Professional Documents
Culture Documents
CIB9973
CIB9973
Dependency Framework
Andrew Fleming 1
Martin Sexton, Ph.D. 2
Ming Sun, Ph.D. 3
Sepani Seneratne 4
Ghassan Aouad, Ph.D. 5
Abstract
1
Andrew Fleming is a Research Fellow in the School of Construction and Property
Management, University of Salford, UK.
2
Martin Sexton is a Senior Lecturer in the School of Construction and Property Management,
University of Salford, UK.
3
Ming Sun is a Professor in Construction and Property Informatics in the
Faculty of the Built Environment, University of the West of England, UK.
4
Sepani Seneratne is a Reseacher in the School of Construction and Property Management.,
University of Salford, UK.
5
Ghassan Aouad is a Professor in Construction IT and Head of School of Construction and
Property Management, University of Salford, UK.
INTRODUCTION
The UK construction industry was the focus of an in depth study carried out by a UK
Government task force in 1998. Headed by Sir John Egan the task force produced the
document “Rethinking Construction.” The report found that one third of major construction
client’s were currently dissatisfied with how their construction products were being delivered
to them by the industry. They were unhappy with contractor performance in three key areas;
cost, quality and time. Consultants also drew criticism in the areas of team co-ordination,
design and innovation, timeliness, reliability and value for money. Couple these factors with
the statistic that fifty percent of construction projects suffer from delay and over expenditure
and that over thirty percent of completed projects have quality defects and the client’s have a
reasonable expectation that the industry will take measures to improve.
External / Global
Inter-organisational
Project
EXTERNAL CAUSES
External causes originate from outside the realm of the organisations that are
undertaking the project and the project entity itself. This type of cause cannot be controlled
from within the project domain. External conditions should be monitored to enable these
causes to be prepared for and managed effectively. The Construction Industry is subjected to
change from events that occur on a global level. Al-Sedairy (2001) remarks that increased
global competition, technological innovation and a growing scarcity of resources all exert
great pressures. Atkinson (2002), states that during the course of one week a quarter of the
errors on a construction site were attributable to economic, time and societal pressures.
Inter-organisational Causes
Project causes originate from within the boundaries of the project organisation. When
change originates from within the “project organisation” it is referred to as “change caused by
project factors”. Al-Sedairy (2001) refers to issues emanating from within the project
organisation as being internal. According to Stephenson et al (2002) there are several internal
factors that are likely to cause failure; these include design error, workmanship error, faulty
materials, and procedural error. Therefore The Framework suggests three areas for
consideration when examining change caused by the project, people issues, design process
change issues and construction process change issues.
By considering aspects of project team management it may be possible to reduce the
number of project errors, increase accuracy and therefore reduce the amount of change that
originates from the project level. The Framework suggests that examining items such as
communication (Atkinson 2002), skills (Tombesi 2000, Williams 1988, Kaming et al 1997),
team composition, leadership, uncertainty, role ambiguity (Webster 1999), document
misinterpretation and human error (Kim 1989) could achieve this.
Design process change issues are those changes that occur as a natural result of the
project’s design process. Improved management can be achieved by considering the
common causes of design change. Wantanakon et al (1995) states that design changes are
frequently caused by modifications in design, specifications, details, omissions and alterations
in the method of construction in order to avoid interference among various tasks and
amendments made by the client.
Construction process change issues are those changes that occur as a natural result
of the project’s construction process. This refers to changes to construction that originate from
causes during the construction phase. These changes can be caused by adopting new
construction techniques / methods, damage, poor workmanship and site conditions.
The change events that occur on a project can cause substantial adjustment to the
contract duration time, total direct and indirect cost (Tiong 1990; Ibbs 1997; Ibbs et al. 1998).
Therefore it is important to consider the project and its characteristics to determine whether
the project is itself acting as an incubator for change to occur. It may be possible to re-
configure the project to reduce non-beneficial changes. For example, if a change originates
because of an error in the design documentation and the project in question has an extensive
design team and a complex design then the change may be exacerbated if the project has
non-effective communication protocols.
According to the Construction Industry Institute the project characteristics are the
elements that comprise the form of a project for example, complexity, scope, delivery and the
project controls (Ibbs 1994). The Framework also views organisational and project team
issues as contributing towards the project characteristics. The characteristics considered by
the framework are project scope, team, delivery and execution and the project controls, see
Figure 2.
