Professional Documents
Culture Documents
007 Sri Iee 02
007 Sri Iee 02
007 Sri Iee 02
July 2013
Prepared by the National Water Supply and Drainage Board Government of Sri Lanka for the
Asian Development Bank.
CURRENCY EQUIVALENTS
(as of 11 July 2013)
Currency Unit – Sri Lanka rupees (SLRs)
SLRs1.00 = $0.007645
$1.00 = SLRs. 130.80
ABBREVIATIONS
km – kilometer
km2 – square kilometer
m2 – square meter
mm – millimeter
m3/day – cubic meter per day
NOTE{S}
This initial environmental examination is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB's Board of Directors, Management, or staff,
and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, ADB
does not intend to make any judgments as to the legal or other status of any territory or area
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY
I. INTRODUCTION 1
II. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK 3
A. ADB Policy 3
B. National Laws 4
III. DESCRIPTION OF THE PROJECT 7
A. Existing Condition and Need for the Project 7
B. Proposed Project Components 7
C. Implementation Schedule 9
IV. DESCRIPTION OF THE ENVIRONMENT 9
A. Methodology Used for the Baseline Study 9
B. Physical Characteristics 10
C. Ecological Characteristics 13
D. Socioeconomic Profile 14
E. Social and Cultural Characteristics 17
V. ANTICIPATED IMPACTS AND MITIGATION MEASURES 18
A. Anticipated Impacts – Planning and Design Phase 18
B. Anticipated Impacts – Construction Phase 22
C. Anticipated Impacts – Operations and Maintenance Phase 24
D. Mitigation Measures 25
E. Cumulative Impact Assessment 31
VI. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 32
A. Public Consultation Conducted 32
B. Future Consultation and Disclosure 33
VII. GRIEVANCE REDRESS MECHANISM 34
VIII. ENVIRONMENTAL MANAGEMENT PLAN 36
A. Institutional Arrangement 37
B. Capacity Building 41
C. Environmental Management Action Plan 42
D. Reporting 60
E. Environmental Costs 60
IX. CONCLUSION AND RECOMMENDATION 63
APPENDIXES:
1. ADB REA Checklist 65
2. Details of Ambatale Project Investments 68
3. Records of Public Consultations 69
4. Sample Grievance Redress Form 79
5. Outline TOR for Environment Management Specialist (MASC) 80
6. Suggested Outline for the Environmental Monitoring Report 81
7. Summary of Procedure for Obtaining Written Permission from Department of 83
Archaeology
EXECUTIVE SUMMARY
2. The investment program uses a multitranche financing facility (MFF) and will be
implemented from 2013 to 2020. Investments under the MFF will be delivered in four projects.
As per ADB’s safeguard requirements, an environmental assessment and review framework
(EARF) is prepared to guide environmental assessment throughout the entire MFF period.
3. Ambatale water supply system improvements and energy saving project is one of the
projects proposed in GCWWMIIP. Energy audits carried out in 2006 and 2008 had shown that
efficiency of the pumps in Ambatale water treatment plant has fallen below acceptable levels. It
is found in these studies that the energy cost can be effectively saved by introducing efficiency
enhancement measures. ADB requires the consideration of environmental issues in all aspects
of the Bank’s operations, and the requirements for environmental assessment are described in
ADB’s Safeguard Policy Statement (SPS, 2009). This Initial Environmental Examination (IEE)
addresses components proposed under GCWWMIIP which includes water supply and
sewerage components.
5. Project Scope. The project is formulated under GCWWMIIP to address gaps in water
supply infrastructure in a holistic and integrated manner. The main objective of GCWWMIIP is to
improve water and wastewater service and management efficiency, security and have an
important effect on public health in Greater Colombo. Investments under this project includes: (i)
improving energy efficiency and service efficiency at Ambatale water treatment plant; (ii)
Improving level of water supply service to Colombo City until the year 2040; and (iii) building
capacity on operation and maintenance of treatment plant and in energy saving.
wetlands, mangroves, or estuaries in or near the project location. There are no forest areas
within or near Ambatale. Soils are deep, and do not require cutting of rocks for pipe laying.
9. Locations and siting of the proposed infrastructures were considered to further reduce
impacts. These include (i) locating facilities on government-owned land to avoid the need for
land acquisition and relocation of people; and (ii) laying of pipes in RoWs alongside
main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in
densely populated areas of the city.
10. Potential impacts were identified in relation to location, design, construction and
operation of the improved infrastructure. Planning principles and design considerations have
been reviewed and incorporated into the site planning process whenever possible. Various
design-related measures suggested for the water treatment plant are: energy efficiency design,
automation and Improvement to existing telemetry system, and sludge treatment and disposal
system.
11. During the construction phase, impacts mainly arise from the need to dispose of
moderate quantities of waste soil and disturbance of residents, businesses, and traffic.
Mitigation measures have been developed in generic way to reduce all negative impacts to
acceptable levels. These are common impacts of construction in urban areas, and there are well
developed methods for their mitigation. Measures such as conducting work in lean season and
minimizing inconvenience by best construction methods will be employed. Traffic management
will be necessary during pipe-laying on busy roads. Temporary social impacts due to
construction activities are not avoidable, as residential and commercial establishments exist
along the project corridor. A resettlement plan has been developed in accordance with ADB
SPS, 2009 and Sri Lankan laws and regulations.
12. In the operational phase, all facilities and infrastructure will operate with routine
maintenance, which should not affect the environment. Facilities will need to be repaired from
time to time, but environmental impacts will be much less than those of the construction period
as the work will be infrequent, affecting small areas only.
13. Mitigation measures have been developed to reduce all negative impacts to acceptable
levels. Mitigation will be assured by a program of environmental monitoring to be conducted
during construction. The environmental monitoring program will ensure that all measures are
implemented, and will determine whether the environment is protected as intended. It will
include observations on- and off-site, document checks, and interviews with workers and
beneficiaries. Any requirements for corrective action will be reported to the ADB.
14. The stakeholders were involved in developing the IEE through discussions on-site and
public consultation, after which views expressed were incorporated into the IEE and in the
planning and development of the subproject. The IEE will be made available at public locations
in the city and will be disclosed to a wider audience via the ADB and NWSDB websites. The
iii
consultation process will be continued and expanded during project implementation to ensure
that stakeholders are fully engaged in the project and have the opportunity to participate in its
development and implementation.
15. The citizens of the Greater Colombo will be the major beneficiaries of this subproject.
With the improved water supply, they will be provided with a constant supply of better quality
water, piped into their homes. In addition to improved environmental conditions, the project will
improve the over-all health condition of the town.
16. The most noticeable net environmental benefits to the population of the towns will be
positive and large as a result of improved: (i) water efficiency and security through the
implementation of NRW reduction programs and expansion and rehabilitation water supply
infrastructure respectively; and (ii) river water quality through the expansion of sewerage
networks, treatment capacity and sanitation coverage.
17. Consultation, Disclosure and Grievance Redress. Public consultations were done in
the preparation of the project and IEE. Ongoing consultations will occur throughout the project
implementation period with the assistance of the NGOs. A grievance redress mechanism is
described within the IEE to ensure any public grievances are addressed quickly.
18. Monitoring and Reporting. The PMU, PIUs, and management and supervision
consultants (MASC) will be responsible for monitoring. The MASC will submit monthly
monitoring reports to PMU, and the PMU will send semi-annual monitoring reports to ADB. ADB
will post the environmental monitoring reports on its website.
2. The impact of GCWWMIIP will be improved urban environment and quality of life for the
residents of Greater Colombo. The expected outcome will be improved water and wastewater
service and management efficiency in Greater Colombo. The expected outputs are:
(i) Rehabilitated water supply network and reduced non-revenue water (NRW)
in Colombo City: (a) network rehabilitation and replacement in critical areas 2 of
Central Colombo; (b) network rehabilitation and replacement outside critical
areas of Central Colombo; and (c) NRW reduction mechanism in Colombo City.
