

Where shown on the services drawings stop up to concealed hinge ceiling access panels as
follows:

Supply and install CSR Gyprock concealed hinged Access Panels as indicated on the
drawings.

Size: 600 x 600mm with push click closing mechanism.

N4 Plaster Repairs
To any existing plaster surfaces that are scheduled to be retained allow to patch cracks and holes
and bring the surface to a smooth finish ready for painting. Refer to finishes schedule.
MONASH BUILDING H LEVEL 2 TILING 63

P TILING

P1 General
P1.1 SCOPE OF WORKS

For the extent of all tiling refer to the drawings and Section S of this specification – Finishes
Schedule.

P2 Materials
P2.1 WALL TILES SCHEDULE

To the extent shown on the drawings provide the following wall tiles as follows:

Location / Room Surfaces Wall Tile Specification Colour & Colour Image
Finish
Kitchen JU.02B Kitchen Classic Ceramic Colour:
Splashback Lavanda
Walls where Range: Vogue System
shown Interni & Trasparenze Finish:
Satin IN Interni
Size: 100 x 200
Stacked horizontally

Available from:
Classic Ceramics
Contact: Angela Young
Tel: 03 9682 6555

Lead Times
Ensure that lead times are established and orders are placed in time to secure materials well
before needed.

Grout Colours
Grout colours to be selected generally to match with colour of tile. Sample area to be provided.

P2.2 TACTILE INDICATORS

Refer Section W6 Tactile Indicators

P2.3 ADHESIVES

a) Adhesives shall comply generally with AS 2358 for thin or thick bed applications as
appropriate. Use adhesives to fix dry tiles to dry backgrounds only except that some
cement based adhesives may be used to butter dry tiles before fixing to mortar beds.
Spread adhesives to backgrounds in all small areas (not exceeding 1m²) and fix the tiles to
each area before surface drying of the adhesive commences. When using adhesives
provide adequate ventilation and take necessary fire precautions.

b) Cement based adhesives may be used on backgrounds of render, concrete, brick or block
but not on plaster, wood, paint or glazed surfaces.
MONASH BUILDING H LEVEL 2 TILING 64

c) Organic based adhesives may be used on backgrounds of render, concrete, brick, block,
plaster, wallboards and sheets, metal, glazed surfaces (eg existing tiling) and also painted
surfaces if the adhesive is not solvent based. Where so specified, organic based adhesives
shall be types recommended by the manufacturer for flexibility or superior waterproof
qualities.

d) Mortar Beds: Tiling: Mortar beds may be used on rigid low movement backgrounds with
adequate key and suitable suction. The latter may be achieved where necessary by wetting
the background. Alternatively a bonding agent may be applied to the background to
improve adhesion.

Make mortar beds from Portland cement and graded sand, with minimum water added.
Proprietary admixtures may be included if approved. Measure materials by volume in
suitably calibrated devices. The selected proportions shall remain uniform from batch to
batch. Mix materials mechanically unless otherwise approved. Use mortar within 2 hours of
mixing.
Thick Mortar Beds: Select proportions from the range 1:3 to 1:4 cement:sand
Thin Mortar Beds: Select proportions from the range 1:1 to 1:2 cement:sand

e) Bedding Thickness: Tiling


Thin Bed may be used when the background is true to within 3mm when tested with a 2m
straight edge. Thin beds shall not exceed the maximum thickness recommended by the
manufacturer. If the surrounding conditions are dry, application may be by the notched
trowel method; otherwise use the solid bed method. With either method the entire back tile
shall be covered by adhesive when the tile is bedded.
Thick Bed use on backgrounds with deviations up to 6mm from true when tested with a 2m
straight edge and with tiles having deep keys or frogs. Thick beds shall not exceed the
maximum thickness recommended by the manufacturer, or 12mm whichever is the less,
except that mortar beds for floor tiles may be up to 20mm thick. Apply thick beds by the
solid bed method or by the buttering method.

f) Bedding Methods: Tiling


Notched Trowel Method apply the bed to the background as a floated coat, bring to a true
surface, then form ribs on the surface by combing with a notched trowel of the type
recommended by the adhesive or additive manufacturer.
Solid Bed Method apply the bed to the background as a floated coat and bring to a true
surface.
Buttering Method spread the appropriate mix evenly over the back of the tile to a thickness
slightly greater than the final thickness required, to that when the tile is pressed or tapped
firmly into position the correct thickness is achieved and the tile is solidly bedded over its
entire surface, including corners. Fill keys or frogs with the bedding mix before buttering.

P2.4 STAINLESS STEEL TILE TRIMS

To the perimeter and meeting corners of all wall tiles provide BAT stainless steel tile trims unless
noted otherwise as detailed and shown on the drawings.

P3 Workmanship

P3.1 DRYING OF SUBSTRATE


No tiling works shall commence until tiling substrate has reached required dryness in accordance
with AS1884 - Floor Coverings - Resilient Sheet and Tiles - Laying and Maintenance Practices and
Manufacturers Recommendations. Carry out all testing of substrate to confirm requirements of
AS1884.
MONASH BUILDING H LEVEL 2 TILING 65

The sub-contractor shall make the necessary allowances to provide proprietary sealants to enable
tiling works to proceed if the moisture content can not be reached in time to meet project
programming commitments.

P3.2 WALL TILE FIXING

Fix wall tiles to WR sheets using only an organic based adhesive complying with Australian
Standard AS 2358-1980, "Adhesives for Ceramic Wall Tiles and Mosaics" Part 1-139a Type 1.

After adequate preparation of the surface apply adhesive to the whole of the area to be tiled, one
square metre at a time, in accordance with the manufacturer's specifications. Use a notched edge
trowel in a horizontal direction, never vertically, ensuring all fastener heads are properly sealed.
Firmly press tiles into the ribs of the adhesive before skinning occurs, ensuring there is contact
over the entire back surface of each tile.

Fill joints continuously at internal corners in accordance with tile and adhesive manufacturer's
specifications. Expansion joints are to be filled entirely with an approved flexible waterproof
sealant.

P 3.3 JOINTING

Joints shall be filled with a mortar of one part white cement and four parts whiting or pre-mixed
tiling grout. Colouring shall be introduced to Architect's directions.

P 3.4 SET-OUT

Confirm set out points for all interior and exterior paving prior to the commencement on works on
site.

P4 Completion

P 4.1 PROTECTION UPON COMPLETION

Upon the completion of the works all tiled surfaces are to be cleaned and protected from following
trades that require access onto the tiled areas to carry out their works. Protection works shall
remain in place until the builders final project clean in carried out.

Do not place tool and or other items of equipment such as fixtures or fittings to be installed directly
onto newly tiled surfaces.

P4.2 REPLACEMENT TILES

A minimum area of 0.5m2 of spare wall tiles is to be supplied to the Proprietor on completion for
future replacements.
MONASH BUILDING H LEVEL 2 PAINTING 66

Q PAINTING

Q1 General
Q 1.1 SCOPE OF WORKS

Scope generally includes all plasterboard & Villaboard lined walls, bagged masonry walls,
plasterboard ceilings and bulkheads, concrete floors and selected concrete ceilings, plywood and
timber batten linings, and door & window frames where scheduled to receive paint/stain finish.

Q 1.2 WARRANTY

Minimum 3 years warranty on painting.

Q 1.3 RELEVANT STANDARDS AND CODES

Comply at all times with the following standards:

AS 2060-1977 Pressure Sensitive Adhesive Masking Tapes


AS 2105-1980 Inorganic Zinc Silicate Paint
AS 2204-1978 Zinc-rich Organic Priming Paint
AS 2301-1980 Wood Primer, Solvent Borne, Brushing
AS 2302-1980 Undercoat, Solvent Borne, Exterior/Interior
AS 2602-1983 Paints for Steel Structures - Full Gloss Polyurethane (two-pack)
AS 2603-1983 Paints for Steel Structures - Full Gloss Epoxy (two-pack)
AS 2798-1985 Paints and Related Materials - Extenders
AS K108-1963 Metal Priming Paint, Anti Corrosive
AS K126-1964 Full Gloss Enamel, Oil and Petrol Resistant
AS K143-1962 Semi-gloss Enamel, Oil and Petrol Resistant
SAA TRI, Parts 1 to 10 -1982 Paints for Buildings

Q2 Workmanship

Q 2.1 MATERIALS

All paint products must be manufactured by Dulux.

Paint products must also satisfy all of the below requirements:


1 All interior paints, finishes, adhesives and sealants to be low-VOC or zero-VOC, unless
specified otherwise
2 Paints to be grey water safe
3 Paints to be water based unless specified otherwise
4 Paints to be non-toxic
5 Paints to be biodegradable
6 Paints to be ozone friendly and free from carcinogens and phosphates

Q2.2 ACCEPTANCE OF WORKING CONDITIONS AND SURFACES

Ensure that the subcontractor and tradesmen carrying out work specified in this Section shall upon
commencing work accept responsibility without reservation for the surface upon which the paint or
coating shall be applied and the conditions prevailing or likely to prevail during the application of
the finish and while it is still wet.

The application of a base coat or finish shall be deemed to be acceptance of the surface and
prevailing conditions.
MONASH BUILDING H LEVEL 2 PAINTING 67

Q 2.3 PREPARATION

All work to be coated shall be prepared by scraping or rubbing down, priming and stopping up and
shall be brought to a smooth, even surface before coating.

Timber work to be stained must be thoroughly sanded smooth and all sharp edges arrised before
staining is commenced.

Q 2.4 BETWEEN COATS

Stopping shall be done between coats and surfaces shall be lightly sanded between coats.

Q 2.5 COATING BEFORE FIXING

Timber slats are to be stained and clear finished prior to fixing to the wall.

Ensure that all areas to be finished with timber slats or plywood panels with expressed joints have
substrates or battens painted black prior to fixing of finishes.

Q 2.6 APPLICATION OF TIMBER FINISHES

a) Scope
The scope of timber surfaces to be receive clear or stained finishes includes:
▪ Timber door and window framing to Function Rooms 1-4
▪ Timber Roller Shutter to Kitchen/Bar
▪ Timber batten wall linings near Kitchen servery in Passage
▪ Timber servery counter in Kitchen/Bar
▪ External and Internal plywood linings

Q 2.7 EXISTING SURFACES

Existing surfaces to be painted shall be prepared by removing all loose and flaking paint and
sanding in preparation for primer. Resultant bare areas to external woodwork should be filled and
spot primed. Bring all surfaces to a clean, smooth and even state before priming.

Apply appropriate primer and/or undercoat to all existing surfaces that are to be painted.

Q3 Paint Systems

Q 3.1 COLOUR SCHEDULES

Allow in all areas for colour changes between ceilings and walls. Allow for the use of up to 8
different wall and door colours throughout.

A specific colour schedule will be provided by the Architect.

Q 3.2 COLOUR SAMPLES

Provide samples of the following;


- Clear/stained external and internal plywood. Samples must be provided on the actual
plywood material to be installed.
- Clear/stained timber batten linings. Samples must be provided on the actual timber batten
material to be installed.
MONASH BUILDING H LEVEL 2 PAINTING 68

Q 3.3 PAINT SYSTEMS SCHEDULE

The following paint systems are to be used on the areas as set out in the finishes schedule for
walls and ceilings and for specific areas as also listed below:

The following paint systems are to be used on the areas as set out in the finishes schedule for
walls and ceilings and for specific areas as also listed below:

Paint System Products and Application Extent


Dulux Ceiling White 1 coat sealer / undercoat All plasterboard ceilings and
Acrylic (Flat Finish, 2 coats Dulux Ceiling White ceiling bulkheads
low VOC)

Dulux Low Sheen 1 coat sealer / undercoat All plasterboard walls and
Acrylic (low VOC) 2 coats washable low sheen Villaboard walls
acrylic
Dulux Aquanamel, 1 coat sealer/undercoat -
Semi Gloss 2 coats enamel top coat

Dulux High Gloss 1 coat sealer / undercoat Doors, Painted Timber & MDF,
Acrylic (low VOC) 2 coats washable gloss acrylic Painted timber door frames,
painted steel door frames

Dulux Duremax 1 coat oil based Internal Steel Work


GPE Long Life primer/undercoat
Epoxy System 2 coats gloss enamel

Dulux Intergrain 2 coats timber stain (sample to Interior timber veneer, plywood
Ultraclear Interior be provided to confirm number linings, timber door and window
Stain or equivalent of stain coats) frames
2 coats clear finish
(colour to be
selected)

Q4 Timber Work - Clear Finishing


All timber linings, plywood linings and timber frames specified to receive clear/stained timber
finishes shall be treated as follows:
a) Punch and fill all nail fixing points with non shrink filler in colour to match the timber.
b) Sand all timber work progressively to a fine 300 grit finish removing any sharp corners.
c) Apply coats as per Q3.3 Paint Systems
d) Lightly sand all timber work with fine sand paper and/or steel wool in between coats of clear
finish to achieve a furniture quality silky smooth finish.

Q5 Completion
Q6.1 TOUCH UP WORK

Touch up painting where required to make good all trades, clean off all marks, paint spots and
stains throughout, including all hardware and fittings and leave job in a clean and tidy condition.

Q6.2 TOUCH UP PAINT


One litre tin of each colour and finish used on the works shall be left by the Painter for future
touching up by the Proprietor. Clearly mark the colour on the lid of each tin.
MONASH BUILDING H LEVEL 2 METALWORK 69

R METALWORK

R1 General
R 1.1 SCOPE OF WORK

Generally but not limited to the supply and installation of new metalwork items as shown on the
drawings and described in this Section.

R 1.2 STANDARDS AND CODES

Pursuant to General Requirements, comply with the following standards unless otherwise
specified:

Workmanship
AS 2047 Aluminium Windows
AS 1627 Code of Practice for Preparation and Pretreatment of Metal Surfaces Prior to
Protective Coating
AS 1796 SAA Welding Certification Code
Steel
AS 1131 Dimensions of Hot-Rolled Structural Steel Sections
AS 1163 Structural Steel Hollow Sections
AS 1397 Hot-Dipped Zinc-Coated or Aluminium/Zinc-Coated Sheet in Coil and Cut Lengths
AS 1449 Wrought Alloy Steels - Stainless and Heat Resisting Steel Plate, Sheet and Strip
AS 1769 Welded Stainless Steel Tube for Plumbing Applications
Aluminium
AS 2047 Aluminium Windows
AS 1231 Anodic Oxidation Coatings on Aluminium for Architectural Applications
AS 1734 Wrought Aluminium and Aluminium Alloy Flat Sheet, Coiled Sheet and Plate for
General Engineering Purposes
AS 1866 Wrought Aluminium and Aluminium and Aluminium Alloy Extruded Rod, Bar and
Solid
AS 1867 Wrought Aluminium and Aluminium Alloy Drawn Tubes for General Engineering
Purposes
AS 1956 Anodic Oxidation Coatings in Aluminium for Decorative and Automotive
Applications.
Coatings
AS 1192 Electroplated Coatings of Nickel and Chromium
As 1650 Galvanised Coatings

R 1.3 WORKMANSHIP

All work shall be of high standard, accurately and neatly constructed and fitted, and securely fixed.
Proprietary products shall be installed in accordance with manufacturer's instructions. All
dimensions and details shall be checked on site before work proceeds.

Form bends in steel tube without deforming the true cross section, using methods recommended
by the tube manufacturer.

Items to be assembled and erected on site shall be pre-assembled in the workshop and match
marked. During assembly and erection, do not strain, twist, bend or open such items to bring them
to their true positions.

Generally, fixings of metal units shall be concealed, but where concealment is not practicable,
fittings shall be countersunk flush with adjacent surface and shall have finish to match that of the
unit concerned.
Welding and/or brazing exposed to view in completed work shall be completely filled, ground off
MONASH BUILDING H LEVEL 2 METALWORK 70

flush with adjacent surfaces, and finished to match exactly with the finish of the item concerned.
Exposed joints and surfaces shall be free from welding, brazing and heat blemishes. Welding in
aluminium shall be by an inert gas Architect process or by resistance or pressure welding where
appropriate.

