REPUBLIC OF THE PHILIPPINES

NATIONAL IRRIGATION ADMINISTRATION


MAGAT RIVER INTEGRATED IRRIGATION SYSTEM (MARIIS)
DIVISION II
SAN MATEO, ISABELA

DAILY INSPECTORS REPORT

Contract No. : 2023-DII-RNIS, SAN ISIDRO 4/22/2023


Package No. : 03
Project Description: Construction of Concrete Lining along -E, Sta. 5+955-6+459(L=504m)
I. DAILY ACCOMPLISHMENT:
ACCOMPLISHMENT UNIT PRICE TOTAL AMMOUNT 5289338.23
ITEM OF WORK UNIT QUANTITY
Previous This Day To-Date Accomplishment
1. Mobilization & Demob. of Construction Equipment LS 1.00 0.50 124,513.20 62256.6 1.18% 42.3092954
2. Temporary Works/Facilities LS 1.00 0.50 82,906.32 41453.16 0.78% 0.42309295 5,685,209.82
3. Class B Concrete cu.m. 498.92 256.35 4,218.60 1081438 20.45% 11,395.03
4. Furnishing and Stockpiling of RSB kgs. 22,177.53 11,395.00 64.41 733952 13.88%
5. Cutting, Bending and Placing of RSB kgs. 22,177.53 11,395.00 21.92 249778.4 4.72%
6. Gravel Blanket cu.m. 73.90 785.12 0 0.00%
7. Structure Excavation cu.m. 11.09 600.47 0 0.00%
8. Structure Backfill cu.m. 8.87 721.48 0 0.00%
9. Canal Excavation cu.m. 260.05 35.95 458.71 16490.62 0.31%
10. ECF (S,W,F) cu.m. 234.04 32.36 264.62 8561.78 0.16%
11. ECF (Q,L,H,S,W,F) cu.m. 588.30 500.00 0 0.00%
12. Overhaul cu.m. 0.00 0 0.00%
13. Grading/Levelling sq.m 2,412.40 66.72 0 0.00%
14. Road Surfacing Materials cu.m 241.24 857.56 0 0.00%
15. Concrete Demolition cu.m. 0.00 - 0 0.00%
16. Construction Safety & Health Program LS 1.00 0.50 75,322.80 37661.4 0.71%
17. Project Billboards LS 1.00 0.50 12,579.42 6289.71 0.12%
2237882 42.31%
II. EQUIPMENT UTILIZATION
EQUIPMENT No. Status No. Status EQUIPMENT Status Status
1 Dozer 9 Transit Mixer
2 Payloader
3 Grader
4 Compactor
5 Water Truck
6 Dump Truck
7 Backhoe
8 One Bagger Concrete Mixer

III. MANPOWER UTILIZATION:


1 Project Manager 10 Concrete Mixer Operator LEGEND: - Equipment Status
2 Foreman 11 Carpenter OU
3 Dozer Operator 12 Mason OS
4 Grader Operator 13 Steelman UR
5 Payloader Operator 14 Bar Cutter
6 Water Truck Driver 15 Laborer
7 Backhoe Operator
8 Compactor Operator
9 Dump Truck Driver

IV. DELIVERIES MADE:


BAMBOO FOR TEMP FACILITIES
_________________________________________________________________________________________________________

V. REMARKS/COMMENTS:
__________________NO ACTIVITY_______________________________________________________________________________________
_________________________________________________________________________________________________________

WEATHER CHART 12 Mid

9 3
COLOR CODING:
Fair - - - - - - - - - - - - - Yellow 6
6
Rainy - - - - - - - - - - - - Blue
Stormy - - - - - - - - - - - Red
3 9

12 N
Prepared by: Conforme:

LENARD J. SANTIAGO GIL C. RUECO


PROJECT-IN-CHARGE UCORE CONSTRUCTION & DEVELOPMENT CORP.

CheckeChecked by: Approved:

MORRIS A. PASCUA RONNIE B. BESA


Engineering Unit, Head Acting Division Manager, A

San Mateo, Isabela, Philippines Telefax No.: (078) 323-0701 Website: www.mariis.nia.gov.ph • Facebook: www.facebook.com/niamariisd2 TIN: 000916415159 NIA-MARIIS-D2-OMS-ENU-INT-Form15 Rev.02