(ii) Improved wastewater services in Greater Colombo: (a) rehabilitation of 30 km
of critical sewers, and expansion of collection sewers to unsewered areas (45
km) and unserved areas (400 km); (b) provision of sewer connections; and (c)
construction of two wastewater treatment plants 3, with total capacity of about
174,000 m3/day, to secondary treatment standard.
(iii) Institutionally strengthened, reformed, and more capable service providers:
For NWSDB: (a) establishment of an operations performance audit cell 4 in
NWSDB; (b) decentralization of all Colombo City operations to the Regional
Support Center Western Central (RSC WC) 5, including delegation of greater
administrative and financial authority to the deputy general manager, RSC WC;
(c) preparation of an asset management register for RSC WC; (d) provision of
management advisory services to coordinate and manage all NRW reduction
activities in Colombo City, including productivity-linked payments for physical
water loss reduction; (e) implementation of an effective public awareness
campaigns, and participation of women and nongovernment organizations
(NGOs); and (f) enhancement of financial sustainability through increasing water
tariffs to affordable levels, in line with the regional tariff study 6, and progressively
increasing the introductory tariff of SLRs. 3/m3 tariff 7 levied on tenement gardens
to the same level as the residential tariff. For CMC: (a) preparation of an
inventory of wastewater assets; (b) establishment of an accounting system as a
separate cost center, and preparation of financial projections for the wastewater
1
Government of Sri Lanka. 2010. Mahinda Chintana: Vision for a New Sri Lanka. 2010-2020.
2
The critical areas in Central Colombo are Kotahena, Mattakkuliya, Grandpass, and Modera. The Japan
International Cooperation Agency (JICA) is currently implementing network rehabilitation in the adjacent area.
3 3 3
Two treatment plants at Mutwal/Madampitiya, 120,000 m /day, and Welawatta, 54,000 m /day
4
The cell will monitor corporate performance indicators and audit NRW reductions in all RSCs.
5
Includes transfer of meter reading and billing of all customers, including priority customers, O&M, and NRW
reduction in Colombo City, and planning, GIS map validation, and network model calibration.
6
ADB R-CDTA 45373. Promotion Financially Sustainable Regulatory Framework for Water Tariff in South Asia
7
The tariff will be increased to the same level as the residential tariff by 2018.
2
3. The executing agencies are the Ministry of Water Supply and Drainage (MWSD) and the
Ministry of Local Government and Provincial Council (MLGPC). The implementing agencies are
the National Water Supply and Drainage Board (NWSDB) for water supply components and the
Colombo Municipal Council for wastewater components. The investment program uses a
multitranche financing facility (MFF) and will be implemented from 2013 to 2020. Investments
under the MFF will be delivered in four projects. Project 2 will be implemented in 2013 and will
continue to focus on reducing NRW and improving water service efficiency in Colombo City.
Projects 3 and 4 will be implemented in 2015 and 2016 respectively, and both will include
improvements in wastewater services and expand the service coverage to other areas of
Greater Colombo. 8
4. ADB requires consideration of environmental issues in all aspects of its operations, and
the requirements for environmental assessment are described in ADB’s Safeguard Policy
Statement (SPS), 2009. According to the SPS, environmental assessment is required for all
projects under a MFF modality. An environmental assessment and review framework (EARF) is
prepared to guide environmental assessment throughout the entire MFF period.
5. This initial environmental examination (IEE) is prepared for Ambatale water supply
system improvements and energy saving project (Ambatale project) which includes civil works,
capacity building activities, and project management and implementation. A detailed description
of the investments is provided in Section III. Under this project, the proposed project is expected
to have the following benefits: (i) rehabilitation of distribution network, which will result in
substantial reduction in water losses in the project area from the current 49% losses to 20%
losses; and (ii) proper accounting for use of water and system losses by installation of metered
connections.
6. The environmental impacts of the investments under Ambatale project have been
identified and assessed as part of the planning and design process, and actions will be taken to
reduce those impacts to acceptable levels. An environmental assessment using ADB’s Rapid
Environmental Assessment (REA) Checklist for Water Supply (Appendix 1) was conducted, and
results of the assessment show that the project is unlikely to cause significant adverse impacts.
Thus, this IEE has been prepared in accordance with ADB SPS’s requirements for environment
category B projects and to meet the following objectives:
8
Greater Colombo comprises 7 local authorities: 3 municipal councils (Colombo, Dehiwala-Mount Lavinia, and Sri
Jayawardenepura-Kotte), 2 urban councils, and 2 Pradeshiya Sabhas (smallest political unit in peri-urban or rural
areas).
3
A. ADB P o lic y
10. Public disclosure. ADB will post the following safeguard documents on its website so
affected people, other stakeholders, and the general public can provide meaningful inputs into
the project design and implementation:
(i) for environmental category A projects, draft EIA report at least 120 days before
Board consideration;
(ii) final or updated EIA and/or IEE upon receipt; and
(iii) environmental monitoring reports submitted by the project management unit (PMU)
during project implementation upon receipt.
B. Na tio n a l Laws
11. The implementation of the projects will be governed by Government of Sri Lanka
environmental acts, rules, regulations, and standards. These regulations impose restrictions on
the activities to minimize/mitigate likely impacts on the environment. It is the responsibility of the
project executing and implementing agencies to ensure projects are consistent with the legal
framework, whether national, state, or municipal/local. Compliance is required in all stages of
the project, including design, construction, and operation and maintenance. The summary of
environmental regulations and mandatory requirements for the proposed project is shown in
Table 1.
9
Sensitive areas are defined in the EIA Regulations as: (i) any erodable area declared under the Soil Conservation
Act (Chapter 540); (ii) any flood area declared under the Flood Protection Ordinance (1924, 1955); (iii) any flood
protection area declared under the Land Reclamation and Development Corporation Act (1968, 1982); (iv) 60 m
from the bank of a public stream as defined in the Crown Land Ordinance (Chapter 454) and having a width of
more than 25 m at any point in its course; (v) any reservation beyond the full supply level of a reservoir; (vi) any
archaeological reserve, ancient or protected monument as defined or declared under the Antiquities Ordinance
(1965); (vii) any area declared under the Botanic Gardens Ordinance (1928, 1973); (viii) areas within or less than
100 m from the boundaries of any area declared under the Forest Ordinance and National Heritage and
Wilderness Act (1988); (ix) areas within or less than 100 m from the boundaries of any area declared as a
sanctuary under the Fauna and Flora Protection Ordinance (1937); (x) areas within or less than 100 m from the
high flood level contour of a public lake, as defined by the Crown Lands Ordinance (1947, 1949, 1956), including
those declared under Section 71 of the ordinance.
5
10
In consideration of the tsunami event of December 2004, the government declared that “A 100-m buffer zone from
the permanent vegetation line of the beach front should be delineated for any new construction in the west and
south coast from Kala Oya river mouth (Gange Wadiya) to Kinindi Oya river mouth, and a 200-m buffer zone from
the permanent vegetation line of the beach front should be delineated for any new construction in the east and the
north coast from Kinindi Oya river mouth to Kala Oya (Gange Wadiya).” All permits for the development activities
within the buffer zone will be issued by the director, Coast Conservation.
11
Lunupokuna, Modara, Aluth Mawatha, and Mattakkuliya Grama Niladhari (GN) Divisions are areas (i) lying within
the limit of 300 m landwards of the mean high water line and a limit of 2 km seawards of the mean low water line;
and (ii) landward boundary shall extend to a limit of 2 km measured perpendicular to the straight baseline drawn
between the natural entrance point thereof, and shall include waters of such rivers, streams, and lagoons or any
other body of water connected to the sea. There are no environmentally sensitive features in these areas.
6
12
A summary of procedure to obtain the written permission is summarized in Appendix 7.