Cut edges, drilled holes, rivetted joints, and flat sheets shall be clean, neat, free from burrs and
indentations. Remove sharp edges without excessive radiusing. Fit mitred joints accurately to a
fine hairline. All exposed surfaces shall be free from warps, hammer marks, distortions, scratches
and other imperfections.

R2 Metal Ceiling & Wall Framing


R2.1 SUSPENDED METAL CEILING FRAMING

Provide suspended metal ceiling framing to all areas to receive new ceilings as shown on the
drawings. Plasterboard ceilings will be screwed into suspended furring channels.

Ceiling tile areas to have lay in tiles into suspended grid system as specified in Section N
Plastering.

Metal ceiling grid ‘T’ bars to be powdercoated in colour to be selected to match acoustic lay
in tiles.

R2.2 METAL STUD WALL FRAMING

Provide metal studwork as shown on the drawings. Refer Section G for wall construction and metal
stud specification.

Note: some wall framing is to be carried with timber stud refer section G.

R3 Window and Door Frames


R 3.1 ALUMINIUM DOOR & WINDOW FRAMES

a) AL1 - Internal Showcase Aluminium Window Frames


To Tutorial Room windows AL1 as scheduled in R3.2 Window Schedule.

Provide 32 x 25 x 3mm Aluminium channel glazing to fixed glazed panels with 8mm thick
Aluminium perimeter window reveals as detailed on the drawings.

Powdercoat finish aluminium window reveals and channel glazing in colour to be selected

b) CR120 - Internal Full Height Aluminium Window Frames


To Aluminium windows CR120 as scheduled in R3.2 Window Schedule.

Provide Criterion Platinum 120 Aluminium window suite with Offset single glazing frame.
Aluminium frames are to be black anodised or black powdercoated aluminium frames.
Provide Single Glazing to windows in 6.5mm VLam Hush Glass.

Door and Window frame to suit a 92mm wall framing and 13mm plasterboard wall linings.
MONASH BUILDING H LEVEL 2 METALWORK 71

c) AL2 - Internal Round Aluminium Window Frames


To Window W22, W24 and W12 in Group Study C1, C2 and Tutorial Room 5.

Provide a combination of 32 x 25 x 3mm Aluminium channel glazing and 25 x 25 x 3mm


aluminum angle to house round shaped glass panels. Provide 8mm thick Aluminium
perimeter window reveals as detailed on the drawings.

8mm thick aluminium window reveal to be rolled to required radius.

Powdercoat finish aluminium window reveals and channel glazing in colour to be selected

d) Automatic Sliding Door Operator


Provide a low profile automatic sliding door operator to Door D09, D13, D14, D15 and D21.
Auto sliding door operator are to be encased in black anodised or powdercoated aluminium
frame. Install as per manufacturers instruction and securely fixed to structural steel door
head beam support.

Automatic Sliding Door Operator shall be as follows Record STA-Series STA21 110H x
165D. Refer also to Appendix A – Door Hardware Schedule and Services Engineer’s
document on electronic door lock security requirements.

e) Internal Acoustic Aluminium Glazed Sliding Doors


Doors D16 and fixed side panel windows.

Provide Lotus SL80+ Glazed Acoustic Sliding Doors System. Refer Appendix B for
Acoustic Sliding Door specification.

Refer also Section H4 Door Schedule and Appendix A Door Hardware Schedule and the
Drawings.

f) South Corridor Informal Breakout Area - Internal Screen Partitions

Provide Criterion Gallium 45 Glazing frame and 50mm square Corner Post as detailed on
the drawings.

Provide textured glass and timber veneered infill panel as shown on the drawings. Refer
also Section J Glazing and Section G Carpentry

g) Shop drawings
Prior to fabrication, supply shop drawings showing the following information where
applicable to the window installation:
• Layout (sectional plan and elevation) of the window assembly.
• Full size sections of members.
• Methods of assembly
• Methods of installation, including fixings, caulking and flashing.
• Provision for vertical and horizontal expansion.
• Junctions and trim to adjoining surfaces.
• Hardware, fittings and accessories.
• Lubrication requirements.
• Glazing details including glass type & thickness, method, tolerances, rebate depths, edge
restraint, and the like.
MONASH BUILDING H LEVEL 2 METALWORK 72

h) Warranty
The contractor for this work shall provide a written and signed warranty in a form approved
by the Builder that warrants the installation for a specified period against defects which
might occur after Practical Completion of the works, normal wear and tear excepted. The
warranty shall certify that any such defects shall be rectified by the Contractor, or an
alternative party if approved by the Proprietor, and that any cost of the rectification work
shall be borne by the Warrantor.

The warranty period shall commence on the Date of Practical Completion as indicated on
the Certificate of Practical Completion to be issued by the Construction Manager.

The warranty period shall be 5 years from the Date of Practical Completion

R3.2 RETROFIT DOUBLE GLAZING – SPECIALIST SUBCONTRACTOR

AL3 – Retrofit Add On Double Glazing to Existing External Glass for Soundproofing
To Tutorial Room 1 and 2 External Windows, W35, W36, and W36.

Provide an additional layer of aluminium framed horizontal sliding window with single
glazing. Horizontal sliding window are to be retrofitted on the interior side of existing
external window with an airgap to create a double-glazed window system for noise
reduction. Aluminium frame colour to match existing window

Window frame are to be a proprietary window system and installed by a specialist glazing
contractor for retrofitting existing external windows for noise reduction.

Retrofit Double Glazing composition shall be:


6mm thick external window glass (Existing external window), with 100mm airgap, and a
new layer of 10.38mm laminated glass (New internal window). Refer also Section J Glazing

Suggested specialist subcontractors for this work are as follows:


Stop Noise
Website: www.stopnoise.com.au
Email: info@stopnoise.com.au
Phone: (03) 9775 0550
Or
Magnetite
www.magnetite.com.au

R3.3 WINDOW SCHEDULE

Window Location Size Width x Frame Glass Other


No Height
(approx.)
W01 Tutorial 1 2600 x 1650 AL1 6.5V
W02 Tutorial 2 2000 x 2700 CR120 6.5V DC
(Black)
W03 Tutorial 2 2900 x 1650 AL1 6.5V
W04 Tutorial 3 3100 x 1650 AL1 6.5V
W05 Tutorial 3 900 x 2700 CR120 6.5V DC
(Black)
W06 Tutorial 3 700 x 2700 CR120 6.5V DC
(Black)
MONASH BUILDING H LEVEL 2 METALWORK 73

Window Location Size Width x Frame Glass Other


No Height
(approx.)
W07 Tutorial 4 2700 x 1650 AL1 6.5V
W08 Tutorial 4 2400 x 1650 AL1 6.5V
W09 Tutorial 5 850 x 2700 CR120 6.5V DC
(Black)
W10 Tutorial 5 8400 x 1650 AL1 6.5V
W11 Group Study A-1 2700 x 1650 AL1 6.5V
W12 Tutorial 5 2300mm AL2 6.5V
Round Diameter
W13 Group Study A-3 1450 x 2700 CR120 6.5V DC
(Black)
W14 Tutorial 6 900 x 2700 CR120 6.5V DC
(Black)
W15 Group Study A-4 1500 x 2600 TF2 6.5V
W16 Group Study A-4 1200 x 2700 ALC 6.5V DC
W17 Group Study A-1 1500 x 2700 CR120 6.5V DC
(Black)
W18 Tutorial 6 1500 x 2700 CR120 6.5V DC
(Black)
W19 Tutorial 6 2300 x 1650 AL1 6.5V
W20 Tutorial 6 2300 x 1650 AL1 6.5V
W21 Group Study C-1 1500 x 2600 TF 6.5V
W22 Group Study C-1 1200mm AL2 6.5V
Round Diameter
W23 Group Study C-2 1500 x 2600 TF 6.5V
W24 Group Study C-2 1200mm AL2 6.5V
Round Diameter
W25 Group Study C-3 1500 x 2700 CR120 6.5V DC
(Black)
W26 Group Study C-3 1500 x 2600 TF 6.5V
W27 Industry 1200 x 2700 CR120 6.5V DC
Engagement Silver
Space (IES)
W28 Tutorial 9 5650 x 1650 AL1 6.5V
W29 Tutorial 8 5650 x 1650 AL1 6.5V
W30 Group Study B-2 5000 x 900 ALC 10L
W31 Tutorial 7 1450 x 2700 CR120 6.5V DC
(Black)
W32 Tutorial 7 5000 x 1650 AL1 6.5V
W33 Group Study B-1 1500 x 2600 TF 6.5V DC
W34 Group Study B-1 2600 x 1650 AL1 6.5V
W35 Tutorial 1 9600 x 2700 AL3 10L
Full Height
External Glazing
MONASH BUILDING H LEVEL 2 METALWORK 74

Window Location Size Width x Frame Glass Other


No Height
(approx.)
W36 Tutorial 1 6600 x 2700 AL3 10L
Full Height
External Glazing
W37 Tutorial 2 9000 x 2700 AL3 10L
Full Height
External Glazing
Legend

FRAMING
CR120 Aluminium 130 x 35 Criterion Platinum Suite 120 with Offset Glazing Frame with
Single glazed. Aluminium frame in black or silver anodised
AL1 32 x 25 x 3mm Aluminium channel glazing with 8mm Aluminium window reveals.
Refer clause R3.1
AL2 Aluminium Frame
AL3 Aluminium Frame. Retrofitted Add-On Double Glazing.
ALC Aluminium Channel Glazing 32 x 25 x 3mm unless noted otherwise on the drawings
with powdercoat finish in colour to be selected.
TF Timber Frame

GLAZING
10L 10.38mm Laminated Clear Glass
12L 12.38mm Laminated Clear Glass
6.5V 6.5VLam Hush Clear Glass

OTHER
DC Adhesive film decal strip to Monash University Signage Standard

**Glazier to confirm all glass types and colours with Architect prior to manufacturing the windows.

Supply all window suites complete with sub sills with drainage slots.

All frames shall be mechanically joined with stainless steel spline screws. Seal all mullion to sill
joints with silicon sealant. Provide strengthening plates to jamb frames supporting solid timber
doors.

All installations shall be installed by an experienced aluminium installer to the specification of the
fabricator and manufacturer’s recommendations. Refer to the drawings for details. All installations
shall be level and plumb and securely fixed at jambs head and sill. TIMBER PACKING SHALL
NOT BE USED.

All frames shall be delivered to site with protective adhesive tape to protect frame finish from
damage until completion of work.

R4 Aluminium Components
R4.1 ALUMINIUM PLATE, ANGLE & CHANNEL TRIMS

Where detailed on the drawings around door and window reveals, provide 3mm thick aluminium
plate.

Angle & channel trims in black anodised or matt powdercoated finish unless noted otherwise.
MONASH BUILDING H LEVEL 2 METALWORK 75

R5 Whiteboards & Pinboards


R5.1 WHITEBOARDS

Provide whiteboards as shown on the drawings as WB as follows:

Whiteboards shall be:


- Slimline Aluminium frame
- Hard wearing commercial quality whiteboard
- Magnetic surface
- Provided with pen tray

Whiteboards noted on the drawings as WBC to be provided with AV screen capture decals to be
installed by Audio Visual contractor.

Whiteboard units are supplied by Educational Writing Boards.


Educational Writing Boards
Ph: (03) 9561 6000

R5.2 PINBOARD WALL LINING

To the area described in clause G5.7 and shown on the drawings, provide pinboard directly
adhered to the wall linings. Provide natural anodised aluminium angle trim to the exposed edges of
the pinboard material. Trim angles are to cover cut edges and not faces of panel.

R6 Stainless Steel
R6.1 HANDRAILS

To the extent described on the drawings modify existing stainless steel handrails and brackets.

Fabricated entirely from 316 Grade stainless steel sections. All components are to be welded,
welds ground down neatly and buffed to produce an even No 4 polished seamless finish.

Provide wall mounted Matco TC100 CTP50 Stainless Steel Curved top plate handrail brackets to
support handrails off walls at max 1200mm centres as shown on the Drawings.

R7.2 WOVEN STAINLESS STEEL MESH – CEILING LININGS


Refer to clause G6.4

R7.3 STAINLESS STEEL PANEL

As detailed on the door schedule drawings and described in the door schedule clause H4 provide
the following stainless steel panel to doors

Legend / Location Stainless Steel Colour & Colour Image


Code Specification Finish

SS1 Custom Door Rimex Colour:


Panels. Copper

Refer Door Finish:


Schedule Satin
MONASH BUILDING H LEVEL 2 METALWORK 76

Legend / Location Stainless Steel Colour & Colour Image


Code Specification Finish

SS2 Custom Door Rimex Colour:


Panels. Champagne

Refer Door Finish:


Schedule Satin

R8 Window Blinds
R8.1 BLINDS GENERALLY

Roller blinds are to have “Metaco Roll Screen” hand drive mechanism with blind fabrics as
scheduled below and are to be manufactured by one of the following suppliers:
• Absolutely Blinds Tel: (03) 9676 9432
• Commercial Blinds
• Luxaflex

Blinds are generally required with a 2700mm drop. Measure on site.

R8.2 GLARE REDUCTION & PRIVACY BLINDS

To the following rooms provide Alessi – Translucent glare reduction fabric blinds or approved
similar with electric or manual roller chain winder operation as scheduled below:

Room Window / Door Blind Operator Colour


Tutorial 1 External perimeter windows Manual TBC
Tutorial 2 External perimeter windows Manual TBC
Tutorial 3 External perimeter windows Manual TBC
Tutorial 4 External perimeter windows Manual TBC
Tutorial 8 External perimeter windows Manual TBC
Tutorial 9 External perimeter windows Manual TBC
Industry Engagement External perimeter windows Manual TBC
Space (IES)

North Corridors at External perimeter windows Electric TBC


Informal Booths
JU.08A, JU.08B,
JU.08C, JU.08D
North Corridors External perimeter windows Manual TBC
South Corridors External perimeter windows Manual TBC

Blind fabric available through:


Alessi Design Group Pty Ltd
Tel: 03 9318 8732
MONASH BUILDING H LEVEL 2 METALWORK 77

R9 Signage
R9.1 WAYFINDING AND ROOM SIGNAGE

Provide Wayfinding and Room Signage as documented in separate documents by Studio


Semaphore signage consultant.

Signage sub-contractor to be selected from list of Monash approved signage contractors.


Builder to engage signage contractor.

R9.2 STATUTORY SIGNAGE

a) Fire Extinguisher Signage


Provide signage as required by Australian Standards to all fire extinguishers.

Signs shall be rigid metal and adhered to the wall in the locations as shown on the
Drawings.

b) Fire Hose Reel and Switchboards Cupboard signage


Provide laser cut self-adhesive 40mm high capital vinyl lettering in colour to be selected to
the following doors:
Font Type shall be Microgramma Medium.
Fire Hose Reels – wording “Fire Hose Reel”

New electrical distribution board - wording to be confirmed by Services Engineer

c) Braille and Tactile Exit Signage

Provide new braille and tactile exit signage on doors leading to emergency fire stairs to
Stair 1 H2-ST01 and Stair 2 H2-ST-02. Signage must comply with NCC Specification D3.6.

Refer also separate documents by Studio Semaphore signage consultant.

d) Infrared Hearing Assistance Signage


Provide new braille and tactile signage for infrared hearing assistance to rooms provided
with portable infrared system. Signage must comply with NCC Specification D3.6.

Refer also separate documents by Studio Semaphore signage consultant.

General
Provide shop drawings of all signage for review prior to the manufacture and installation of all
signage.

All signage wording to be approved by the Architect prior to manufacture.