Change Characteristics
There are tools / strategies available to construction projects that will help them
manage change. When these are applied, the project will assume certain change
characteristics. Construction projects vary in terms of client, contractor, location, team, budget
and schedule. Therefore different projects will have different drivers and therefore require
different tools / strategies. For example a retail client may require the contractor to be able to
incorporate design changes at very late notice. Therefore it is important to understand the
context in which the project takes place when designing the change characteristics. The
framework considers several approaches that can affect the change characteristics of a
project.
Changes can be proactively anticipated and built in to the programme, or they can be
reactively considered as and when they arise (Ibbs et al, 2001).
Change may be implemented gradually or radically. Gradual implementation over a
period of time may be chosen to minimise disruption, align with budgets or simply because
the change cannot be implemented immediately. A radical implementation will change
fundamental aspects of the project, often unexpectedly, for example, upon arrival of an
unscheduled component changes may need to be made to save the schedule from disruption.
The evaluation of change as either essential (involuntary change) or non essential
(voluntary change) to a project’s success. By prioritising changes it will be possible to allocate
resources to the most essential changes (Ibbs 1994).
The change event consequence is concerned with the change event after it has been
caused. The New Shorter Oxford Dictionary, states that consequence “is the relation of an
effect to its cause” therefore, if the consequence of a change event is understood it will allow
the project to be planned and the change to be successfully integrated with the minimum of
disruption. This will enable key decisions to be made, for example whether to abort the
change because the consequences are too disruptive. Considering the consequence of a
change in this way will be a departure from the common industry practice of quantifying the
amalgamated changes at the end of a project (Akinsola, 1997). The Framework identifies
direct and indirect consequences.
Direct Consequences
Direct consequences are directly attributable to a change event and will have an
identifiable and clearly defined effect on the project. They will often have quantifiable metrics.
Failure to meet quality standards and alterations to the project budget or schedule may be
viewed as direct consequences. The Framework also considers work additions, deletions and
revisions to the project (Ibbs, 2001).
Indirect Consequences
The project team may or may not be aware of all the changes that occur during a project’s
lifecycle. By actively looking for signs of indirect or direct consequences, it is possible that
smaller change events will be identified. These may have been dealt with at an operational
level and therefore not documented. There will also be changes that have been documented.
The framework will allow both of these change events to be audited.
CHANGE REVIEW
The physical aspects of the project that could have been subject to a change
including, labour, materials, plant and environment.
The control systems that control how the project is managed and progresses, for
example the project management strategy employed on the project.
The procedures and processes employed on the project. Where new processes are
implemented or new models adopted, this represents a change to the way the project
is performed.
The content of The Framework consists of the elements previously described; the
causes, the consequences, the project/change characteristics and the change review. These
elements are illustrated on templates that have been designed on Visio and show four levels
of decomposition.
A key requirement for representing The Framework is that no special or technical
skills should be required for interpreting and using The Framework. The key was in the
representation (Cheung, 1998) of the process and it was felt that none of the tools available
met the project’s requirements. Therefore it was necessary to develop an original process
map template. A map was created that represented all of the information that the project
required.
CONCLUSION
External
Indirect
Consequence
Inter-
organisational Consequence
Cause
Direct
Project Consequence
Ibbs, C. W., et al (1994) “Project Change Management”. CII Special Publication 43-1, The
University of Texas at Austin.
Ibbs, C. W. (1997) ‘‘Quantitative impacts of project change: size issues”. Journal Construction
Engineering and Management, ASCE, 123(3), pp 308–311.
Ibbs, C. W., Lee, S. and Li, M. (1998) ‘‘Fast-tracking’s impact on project change”. Project
Management Journal, 29(4), pp35–41.
Ibbs, C. W., Wong, C. K. and Kwak, Y. H. (2001) “Project Change Management System”.
Journal of Management In Engineering, 159
Kim, K. (1989) “Human reliability model with probabilistic learning in continuous time domain”.
Microelectronics and Reliability, 29(5), pp 801–811.
Stocks, S. and Singh, A. (1999) “Studies on the impact of functional analysis concept design
on reduction in change orders”, Construction Management and Economics, Vol. 17, pp. 251-
267.
Tiong, R. (1990) ‘‘Effective controls for large scale construction projects”. Project
Management Journal, 11(1), pp 32-42
Tombesi, P. (2000) “Modelling the dynamics of design error induced rework in construction:
comment”. Construction Management and Economics, Vol. 18, pp 727-732.
Webster, G. (1999) “Project definition – the missing link”. Industrial and Commercial Training,
Vol. 31(6), pp 240-244.
Williams, J.C. (1988) “A human factors data-base to influence safety and reliability. Human
factors and decision making: their influence on safety and reliability”. Symposium for the
Safety and Reliability Society, pp. 223–240.