7
12. Colombo, the capital city and economic and administrative hub of the country, was one
of the few cities in Asia that was fortunate to get piped water supply in the 1800s. Many parts of
the distribution network were built in Colombo as early as 100 years ago. 13 Though there have
been various projects to address the increasing water demand and 95% coverage has been
reached in the city with piped water supply, significant rehabilitation of the network has not been
carried out, causing the NRW to reach extremely high levels of around 49%. 14
13. NWSDB supplied piped water to 127,000 service connections in Greater Colombo as of
December 2011. The water tariff is currently below the total cost recovery level. The system
suffers from flunctuating pressures, with some low-pressure areas receiving water only at off-
peak hours. There are around 4,036 unmetered standpipes in the city that supply free water to
low income settlements called “tenement gardens.” In order to control the amount of free water
supplied through standpipes and increase revenues from them, NWSDB launched various
programs which need to be implemented on a larger scale. 15
14. NWSDB carried out limited network rehabilitation and leak repairs under its routine O&M
activities, without much impact on NRW reduction. More recently, a focused program of pipe
replacement and metering was implemented in a small part north of Colombo City.
15. The Ambatale water treatment plant is situated 11 km from the Colombo city. Ambatale
is the major water source producing 518,000 m3 of water per day with capacity of 549,000 m3
per day. The water treatment plant has three water intakes (commissioned in 1966, 1986 and
2010 respectively) and two storages reservoirs. There are 42 low and high lift pumps at the
plants. Out of these, 25 pumps are increasingly inefficient, thus operation and maintenance
costs are prohibitively high. Energy audits carried out in 2006 and 2008 had shown that
efficiency of the pumps have fallen below acceptable levels. It is found in those studies that the
energy cost can be effectively saved by introducing efficiency enhancement measures.
16. Improvement to Ambatale water treatment plant has been identified as a priority in the
Colombo NRW reduction programme by the ongoing JICA-funded Master Plan Update.
Ambatale will become the primary water source for Colombo City thus has become a priority
project owing to its importance in providing reliable water supply to Colombo City till the design
year of 2040.
B. P ro p o s e d P ro je c t Com p o n e n ts
17. The Ambatale project investments aim to deliver better urban water supply services in
an effective and efficient manner by reducing NRW in Colombo City and improving the
efficiency of the water treatment plant. The project will involve both physical network
rehabilitation, and institutional and management enhancement to reduce the NRW. The major
objectives of the project are: (i) to increase water supply availability and efficiency in Colombo;
13
About 700 km out of total 927 km of water supply distribution network in Colombo City are more than 50 years old.
14
The 49% NRW for Colombo, which is twice the average NRW for the rest of the country, comprises 33% physical
losses, 5% commercial losses, and 11% free water supplied to low-income settlements.
15
NWSDB managed to form about 170 consumer societies, out of some 400 standpipes in Colombo City, on a
3
community participation basis, and charges the minimum tariff of Rs 3 per m .
8
(ii) to enhance the distribution system and reduce NRW; (iii) to establish a mechanism to reduce
NRW; and (iv) to enhance the institutional, operational, and project management capacity of
NWSDB. The proposed project is expected to have the following benefits: (i) rehabilitation of
distribution network that will result in substantial reduction in water losses in the project area,
from the current 49% losses to 20% losses; and (ii) proper accounting for use of water and
system losses by installation of metered connections.
18. There are two water pipelines laid in to the city starting from Ambatale water treatment
plant and Gotatuwa. The improvements from Ambatale water treatment plant up to Colombo city
border are to be implemented under this project and the sections within the city will be
implemented under the GCWWMIIP Project 1.
(i) Output 1: Improved energy efficiency and service efficiency at Ambatale water
treatment plant;
(ii) Output 2: Improved level of water supply service to Colombo City until the year
2040; and
(iii) Output 3: Capacity building on operation and maintenance of treatment plant and
in energy saving.
20. The Ambatale project will involve the following types of physical works:
21. The project is to be implemented over a period of 4 years including procurement period.
The detailed design stage is expected to commence in 2014, and the construction period will
cover 36 months.
22. Data collection and stakeholder consultations. Data for this study has been primarily
collected through comprehensive literature survey, discussion with stakeholder agencies, and
field visits to the proposed subproject sites.
(i) project details, reports, maps, and other documents available with the ADB
Project Preparatory Technical Assistance (PPTA) consultants, NWSDB, Urban
Development Authority, and Colombo Municipal Council (CMC);
(ii) National Environment Act, Extra Ordinary Gazettes, its relevant guidelines and
standards;
(iii) other relevant acts, extraordinary gazettes, and guidelines issued by other
Government of Sri Lanka agencies; and
(iv) literature on land use, soil, geology, hydrology, climate, socioeconomic profiles,
and environmental planning documents collected from Government of Sri Lanka
agencies and websites.
24. Several visits to the project sites were made in December 2012 and February 2013 to
assess the existing environment (physical, biological, and socioeconomic) and gather
10
information with regard to the proposed sites and scale of the proposed project. A separate
socioeconomic study was conducted to determine the demographic information, archeological
and religious places, densely populated pockets, and settlements.
25. Data analysis and interpretation. The data collected was analyzed and interpretations
made to assess the physical, biological, and socioeconomic features of the project area. The
relevant information is presented in the succeeding paragraphs.
B. P h ys ic a l Ch a ra c teris tics
26. Location. The geographical location of Colombo is 6º 55’ N latitude and 79º 52’ E
longitude. The project area is located within CMC area (extent of 4,021.14 ha).
27. Geology and geomorphology. The project area falls in the pre-Cambrian South
Western group (600 million years old) lowest peneplain of Sri Lanka. This coastal peneplain
rises to a maximum elevation of less than 500 ft from the sea coast. The underlying geological
formations of the present coastal plain consist of gneisses and granites, predominantly of the
Vijayan complex of the pre-Cambrian era. As a consequence of the sea level rising during the
Holocene period, this old basement is covered by more recent coastal deposits.
28. The major rock types in Colombo consist of meta-sediments (quartzites and quartz
schist, garnet sillimanite, gneisses, quartz feldspar, and granulites), charnockite gneisses and
allied rocks, basic rocks, migmatitic and granitic gneisses, granite, and pegmatite. Overlying the
pPre-Ccambrian basement are alluvial and littoral sedimentary deposits of Quaternary age,
within the project area. The fluvial deposits here include a thick alluvium (20–30 m) in some
areas of marshes, and water bodies. These alluvial deposits include lean/plastic clays, organic
clays/peat, and sand with clay.
29. Soil. According to the Sri Lankan Survey Department soil maps, the main soil types in
the project area are as follows: (i) red yellow podzolic soils with soft or hard laterite: undulating
and rolling terrain; (ii) bog and half-bog soils: flat terrain; (iii) alluvial soils of variable texture and
drainage: flat terrain; and (iv) regosols on recent beach and sand sands: flat terrain.
30. Topography. Greater Colombo’s topography is a mix of flat and marshy land. The east
and southeast areas are bordered by marshy land. The city has many canals, and Beira Lake is
in the heart of the city. On the north and the northeast borders of the city flows the Kelani River.
The river meets the sea in part of the city known as the “Modera” in Sinhala, which literally
means “delta.” The project area is more or less flat to gradual undulating.
31. Hydrology and drainage. The Colombo drainage system consists of a network of
canals and marshes functioning as retention basins. The Colombo canal drainage network has
6 outlets, 3 discharging to the sea (Wellawatta, Dehiwala, and Mutwal tunnel), 1 closed at
present (Beira Lake), and the other 2 draining into the Kelani River. The Mutwal tunnel,
Wellawatta canal, and Dehiwala canal have discharge capacities of 5, 60, and 30 m3/s,
respectively. A fourth outfall, St. Sebastian South Canal and Beira Lock, has no drain function
under normal circumstances due to the high crest level of Beira Lake (+1.8 m mean sea level or
11
msl). 16 There are four marshy lands identified as “flood retention areas” in Colombo, namely (i)
Bloemendhal Marsh, (ii) Kolonnawa Marsh, (iii) Heen Marshes, and (iv) low-lying lands known
as the Green Belt surrounding the Parliament Lake.