Provide compliant braille/tactile signs in accordance with AS1428 & NCC.


Signage lettering, text, size, corners, relevant symbols etc must all comply with NCC 2015
Specification D3.6. Ensure signage supplier provides signs that comply with this code. The code is
available for free viewing online:

https://services.abcb.gov.au/NCCOnline/

Mounting Position
Signs on walls beside latchside of doors to be mounted 1250mm AFL to bottom of sign, and edge
of sign 100mm from architrave/frame of door.

Signs on doors to be mounted 1250mm AFL to bottom of sign, and centred on width of door.
MONASH BUILDING H LEVEL 2 METALWORK 78

R10 Metalwork & Steelwork for Joinery


Allow for all steelwork, metal reveal linings and trims as detailed on the architectural drawings.

Some steelwork has been designed to support joinery units and screens which may not
necessarily be included in the structural engineering documentation.

R11 Fire Extinguishers


Refer Fire Services Engineer’s Drawings for location and specification of fire extinguishers.
MONASH BUILDING H LEVEL 2 FINISHES SCHEDULE 79

S FINISHES SCHEDULE
Refer to Appendix B for Joinery Colour Schedule.

Refer to the Architectural drawings for extent and location of all wall finishes.

Other finishes and materials are scheduled throughout the body of this specification.
MONASH BUILDING H LEVEL 2 STRUCTURAL STEEL 80

T STRUCTURAL STEELWORK

T1 Scope of Works
T 1.1 GENERALLY

Supply, fabricate and erect all steelwork shown on the Drawings or specified herein, in accordance
with the provisions of this section.

Allow for all necessary operations, and for hoisting and fixing in position.

Supply all tools, machinery and appliances including drift pins and fitting-up bolts necessary for the
expeditious handling of the work. The suitability and capacity of all plant and equipment used for
erection shall be subject to approval. Structural steelwork is to be co-ordinated with all other
relevant trades, including but not limited to, concrete, masonry, metalwork, joinery, plaster,
electrical, plumber.

Provide data confirming that the tradesmen engaged for this project have a minimum of 5 years
experience in such work as required by this specification. The nominated experienced foreman is
to be present on site at all times work is being performed.

T1.2 QUALITY ASSURANCE

Do work in accordance with the Drawings and Specifications, which form part of this contract, and
further details and/or instructions issued by the Superintendent during the currency of the works.

Submit evidence of experience appropriate to the class of work required. Install under the direct
supervision of a capable Foreman, experienced in the class of work under construction.

T1.3 SHOP DRAWINGS

Before commencing fabrication, prepare shop drawings showing clear and complete details of
each assembly, component and connection in the work together with all information relevant to
their fabrication, surface treatment and erection.

Verify that all members can be erected properly.

Prepare shop drawings with reference to all relevant contract drawings and details. Take
responsibility for conformity with the Drawings, as well as dimensions, tolerances, and hole
positions. Submit shop drawings to Architect and Engineer for review. Shop drawings which are
unsatisfactory shall be corrected and resubmitted for approval before fabrication.

Builder to allow for liaison between shop detailer, Architect and Engineer during preparation of
shop drawings; to clarify intent and specific detail of steelwork as required.

Review of shop drawings by the Architect or Engineer does not affect the responsibility of the
Contractor under the contract. The Contractor remains solely responsible for the correct
fabrication and erection of all steelwork in accordance with the drawings and this specification.
MONASH BUILDING H LEVEL 2 STRUCTURAL STEEL 81

T1.4 Standards

Structural steelwork shall conform with the current relevant codes including the following:
AS 1111- ISO Metric Hexagon Commercial Bolts and Screws
AS 1112- ISO Metric Hexagon Nuts, including Thin Nuts, Slotted Nuts and Castle Nuts
AS 1131- Dimensions of Hot-Rolled Structural Steel Sections (Metric units)
AS 1163- Hollow Section AS 1204- Structural Steels (Ordinary Weldable Grades)
(metric units)
AS 1227- General Requirements for Supply of Hot Rolled Steel Plates, Sections, Piling
and Bars for Structural Purposes
AS 4100- Steel Structures.
AS 1252- General Grade High-Strength Steel Bolts with Associated Nuts and Washers
for Structural Engineering (ISO metric units)
AS 1552- Classification of Covered Electrodes
AS 1553- Low Carbon Steel Covered Electrodes for Manual Metal Arc Welding
AS 1554- SAA Code for Welding in Building

T1.5 INSPECTION

All material and work is subject to inspection. Provide reasonable and safe access and facilities, to
not less than DOL requirements, during both fabrication and erection.

T1.6 ACCESS FOR INSPECTIONS

The Superintendent and/or his representative shall be permitted access to the Steel Fabricator’s
workshop and yard for inspection of the work in progress at any time during working hours.

The Steel Fabricator shall also provide facilities as necessary to enable inspections and testing of
steelwork to be made.

T1.7 NOTICE

The Builder shall give the Superintendent at least two (2) days prior notice of the dates when the
following parts of the steel fabrication will be ready for inspection: -
a) All steelwork before surface treatment.
b) All welded joint areas before surface treatment.

T2 Materials
T2.1 STEEL

Unless otherwise specified or permitted by the Superintendent, all steel used in the works shall be
of Australian manufacture, conforming with the applicable requirements of Australian Standards
Specifications and free from damage and other unacceptable defects.

T2.2 SUBSTITUTIONS

If steel sections of the required sizes are not available, the Superintendent may permit
substitutions from available stocks.

As soon as practicable after commencement of the Contract, the Builder shall notify the
Superintendent of any sizes which are not available and shall submit a list of possible substitutions
which could maintain structural adequacy and architectural detailing. No substitution of steel
member shall be made without the Superintendent’s written approval.

No variations to the Contract Sum or extensions of the Contract Time will be permitted as a result
MONASH BUILDING H LEVEL 2 STRUCTURAL STEEL 82

of the adoption of any substitutions for designed sections.

T2.3 CERTIFICATES

Steel manufacturers certificates, indicating the composition and tensile properties of the steel
supplied, shall be submitted to the Superintendent.

T2.4 REJECTION OF MATERIALS

Inspections by the Superintendent shall not in any way relieve the Builder of responsibility for
providing steelwork of the required quality.

Defective materials and unsatisfactory steelwork shall be liable to rejection at any time prior to final
acceptance of the work. The Builder shall remove all rejected materials and workmanship and
supply new materials and reconstruct the steelwork to the standard of quality satisfactory to the
Superintendent.

No variations to the Contract Sum or extensions of the Contract Time will be permitted as a result
of the rejection of materials or workmanship.

T2.5 MARKING

Before delivery, each member shall be clearly marked in paint with the identification mark which is
shown on the Drawings or the shop drawings, or both. The weight of all major members of weight
greater than two tonnes shall be marked on the shop drawings and on the members.

T2.6 HANDLING & STORAGE

Steelwork shall be handled and stored without overstress or deformation.

Store steelwork clear of ground and in such a way that water does not lie on it. Supply bolts, nuts,
and washers in grit-free containers and store in water-tight premises. Burred, damaged, corroded
or otherwise unserviceable bolts shall not be used. Steel shall arrive on site with the protective
finish only so as to permit inspection prior to decorative coats being applied. Care shall be taken
during delivery, off-loading, stacking and erection so workshop applied finishes are not damaged.

T2.7 TYPE AND GRADE OF STEEL

Unless otherwise specified, all steel shall comply with AS 1204 or 1163.

T3 Workmanship
T3.1 WORKMANSHIP AND ERECTION

Where work is not exposed to view workmanship and finish shall be equal to good general
practice.

Where work is exposed to view and forms part of the architectural treatment, special attention shall
be given to the finish. Shearing, flame cutting and chipping shall be done carefully and accurately,
sharp corners and rough edges shall be faired by grinding or other approved means, and where
noted on the Drawings, welds shall be made smooth to approval.

T3.2 FABRICATION AND TOLERANCES

Do not exceed the end clearances shown on the Drawings, or if not shown, ascertain in clearances
used in the design of the connections.
MONASH BUILDING H LEVEL 2 STRUCTURAL STEEL 83

Lateral variation of compression members shall not exceed 1/1000 of the axial length between
points of lateral restraint. For all other members the variation shall not exceed 1/500.

Subject to the above, the tolerances on members after fabrication shall be those given in AS 4100
for the supply of the relevant section, or in the case of build-up members, those given in AS 4100
for universal beams. Completed members shall be free of twists, bends, and open joints.
Straightening or flattening, if required, shall be done without injuring the material. Sharp kinks or
bends shall be cause for rejection. Beams shall be precambered if so indicated on Drawings.

Maximum variation in overall length of members which have both ends finished for contact bearing
shall be 0.8mm.

Members with ends not finished for contact bearing, which are to be framed to other steel parts of
the structure, may vary in length up to plus 0 minus 2mm if not more than 9m in length, and up to
plus 0 minus 5mm if over 9m.

The above tolerances shall not be cumulative.


Contact bearing surfaces shall be machined square to the longitudinal axis of the member unless
otherwise specified. The clearance as tested by feeler gauge shall not exceed 0.254mm at any
point and 0.127mm over 90% of the splice area.

Adjacent members shall be shop matched at the fabricator's yard to ensure that the tolerances
have been maintained. Bolt holes for splices shall be drilled whilst the sections are fixed together
and held in line.

Members shall not be made of short lengths without approval.

T3.3 SITE CUTTING, DRILLING AND WELDING

During erection steel members shall not be cut, burnt, welded or drilled without approval. Drifting
may only be used for bringing parts into position, not to match unfair holes, or enlarge holes or
distort metal.

T3.4 ERECTION

Erect, fix, adjust and maintain all members in their intended vertical and lateral alignment and level.

During erection the steelwork shall be made safe against all loads and stresses to which it may be
subjected, including those due to erection equipment. Temporary bracing if used for this purpose
shall be affixed in a manner which does not weaken or deface permanent work. The Contractor
shall design and supply this bracing and be solely responsible for its adequacy.

Temporary bolting or welding shall be sufficient to resist all loads and stresses while the structure
is being prepared for permanent fixing.

Permanent bolting or welding shall not be carried out until correct alignment and camber, if any,
has been obtained in each member.
MONASH BUILDING H LEVEL 2 STRUCTURAL STEEL 84

T3.5 ERECTION TOLERANCES

The maximum deviation from the intended position shall be as follows:


Beams and trusses: 2mm measured horizontally at the support, relative to the
supporting member or structure.
Columns: 1.5mm at the column base. At the top of the column or at
intermediate points of connection, 1/1000 of the distance
between the point considered and the column base.
Other Compression: At the end of the member, 3mm.
Members: At intermediate points of connection, 1/500 of the distance
between the point considered and the nearer end.

T3.6 CONNECTIONS

Where end cleats, brackets and other connections are not otherwise specified or shown on the
contract drawings they shall be suitable to the location and reaction shown thereon.

Erection clearances shall not exceed 1.6mm at each end for web cleated ends of beams, and
3.2mm for beams without web cleats.

T3.7 BOLTED CONNECTIONS

Bolts in bearing shall be of such lengths that no threaded portion shall be within the thickness of
the parts joined. At least one washer shall be placed under the bolt head or nut, whichever is to be
rotated. Taper washers shall be used where the part under the bolt head or nut is not
perpendicular to the centreline of the bolt. At least one full thread shall project past the end of the
nut. Nuts or bolts subject to severe vibration and vertical bolts in tension shall be locked in position
by an approved method.
Unless otherwise specified, mild steel bolts shall be used for all bolted connections. Holes shall be
drilled oversize not more than 1.6mm in diameter. All exterior bolts, nuts and washers are to be hot
dip galvanised.

Close tolerance bearing bolts shall comply with AS B117 or B147. Diameter of holes shall be equal
to the nominal diameter of the bolt shank with a tolerance of minus 0 and plus 0.13mm.

High tensile bolts: Seek the approval of the Engineer of the type of bolt, nut and washer to be used
for high tensile bolts. The bolts, nuts and washers shall be clearly marked to avoid confusion. High
tensile steel bolts shall be assembled with a hardened steel flat or tapered washer under the head
and nut.

Tightening shall be by the turn of the nut method, generally, as laid down in AS 1511, to achieve
the following minimum bolt tensions:

BOLT DIA. (mm) MINIMUM TENSION (kg)


16mm 8700 kg
20mm 13500 kg
24mm 17600 kg
25mm 18300 kg

Match marking of nut and bolt is to be carried out using indelible crayons and only after the 'snug
tight' position has been achieved in all bolts in a connection.
MONASH BUILDING H LEVEL 2 STRUCTURAL STEEL 85

T3.8 WELDING

Manual welding shall be in accordance with AS 1554 Part 1. Semi-automatic or automatic welding
may be used, and shall be in accordance with the welding equipment manufacturer's instructions.

Connections noted for site welding are to be shop prepared to enable adequate weld penetration.
Unless shown otherwise:
- Welding electrodes shall be "E41 XX"
- Weld category shall be "SP"
- Welding consumables shall be of the low hydrogen type
- All butt welds to be qualified full penetration butt welds.
All fillet welds to be 6mm continuous
Abutting edges of boxed members shall be connected and sealed with a continuous weld.
All feature steelwork, exposed to view, shall be continuous fillet weld or butt welded at joins.
All exposed welds shall be of a high quality architectural finish.

T4 Metalwork & Steelwork for Joinery


Allow for all steelwork and metal reveal linings and trims as detailed on the architectural drawings.

Some steelwork has been designed to support joinery units and screens which may not
necessarily be included in the structural engineering documentation.

Refer also to Clause R10 in Metalwork.


MONASH BUILDING H LEVEL 2 MECHANICAL SERVICES 86

U MECHANICAL SERVICES
Refer to separate documents issued by services engineers Lucid Consulting Australia.
MONASH BUILDING H LEVEL 2 FLOOR FINISHES 87

W FLOOR FINISHES
W1 Floor Preparation
W1.1 PREPARATION

Make good all existing floors prior to the application of new floor finishes. Remove all residual
carpet underlay, smooth edges, glues and adhesives. Prepare existing surfaces and bring to the
required level to receive the specified floor finishes.

W1.2 INSPECTION OF EXISTING CONDITIONS

The contractor(s) shall have inspected the site during the tender period and made the necessary
allowances for floor preparation in their tender.

W1.3 LEVELLING COMPOUNDS

Throughout all areas that are scheduled to receive new floor finishes allow for the provision for
general patching and make good to existing floor slab surfaces. Allow to apply levelling compounds
to suit the intended flooring finishes.

W1.4 PRODUCT AND MATERIAL LEAD TIMES

The builder shall be responsible for the coordination of their own staff and that of sub-contractors
to ensure the placement of orders for of all specified products and materials are made within the
appropriate timeframes to ensure availability for installation within the works in accordance with the
project program.

W2 General & Nominated Installers


General
The laying of any floor finish by the Contractor shall signify his acceptance of the responsibility that
the floor is in good order to receive the finish.

VOC content
All interior materials, finishes, adhesives and sealants to be low-VOC or zero-VOC.

Lead Times
Confirm current lead times with product suppliers at commencement of building works, and allow
for product lead times.
MONASH BUILDING H LEVEL 2 FLOOR FINISHES 88

W3 Marmoleum Flooring and Joinery Linings


Scope of Work
Refer to the Architectural Drawings for extent of Marmoleum floor and joinery lining, and Section S
Finishes Schedule of this Specification.

Product Selection
Product Colour / Image Location Legend

Manufacturer: Forbo Lift Lobby, Arrival and Catchup MR1


Range: Marbled Real Zone, IES Foyer H230
Colour: 3881 Green
Wellness Joinery JU.01A & JU.01B – Top
Thickness: 2.5 mm and underside

Underside of bulkhead above


JU.01A
Green Wellness
Manufacturer: Forbo Kitchen MR2
Range: Marbled Terra
Colour: 5802 Alpine Mist Joinery JU.01C – Top and
Thickness: 2.5 mm underside

Alpine Mist

General
The laying of sheet vinyl on any floor and walls by the Contractor shall signify his acceptance of the
responsibility that the floor is in order to receive the finish.

