Industrial Training Programme BEEI

Training Session : 18/02/2019 to 02/08/2019

HARIHARAN A/L MATHANSUNDRAN


B071510052

BACHELOR OF ELECTRICAL ENGINEERING TECHNOLOGY


(INDUSTRIAL POWER) WITH
HONOURS
Introduction
To fulfill the requirement of University Technical Malaysia
Melaka, all engineering students have to undergo

Expose the students to the actual working environment

Objective To adapt readily to real-life working environment and practice


right work attitude

To apply knowledge learnt, gained new skills and be


aware of current technologies

To identify the industrial problems and able to suggest


possible solutions
Electricity
Network
In
Malaysia
TENAGA NASIONAL BERHAD ELECTRICITY SYSTEM
DISTRIBUTION DIVISION

Supply Frequency
Voltage
• The supply frequency is 50Hz  1%.
• 33kV, 11kV and 0.4kV/230 Volts

Power Factor
Act and Regulation
• minimum of 0.85 for voltage level
• Electricity Supply Act 1990 – Act 447 less than 132kV and
• 2 Licensee Supply Regulations 1990 • 0.90 for voltage level 132kV and
• 3 Electricity Regulations 1994 above
Organization Chart: TNB BATU GAJAH
Operational and Maintenance

HIGH VOLTAGE LOW VOLTAGE


DEPARTMENT DEPARTMENT

11kV Team Low Voltage


Team
Meter and
Cable Team Service Team

Substation
Team Fault Finder
HIGH VOLTAGE DEPARTMENT
11kv and Cable O&M
• Change Drop Out Fuse.

• Change Disc/Pin Insulator.

• Shutdown Maintenance.

• Taking Poles Data for


upgrading system.

• Change Suspension Clamp.


Install Joint Straight Thru ABC
type cables.
• PD Mapping.
• Check underground cables
flashover
• Investigation on Request Job
Order works
• Send Preventative
SUBSTATION TEAM
Maintenance notice to
effected area.

• Install EFI (Earth Fault


Indicator) inside Substation.

• IR Test on cables.

• Oil Insulation Test.

• Grounding Test.

• Install photovoltaic lamp.

• Panting and Sign Board


upgrading.

• Install Heater inside RMU


(Ring Main Unit).

• Install/Change Battery Acid.


LOW VOLTAGE DEPARTMENT
LOW VOLTAGE TEAM

• Send PM notice to effected


area.
• Install new street light or only
fix new street light cable into
main pole.
• Patrol thru low voltage lines
follow by date and place /
Clean Creeps.
• Change bare wire to ABC wire
from pole to residence.
• Change Suspension Clamp.
• Change Dead End Clamp.
• Upgrading LV lines during
preventative maintenance.
• Install stay wire to some
unstable pole area.
• RJO (Request Job Order) by
customer.
LOW VOLTAGE TEAM
ABC Cables & Capacity current carry

Nominal Cross- 16 16 25 35 50 70 95 120 150 185


Sectional Area mm²
Number of Cores 1 3 3 3 3 3 3 3 3 3
Current Rating Carry (A) 61 61 84 104 129 167 209 246 283 332
Street Light
Components in Street Light
• Cable Size – 1x16mm
• Ignitor - to make low voltage
• Capacitor – charge/discharge
• Choke – kick voltage
• Bulb – output/load
METER & SERVICE TEAM FAULT FINDER TEAM
• 24/7 fault finder
• Device inspection • Receive and complete report from
• Project new connection system (TOMS)
• Normal new connection • Change IPC regarding cable size
• Device accuracy test • Change cut-out (Fuse blow out)
• Device replacement • Change black box fuse
order • Inspection on overloading
• LPC reading • Inspection on neutral link
• On/off load on meter
• Normal move out
CONCLUSION

Industrial training experience that received in TNB is very knowledgeable

Technical with Hands On work well educated and experienced


Thank You
FOR LISTENING