32. Climate. The climate is classified as tropical monsoon, having a wet season and a short
dry season. The project area is located in the southwestern quarter of the island, which is
classified as a wet zone. The climate is characterized by the northeast monsoon from
December to February, and the southwest monsoon from May to September. Heavy rainstorms
occur mainly in the southwest monsoon period from May to September and occasionally in the
two intermonsoon periods (March-April and October-November), as well. The average annual
rainfall is around 2,000–3,000 mm. There are two peaks of monthly rainfall in a year, May and
October. The mean daily maximum temperature ranges from 31.1 oC in April to 29.3 oC in
August, while the mean daily minimum temperature ranges from 25.3 oC in May to 22.2 oC in
January.
33. Water quality. Surface water pollution is the most serious issue among the
environmental problems in the project area. Pollution of urban water bodies by domestic
wastewater and industrial wastewater causes environmental problems as well as health
hazards. The main causes of surface water pollution are: (i) discharge of urban drainage water
mixed with waste of industrial and domestic origin into natural streams; (ii) runoff from open
markets and garbage dumps; (iii) unauthorized connections of domestic wastewater pipes into
drainage canals; (iv) direct discharge of industrial wastewater into rivers, lakes, canals, and
lowlands; (v) uncontrolled and illegal dumping of waste of industrial and domestic origin in
waterways, embankments, and lowlands; (vi) discharge of sewage into canal/surface water
bodies mainly by shanty settlements along canals and around the lowlands such as marshes;
and (vii) insufficient maintenance and cleaning of watercourses and embankments resulting in
siltation, blockage, and aquatic plant growth. Table 4 shows the results of surface water
monitoring in the project area conducted by the Central Environment Authority (CEA).
Temperature
Phosphate
Ammonia
Turbidity
Salinity
Nitrate
COD
BOD
Station
DO
pH
Description
No.
16
Beira Lake is artificially kept at +1.8 m mean sea level (msl) by means of pumps installed at Beira Lock. This is
mainly done to prevent buildings constructed on wooden piles along the lake from collapsing. As a consequence,
Beira Lake’s flood discharge function is only operational at water levels exceeding +1.8 m msl.
12
Conductivity
Temperature
Phosphate
Ammonia
Turbidity
Salinity
Nitrate
COD
BOD
Station
DO
pH
Description
No.
34. The Beira Lake plays an important role in conveying surface drainage and flood waters
in CMC. The lake is a stagnant water body which covers approximately 65.4 ha and has an
average depth of 2 m at maximum elevation. It comprises of four main basins: East Lake, Galle
Face Lake, West Lake, and South West Lake. Beira Lake’s flood discharge function is only
operational at water levels exceeding +1.8 m msl.19 Although the local people do not derive
other benefits than diverting their surface drainage into these canals, the intrinsic function is vital
and most important in draining the flood waters of the area. There are numerous illegal
13
discharge points of gray water from residences, commercial establishments, and warehouses
adjoining the lake, and due to the high level of water pollution, no other local uses can be
derived from the water body. At present, most of the lake bank is covered with commercial
establishments, human settlements, institutions, religious places, etc. Therefore, it is hard to see
vegetation or ground cover. Only in some part of the lake bank, which has been interrupted by
human interventions, can vegetation and tree cover be found. Mangifera indica (amba), Cocos
nucifera (pol), Terminalia catappa (kottan), Gliricidia sepium (weta mara), Leucaena
leucocephala (ipil-ipil), Azadirachta indica (kohomba), Filicium decipiens (pehimbiya), Plumeria
obtuse (araliya), Musa x paradisiaca (kesel), Carica papaya (papol), Ficus religiosa (bo),
Hibiscus rosasinensis (wada), Delonix regia (mai mara), Calotropis gigantiea (wara), Lantana
camara (gandapana), etc. are the tree species which can be found on the bank. These provide
an ecological niche to many bird species. However, these are common trees and do not have a
special conservation status.
35. Air quality. The population growth and increase in commercial and social activities have
led to an unprecedented increase in the demand for mobility, with a consequential increase in
the number of motor vehicles entering CMC daily. The project area is generally along roadsides,
which are experiencing heavy traffic. Vehicle emissions are considered the major contributor for
air pollution in Colombo. Based on monitoring conducted by CEA, the ambient air quality in the
project area is within the prescribed standards.
36. Noise levels. The project area is in the built-up part of Colombo, with residential,
commercial, and institutional establishments. A significant volume of traffic passes through
these sections, causing frequent traffic jams. Heavy traffic movement is considered the major
cause of noise pollution.
37. Forests and ecological sensitive areas. As Colombo is considered a built-up area,
there are no protected forests or ecologically sensitive areas in the project area.
38. Flora and fauna. Animals and plants in the project area are those commonly found in
urban and built-up areas. There are no rare or endangered animal or plant species reported in
the project area.
17
The National Policy and Strategies on Wetlands (2005) seeks to give effect to the National Environment Policy and
other relevant national policies, while respecting national commitments towards relevant international conventions,
protocols, treaties, and agreements on wetland protection to which Sri Lanka is a party. Among the international
conventions, the Ramsar Convention on Wetlands of International Importance (1971), the Convention on
Conservation of Migratory Species of Wild Animals (1979), and the Convention on Biological Diversity (1992) are
significant.
14
water, acting as kidneys, purifying wastes entering into the wetland systems and safeguarding
human health.
40. The wetlands located within the project area are mostly inland systems 18 and are not
categorized as protected wetlands or wildlife sanctuaries. It has also been observed during the
field visits conducted for this IEE that the wetlands in the project area were drained or used to
dump refuse and urban waste.
D. S o c io e c o n o m ic P rofile
41. According to the Department of Census and Statistics, the estimated population in CMC
in 2010 was 1,000,000. Table 5 summarizes the population density by planning units in
Colombo City.
42. The total occupied housing units in Colombo district was 473,045 in 2001. There was a
sharp increase of occupied housing units in Colombo district by year 2011. Building survey
conducted by the Department of Census in 2011 indicated that the number of housing units in
Colombo district was 637,749. For the project area, it was indicated that the number of
households was around 73,637, number of housing units was approximately 48,000, and
number of families was 55,361. This comprises around 65% of the total occupied housing in
Colombo City. The family size was 5.1, much higher than the national average family size of
4.3.
43. The population in the project area is ethnically diverse, with a preponderance of ethnic
minorities particularly in tenement gardens. Nearly 50% of population in the project area is
Sinhala, followed by Muslims (26%). The Tamil community has become smaller, and is 13% at
present. Only 1% of the population represents the Burghers and Malay communities. However,
in the Colombo Divisional Secretariat area (slightly bigger than the project area), according to
the 2001 census, Tamil was the majority ethnic group at 33.2%, the Sinhala second highest at
30.8%, and Muslims third at 30.2%.
18
There are three major types of wetlands in Sri Lanka, namely: (i) offshore and marine systems; (ii) coastal systems;
and (iii) inland systems.
15
44. Distribution by religion showed that 30.2% of the population in the project area is
Christian. This was because a substantial percentage of Sinhala and Tamil communities
practiced the Christian religion. According to the primary survey 19, the percentage of the
population practicing Islam and Buddhism in the project area was 27.2% and 26.9%
respectively. The Hindus were the smallest religious group, at 15.5% of the population.
45. Data revealed that 15% of sample households lived in tenement gardens, while the
balance (85%) was in areas where adequate space is available. Approximately 36% of the
households had been living in their communities for more than 30 years. About 38% of the
households had lived in their communities between 10 and 30 years, and the balance
households had been was living in their communities for less than 10 years.
46. Primary data indicated that the percentage of women-headed households in the project
area was somewhat high, around 23% of total households surveyed. The women-headed
households in tenement gardens was 4%. Percentage of women-headed households in other
areas was 19%.
47. Occupation data of the samples indicated that the majority of the active workforce
(25.9%) in the project area was involved in the provision of unskilled labor. Employment in the
government sector was approximately 7%, while 16% worked in the private sector. A substantial
percentage (38%) of the active workforce in the project area was self-employed or engaged in
their own business. Percentage of overseas employment was around 2%, mostly as
housemaids. Reported unemployment among the people in the area was 29%. Percentage of
male employment in the project area was higher than the female employment. Unemployment
among females was around 24%, which is substantially high.