Substrate
Prepare existing substrates to receive new sheet marmoleum floor linings.

Installation
Installation shall be in accordance with manufacturer’s specifications and to AS 1884.

All seams, mitred corners etc shall be hot welded, using matching coloured PVC weld rod.
Adhesive in wet areas shall be Altrofix 30 (2 part polyurethane) or an approved 2 part epoxy
adhesive. In areas not subject to moisture, an approved acrylic adhesive may be used. To any
vertical face, such as upstands to walls and coves, an approved contact adhesive shall be used.

PVC diminishing strips & Door Threshold Strips


Provide “Ramp It” black rubber strip from Australian Flooring Supplies between carpet and vinyl to
ensure surfaces finish flush with each other, with the exception of door thresholds where door
threshold strips are specified – Refer Section H4 Door Schedule.

Ensure new flooring finishes flush with existing flooring where this occurs.

Cleaning
On completion of laying, sweep clean with a soft broom and scrub with a vinyl cleaner.
MONASH BUILDING H LEVEL 2 FLOOR FINISHES 89

W3 Carpet Flooring and Wall Linings


Substrate Preparation
The Builder shall bring all floors to receive carpet to a clean smooth and even surface to receive
the carpet. A cement based levelling compound such as Ardit may be necessary to achieve a
smooth level substrate for carpet.

The carpet must finish flush to all door thresholds and floors in other areas.

Carpet Selection

Product Colour / Image Location Legend

CARPET FLOORING
Manufacturer: • South Corridors, CA1
Miliken Ontera • Industry
Range: Engagement Space
Lightbox (IES)
Colour: • East Corridors,
Smoke / Olive Bright • North Corridors,
Tile Size: • Group Study / B-2
250 x 1000mm • West Corridors
Backing:
Standard backing unless
noted otherwise.

Warranty
15 year product warranty
Install in Ashlar-Random
arrangement with all carpet
planks running in the East-
West direction.
Smoke / Olive Bright
Manufacturer: • Tutorial 1 CA2
Gibbon Architectural • Tutorial 2
Range: • Group Study / A-1
Tretford Interlife Tile • Tutorial 5
Colour: Heather 530 • Group Study / A-3
Tile Size:
500x500 x 8mm

Backing:
Standard backing unless Heather 530
noted otherwise.
Manufacturer: • Tutorial 3 CA3
Gibbon Architectural • Tutorial 4
Range: • Group Study / A-4
Tretford Interlife Tile • Tutorial 6
Colour: Mushroom 571
Tile Size:
500x500 x 8mm

Backing:
Standard backing unless Mushroom 571
noted otherwise.
MONASH BUILDING H LEVEL 2 FLOOR FINISHES 90

Product Colour / Image Location Legend

Manufacturer: • Tutorial 7 CA4


Gibbon Architectural • Tutorial 8
Range: • Tutorial 9
Tretford Interlife Tile • Group Study / B-1
Colour: Thym 642 • Group Study / A-5
Tile Size: • Group Study / C-1
500x500 x 8mm • Group Study / C-2
Backing:
Standard backing unless Thym 642
noted otherwise.
CARPET WALL LININGS
Carpet Wall Lining West Corridor CPT1
Manufacturer: Column Wall Lining
Gibbon Architectural
External Wall Lining
Range: (Public Area Side):
Tretford Roll • Tutorial 5
• Group Study / A–1
Colour:
Burnt Orange 559 Internal Wall Lining
• Group Study / A-2
Roll Size: Burnt Orange 559
2m Wide Rolls
Carpet Wall Lining External Wall Lining CPT2
(Public Area Side):
Manufacturer: • Tutorial 7
Gibbon Architectural
Internal Wall Lining
Range: • Group Study / B-1
Tretford Roll

Colour: Lichen 566


Lichen 566
Tile Size:
2m Wide Rolls

Note: Check carpet lead times and ensure that materials are ordered in time to meet
program.

Carpet Laying
Carpet shall be installed in accordance with manufacturer’s recommendations.
Confirm laying pattern with architect prior to commencement of installation.

Where installed as a wall lining carpet rib direction shall be vertical

Aluminium angles
Provide aluminium angle trims to all junctions between existing floor tiles and other floor finishes.

PVC diminishing strips


Provide “Ramp It” black rubber strip from Australian Flooring Supplies between carpet and vinyl
and ensure surfaces finish flush with each other.

Ensure new flooring finishes flush with existing flooring where this occurs.
MONASH BUILDING H LEVEL 2 FLOOR FINISHES 91

W4 Tactile Indicators
At the top of the stairs as shown and noted as TGI on the Drawings provide the following tactile
indicator:

South and North Stair Landing – Marmoleum Floor

DTAC Black Top Classic Warning Tactile


Stainless Steel Tactile with moulded polymer insert
Slip Rating: R12
Product Code: DTO200

Contact:
DTAC 4/11-12 Phillip Court, Port Melbourne VIC
Ph: 1300 793 478
sales@dtac.com.au

W5 Protection upon Completion


Upon the completion of the works all newly laid floor surfaces are to be cleaned and protected from
following trades that require access onto the floor areas to carry out other works. Protection works
shall remain in place until the builders final project clean is carried out.

Do not place tools and or other items of equipment such as fixtures or fittings to be installed
directly onto newly tiled surfaces.
MONASH BUILDING H LEVEL 2 APPENDIX A

APPENDIX A

DOOR HARDWARE SCHEDULE


02/11/2022 03:57 PM
Cover Letter | Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Project ID: 81425 (02-11-2022)
Revision Note:
Project Address: 900 Princes Hwy CAULFIELD EAST VIC 3145 AUSTRALIA

Keying System: Extension of Existing System

Architect Company: HARMER ARCHITECTURE PTY LTD

Architect Project ID:

Consultant: Lyndon Payne

This schedule is based on the following documentation.

Project Comments:

Spence Doors, an ASSA ABLOY group company, can provide a full compliant solution for rated and non-rated door and frame
requirements excluding aluminium solutions.

ASSA ABLOY Hardware specified within this project is compatible with applicable Spence door applications (at time of production of
this documentation).

For questions concerning details of the Spence doors and frames, their specifications, and their utilisation, please contact Spence
Doors projectenquiry@spencedoors.com.au. Alternatively visit www.spencedoors.com.au.
Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D01 To/From Room: Tutorial 1 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D02 To/From Room: Tutorial 2 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP

Openings Studio Page 2 of 10 2/11/2022


Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D03 To/From Room: Tutorial 3 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D04 To/From Room: Tutorial 4 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP

Openings Studio Page 3 of 10 2/11/2022


Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D05 To/From Room: Plant Room Level: LEVEL 2 Building: BUILDNG H
Height: 2340 Width: 920 Thick: 40 HW Set: 2.0
Door Type: SOLID CORE Frame Type: PRESSED METAL
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772V-SS 1 3772 - ANTI-VANDAL ESCAPE LOCK LOCKWOOD SS
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A350SC 1 A350 WALL MOUNTED DOOR STOP TP LOCKWOOD SC
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: DC
Mark: D06 To/From Room: Tutorial 5 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP

Openings Studio Page 4 of 10 2/11/2022


Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D07 To/From Room: Group Study A-1 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D08 To/From Room: Group Study A-3 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 45 HW Set: 1.0
Door Type: TIMBER GLAZED Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D09 To/From Room: Group Study A-4 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 1500 Thick: 45 HW Set: 3.0
Door Type: TIMBER GLAZED SLIDING Frame Type:
Arc Door Type: Arc Frame Type:
Handing:
REX 1 REQUEST TO EXIT BUTTON OTHER
STA-SERIES SINGLE 1 AUTOMATIC SLIDING DOOR OPERATOR Record Doors NONE
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
Door Notes: AUTO

Openings Studio Page 5 of 10 2/11/2022


Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D10 To/From Room: Tutorial 6 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D11 To/From Room: Arrival & Catchup Zone / FHR Level: LEVEL 2 Building: BUILDNG H
Height: 2340 Width: 920 Thick: 38 HW Set: 5.0
Door Type: HOLLOW CORE Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
P2SS 1 STAINLESS STEEL P2 PULL HANDLE LOCKWOOD SS
7580SC 1 7580 ROLLER BOLT TP LOCKWOOD SC
Mark: D12 To/From Room: North Corridor 2 / FHR Level: LEVEL 2 Building: BUILDNG H
Height: 2340 Width: 920 Thick: 38 HW Set: 5.0
Door Type: HOLLOW CORE Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
P2SS 1 STAINLESS STEEL P2 PULL HANDLE LOCKWOOD SS
7580SC 1 7580 ROLLER BOLT TP LOCKWOOD SC
Mark: D13 To/From Room: Group Study C-1 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 1500 Thick: 45 HW Set: 3.0
Door Type: TIMBER GLAZED SLIDING Frame Type:
Arc Door Type: Arc Frame Type:
Handing:
REX 1 REQUEST TO EXIT BUTTON OTHER
STA-SERIES SINGLE 1 AUTOMATIC SLIDING DOOR OPERATOR Record Doors NONE
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
Door Notes: AUTO

Openings Studio Page 6 of 10 2/11/2022


Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D14 To/From Room: Group Study C-2 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 1500 Thick: 45 HW Set: 3.0
Door Type: TIMBER GLAZED SLIDING Frame Type:
Arc Door Type: Arc Frame Type:
Handing:
REX 1 REQUEST TO EXIT BUTTON OTHER
STA-SERIES SINGLE 1 AUTOMATIC SLIDING DOOR OPERATOR Record Doors NONE
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
Door Notes: AUTO
Mark: D15 To/From Room: Group Study A-5 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 1500 Thick: 45 HW Set: 3.0
Door Type: TIMBER GLAZED SLIDING Frame Type:
Arc Door Type: Arc Frame Type:
Handing:
REX 1 REQUEST TO EXIT BUTTON OTHER
STA-SERIES SINGLE 1 AUTOMATIC SLIDING DOOR OPERATOR Record Doors NONE
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
Door Notes: AUTO
Mark: D16 To/From Room: Industry Engagement Space Level: LEVEL 2 Building: BUILDNG H
(IES)
Height: 2640 Width: 2700 Thick: 42 HW Set: 4.0
Door Type: LOTUS SLIDING GLAZED Frame Type:
Arc Door Type: Arc Frame Type:
Handing:
*LOTUS 1 LOTUS ALUMINIUM FRAMED SLIDING GLAZED DOORS BY OTHER
MANUFACTURER
5541RT1SCNCYLLS 1 5541 - SHORT B'SET MORT D'LOCK & E/TURN AND L/STRIKE ASSY LOCKWOOD SC
NO CYL(FAB)
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
146X450SSS 1 146 ENTRANCE HANDLES WITH 450MM CENTRES LOCKWOOD SSS
Door Notes: AS, Hardware by Lotus

Openings Studio Page 7 of 10 2/11/2022


Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D17 To/From Room: IES Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D18 To/From Room: Tutorial 9 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP

Openings Studio Page 8 of 10 2/11/2022


Door Hardware Schedule
Project Name: MONASH UNIVERSITY - BUILDING H LEVEL 2 REFURBISHMENT
Schedule No: 81425

Item Qty Description Brand Finish


Mark: D19 To/From Room: Tutorial 8 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D20 To/From Room: Tutorial 7 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 920 Thick: 40 HW Set: 1.0
Door Type: SOLID CORE - PANEL Frame Type: TIMBER
Arc Door Type: Arc Frame Type:
Handing:
LW10075BBSSS 4 HINGES 100X75X2.5 BALL BEARING LOCKWOOD SSS
3772X-SS 1 3772 - KEY ENTRY ESCAPE LOCK LOCKWOOD SS
ES2100 1 ES2100 E/STRIKE 12-30VDC M/FUNCTION DOOR MONITORED ~ LOCKWOOD
BL570SC 1 BILOCK 570 CYLINDER MASTERKEYED OTHER SC
CUTKEY-MK 1 CUT KEY TO EXISTING BILOCK MASTER KEY SYSTEM OTHER
2801/70SC 1 2801 ROUND END PLATE WITH CYLINDER HOLE & 70 LEVER LOCKWOOD SC
2905/70SC 1 2905 ROUND END PLATE WITH 70 LEVER LOCKWOOD SC
2615DASIL 1 2615 SERIES CAM ACTION DOOR CLOSER SIZE 1-5 DELAYED LOCKWOOD SIL
A250SC 1 A250 FLOOR MOUNTED DOOR STOP TP LOCKWOOD SC
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
LAS7001/LSDS/S 1 SLIM-LINE DOOR PERIMETER SEAL BULB LNG SGL DR SET SIL LORIENT SIL
LAS8001/0920/S 1 DROP SEAL MORTICE 0920 SIL LORIENT SIL
Door Notes: AS, ELS, DC, VP
Mark: D21 To/From Room: Group Study B-1 Level: LEVEL 2 Building: BUILDNG H
Height: 2640 Width: 1500 Thick: 45 HW Set: 3.0
Door Type: TIMBER GLAZED SLIDING Frame Type:
Arc Door Type: Arc Frame Type:
Handing:
REX 1 REQUEST TO EXIT BUTTON OTHER
STA-SERIES SINGLE 1 AUTOMATIC SLIDING DOOR OPERATOR Record Doors NONE
SIGNO20STANDARD 1 HID SIGNO 20 SMART CARD READER, STANDARD MULLION PROFILE HID BLK
~
Door Notes: AUTO

Openings Studio Page 9 of 10 2/11/2022


ASSA ABLOY is represented in all major regions, in both mature and emerging
markets, with leading positions in Australia, Europe and North America.

As the world’s leading lock group, ASSA ABLOY offers a more complete product
range of door opening solutions than any other company in the market.

Openings Studio is a suite of BIM software tools for creating and


visualising 3D doors, frames, and hardware objects for use in design,
construction, and facility management. This program enables our
consultants to write schedules with greater efficiency and contains built-in
workflow tools for RFI’s, change management, and collateral material.

Download Openings Studio


Visit assaabloy.com.au/openings to download a copy.