48. The majority of people, 38%, in the service area, had studied up to General Certificate of
Education (Ordinary Level or Advance Level). A substantial percentage (6%) of children
dropped out after grade 5 due to various reasons. Information on higher education indicated that
only 2% of people in the service area studied up to degree and post-graduate levels. Prevailing
socioeconomic status, culture, poverty, and income-earning opportunities in informal and formal
sectors influenced children and young people to start early employment.
49. The gender gap in literacy was insignificant in the project area. According to the
available data, literacy among the male and female population over 10 years of age was 92.1%
and 89% respectively. These figures were in agreement with the district literacy rate of 94.7%.
50. According to the Department of National Census, the average monthly income of
households in Sri Lanka in 2009–2010 was Rs. 20,427. According to the declared income of the
households surveyed, monthly income of 87% in the project area was Rs. 15,000 or more. Of
that, 30% of the ehouseholds eardn Rs. 30,000 or more per month. Percentage of households
below poverty line was only 0.3%, which is negligible. However, 5% of the households were
low-income.
19
Sample household survey has been conducted under ADB PPTA 7854 for the social analysis of the project area.
The survey and focus group discussions were conducted for six sample communities (small administrative
divisions called GNDs), namely Bluemandle, Grandpass, Lunupokuna, Maligawatta, Modara, and
Sammanthranapura.
16
51. Primary data revealed that 14% of the total surveyed received Samurdhi benefits
(assistance from the government to cover food expenses). The data indicated that the total
numbers of families receiving Samadhi benefits in the project area was only 1,870, which was
negligible (around 4% of total families). However, this data implies that a substantial level of
poverty is concentrated in the proposed project area.
52. Disease incidence based on 180 days’ recall method revealed that incidence of water-
borne disease was two per population of 1,000, while incidences of vector-borne diseases,
especially dengue, were reported moderate at six per 1,000. Vomiting, dengue, and diarrhea
were the only reported diseases during the primary survey.
53. Overall average health expenditure in the project area was Rs. 1,110 per month. Health
expenditure of households in the income category of more than 20,000 per month was
substantial. The households in low-income groups did not have health expenditures, as all
citizens of Sri Lanka have access to free medical facilities, including free medicine, lab tests,
etc.
54. Access to water. Water sources were reported to be the same in dry and wet seasons
by all households. Almost all households were enjoying the NWSDB’s water supply. Eighty-two
percent (82%) of the sample households reported access to individual water service
connections. Around 6% of households used water from shared house connections, while 12%
of households got water from public stand posts. None of the households used groundwater
either from tube wells or hand-dug shallow wells. None of the sample households reported
having installed pumps. However, in CMC area, there were several wells and hand pumps, and
people used them as secondary water sources, and in asome instances as primary water
sources, as well. Generally, such water sources were used by industries and laundries, which
required large quantities of water.
55. According to the primary survey, per capita water consumption in the project area was
low at 61 liters per day (lpd). For the households below poverty line (Rs. 3,551), it was 49 lpd.
However, per capita consumption of water by income category of Rs. 3,551–Rs. 5,000 and Rs.
5,001–Rs. 10,000 was in line with the urban consumption level, which were 106 and 118 lpd
respectively. Per capita consumption of water by all income categories over and above Rs
10,000 was between 46 and 67 lpd. During the focus group discussion (in a location where
mixed services are provided), it was revealed that people monitored the quantity of water they
used daily and took precautions to limit their monthly usage below 15 m3. It was revealed that
households who have individual connections use water from public stand posts once their
households water meters indicate that they are close to high usage category (>15m3). This was
a common practice of all households in tenement gardens.
56. Following, quality issues were reported: bad taste (74%), contaminated with waste
(13%), bad color (6%), high chlorine concentration (4%), and bad smell (1%). It was assumed
that these quality issues were mainly associated with the conditions of the distribution network.
57. Access to sanitation. All households in the project area used latrines with septic tanks,
as CMC by-laws do not provide any room to construct low-cost latrines within the municipal
area. Hence, service level of sanitation infrastructure was somewhat acceptable with the
majority of the surveyed households (83%) who had access to individual toilets in the project
area. Only 15% of households used communal latrines, and the remaining 2% shared the
neighbors’ or relatives’ latrines. Field observations revealed that some sanitary issues prevailed
17
in some of the communal latrine blocks, such as outflowing of septic tanks, substructure
damages, etc.
58. Observation confirmed that open-air defecation (OAD) was not a practice in the project
area. Children’s fecal matter was also disposed of in individual and public latrines. The major
reason for the absence of OAD was the availability of public sanitation facilities in tenement
gardens. Discussion revealed that the user groups attended to minor repairs such as water
supply, lighting, etc. in latrine units, while the CMC attended to major repairs such as emptying
of septic tanks, repair of substructures, etc.
59. Access to solid waste disposal. Lack of systematic disposal of solid waste was one of
the main factors influencing environmental sanitation. Solid waste collection and safe disposal
are the responsibility of local authorities, as people pay directly and indirectly for such services
by way of property assessment taxes and stamp duty and other levies. Almost all househoulds
in the project area benefitted from the recently improved solid waste disposal collection in
Colombo City. About 82% of surveyed households reported access to a household (door-to
door) collection facility, while 4% of households had access to municipal vats and other means
of waste disposal. A substantial percentage (15%) of people, including households that did not
respond to this question, still dropped their waste by the wayside and or in CMC-built garbage
bins. Irregular and ad hoc collection of waste was the main problem mentioned by the people in
many places, especially in the households of tenement gardens.
60. Availability of storm water drainage and wastewater disposal. Surface drains and
underground drainages were available in almost all areas of the project. About 86% households
reported using underground drainages (UGD) and open drains for wastewater disposal. Only
1% of households diverted their wastewater into nearby open areas, while 3% diverted them
into surface water bodies.
61. Generally, Colombo City’s drainage system is not efficient enough to bear the runoff
water during monsoon, resulting in the submerging of several low land areas. Thirty percent
(30%) of surveyed households reported incidence of flooding in the vicinity of their house during
monsoons (May-July and September-December). Of that, 26% lived in non-slum areas while
only 4% lived in tenement gardens (slum households). However, due to lack of appropriate
drainages, most tenement gardens were badly affected during monsoons. It is evident that 20%
of households affected during floods are in high-income categories (monthly income > Rs
15,000). Only 2% of households in low-income categories were affected by seasonal floods.
62. Existing public parks and playgrounds in the CMC area. Parks and playgrounds
account for 95.4 ha or 2.5% of CMC total area. There are also 75.91 ha of other private and
semi-public outdoor recreation spaces and 171.15 ha of outdoor recreation spaces (almost half
of which belongs to private clubs and other organizations).
63. Historical and archaeological sites. Colombo has a number of historical places with
the potential for expanding both local and foreign tourism. The list of archaeological sites found
in CMC 20 is detailed in Table 6. St. Lucia Church in Kotahena and Vihara and Awasageya in
20
Complete list for Colombo District can be found at http://www.archaeology.gov.lk/.
18
Deepaduththaramayaare are located in the project area. However, excavation works will not be
conducted in the vicinities of these archaeological sites.
64. The present report assesses the impacts of the proposed activities on various
environmental attributes of the project site.
65. Methodology. Issues for consideration have been raised by the following means: (i)
input from interested and affected parties; (ii) desktop research of information relevant to the
proposed project; (iii) site visit and professional assessment by environment specialist engaged
by the implementing agency; and (iv) evaluation of proposed design scope and potential
impacts based on the environment specialist’s past experience. Categorization of the project
and formulation of mitigation measures have been guided by ADB’s REA Checklist for Water
Supply (Appendix 1) and ADB SPS 2009.