ASSA ABLOY Australia Pty Ltd


235 Huntingdale Road
Oakleigh, Victoria, 3166
Australia
ABN 90 086 541 907

1300 LOCK UP (1300 562 587)


lockweb.com.au

MELBOURNE FAX 1800 647 673


BRISBANE FAX 1800 626 140

Disclaimer
Whilst every effort has been made to ensure that the information (including product images and drawings) contained in this documentation is accurate at the time of print, ASSA ABLOY Australia Pty Limited (“ASSA ABLOY”)
recommends that you consult ASSA ABLOY or its agents prior to placing an order to ascertain current information on specific products, as ASSA ABLOY reserves the right to make changes without notice. ASSA ABLOY will not be
liable for any injury, loss or damage whatsoever, arising from any errors or omissions in the information contained in the documenation or arising from the use or application of the information contained herein. © 2022 copyright by
ASSA ABLOY All rights reserved
MONASH BUILDING H LEVEL 2 APPENDIX B

APPENDIX B

JOINERY COLOUR SCHEDULE


Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Joinery Colour Schedule


Note: Revisions are highlighted in Yellow

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
JU.01A Arrival and Forbo
Arrival Table Catchup
Zone Benchtop
Marmoleum /
and
Green
Bulkhead
Wellness
Soffit

Laminex
Benchtop
Edging and Compact
Bulkhead Laminate /
Edging and Fossil
Trims

Spectrum

Table Base
Studded
and
Rubber / G816
Bulkhead
Glacier
Lining

JU.01B South Forbo


IES Foyer Corridor 2
Table
Marmoleum /
Benchtop Green
Wellness

Laminex

Compact
Benchtop
Laminate /
Edging
Fossil
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
Spectrum

Studded
Table Base Rubber / G816
Glacier

JU.01C Kitchen Forbo


Kitchen Table
Marmoleum /
Benchtops Terra Alpine
Mist

Laminex

Benchtop Laminate /
Edging Moose

Spectrum

Studded
Table Base Rubber / G816
Glacier

JU.02A Arrival and Caesarstone


Arrival Kitchen Catchup
Zone
Ceasarstone –
Benchtop &
Piatra Grey
Splashback
5003

Laminex

Overhead
Carcass, Laminate /
and Fossil
Kicker
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
Laminex

Drawer and
Laminate /
Cupboard
Fossil
Door Fronts

JU0.2B Kitchen Laminex


Kitchen
Benchtop,
Overhead
Laminate /
Carcass,
Moose
and
Kicker

Classic
Ceramics
Wall Tiles /
Vogue
Splashback
Lavanda 200 x
100mm

Laminex

Drawer and Laminate /


Cupboard Bleached
Door Fronts Wenge

JU.03A – South Formica


JU.03G Corridor
Breakout Laminate /
Benchtops,
Tables Shitake
Side and
Modesty
matching ABS
Panels
edge colour

Timber KD /
Benchtop
Black Japan
Edging
Timber Stain
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
JU.03H – North
JU.03M Corridors
Breakout Laminate /
Benchtops,
Tables Bliss Cinder
Side and
Formica
Modesty
matching ABS
Panels
edge colour

Vic Ash Timber


Benchtop
KD / Liming
Edging and
White Timber
Trim
Stain
JU.04A & South
JU.04B Corridor
Single Side 1&2
Banquette
Seat Upholstery Vinyl Textile /
Seat and Serenity Materialised
Back Terrain

Laminex

Kicker Laminate /
Plinth Fossil

JU.05A – South
JU.05C Corridor
Double Side 1&2
Banquette
Seat Upholstery Vinyl Textile /
Seat and Serenity Materialised
Back Terrain

Laminex

Kicker
Plinth Laminate /
Fossil
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
JU.06A & East
JU.06B Corridor 2
Bench Seating
Vinyl Textile /
Cushion
Natural Linen Materialised
Upholstery
Moss

Plywood TBC
Bench Bench Support
/ Painted
Steel Seat TBC
Painted Steel
Support
JU.06C East
Bench Seating Corridor 1

Vinyl Textile /
Cushion
Natural Linen Materialised
Upholstery
Gray

Plywood TBC
Bench Bench Support
/ Painted
Steel Seat TBC
Painted Steel
Support
JU.07A West
Banquette Corridor 1
Seat and
Desk Banquette
Vinyl Textile /
Upholstery
Sandhills Materialised
Seat &
Meadow
Back

Table
Benchtop Laminate /
Formica
and Side Bliss Cinder
Panels

Timber KD /
Table
Liming White
Edging
Timber Stain
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
JU.07B West
Banquette Corridor 2
Seat and
Desk
Upholstery Vinyl Textile /
Seat and Serenity Materialised
Back Terrain

Table
Benchtop Laminate /
Formica
and Side Shitake
Panels

Vic Ash Timber


Table KD / Black
Edging Japan Timber
Stain
JU.08A North
Informal Study Corridor 1
Booths
Banquette
Vinyl Textile /
Upholstery
Sandhills Materialised
Seat &
Meadow
Back

Laminex

Laminate /
Kicker
Fossil

Timber
Veneered
Booth Wall
Board / Plyco
Lining
American
Walnut
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour

Perforated
Timber
Booth Soffit Veneered
Plyco
Lining Board /
American
Walnut

JU.08B – North
JU.08D Corridor 1
Informal Study
Booths Banquette
Vinyl Textile /
Upholstery
Sandhills Materialised
Seat &
Meadow
Back

Laminex

Laminate /
Kicker
Fossil

Timber
Veneered
Booth Wall
Board / Plyco
Lining
American
Cherry

Perforated
Timber
Booth Soffit Veneered
Plyco
Lining Board /
American
Cherry

JU.09A West
Bin Enclosure Corridor 1
Laminate
Laminate /
Bin Formica
Bliss Cinder
Enclosure
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
JU.09B West
Bin Enclosure Corridor 2
Laminate
Laminate /
Bin Formica
Shitake
Enclosure

JU.09C East Laminex


Bin Enclosure Corridor 1
Laminate Laminate /
Bin Bleached
Enclosure Wenge

JU.10A Group
Group Study Study A-1
Meeting Table
Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging

Laminex

Laminate /
Table Base
Fossil

JU.10B Group
Group Study Study A-2
Meeting Table
Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
Laminex

Laminate /
Table Base
Fossil

JU.10C Group
Group Study Study A-4
Meeting Table
Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging

Laminex

Table Base Laminate /


Fossil

JU.11A – Group
JU.11D Study A-3
Group Study
Meeting Table Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging

Laminex

Table Base Laminate /


Fossil
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
JU.11B Group
Group Study Study C-1
Meeting Table
Laminate /
Benchtop Laminex
Sarsen Grey

Table Laminex
ABS / Fossil
Edging

Laminex

Laminate /
Table Base
Fossil

JU.11C Group Group


Study Meeting Study C-2
Table
Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging

Laminex

Laminate /
Table Base
Fossil

JU.11D Group
Group Study Study A-5
Meeting Table
Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
Laminex

Laminate /
Table Base
Fossil

JU.12A Group
Group Study Study B-1
Meeting Table
Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging

Laminex

Laminate /
Table Base
Fossil

JU.12B Group
Group Study Study B-2
Meeting Table
Laminate /
Benchtop Laminex
Sarsen Grey

Laminex
Table
ABS / Fossil
Edging

Laminex

Table Base Laminate /


Fossil
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
JU.13 East
Bench Seating Corridor 1

Vinyl Textile /
Seat
Natural Linen Materialised
Upholstery
Gray

Laminex

Laminate /
Kicker
Fossil

ST / DR IES Benchtops Laminate TBC Laminex


Wireless
Cupboards Laminate TBC Laminex
Microphone
and Side
Charging
Panels
Station and
Data Rack Laminate TBC Laminex
Cupboard Kicker
Storage
SC South Textured Alltrade
Aluminium Corridor Glass Aluminium
and Glazed Glass &
Textured
Screen Gluechip Stainless Steel
Glass 1
Breakout
(TG1) Glass
Partition

Textured Alltrade
Glass Aluminium
Textured Glass &
Glass 2 Stainless Steel
(TG2)
Drift Glass

Textured Alltrade
Glass Aluminium
Glass &
Textured Broadline Stainless Steel
Glass 3 Reeded
(TG3) Glass (20mm
centred gaps)
Monash Building H Level 2
Joinery Colour Schedule – Construction Issue Rev C1 | Date: 16.02.23

Unit No & Location Material / Colour image


Item Manufacturer
Description Colour
Plyco

Timber Timber
Modesty Veneered
Infill Panel Board / Panel

Tasmanian Oak

Timber
Timber Veneered
Modesty Board / Plyco
Panel American
Cherry

American Cherry
Criterion Dulux
Gallium Colorbond
Aluminium
Aluminium
Powder coated
Window
Monument Satin
Suite
Sliding Group Vic Ash Timber
Light
Timber Door Study KD / Liming
Timber
Panel and Sliding White Timber
Frame
Window Door and Stain
Frame Window
Sidelight
Panel Walnut Vic Ash Timber
Timber KD / Walnut
Frame Timber Stain
MONASH BUILDING H LEVEL 2 APPENDIX C

APPENDIX C

FURNITURE SCHEDULE
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2

Monash University Bulding H

Furniture Schedule Summary
Floor Level Total Cost 
Building H Level 2 $                                     ‐

Total $                                    ‐
Allowance for contingency, deliveries, installation, and 
$                                     ‐
rubbish removal
Grand Total $                               ‐

Revised items highlighted yellow DATE 16.02.2023


‐Refer also Specificaction Notes to be issued seperately.
‐Images shown are indicative of the actual proposed furniture. 

FURNITURE SUPPLIERS CONTACT
Supplier Contact Phone Mobile
Schiavello Melissa Chen mchen@schiavello.com 03 9674 1511
UCI Tamika Taylor tamika.taylor@uci.com.au 03 8379 0235
Watson Robyn Chivers Robyn@watsonci.com.au 03 9873 8484
Zenith Chris Fullalove Chris.Fullalove@zenithinteriors.com 03 9693 2626
Didier Ross Didier mail@didier.com.au 03 9459 1893 0418 511 619

Ergonomics 101 Kevin Darling ‐ Filby kevin@ergonomics101.com.au 03 9693 2626

Page 1 of 8
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2
Rooms
Colours &  PC per item 
Code Product Qty Photo Supplier Colours & Finishes Notes Lead Time PC Sum Total
Finishes Image (indicative)

Table
Custom Kite Shaped Tutorial Table Tutorial 1 3 Top: 25mm thick  Writable 
Kissen Table Plectrum Laminate Surface with 
Size: 1770W x 1770D x 750H approx Tutorial 2 2 laminex laminated border 
Top: Laminex Battalion with writeable  and matching abs edge.
Tutorial 3 2
insert in Diamondgloss Laminate 
Surface  Tutorial 4 Base: Standard Black with 
1 polished aluminium feet on 
Frame / Legs: Powdercoated Tutorial 5 lockable castors
2 Zenith 
T1 Leg on lockable castors 7 ‐ 9 Weeks $                       ‐   
Tutorial 6 Interiors
1
Tutorial 7 3
Tutorial 8 3

TOTAL 17
Custom Kite Shaped Tutorial Table Tutorial 2 Top: 25mm thick  Writable 
Kissen Table Plectrum 2 Laminate Surface with 
Size: 1770W x 1770D x 750H approx Tutorial 3 laminex laminated border 
Top: Laminex Battalion with writeable  1 and matching abs edge.
insert in Diamondgloss Laminate 
Tutorial 4
Surface  2 Base: Standard Black with 
Frame / Legs: Fixed Powdercoated polished aluminium feet on 
Leg Tutorial 5 lockable castors
1
Power/Data Supply: soft wiring  Tutorial 6
2 Zenith 
T1B connection within umbilical from 
Interiors
7 ‐ 9 Weeks $                       ‐   
surface mounted  floorbox underneat 
Tutorial 7
desk 2

GPO: Provide OE Elsafe Phase Single  Tutorial 8
4
outlet with Fast Charging USB Charging 
ports per two seats location mounted 
below desk (three power outlets in 
total). Colour in Black TOTAL
14

Page 2 of 8
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2
Custom Shape Tutorial Table Tutorial 2 Top: 25mm thick  Writable 
1
Kissen Table Taper Laminate Surface with 
1200D x 2400W x 750H Tutorial 3 laminex laminated border 
1
and matching abs edge.
Tutorial 4
Top: Laminex Battalion with writeable  2
insert in Diamondgloss Laminate  Tutorial 5 Base: Standard Black with 
Surface  1 Zenith  polished aluminium feet on 
T2 Tutorial 6 Interiors lockable castors
7 ‐ 9 Weeks $                       ‐   
2
Frame / Legs: Powdercoated Tutorial 8 3
Leg on lockable castors

TOTAL 10
Custom Shape Tutorial Table Tutorial 1 Top: 25mm thick  Writable 
Kissen Table Taper Laminate Surface with 
1200D x 2400W x 750H 2 laminex laminated border 
Top: Laminex Battalion with writeable  and matching abs edge.
insert in Diamondgloss Laminate 
Surface  Tutorial 3 Base: Standard Black with 
Frame / Legs: Fixed Powdercoated polished aluminium feet on 
Leg lockable castors
1
Power/Data Supply: soft wiring 
connection within umbilical from  Zenith 
T2B surface mounted  floorbox underneat  Interiors
7 ‐ 9 Weeks $                       ‐   
Tutorial 5
desk
GPO: Provide OE Elsafe Phase Single 
outlet with Fast Charging USB Charging  1
ports per two seats location mounted 
below desk (three power outlets in 
total). Colour in Black TOTAL

Rectangular Meeting Table Industry  Top: 25mm thickTimber Grain


Flip top tables on castors with timber  Engagement  Laminex with matching abs edge.
grain laminex laminated tabletop Space
Zenith  Base: Standard Black with polished
T3 Size: 1800L x 900D x 750H
7
Interiors
aluminium feet on lockable castors 6 ‐ 8 Weeks $                       ‐   

Page 3 of 8
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2
Sol ‐ LAP West Corridor Table Top:
Laptop Table Natural Oak
Laminated Table Top  and 
Zenith  Base: Olive (Matt)
Powdercoated Steel Legs 
T4 13
Interiors
6 ‐ 8 Weeks $                       ‐   

120mm Deep x 220 Wide x 250mm 
High

Breakout Rectangular Table West Corridor Table Top:


Ross Didier Liqueur Table American Oak
Size: 1200 Dia x 750H
Base:
‐ Round shaped with bevelled 
Ross American Oak
T5 sharknose edge profile  1
Didier
6 ‐ 8 Weeks $                       ‐   
‐ Single Pedestals
‐ Natural Clear

Breakout Rectangular Table South Corridor Table Top:


Ross Didier Liqueur Table American Oak

Base:
Custom Size: 2000 x 1350D x 750H
Ross American Oak
T6 ‐ Elliptical shaped with bevelled  1
Didier
8 ‐ 10 Weeks $                       ‐   
sharknose edge profile 
‐ Twin Pedestals
‐ Natural Clear

Breakout Rectangular Table South Corridor Table Top:


Ross Didier Liqueur Table American Oak
Custom Size: 2500L x  1350D  x 750H
Base:
‐ Elliptical shaped with bevelled 
Ross American Oak
T7 sharknose edge profile  1
Didier
8 ‐ 10 Weeks $                       ‐   
‐ Twin Pedestals
‐ Natural Clear

Page 4 of 8
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2

CHAIR
Tutorial Room Student Chairs Tutorial  1 30
Aichi Tipo Chair Tutorial  2 30
Tutorial  3 Flexible Back Membrane: 
30
Arms: No Arms Black
Back: Flexible Mesh Membrane  Tutorial  4 30
Tutorial  5 30 Zenith  Frame: Black
C1 Castors: Hard suitable for Carpet  Tutorial  6 Interiors
14 ‐ 16 Weeks $                       ‐   
30
Flooring Seat Uphostery:  
Tutorial  7 30
Allow for standard Instyle  
Tray: Wire Tray / Bag storage under  Tutorial  8 60 fabric $50/lm
seat. 
TOTAL 270
Group Study Room Meeting Chairs G. Study A‐1 8
Upholstered Meeting Chairs G. Study A‐2 8
G. Study A‐3 8
Stanza Chair G. Study A‐4 8 Upholstery:
565W x 550D x 780H mm G. Study A‐5 8  Allow for standard Instyle  
fabric $60/lm
C2 G. Study B‐1 4 Schiavello 6 ‐ 8 Weeks $                       ‐   
Sled Based Chair
G. Study B‐2 4 Frame: TBC
G. Study C‐1 10
G. Study C‐2 10
IES 15
TOTAL 83
Breakout Chairs North Corridor
Lottus Chairs 10

South Corridor
Upholstery:
33 Allow for $60/lm for supply 
Zenith  of upholstery fabric
C3 West Corridor Interiors
4 ‐ 6 Weeks $                       ‐   

8 Frame: 
TBC

TOTAL
51

Page 5 of 8
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2
Modular Lounge West Corridor
Sol‐Sit

Convex Lounge Double Upholstery Seat and Back:


Round Modular Seats Zenith  Range: Materialised
C4 1340mmW x  1340mm D x  Seat Height   3
Interiors Colour: Artisan Zest
8 ‐ 10 Weeks $                       ‐   
450mm x 830mm Height

Single tone upholstery seat and back 

Modular Lounge West Corridor
Gather Around

Concave Round Modular Seats Upholstery Seat and Back:


Zenith 
C5 780mm W x  750mm D x  Seat Height   16
Interiors
Range: Materialised 8 ‐ 10 Weeks $                       ‐   
450mm x 760mm Height Colour: Artisan Sunset

Single tone upholstery seat and back 

2 Seater Lounge Chairs  North Corridor
Upholstery Exterior:
Tonella  Materialised Crypton Cover
Cloth Shire

Two tone upholstery ‐ “Base” quilted  Zenith  Upholstery Interior:


C6A outer and “Cushion” inside of the chair 2
Interiors Materialised Artwork Leaf
18 ‐ 20 Weeks $                       ‐   
Option 3

Frame:
Bronze

2 Seater Lounge Chairs  South Corridor
Upholstery Interior:
Tonella  Materialised Crypton Cover
Cloth Shire

Two tone upholstery ‐ “Base” quilted  Zenith  Upholstery Exterior:


C6B outer and “Cushion” inside of the chair 4
Interiors Materialised Artwork Leaf
18 ‐ 20 Weeks $                       ‐   
Option 2

Frame:
Bronze

Page 6 of 8
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2
Lounge Arm Chairs  North Corridor

Tonella armchair Upholstery Exterior:


Materialised Crypton Cover
Cloth Shire
Two tone upholstery ‐ “Base” quilted 
outer and “Cushion” inside of the chair Zenith  Upholstery Interior:
C7A 4
Interiors Materialised Artwork Leaf
18 ‐ 20 Weeks $                       ‐   
Option 3

Frame:
Bronze

Lounge Arm Chairs  South Corridor

Tonella armchair Upholstery Interior:


Materialised Crypton Cover
Cloth Shire
Two tone upholstery ‐ “Base” quilted 
outer and “Cushion” inside of the chair Zenith  Upholstery Exterior:
C7B 6
Interiors Materialised Artwork Leaf
18 ‐ 20 Weeks $                       ‐   
Option 2

Frame:
Bronze

Low Stool Chairs Arrival Zone / 
Magnum Stool Reception  5
Reception Stool Chairs Upholstery:
Materialised Lawson 
South Corridor /  Burgundy
DIMENSIONS Zenith 
C8 IES Foyer 10 18 ‐ 20 Weeks $                       ‐   
Length: 480mm Interiors
Width: 520mm Frame: 
Seat Height: 660 mm TOTAL Gold (Oro Eletroplated)
Overall Height: 950mm Metal Feet
15

Page 7 of 8
CONSTRUCTION ISSUE ‐ C1 FURNITURE SCHEDULE
16/02/2023 MONASH UNIVERSITY BUILDING H LEVEL 2
Kitchen Stool Chairs Kitchen

TIPO Stool Backrest and Seat:


Pebble

610 seat high to suit 900mm high  Zenith  Seat Pad Upholstery:


C9 counter 8
Interiors Pebble
14 ‐ 16 Weeks $                       ‐   
No Handle 
Sled Base Frame:
seat cushion  Pebble

Breakout Lounge Chair South Corridor

CONIC Lounge Chair
Seat Pad Upholstery:
A633
Materialised P/Kaufmann
Zenith  Camille Tangerine
C10 Pedestal Base 9
Interiors
18 ‐ 20 Weeks $                       ‐   
Frame / Base: Polished
Chrome Pedestal Base

Ottoman Seat South Corridor 
Precinct Ottoman / IES Foyer
Upholstery Top:
Baresque / Journey - Aire
Rectangle 1400
Daylight

1400mm x 650mm x 450mm Zenith  Upholstery Bottom:


OT1 5
Interiors Materialised / Natural Linen
8 ‐ 10 Weeks $                       ‐   
Grey

Frame / Base: Polished


Chrome Pedestal Base

SUBTOTAL
544 $                                               ‐   
Level 2 Furniture
TOTAL $                                        ‐   
 Allowance for contingency 
deliveries, installation, and rubbish  $                                     ‐
removal
Grand Total $                               ‐

Page 8 of 8
MONASH BUILDING H LEVEL 2 APPENDIX D

APPENDIX D

LOTUS GLAZED SLIDING DOORS


SPECIFICATION

MONASH UNIVERSITY – BUILDING H


LOTUS SL80+ GLAZED ACOUSTIC SLIDER
Project Name: Monash University – Building H
Quote Ref: 20011624
Date: 25/10/22

1. SUMMARY

ITEM GLAZED ACOUSTIC SLIDER

Door Number(s) D16


Lotus Folding Walls & Doors
Supplier 20-24 National Drive, Dandenong South, Vic
Tel (03) 9771 8200, e-mail vic.sales@lotusdoors.com.au
Quantity & Size 1 off @ 2700mm high x 2400mm wide (opening)
Description Lotus SL80+ Glazed Acoustic Face Slider – Dual
Product Code SL80+/37/FD1
Rw Rating Rw37
80mm perimeter frame with 110mm leading stile. Finished in Dulux Duralloy
Frame
powdercoat
Track Lotus 100-1 tracks finished in Pearl White Powdercoat
Sabre 750mm SSS Bar Handles
Hardware
Lever Turn Snib on inside and keylock from outside
Seals Lotus Type 1 Seal Configuration
Configuration Dual Slider Configuration. 2 panels consisting of 1 module per slider.
Panel Finishes 12mm clear acoustic laminated safety glass. Decals by others.
Braking Device Lotus SABS Motion adjustable resistance, velocity damping/braking device
Weight 39 kg/sqm
Opening Force Ensure leading slider can be opened with 20N force
1 x Lotus Fixed Glazed Panels to match slider acoustic rating.
2700mm high x 1200mm wide ( 1 module)
Code: FP400/1/12.8L
Fixed Glazed Panel
- 44x102mm Aluminium Mullion around perimeter with no intermediate mullions.
Finish to match sliders
12mm clear acoustic laminated glass. Any decals / film to be applied by others on site
Track fixed to undrilled structural steel support supplied and installed by others so that
packing to track by Lotus does not exceed 10mm and meets Lotus layout requirements.
Installed To
Structural support to be designed for a maximum of 2mm deflection under moving
load.

CREATING SPACES WHERE PEOPLE THRIVE 2


Project Name: Monash University – Building H
Quote Ref: 20011624
Date: 25/10/22

2. Supports
2.1. Sliders shall be supported from the structural member above with no floor tracks.
2.2. Head tracks shall be fixed to undrilled structural steel supplied and installed by others so that packing to
track by Lotus does not exceed 10mm and meets Lotus layout requirements.
2.3. Steel supports to be designed with a maximum of 2mm deflection under moving load.

3. Panels
3.1. Panels shall be Lotus SL80+ series slider panels and shall be constructed of a perimeter frame containing
individual modules of toughened safety glass conforming to AS1288.
3.2. Glass shall be replaceable in the field.

4. Acoustics
The manufacturer shall guarantee that the sliding door system is of a construction to achieve Rw 37 based on
acoustic tests to AS1276 by a NATA approved independent Australian acoustic laboratory.

5. Opening Force
5.1. The manufacturer shall ensure the sliders can be opened with 20N of force for the first 850mm or more of
travel.
5.2. Lotus Low Friction trolleys to be used for larger / heavier sliders.
5.3. All breaking / anti-slam mechanisms should not in increase this opening force.

6. SABS MOTION dampening device


The acoustic sliding door will include ‘SABS Motion’ an integrated closing velocity damping/braking device which
slows the sliding door proportional to its speed when approaching the jamb (closing direction). Adding no
resistance in the opening direction such that the first 850mm or more of travel will maintain a 20N or less
opening force. The dampening force of the Device must be adjustable within a predefined range by a qualified
Lotus technician to meet the customer’s needs.

7. Accessories & Hardware


7.1. Sabre 750mm SSS Bar Handles.
7.2. Lever turn snib on inside and keylock from outside.

CREATING SPACES WHERE PEOPLE THRIVE 3


Project Name: Monash University – Building H
Quote Ref: 20011624
Date: 25/10/22

8. Surface Finishes
8.1. Panel surfaces shall be finished in grade A safety laminated glass to code.
8.2. Glass Manifestations or decals are to be supplied and installed by others following Lotus install.
8.3. Panel frames shall be finished in Dulux Duralloy Powdercoat.
8.4. Head track shall be finished in Pearl White Powdercoat.

9. Customer Care
9.1. The supplier is required to provide a handover to the end user.
9.2. The supplier will provide a one-year warranty against manufacturing and installation defects.
9.3. Extended warranties are available subject to a Preventative Maintenance Agreement being entered with
Lotus Service Division.

CREATING SPACES WHERE PEOPLE THRIVE 4


MONASH BUILDING H LEVEL 2 APPENDIX E

APPENDIX E

ACOUSTIC REPORT
Building H Level 2

Acoustics design report

Monash University

Job No: 1036431


Doc Ref: 1036431-AS-RPT-01
Revision: B
Revision Date: 16 November 2022
Building H Level 2 – Acoustics design report

Project title Building H Level 2 Job Number

Report title Acoustics design report 1036431

Document Revision History

Revision Ref Issue Date Purpose of issue / description of revision

— 09 September 2022 Schematic design

A 07 November 2022 Detailed Design

B 16 November 2022 Tender Issue

Document Validation (latest issue)

16/11/2022
16/11/2022 16/11/2022

X X X
p.p. Principal author Daniele Albanese Checked by Vahid Alamshah Verified by Vahid Alamshah

Signed by: Vahid Alamshah Signed by: Vahid Alamshah Signed by: Vahid Alamshah

© Cundall Johnston & Partners PTY Ltd (“Cundall”) owns the copyright in this report and it has been written for the sole and confidential
use of Monash University. It must not be reproduced in whole or in part or relied upon by any third party for any use whatsoever without
the express written authorisation of Cundall. If any third party whatsoever comes into possession of this report, they rely on it at their
own risk and Cundall accepts no duty or responsibility (including in negligence) to any such third party.

Document Ref. 1036431-AS-RPT-01 Template version 1.4 – 3 October 2017


Building H Level 2 - Acoustics design report

Contents

1.0 Introduction 5

1.1 The Project 5


1.2 Proposed plans 5
1.3 Purpose of report 5
1.4 Information provided 5
1.5 Key assumptions and risks 5
1.6 Key outstanding information requirements 5

2.0 Acoustic design standards and guidelines 7

2.1 Basis of design 7


2.2 Internal noise criteria 7
2.3 Internal sound insulation 7
2.4 Reverberation 7

3.0 Internal noise levels 9

3.1 General 9
3.2 Road traffic noise intrusion 9
3.3 Review of proposed mechanical services design 9

4.0 Reverberation control 12

4.1 General 12

5.0 Partitions and doors 14

5.1 Partitions – enclosed spaces 14


5.2 General partition guidelines 14
5.3 Doors 14
5.4 Acoustic sliding glazed door 15

Appendices

Appendix A Acoustics terminology


Appendix B Acoustics strategy drawings
Appendix C ASHRAE Handbook Table 47
Appendix D VAV Sound power level data

Document Ref. 1036431-AS-RPT-01


Building H Level 2 - Acoustics design report

1.0Introduction

Document Ref. 1036431-AS-RPT-01


Building H Level 2 - Acoustics design report

1.3 Purpose of report


1.0 Introduction
This report outlines the acoustic strategy that is proposed for various elements of the development and suggests design and
construction solutions to accompany the strategy. The proposals are provided for discussion and coordination with the Client
1.1 The Project and design team.

Cundall have been commissioned to prepare an acoustic design strategy report for the proposed refurbishment at Level 2 of This report covers the following criteria:
Building H at the Monash University Caulfield Campus. ▪ Internal noise levels from exterior noise sources (e.g. road traffic noise);
The project includes the fit-out of the following spaces: ▪ Internal noise levels from building services;
▪ Tutorial rooms; ▪ Sound insulation / transmission between spaces; and
▪ Group study rooms; ▪ Reverberation control.
▪ IES space;
1.4 Information provided
▪ Reception;
▪ Kitchen; and ▪ Level 2 proposed mechanical services arrangement (ref. LCE22129-M300 Rev.P4);
▪ Corridors. ▪ Existing mechanical services arrangement – LEVEL TWO (L02) (MON) (ref. A0-M-P-1003 Rev.C);
▪ Proposed Level 2 Floor Plan (ref. A01 dated 4/10/2022);
▪ Proposed Level 2 RCP (ref. A03 dated 4/10/2022);
Acoustics terminology used in this report is described in Appendix A.
▪ Learning and Teaching Building Acoustic Design Development Report prepared by Marshall Day Acoustics (MDA
1.2 Proposed plans Acoustic Brief) (ref. Rp 003 R03 2015304ML dated 7 April 2016);
▪ VAV Sound power level data, included in Appendix D.
Figure 1.1 shows the current design floor plans for the proposed fit-out.
1.5 Key assumptions and risks

▪ Building façade and façade elements performance is unknown.


▪ Existing AHU noise and silencer performance is unknown.
▪ Adequacy of sound insulation criteria from the MDA Acoustic Brief and the MDCS will need to be reviewed.
Considerations on speech privacy will need to be discussed with the Client and the project team. Current proposals do
not meet the typical recommended acoustic criteria for the understood use of the space.

1.6 Key outstanding information requirements

Other key outstanding information which will affect the development of the design and progress in the next stage is as
follows:
▪ Existing AHU noise and silencer insertion loss performance.
▪ Existing walls to be retained.
▪ Adequacy of existing wall detailing and penetrations to be retained.

Figure 1.1 Schematic design floor plan – Level 2

Document Ref. 1036431-AS-RPT-01 5


Building H Level 2 - Acoustics design report

2.0
Acoustic design standards and
guidelines

Document Ref. 1036431-AS-RPT-01 6


Building H Level 2 - Acoustics design report

2.3 Internal sound insulation


2.0 Acoustic design standards and guidelines
Clause B 05.01 of the MDCS states that:
Spaces which require a:
2.1 Basis of design
• high level of acoustic separation to be designed to a minimum sound reduction loss of 40dB(A), characterised
Based on discussion with the client, the project will need to achieve similar acoustic standard to those achieved in the LTB
by low level of audible sounds from adjoining spaces.
(Learning and Teaching Building). As a reference, Monash University provided the document Learning and Teaching
• medium level of acoustic separation to be designed to a minimum sound reduction loss of 32dB(A),
Building Acoustic Design Development Report prepared by Marshall Day Acoustics (MDA Acoustic Brief) (ref. Rp 003 R03
characterised by intelligible but not distracting sounds from adjoining spaces.
2015304ML dated 7 April 2016). The report proposed some departures from the Monash University Design & Construction
• low level of acoustic separation is adequate to be designed to a minimum sound reduction loss of 27dB(A).
Standards and these are understood to be desirable for this project.
• two different acoustic separation requirements, adopt the higher level of separation."
2.2 Internal noise criteria The clause does not specify whether the term “sound reduction loss” refers to the Sound Reduction Index (Rw) or the Sound
Level Difference (Dw). Based on the MDA Acoustic Brief and previous work carried out by Cundall for Monash University,
Clause B 05.02 of the Monash Design & Construction Standards (MDCS) states that:
this is intended as in-situ Sound Level Difference (Dw).
Ambient sound levels are to be at or below:
For the purpose of this report the Sound Level Difference (Dw) is assumed to be 5 dB lower than the Sound Reduction Index
• NR30 in lecture theatres and conference rooms (Rw).
• NR35 in individual offices and tutorial rooms The criteria in this report are expressed in terms of Rw in line with the MDA Acoustic Brief.
• NR40 in open planned offices, waiting areas and circulation spaces.
A summary of the relevant sound insulation criteria is provided in Table 2.2 and in the drawings mark-up provided in
The internal noise level criterion presented in the have MDA Acoustic Brief is more stringent with respect to tutorial rooms, Appendix B.
where NR30 is indicated. This has been adopted in this report.
Table 2.2 Partition and doors sound reduction index (Rw)
For waiting areas and circulation spaces the MDA Acoustic Brief provides a higher noise criterion (NR45), this has been
adopted in this report. For the reception area the criteria provided for waiting areas has been adopted. Space Room-to-room Partition with door Doorset rating (Rw)
partition rating (Rw) rating (Rw)
The internal noise criteria applicable to exterior road traffic noise intrusion would follow the same criteria outlined above.
Tutorial rooms 45 35 30
The internal noise criteria adopted are taken from the MDA Acoustic Brief as summarised in Table 2.1.
Group study rooms 45 35 20

IES space 45 35 30
Table 2.1 Ambient sound level criteria
Reception n/a - -
Space Building services Exterior road traffic
noise, NR noise, NR Kitchen n/a - -

Tutorial rooms 30 30 Corridors n/a - -

Group study rooms 30 30

IES space 30 30 2.4 Reverberation


Reception 45 45
Provision of suitable reverberation times (RT) enables clear communication of speech between speaker and listener and
Kitchen 45 45 controls reverberant noise build-up in larger multi-occupancy spaces.
Corridors 45 40 The reverberation time criteria are for rooms that are finished, furnished for normal use, but unoccupied. The reverberation
time is intended in terms of the T60 reverberation time averaged at 500 Hz, 1 kHz and 2 kHz octave bands.
Table 2-3 - Summary of proposed project specific RT60 criteria

Room type RT60 (seconds)

Tutorial rooms 0.6 to 0.7

Group study rooms 0.6 to 0.7

IES space 0.6 to 0.7

Kitchen -

Corridors 0.6 to 0.8

Document Ref. 1036431-AS-RPT-01 7


Building H Level 2 - Acoustics design report

3.0
Internal noise levels

Document Ref. 1036431-AS-RPT-01 8


Building H Level 2 - Acoustics design report

Due care and attention should be taken to ensure that the plant rooms do not adversely affect internal noise and/or vibration
3.0 Internal noise levels levels. Where these are found to be a problem, allowance should be made for retrofitting noise and vibration mitigations such
as separate studwork lining to internal plant rooms or vibration isolators.