A. An tic ip a te d Im p a cts – P la n n in g a n d De s ig n Ph a s e
66. Planning principles and design considerations have been reviewed and incorporated into
the site planning process whenever possible. The concepts considered in design of the water
supply project are: (i) no involuntary land acquisition; (ii) substantial reduction of NRW; ((iii)
augmentation in adequacy of drinking water supply at the user end; (iv) enhancing the efficiency
of existing water treatment plant; (v) providing adequate infrastructure facilities for production
and storage of water in deficient areas; (vi) most suitable construction methodology; and (vi) site
constraints.
19
67. The winning contractor will bid based on the concept and details included in the bid
documents. The bidders will be advised to make their own diligence study prior to the bidding.
Necessary documents and studies will be made available to them for their evaluation. It will be
up to the bidders to maximize the use of resources made available to them. The following
design criteria which are the criteria for the Projects 1 and 2 will also be applied in the
implementation of Ambatale project. Salient design features are presented in Table 7.
21
Roadside pollution is often localized and generally only affects a narrow band of roads along the sides of the road.
The major source of roadside pollutants is vehicle exhaust emissions. Other pollution sources emanate from
combustion of hydrocarbon fuels in air, producing carbon dioxide (CO2) and secondary pollutants such as
hydrocarbons (HC), nitrogen oxides (NOx), carbon monoxide (CO), and sulfur dioxide (SO2). Emissions depend on
the volume of traffic, the type of vehicle (including age, technology, and maintenance levels of the vehicle), fuel
20
68. During construction phase, it is expected that some problems are to be encountered
because many of the streets are narrow, with no sidewalks which can be used to lay different
consumption and quality, engine temperature, and road geometry. The highest emission rates are encountered in
congested, slow-moving traffic, and whenever vehicles shift gears, decelerate, accelerate, or travel over steep
gradients. There is also a tendency for emission rates to increase at high speeds.
22
Aesthetics refer to the visual quality of an area as imparted by the physical properties of an area, such as scale,
color, texture, landform, level of enclosure, and in particular, the land use occurring within an area. Landscape
character refers to an area’s intrinsic appeal and is not dependent on its visual quality, but rather on its specific
situation as determined by the following: its level of accessibility or remoteness, level of naturalness, lack of
disturbance, current and potential use, rarity, cultural or historic importance, and potential value to people. The
landscape character determines the extent of visual compatibility of the water supply structures with their
immediate surroundings. Impacts are not restricted to the vicinity, but the entire viewshed (area from where the
infrastructure will be visible). The spirit or sense of place (genius loci) can be defined as the extent to which a
person can recognise or recall a place as being distinct from other places and as having a vivid, unique, or at least
a recognizable character. It is indicates the intrinsic value that a community places on the aesthetic, therapeutic, or
emotional qualities and character of an area. Aesthetics, landscape character, and sense of place are all subjective
concepts that are often influenced by individuals’ perceptions.
21
utilities. Careful planning and extensive coordination with various government agencies must be
established. A massive information campaign must precede any construction activity in order to
make the public aware of the extent of the problem that might be present during the period of
construction.
69. The following table (Table 8) outlines the guidelines the ADB PPTA design engineers
recommend to be considered in the final design and implementation schedule for the pipe
replacement activities. As a result, some measures have already been included in the project
designs. This means that the impacts and their significance have already been reduced.
70. Construction method. Tasks to be performed for the transmission pipe works are listed
in the order of priority as:
71. The pipes will be buried in trenches on or immediately adjacent to roads. Trenches will
be dug by backhoe digger, supplemented by manual digging where necessary. Excavated soil
will be placed nearby, and the pipes (brought to site on trucks and stored on unused land
nearby) will be placed in the trench by crane or using a small rig. After the pipes are joined,
loose soil will be shoveled back into the trench, and the surface layer will be compacted by
hand-operated compressor. Any excavated road will be reinstated.
72. Tasks to be performed for the ground water reservoir construction are listed in order of
completion as follows:
73. The Ambatale WTP and site for the ground reservoir are on government-owned. There
is sufficient space for a staging area, construction equipment, and stockpiling of materials.
74. Table 9 summarizes the activities and facilities that are likely to be undertaken during
construction of the project, including the associated inputs and outputs.
Table 9: Activities and Facilities, Resource Use, and Produced Outputs during Construction Phase
Activities and Facilities Inputs/Resource Use Outputs/Waste Production
• Construction camp and its • Bitumen • Old asphalt (removed from road
associated facilities (including • Cement carriageway during laying of
lay-down areas) • Chemical additives used in pipelines) 23
• Storage camps and lay-down concrete • Waste concrete and other
areas • Chemical blasting agents construction rubble
− Materials and equipment • Paving blocks • Waste bitumen 24
stockpiles • Aggregate (sand and stone) • Materials from pipe descaling
− Handling and storage of • Gravel (fill material and selected and re-lining
hazardous materials material for sub-base and base • Used fuels, lubricants, solvents
including chemicals layers) and other hazardous waste
additives, gravel, cement, • Water
concrete, and lubricants • General waste
− Drinking, cooking, and • Contaminated soil
• Source of water sanitation at construction
• Vegetation clearance − Soil contaminated with
camps bitumen
• Bulk earthworks, grading, and − Water for dust suppression − Soil contaminated with
contouring − Water applied to base and petrochemicals (i.e. oils and
• Drilling sub-base layers during − lubricants) and other
• Movement of construction staff,
23
The water supply rehabilitation works affecting roads may involve the stripping and demolition of old asphalt
layers. Ideally, old asphalt shall be reused during construction of the new road in order to avoid large quantities of
waste being produced. However, depending on the availability and cost of virgin aggregate in the area through
which the road is aligned, reusing the old asphalt may be more costly than using virgin aggregate.
24
Bitumen has relatively low levels of polycyclic aromatic hydrocarbons (PAHs) and is largely inert. However, certain
other potentially hazardous chemical may be added to the bitumen or to the aggregate during the construction
process in order to render the compound more workable. The objective is to use the least hazardous chemicals
available and to locate asphalt plants, aggregate stockpiles, and mixing areas where they do not pose a significant
environmental risk.
24
75. The main operations and maintenance (O&M) activities of the rehabilitated pipes will be
detection and repair of leaks and pipe bursts. These are, however, likely to be minimal as
proper design and selection of good quality pipe material shall mean that leaks are minimal.
Leak repair work will be similar to the pipe-laying work as earlier explained. Trenches will be
dug to reveal the leaking area and the faulty connection will be refitted, or the pipe will be
removed and replaced if necessary.
76. Table 10 presents an indication of what activities and facilities are likely to be
undertaken during operation and maintenance of the project, including the associated inputs
and outputs.
Table 10: Activities and Facilities, Resource Use, and Produced Outputs during
Operation and Maintenance Phase
Activities and Facilities Inputs/Resource Use Outputs/Waste Production
• Signages • Labor • Vehicle exhaust emissions
• Safety barriers • Vehicles and equipment used • Waste/worn-out material
• Lighting for inspections and maintenance removed during maintenance
• Noise and vibrations • Aggregate and other material
• Litter collection used during repairing and
• Maintenance activities (repairing maintenance of pipelines.
and maintenance of pipelines)
25
77. There are no impacts that are significant or complex in nature, or that need an in-depth
study to assess the impact. Thus, the project is unlikely to cause significant adverse impacts.
The potential adverse impacts that are associated with design, construction, and O&M can be
mitigated to acceptable levels with the following mitigation measures (Table 11).
25
Traffic management plan and road safety plan for roadside excavation for trenching along road edges should be
prepared as suggested by the “Construction Manual” by the Road Development Authority, Ministry of Transport
and Highways.
26
Manual on Traffic Control Devices Second Edition, 2007 by Ministry of Highways and Road Development and
Road Development Authority regulations published in the Sri Lanka Government Gazette (Extraordinary) No.
444/19 dated 13 March 1987 under Section 237 along with Section 164 of the Motor Traffic Act is the basis for
providing traffic control devices.
27
These products come in powder forms, and once mixed with water (being the catalyst) simply expand, and crack
the rock from hole to hole. This product is environmentally friendly and can be washed away after it has been used.