3.1 General Pipework and ductwork should be mounted using suitable resilient hangers where appropriate. Flexible connections should
be introduced to minimise plant noise and vibration transfer.
Existing road traffic noise levels have been assessed and opportunities for improvements of façade and façade elements
have been proposed where necessary. 3.3.2 VAV units
The concept mechanical services strategy has been reviewed and recommendations are provided in this section to guide
Preliminary calculation of duct-borne noise levels and VAV casing radiated noise levels has been undertaken within selected
the initial design.
representative spaces. Calculations have been undertaken purely based on the noise generated by the VAVs and do not
consider contribution of mechanical noise from the central plant.
3.2 Road traffic noise intrusion
The sound power level data from the VAV were provided and are presented in Appendix D. The sound power levels may
Measurements of road traffic noise were undertaken on 20th October 2022 within Building H Level 2 and along Dandenong change by varying the valve position and it is not clear to what condition the data provided refer to. Further details are
Road to determine the existing road traffic noise both outside and inside the Monash Caulfield Building H. necessary and, in any event, the contractor should ensure that the selected VAV will comply with the specified noise criteria.
Road traffic noise levels up to LAeq,5 min 48dBA were measured within the proposed Tutorial Room 1 and 2 areas and in the The duct-borne noise from the VAV units and the VAV casing radiated noise is predicted to exceed the internal noise criteria
North Corridor 1 and 2, directly facing Dandenong Road. These correspond to NR 42 and significantly exceed the noise within all tutorial rooms and the IES space.
criteria of NR 30 set for tutorial rooms.
Duct velocities appear to be too high and likely to cause regenerated noise issues within tutorial rooms.
Elevated noise levels were measured also within Tutorial Room 8 with noise levels up to LAeq,5 min 45dBA (NR 40).
In fact, noise generated by air movement in ducts and through duct fittings is a major contributor to the mechanical system
Road traffic noise levels within Tutorial Room 3, 4 and 9 were found to be between LAeq,5 min 37dBA and 41dBA (NR 32-36) noise level. The acceptable level of flow generated noise is dependent on the design criteria of the space being served by
and these levels exceed the noise criteria of NR 30 set in accordance with the MDA Acoustic Brief. However, the noise the mechanical system.
criterion set by the Monash Design and Construction Standards for individual offices and tutorial rooms is equal to NR 35
and the measured noise levels would comply or marginally exceed this criterion. To control turbulence and airflow generated noise to sensitive spaces, it is recommended that the duct velocities detailed in
the Table 3.1 should not be exceeded.
Upgrade of the existing glazing is recommended as follows:
Table 3.1 Recommended maximum duct air velocities
- Tutorial 1, 2 and 8: Modify or replace the existing façade glazing with a double-glazing system to achieve a sound
reduction index Rw of 45 dB (e.g. 6mm glass + 100mm air gap + 12.38mm laminated glass). Design criterion, Maximum duct velocity, m/s
NR
Branch duct Run-out duct Flexible duct
- Tutorial Room 3, 4, 9 and IES Room H208: Modify or replace the existing façade glazing with a double-glazing
system to achieve a sound reduction index Rw 38 dB (e.g. 6mm glass + 24mm air gap + 4mm glass).
40 6.5 5.0 3.5

- North Corridor 1 and 2 (facing Dandenong Road): Modify or replace the existing façade glazing with a double- 35 5.5 4.0 3.0
glazing system to achieve a sound reduction index Rw 38 dB (e.g. 6mm glass + 24mm air gap + 4mm glass).
Existing road traffic noise levels within the two corridors exceed the noise criteria by 3dB. This is considered 30 4.5 3.5 2.5
marginal and unlikely to cause disruption to the normal site operations.
25 4.0 2.5 2.0

3.3 Review of proposed mechanical services design Branch duct All ducts connected directly to the run-out ducting.

Duct layout drawings have been reviewed and unit selections provided in Level 2 proposed mechanical services Run-out duct All ducts connected directly to the terminal register, or within 5 duct diameters of the register.
arrangement (ref. LCE22129-M300 Rev.P1)
Based upon this review, our recommendations for the control of mechanical services noise are detailed in the following
sections.
To resolve VAV noise breakout problems all units should be located outside tutorial rooms, in corridors and open spaces.
3.3.1 General VAV units and ductwork located near return air grilles should be wrapped with Wavebar (10kg/m2) or Muftilag (10kg/m2).

It is important that ambient noise levels are not reduced too low, as a degree of constant background noise, such as In addition, the following acoustic treatments are recommended.
provided by mechanical ventilation systems, helps to mask activity noise intrusion and provides appropriate privacy between
areas.
The contractor should ensure that the existing and proposed mechanical services would comply with the noise criteria
specified in Table 2.1.

Document Ref. 1036431-AS-RPT-01 9


Building H Level 2 - Acoustics design report

Table 3.2 VAV acoustic treatments Table 3.3 Flexible duct minimum insertion loss

VAV/ Room Supply Casing Octave band centre frequency, Hz

All VAV units Ensure the maximum duct velocity values Locate all VAV units outside rooms with Unit 63 125 250 500 1000 2000 4000
provide in Table 3.1 are met. noise criteria of NR 35 or less. Minimum insertion loss per metre 4 10 11 9 10 10 7

VAV (Size 20) in Tutorial rooms and IES Provide 1 radiused bend internally lined with If units are located inside rooms then Wrap
space 50mm acoustic lining. all units and the first 3m (as far as practical)
of duct with Wavebar (10kg/m2) or Muftilag 3.3.6.1 Penetrations
and
Provide a minimum of 3m acoustically lined All services penetrations in acoustically rated walls and above ceiling baffles must be acoustically sealed. Typically,
duct downstream of the unit and 2m of Alternatively, plasterboard ceiling can be penetrations should be kept to no greater than 10 mm larger than the penetrating element and the junction/penetration
internally lined acoustic flexible ducts. installed over the entire Tutorial ceiling area sealed with a non-setting, flexible acoustic sealant such as mastic.
and access panels should achieve Rw 30
dB. Where penetrations are larger, they must be reduced to 10 mm greater than the penetrating element using plasterboard (to
Alternatively, the ductwork should be fitted
with an appropriately sized attenuator.
the same thickness as the rest of the partition) and acoustically sealed.

VAV (Size 8) in Group Study rooms Provide a minimum of 2m acoustically lined Units should be located above a mineral Crosstalk
duct downstream of the unit and 1m of fibre ceiling achieving >CAC 35.
Where ductwork passes through a partition, or where rooms share common ductwork, crosstalk attenuation should be
internally lined acoustic flexible ducts.
applied to ensure that the acoustic performance of the partitions is not degraded.

3.3.3 Return air ducts Potential crosstalk issues have been identified between Tutorial room 8 and Tutorial room 9 and between Group Study C-1,
Group Study C-1 and Group Study A-5.
The existing return air ducts to the plantrooms are being retained, an attenuator is shown in the existing layout. There is a
Crosstalk silencers should be installed to ensure that the acoustic performance of the partition is not degraded. Alternatively,
risk that the attenuators will constitute potential flanking path causing excessive noise in the rooms adjacent to plantrooms.
all ductwork passing through two or more enclosed spaces should be internally lined with 25mm mineral fibre and external
The contractor would need to ensure that the noise from the existing return air ducts comply with the noise criteria specified.
lagging, such as Wavebar (10kg/m2) or Muftilag (10kg/m2), should be installed around the ducts for 2 metres either side of
the wall.
3.3.4 Air diffusers, grilles and registers

Air diffusers, grilles and registers should be selected with air velocities within the range deemed acceptable by the 3.3.1 Air transfer duct
manufacturer for a noise level at least 5 dB below the project design criteria, considering the cumulative effects of the
Return air transfer ducts are to be provided across all full height partitions and baffles to all meeting rooms and are to be
number of diffusers/grilles in each space.
internally lined with 50 mm acoustic insulation. The transfer duct will need to have minimum two 90-degree bends.
Notwithstanding the above, each device should be subjectively quiet in operation, and produce no objectionable tones or
other noticeable features of noise within occupied areas.

3.3.5 Vibration isolation

All mechanical services equipment must be vibration isolated from the structure in accordance with the recommendations of
the ASHRAE Handbook, an extract of which is provided in Appendix C.

3.3.6 Flexible duct

Excessive noise break-out may occur if flexible duct is used as the primary means of providing duct attenuation. Flexible
duct diameters should be selected according to air velocity limits detailed in the table above.
Flexible ductwork should not be compressed, or airflow otherwise restricted, to ensure excessive noise is not generated.
Where flexible ductwork crosses a full height partition, it must be cut short to each side of the partition and a section of steel
ductwork be used to span the partition. Penetrations for the steel duct must then be acoustically sealed.
All acoustic flexible duct is to be perforated, insulated acoustic type such as Westaflex Unilok S R1 A1 with minimum
insertion loss as detailed in Table 3.3.

Document Ref. 1036431-AS-RPT-01 10


Building H Level 2 - Acoustics design report

4.0
Reverberation control

Document Ref. 1036431-AS-RPT-01 11


Building H Level 2 - Acoustics design report

4.0 Reverberation control

4.1 General

Reverberation directly affects speech intelligibility, activity noise build-up and auditory distraction. To suitably control
reverberation within rooms acoustically absorptive surfaces will need to be incorporated.
All dedicated acoustic absorption should be mounted facing towards the main room volume and distributed evenly
throughout the room unless otherwise called for by the Acoustic Consultant.
All finishes should be dimensionally stable and adequately supported so that they exhibit no tendency to warp or bow.
Materials should be suitably robust to withstand typical day-to-day wear and tear and reasonably expected impacts from
within the room for which they are specified.
To prevent room flutter echo, wall panels are recommended over approximately 50% of the wall area on two perpendicular
walls. The wall panels can be installed from approximately 0.8m above floor level to ceiling level.
The recommended location and extent of internal acoustic finishes are provided in Table 4.1 below.
Table 4.1 Acoustic absorption review

Space Floor Ceiling Walls RT Criteria (s)

Tutorial Carpet Mineral fibre tiles achieving not less than NRC 0.7 over 12 mm Echopanel direct fix 0.6 to 0.7
50% of the ceiling area. (Currently it is approximately over (NRC 0.45) over 50% of the
40% of the ceiling area. This will need to be increased) area on two perpendicular
walls.

*For Tutorial 5, 6 and 7 a plasterboard ceiling is proposed.


Ceiling acoustic panels achieving NRC 0.7 should be Plasterboard
included over 50% of the ceiling area.

Plasterboard

Group Carpet Mineral fibre tiles achieving not less than NRC 0.7 over 12 mm Echopanel direct fix 0.6 to 0.7
Study 50% of the ceiling area. (Currently it is approximately over (NRC 0.45) over 50% of the
25% of the ceiling area. This will need to be increased) area on two perpendicular
walls.
Plasterboard
Plasterboard
*For Group Study A-4 and Group Study B-1 a plasterboard
ceiling is proposed. Ceiling acoustic panels achieving NRC
0.7 should be included over 50% of the ceiling area.

IES Carpet Mineral fibre tiles achieving not less than NRC 0.7 over 12 mm Echopanel direct fix 0.6 to 0.7
space 50% of the ceiling area. Currently sound absorptive finish is (NRC 0.45) over 50% of the
located approximately over 45% of the ceiling area. This area on two perpendicular
may be already adequate. Further advice will be provided walls.
as the design progresses.
Plasterboard
Plasterboard

Corridors Vinyl Mineral fibre tiles, NRC 0.7 over 100% of the ceiling area. - 0.6 to 0.8
(Currently it is approximately over 25% of the ceiling area.
This will need to be increased)

Plasterboard

Document Ref. 1036431-AS-RPT-01 12


Building H Level 2 - Acoustics design report

5.0
Partitions and doors

Document Ref. 1036431-AS-RPT-01 13


Building H Level 2 - Acoustics design report

5.0 Partitions and doors 5.2 General partition guidelines

To ensure that acoustic integrity and performance of partitions is maintained and controlled, the following guidance is
The following sub-sections outline the recommended constructions and performance requirements for new separating suggested.
elements within the project, with a view to meeting the sound insulation requirements outlined in Section 2.3. ▪ All partitions should be full height, from the structural floor to the underside of the soffit and well-sealed.
Recommendations for partition rating are provided in the markup drawing in Appendix B. ▪ Electrical switch sockets should not be placed back-to-back within lightweight partitions but spaced a minimum 600 mm
apart (usually one vertical stud spacing).
5.1 Partitions – enclosed spaces ▪ Services penetrating acoustically rated partitions that divide adjacent noise sensitive spaces should be avoided,
Cross-wall partitions generally consist of drywall construction. A sliding glazed partitions would be utilised at the frontage of particularly ductwork. Ideally, service runs would be via the corridor, with branches spurring off the main runs into rooms
the IES room. via the corridor walls.
▪ Where double layers of board are used, joints should be staggered. Facing boards should be well sealed with skim
Dividing partitions between Tutorial rooms, IES space and Group Study rooms should be full height, from structural floor to
finish.
soffit, and well-sealed. This is not practical for glazed or operable partitions; measures to mitigate noise issues and improve
acoustic privacy at these locations are presented later in this section of the report.
Table 5-1 Example suitable partition types (drywall) 5.3 Doors

Example partition constructions Image Doors in Tutorial and IES space should provide a minimum laboratory Sound Reduction Index Rw 30 dB as indicated in the
mark-up plans in Appendix B. It is recommended that a certified guarantee of acoustic performance is provided for review
Rw 35 dB partitions from the supplier.
▪ 1 layer 13 mm thick standard plasterboard
Doors in group study rooms should achieve Rw 20 dB as per MDA Acoustic Brief. Such rating is considered low and
▪ Minimum 64 mm steel studs
generally this type of doors are not tested for sound insulation performance.
▪ No insulation required within cavity
▪ 1 layer 13 mm thick standard plasterboard Typical ratings for various doors are presented in Table 5.2 for reference.
Table 5.2 Door construction

Performance requirements Example door construction

Rw 20 dB ▪ 32mm timber or 10mm glass


Rw 40 dB partitions
Rw 30 dB ▪ 38 mm timber or 10 mm toughened glass with perimeter and threshold acoustic seals
▪ 1 layer 13 mm thick standard plasterboard
▪ 64 mm steel studs
▪ 50 mm thick 10 kg/m³ acoustic cavity insulation The following guidance should be considered:
▪ 1 layer 13 mm thick standard plasterboard
▪ Doors should be correctly aligned and should fit well into the frame; the maximum gap between door and frame must
not exceed 3 mm. For doors rated Rw 30 dB acoustic seals should be compressed evenly around the whole perimeter.
▪ Seals should be designed to avoid damage by regular use of the door and should allow for building tolerances and floor
level variations without loss in performance.
▪ Acoustic doors (Rw 30 dB and above) should be supplied as a complete door set (door and frame together with fitted
Rw 45 dB partitions seals). A certified guarantee of acoustic performance should be available for inspection from the manufacturer.
▪ 1 layer 13 mm thick standard plasterboard ▪ All acoustic seals should be continuous and not interrupted by locks, hinges, and other hardware.
▪ 64 mm steel studs
▪ 50 mm thick 10 kg/m³ acoustic cavity insulation
Doors should be designed and installed such that they do not unduly compromise the sound insulation performance of
▪ 2 layers 13 mm thick standard plasterboard partitions. Performance of partitions between adjacent rooms will be dictated by the following:

▪ Orientation of the doors; and


▪ Physical attenuation of sound through the doors.
With regard to the former, it is recommended that the location of doors in partitions to corridors is such that they are as far
Rw 55 dB Partition (plantroom) apart as possible, e.g. not either side of a junction between a dividing partition and the corridor wall. The latter will depend
- on the sensitivity of the space to which the door provides access and is illustrated in Figure 5.1 and Figure 5.2.
- 150mm solid concrete block

Document Ref. 1036431-AS-RPT-01 14


Building H Level 2 - Acoustics design report

Figure 5.1: Example of good separation between doors Figure 5.2: Example of poor separation between doors

5.4 Acoustic sliding glazed door

In-situ, sliding doors do not perform as effectively as standard doors, and a performance significantly lower than a standard
door is expected.
The MDA Acoustic Brief correctly points out that the maximum achievable sound insulation rating is in the order of Dw 20-25
dB, corresponding to approximately Rw 30-35 dB for sliding doors. The client needs to be informed of the consequences
from adopting such rating. In fact, a rating of Dw 20-25 is generally considered very poor in terms of sound reduction and
speech privacy will be negatively affected so that conversations are clearly heard and understood between rooms, without
significantly elevated ambient noise levels.
Discussion with the Client and the project team is necessary to ensure that the acoustic limitations associated with the use of
sliding doors are understood and accepted.
Similarly, the doors accessing all group study rooms are designed to achieve Rw 20 and would present the same speech
privacy problem described above, if not worse.
In any event, the performance of the sliding door systems should be confirmed by the supplier through appropriate laboratory
test reports.

Document Ref. 1036431-AS-RPT-01 15


Building H Level 2 - Acoustics design report

6.0
Appendices

Document Ref. 1036431-AS-RPT-01 16


Building H Level 2 - Acoustics design report

Vibration amplitude can be expressed as an engineering unit value e.g. 1mms-1 or as a ratio on a logarithmic scale in
Appendix A Acoustics terminology decibels:
Vibration velocity level, LV (dB) = 20 log (V/Vref),
‘A’-WEIGHTED SOUND LEVEL dBA
(where the preferred reference level, Vref, for vibration velocity = 10-9 m/s).
The unit generally used for measuring environmental, traffic or industrial noise is the A-weighted sound pressure level in
decibels, denoted dBA. An A-weighting network can be built into a sound level measuring instrument such that sound levels The decibel approach has advantages for manipulation and comparison of data.
in dBA can be read directly from a meter. The weighting is based on the frequency response of the human ear and has been
WEIGHTED SOUND REDUCTION INDEX (Rw )
found to correlate well with human subjective reactions to various sounds. An increase or decrease of approximately 10 dB
corresponds to a subjective doubling or halving of the loudness of a noise. A change of 2 to 3 dB is subjectively barely The laboratory sound insulation performance usually provided by manufacturers and suppliers is the weighted sound
perceptible. reduction index, Rw. The higher the rating, the better the sound reduction between spaces.

EQUIVALENT CONTINUOUS SOUND LEVEL (LAeq) SOUND ABSORPTION

Another index for assessment for overall noise exposure is the equivalent continuous sound level, Leq. This is a notional When sound hits a surface, some of the sound energy is reflected, while some is absorbed by the surface material. ‘Sound
steady level, which would, over a given period of time, deliver the same sound energy as the actual time-varying sound over absorption’ refers to ability of a material to absorb sound.
the same period. Hence fluctuating levels can be described in terms of a single figure level. NRC NOISE REDUCTION COEFFICIENT
REVERBERATION TIME (RT60) A single number rating between 0 and 1 of the ability of a material to absorb sound. It is the average of the absorption
coefficients in the 250-2000Hz octave bands. The larger the number, the more absorptive the material.
The time, in seconds, taken for a sound within a space to decay by 60 dB after the sound source has stopped is denoted at
the reverberation time. The RT is an important indicator of the subjective acoustic within an auditorium. A large RT
subjectively corresponds to an acoustically ‘live’ or ‘boomy’ space, while a small RT subjectively corresponds to an
acoustically ‘dead’ or ‘flat’ space.
VIBRATION
Vibration may be expressed in terms of displacement, velocity and acceleration. Velocity and acceleration are most
commonly used when assessing structure borne noise or human comfort issues respectively. Vibration amplitude may be
quantified as a peak value, or as a root mean squared (rms) value.

Document Ref. 1036431-AS-RPT-01 17


Building H Level 2 - Acoustics design report

Appendix B Acoustics strategy drawings

Document Ref. 1036431-AS-RPT-01


1036431 A1
DO NOT SCALE FROM THIS DRAWING

Partitions: Sound Reduction Index


(Rw)
Rw 35 dB
Rw 40 dB
Rw 45 dB
Rw 50 dB
Rw 55 dB
A B C D E F G H I
9000 9000 9000 9000 9000 9000 9000 9000 Acoustic sliding glazed
8250 8250 750 8250 750 8250 750 3965 50 4610 door
D-
A- JU.08 3 3
LINE OF CEILING
3 2 3 BULKHEAD 3 A- 2 3 2 3
SHOWN DOTTED 1
C C
Room Criteria:
1 TTDP WB2 WB
1 1

JU.03M
JU.03K

JU.03L
JU.03J
JU.03H
FA FA FA
TUTORIAL 1
H224 LA LA LA LA LA LA Maximum internal ambient
JU.08A LA LA LA LA LA JU.08C SEMI OPEN 35
CA2 H223 H213B JU.08B
0.8 H213A GS / B-2 PRIVACY SCREEN noise level, NR
NORTH CORRIDOR 1 40 JU.08C NORTH CORRIDOR 2
H2-PS04
DOUBLE GLAZING OR 6.5MM VLAM
HUSH GLAZING ON ALUMINIUM H212 WALL AS DETAILED
W0

H2-PS04 REVEALS AND GLAZING CHANNEL.


CA1 CA1 TB Maximum reverberation
H222
1

TV CA1 D22 MODIFY EXISTING C2


0.8
NEW DOOR
STAIR HANDRAIL
W32 JU.12B
30 LA 0.6TV time, s
JU.07A JU.07 W10 OPENING TO W30
D06
30 0.6 A- W0
9 D05 PLANT ROOM BALUSTRADE TO
SUIT PROPOSED RBP D21
R
15
00
C2 PLANT ROOM
EFHR
H2-PL03

P
FA W3

RB
3
TV JU.12A
WB D20 JU.06C C2
LA
TV CA1 RBP
GS /

12000
LA

4
ST TB
RBP B-1 FE

W3
LA CA1
LA H215 BATTEN OUT WALL FOR
WEST TB
REMOVE EXISTING RETICULATION OF CABLING
TV D01
WB WB WB COR. 1 DOOR TO PLANT CA3

H2-PS05 30JU.10A 0.6TV ROOM AND MAKE TV WB TUTORIAL 7 H211C


W11
TV GOOD FRAMING MR1 Doors: Laboratory rating
H214
TTDP WB2 TV WB
TGI
TUTORIAL 5 CA3
W0

JU.14
GS / A-1 TV H214
PLANT ROOM 30 0.6 EAST
2

CA1
H215 WB H2-PL01 WB Rw 20 dB doorset
C
NORTH CORRIDOR 1

JU.09C
CA2
30 0.6

BIN
BIN
CA2 STAIR 2
STAIR WB H2-PS03
H2-ST02 Rw 30 dB doorset
H2-ST03 MR2 TV
R

30 0.6 JU.09A ST
BP

Rw 35 dB doorset

W31
D07
TTDP WB TV WB ST
TUTORIAL 2 EFHR
2 2

LA
H225 WB2 TTDP
SUNDRY SHAFT
H211 MR
W

FE TV H2-RS01 WB WB ST
12

CA2
GS / A-2 JU.11A COMMS TV
3

D19
W0

H216 ROOM

OS
LA
H2-PL02

JU.01C
CA1 LA RBP

JU.02B
ST RBP H22140 0.8 TB
TB
H2-TL02A ALLOW FOR MINOR TOUCH UP
WB
0B
45
R

TV .1 OF EXISTING TOILET. EXACT


BP

LA WB TV D02 JU PROVIDE NEW SCOPE TO AMENITIES TO BE DW


C
AIR
LIFT LIGHT
ACC CONFIRMED
LA WB
TV W1
5 LIFT INDICATOR LIFT WC FEMALE FR TUTORIAL 8
GS / A-3 SHAFT
H218
H2-LF01 H2-LF02
H2-TL03 TOILET 30
H210 0.6
-4 TV LIFT
ST D03 FR
/A
D09 CA4
H2-TL02

B
GS 217 LOBBY
CA2

.06

9
W2
RBP DOUBLE GLAZING OR 6.5MM W

JU
H LA

OS
VLAM HUSH GLAZING ON ES H2-PS01 KITCHEN
W

12000
ALUMINIUM REVEALS AND 15 T MR1
H211B
CO
JU

GLAZING CHANNEL. CA RBP C


.10

30 0.6 RB H2 R W13

LA
TB P
- P RI
D08
LIFT FEATURE LIFT MR2
C

WB S0 D
W0

JU.09B H2-LF01 SCULPTFORM H2-LF02 FE


WB 6 OR WF
WB2 TV WB TTDP
4

TIMBER
C TUTORIAL 3 LA BIN TV P 3 ALLOW FOR MINOR TOUCH UP
T TD BATTENS TO
OF EXISTING TOILET. EXACT H211A
H226
C WB
LIFT LOBBY ELEC SCOPE TO AMENITIES TO BE
WB2 TV WB TTDP
CA3 TV RISER MALE CONFIRMED
WB
W17

30 0.6 W
14
LIFT LIFT
H2-RS02 TOILET H2-TL01A VM VM
WEST H2-TL01
WB H2-LF01 H2-LF02
COR. 2

TV
TV

W2
W18

C H2-PS05 JU.11D

8
RB
P
WB CA1 LA TUTORIAL 9
STAIR 1 30H209 0.6
5

30 0.6
W0

3 3

W26
LA TUTORIAL 6 H2 - ST01
FE CA4
TV TB
H219
TTDP
W06

TV TV TV
WB2 FA ST
30
CA3 0.6 FHR
OS
LA
BF
TV GS / JU.11B GS / JU.11C
D15 EAST
WB C-1 C-2 GS / RBP
2000

ST TV JU.02A CORRIDOR 2
D04
JU.07B
SOUTH H204 LA H206 LA A-5 - 08.08.2022 For Detailed Design DA JL DA
TV D11 D12 H2-PS03
MR1
TGI STAIR CA4 CA4 H207 D18
TV - 08.09.2022 For information DA JL DA
WB RBP WB H2-ST04 CA WB WB ST
C H220 TB
30 TB
0.6 W25
1200

MR JU.01A
30 0.6 40 0.8 D17
WB2
Issue Date Description By Chkd Verfd

TV C
ARRIVAL AND WB
1110

CATCHUP ZONE JU.06A LOTUS ALUMINIUM FRAMED RBP C


Project
C H201 RBP ACOUSTIC SLIDING GLAZED
RBP D10
DOORS WITH SINGLE FIXED
CA1 RBP
LINE OF MODIFY EXISTING STAIR WINDOW PANEL Monash Caulfield Building H Level 2
TV 30 0.6 W19 W2
0
CHANGE IN HANDRAIL BALUSTRADE AND W21
2 W23 2

12000
FLOOR FINISH CONSTRUCT NEW BALUSTRADE W2 W2 TV
D13 D14
ALUMINIUM FRAMED WALL AS DETAILED
LINE OF CEILING BULKHEAD FEATURED CEILING
SCREEN PARTITION WITH
TEXTURED GLASS AND
SOUTH CORRIDOR 1 SHOWN DOTTED
SC
BULKHEAD ABOVE ACOUSTIC CUSTOM CUSTOM DESIGN
7

SC SOUTH CORRIDOR 2 IES


W0

JOINERY BENCH
JU.04A
VENEERED PLYWOOD
PANELS 40 H2-PS02
0.8 JU.04B
FA FA
SC
SC 40
JU.04E 0.8 H2-PS02
TIMBER SLIDING DOOR
PANEL AND TIMBER
JOINERY BENCHTOP
D16 H208 Client
WB SC LA DOOR AND WINDOW
LA LA
H228 SC SC SC SC FRAME
CA1
JU.03D

Monash University
JU.04D

SC TV
JU.03E

JU.03F
TUTORIAL 4 JU.01B
0.6

JU.03G
MR
30
JU.04C

C Architect
JU.03C

JU.03H
JU.03A

JU.03B

H227
H230
W08

CA3 FA FA FA FA SC Harmer Architecture


TTDP LA C FA FA H205 C
WB2 LA H228A C H229A LA H229B H230A C
H202 H203 H203A C
MR1 WB
C C

W2
C Title

7
4 DR
ST TTDP 4 Level 2 Acoustic Strategy Drawing
1

N
Drawing No. Drawing Status
5990 40 2960 40 5960 40 2960 40 5960 40 5960 40 2955 40 2963 40 5960 40 2960 40 8947 115

AS-3(00)0000 Schematic Design


9000 9000 9000 9000 9000 9000 9000 9000
Job No. Scale

A B C D E F G H I 1036431 Do not scale


FINISHES FIXTURES GENERAL NOTES JOINERY SCHEDULE
LEGEND ACOUSTIC WALL TYPE SCHEDULE Originator Checker Verified Issue

DA JL DA SD

Level 2, 330 Little Collins Street,


Melbourne
VIC 3000
Telephone: +61 (0)3 9635 3700

Website: www.cundall.com
© Copyright Cundall 2017

True scale at 1:1


Building H Level 2 - Acoustics design report

Appendix C ASHRAE Handbook Table 47

Document Ref. 1036431-AS-RPT-01


Building H Level 2 - Acoustics design report

Document Ref. 1036431-AS-RPT-01


Building H Level 2 - Acoustics design report

Appendix D VAV Sound power level data

Document Ref. 1036431-AS-RPT-01


Cundall Johnston & Partners PTY
Level 2 330 Little Collins Street Melbourne VIC 3000
Australia Tel:+61 (0)3 9635 3700
Asia Australia Europe MENA UK and Ireland
www.cundall.com

You might also like