26
28
Careful planning of the construction camp can ensure that time and costs associated with environmental
management and rehabilitation are reduced.
27
29
Storage areas can be hazardous and unsightly and can cause environmental pollution if not designed and
managed carefully.
30
Materials must be sourced in a legal and sustainable way to prevent offsite environmental degradation.
31
These points need to be made clear to all staff on site before the project begins.
32
Layout of traffic control devices, number of traffic signs, traffic cones, barricade boards, and lighting requirement
should follow the Manual on Traffic Control Devices Second Edition, 2007 by Ministry of Highways and Road
Development and Road Development Authority.
28
33
National Environmental (Noise Control) regulations No. 1 1996 defines silent zone as area covered by a distance
of 100 m from the boundary of a courthouse, hospital, public library, school, zoo, sacred areas, and areas set apart
for recreation or environmental purposes.
34
Leq T means the equivalent continuous, A-weighted sound pressure determined over a time interval T (in
decibels).
35
Water quality is affected by the incorrect handling of substances and materials. Soil erosion and sediment are also
detrimental to water quality. Mismanagement of polluted runoff from vehicle and plant washing and wind dispersal
of dry materials into rivers and watercourses are detrimental to water quality.
31
78. The potential adverse environmental impacts are mainly related to the construction
period, which can be minimized by the mitigating measures and environmentally sound
engineering and construction practices.
E. Cu m u la tive Im p a ct As s e s s m e n t
79. The cumulative impact assessment (CIA) examined the interaction between the project’s
residual effects (i.e., those effects that remain after mitigation measures have been applied) and
those associated with other past, existing, and reasonably foreseeable future projects or
activities. The interaction of residual effects associated with multiple projects and/or activities
can result in cumulative impacts, both positive and negative. The project’s potential cumulative
effects were considered with respect to valued components (VCs) in environmental and
socioeconomic categories, in four areas:
(i) of any potential residual project effects that may occur incrementally over time;
(ii) consideration of other known relevant projects or activities within the specified
study area boundaries, even if not directly related to the project;
(iii) potential overlapping impacts that may occur due to other developments, even if
not directly related to the proposed project; and
(iv) future developments that are reasonably foreseeable and sufficiently certain to
proceed.
80. The project has identified the VCs as water quality, noise, traffic management,
socioeconomic and socio-community components, and human health. There are no foreseeable
projects that will overlap with the project. The spatial boundary of the project is the area along
the pipe alignment, existing right of ways, and building sites. The temporal boundary can be
considered as the whole Colombo City.
81. Given the water supply requirement in Colombo will be met and the sources considered
adequate, there are no significant cumulative impacts expected on the future water supply.
32
82. Air quality effects will occur during construction. Consequently, although emissions of
common air contaminants and fugitive dust may be elevated in proximity to active work sites,
this impact will be short-term and localized to the immediate vicinity of the alignment.
Greenhouse gas (GHG) emissions may increase as a result of project activities (i.e., vehicle and
equipment operation, concrete production, disposal of excavated material, landfilling of residual
wastes). Given the project’s relatively minor contribution to common air contaminants and GHG
emissions during construction, the overall significance rating of both these potential residual
effects is considered to be negligible.
83. Noise levels during construction in the immediate proximity of most work sites are
expected to increase. The duration of this exposure will be relatively brief. This exposure
represents a temporary, localized, adverse residual effect of low to moderate significance for
affected receptors. While building damage due to ground vibrations is unlikely, there may be
annoyance to spatially located receptors during construction. Noise levels associated with the
project O&M will be largely imperceptible, as the buildings are located in relatively small sites
within the city proper.
84. Land use/traffic management concerns will occur spatially during construction. Site-
specific mitigation measures will be implemented to address temporary disruptions to land use
and access, traffic delays and detours, parking modifications, and increased volumes of
construction-related traffic. Traffic movement along the alignment will be improved once
construction is completed. Since the project will be the rehabilitation of existing pipelines and a
building to be constructed adjacent to existing water supply facilities, it will not conflict with
existing or planned land use. However, following improvement in infrastructures and services,
added residential developments, commercial, and business facilities and increased densities
are expected to develop and enhance the project area. This can be considered a long-term
cumulative benefit of the project.
85. Upon completion of the project, the sociocommunity will benefit from improved water
supply system. This is considered a long-term cumulative benefit.
86. No adverse residual effects to human health will occur as a result of project construction
or operation. While exposure to elevated noise levels and fugitive dust and common air
pollutants will occur in proximity to project work sites during construction, due to their short-term,
localized nature, these effects are expected to be minor and insignificant with no measurable
effects on human health.
87. Therefore the project will benefit the general public by contributing to the long-term
improvement of water supply system and community livability in Colombo City.
VI. INFORMATION DIS CLOS URE, CONS ULTATION, AND P ARTICIP ATION
88. The public participation process included (i) identifying interested and affected parties
(stakeholders); (ii) informing and providing the stakeholders with sufficient background and
technical information regarding the proposed development; (iii) creating opportunities and
mechanisms whereby they can participate and raise their viewpoints (issues, comments, and
concerns) with regard to the proposed development; (iv) giving the stakeholders feedback on
process findings and recommendations; and (v) ensuring compliance to process requirements
with regards to the environmental and related legislation.
33
89. The following methodologies have been used for carrying out public consultation:
90. Different techniques of consultation with stakeholders were used during project
preparation (interviews, public meetings, group discussions, etc). A questionnaire was designed
and environmental information was collected. Apart from this, a series of public consultation
meetings were conducted during the project preparation. Various forms of public consultations
(consultation through ad hoc discussions on-site) have been used to discuss the project and
involve the community in planning the project design and mitigation measures.
91. Key respondents included project-affected persons, who only include owners of
houses/residences and commercial shops/establishments who will suffer temporary access
disruptions during project implementation due to the laying of pipelines,
shopkeepers/businessmen from the project area, and daily commuters consulted randomly. In
addition to a number of informal consultations conducted regularly in the project corridor, a total
of 42 people, selected on a stratified basis to ensure diversified representation, were consulted
in January to February 2013. Issues discussed and feedback received along with details of
date, time, location, and list of participants are given in Appendix 3.
92. The IEE and other relevant documents will be made available at public locations in the
city and posted on the NWSDB and ADB websites. The consultation process will be continued
and expanded during the project implementation through a nongovernment organization (NGO),
to ensure stakeholders participate fully in project execution, as well as to implement a
comprehensive information, education, and communication plan.
93. The public consultation and disclosure program with all interested and affected partied
will remain a continuous process throughout the project implementation, and shall include the
following:
(i) Consultations during construction phase: (a) public meetings with affected
communities to discuss and plan work programs and allow issues to be raised and
addressed once construction has started; and (b) smaller-scale meetings to discuss and
plan construction work with individual communities to reduce disturbance and other
impacts, and to provide a mechanism through which stakeholders can participate in
project monitoring and evaluation.
(ii) Project disclosure: (a) public information campaigns (via newspaper, TV, and
radio) to explain the project to the wider city population and prepare them for disruptions
they may experience once construction is underway; (b) public disclosure meetings at
key project stages to inform the public of progress and future plans, and to provide
34
94. For the benefit of the community, the summary of the IEE will be translated in the local
language and made available at (i) NWSDB office, (ii) area offices, and (iii) contractor’s
campsites. It will be ensured that the hard copies of IEE are kept at places which are
conveniently accessible to citizens, as a means to disclose the document and at the same time
creating wider public awareness. An electronic version of the IEE will be placed in the official
website of NWSDB and the ADB website after approval of the IEE by ADB.
96. Common GRM. A common GRM will be in place for social, environmental, or any other
grievances related to the investment program; the RP and IEE will follow the grievance redress
mechanism described below, which is developed in consultation with key stakeholders. The
GRM will provide an accessible and trusted platform for receiving and facilitating resolution of
affected persons’ grievances related to the project. The multi-tier GRM for the project is outlined
below, each tier having time-bound schedules and with responsible persons identified to
address grievances and seek appropriate persons’ advice at each stage, as required.
97. The citywide public awareness campaign will ensure that awareness on grievance
redress procedures is generated, using electronic, radio, and print media. The implementing
35
NGO will ensure that poor and vulnerable households are made aware of grievance redress
procedures and entitlements, and will help ensure that their grievances are addressed.
98. APs will have the flexibility of conveying grievances/suggestions by dropping grievance
redress/suggestion forms in complaints/suggestion boxes, or through telephone hotlines at
accessible locations, by e-mail, by post, or by writing in a complaints register in the NWSDB
Area Engineer’s Office (Appendix 4 has the sample grievance registration form). Careful
documentation of the name of the complainant, date of receipt of the complaint, address/
contact details of the person, location of the problem area, and how the problem was resolved,
will be undertaken. The PMU social development/safeguards officer will be responsible for
timely grievance redressal on environmental and social safeguards issues, registration of
grievances, related disclosure, and communication with the aggrieved party.
99. Grievance redress process. In case of grievances that are immediate and urgent in the
perception of the complainant, the contractor and supervision personnel from the PMU/MASC
on-site will provide the most easily accessible contact for quick resolution of grievances. Contact
phone numbers and names of the PMU social development and safeguards officer, MASC
safeguards specialists 36, and contractor site engineer will be posted at all constructions sites in
visible locations. In tenement gardens, the point of contact will be the contractor/supervision
personnel or the project NGO personnel that will be involved in community mobilization and
awareness generation among such communities. The contractors and supervision personnel of
PMU/MASC and/or the project NGO can immediately resolve issues on-site in consultation with
each other, and will be required to do so within 7 days of receipt of a complaint/grievance. If
required, the advice of the area engineer and/or the concerned Grama Niladhari (GN) officer as
well as the advice or assistance of PMU social development and safeguards officer and MASC
safeguards specialists will be sought, for resolution of the issue by any one or all of them jointly.
100. All grievances that cannot be redressed within 7 days at field level will be jointly
reviewed by the PMU social development/safeguards officer and MASC safeguards specialists,
who will attempt to resolve them within 15 days, enlisting the assistance of the local
representative of CEA and other concerned stakeholders, as required.
101. The project director will refer major issues to the grievance redressal committee
(GRC) 37, which will resolve them within 30 days, and very major issues that are beyond the
jurisdictional authority of the GRC, or those that have the potential to cause social conflicts or
environmental damage, will be referred directly to the program steering committee (PSC) 38.
Grievances which the GRC is unable to resolve within 30 days will also be referred to the PSC.
All paperwork (details of grievances) needs to be completed by the PMU social development
and safeguards officer, facilitated by the project public relations officer, and circulated to the
36
MASC environment management specialist and resettlement specialist
37
The grievance redress committee (GRC) will have the following as members: divisional secretary as chairperson,
CWSSIP project director, PMU social development/safeguards officer as the convener, project public relations
officer, director of the project NGO, concerned NWSDB deputy general manager (DGM) for the Western Central
Region, assistant general manager (AGM) in charge of NRW, the area engineer, NWSDB, representatives of APs,
community-based organizations (CBOs), and eminent citizens. The GRC must have at least two women members.
38
The program steering committee responsible for grievance redress will have the following as members: Ministry of
Finance and Planning (MOFP), with the Secretary to Treasury (ST) as the chairperson, the Secretary of the
MWSD, the Secretary of MLGPC and senior officials from Department of External Resources (DER) and
Department of National Planning (DNP), Ministry of Defense and Urban Development, NWSDB, and CMC as
members. Representatives of concerned government ministries such as Ministry of Land and Land Development,
Health etc. may be invited to participate as and when required.
36
respective GRC and PSC members at least a week in advance of the scheduled meetings. All
decisions taken by the GRC and PRC will be communicated to the APs by the project public
relations officer.
102. Despite the project GRM, an aggrieved person shall have access to the country's legal
system at any stage, and accessing the country's legal system can run parallel to accessing the
GRM and is not dependent on the negative outcome of the GRM.
103. Composition of GRC and PSC. The grievance redress committee (GRC) will have the
project director, safeguards officer of the PMU (convener), the PRO (PMU), the divisional
secretary (chairperson), the director of the implementing NGO in tenement gardens, the
concerned deputy general manager (DGM) NWSDB for the Western Central region, assistant
general manager (AGM) in charge of NRW, the area engineer, NWSDB, representatives of
affected persons, community-based organizations (CBOs), and eminent citizens as members.
The GRC must have at least two women members.
104. The local representative of CEA and representatives of Road Development Authority
(RDA), Provincial Road Development Authority (PRDA), CMC, and concerned GN Officers may
be invited to GRC meetings as and when required. Presence of at least five members, including
one AP/civil society representative, is necessary for resolutions to be passed.
105. Recordkeeping. Records will be kept by the PMU of all grievances received, including
contact details of complainant, date the complaint was received, nature of grievance, agreed
corrective actions and the date these were effected, and final outcome.
106. The number of grievances recorded and resolved and the outcomes will be
displayed/disclosed in the offices of the PMU, NWSDB’s NRW office, and the area engineer’s
office and website, as well as reported in monitoring reports submitted to ADB on a semiannual
basis.
107. Periodic review and documentation of lessons learned. The safeguards officer will
periodically review the functioning of the GRM and record information on the effectiveness of
the mechanism, especially on the project’s ability to prevent and address grievances. Lessons
learned will be shared with the CEA and Ministry of Land Development as required under the
National Involuntary Resettlement Policy (NIRP), 2001.
108. Costs. All costs involved in resolving the complaints (meetings, consultations,
communication, and information dissemination) will be borne by the PMU; cost estimates for
grievance redress are included in resettlement cost estimates.
109. The purpose of the environmental management plan (EMP) is to ensure that the
activities are undertaken in a responsible, non-detrimental manner with the objectives of: (i)
providing a proactive, feasible, and practical working tool to enable the measurement and
monitoring of environmental performance on-site; (ii) guiding and controlling the implementation
of findings and recommendations of the environmental assessment conducted for the project;
(iii) detailing specific actions deemed necessary to assist in mitigating the environmental impact
of the project; and (iv) ensuring that safety recommendations are complied with.
37
110. A copy of the EMP must be kept on work sites at all times. The EMP will be made
binding on all contractors operating on the site and will be included in the contractual clauses.
Non-compliance with, or any deviation from, the conditions set out in this document constitutes
a failure in compliance.
111. Executing and implementing agencies. The executing agencies are the Ministry of
Water Supply and Drainage (MWSD) and Ministry of Logal Government and Provincial Council
(MLGPC). The implementing agencies are NWSDB and CMC. PMUs will be established in each
implementing agency.
112. The executing agencies will provide all the necessary logistic support (vehicle,
computers, support staff, etc.) to the PMUs for carrying out the related activities for
environmental and social safeguard implementation and monitoring. The implementing agencies
will ensure that bidding and contract documents include specific provisions requiring contractors
to comply with all applicable labor laws and core labor standards on (i) prohibition of child labor
as defined in national legislation for construction and maintenance activities; (ii) equal pay for
equal work of equal value regardless of gender, ethnicity, or caste; (iii) elimination of forced
labor; and (iv) the requirement to disseminate information on sexually transmitted diseases
including HIV/AIDS to employees and local communities surrounding the project sites.
113. The program steering committee (PSC). At the central level, a program steering
committee (PSC) will be established at the Ministry of Finance and Planning (MOFP), with the
Secretary to Treasury (ST) as the chairperson, the Secretary of MWSD, the Secretary of
MLGPC and senior officials from the Department of External Resources (DER) and Department
of National Planning (DNP), the Ministry of Defense and Urban Development, the NWSDB, and
CMC, as members. The PSC will be the apex decision-making body for the investment
program. The PSC will meet quarterly, review progress, provide policy guidance, resolve inter-
agency issues that impede program progress, and advice on necessary action, particularly with
respect to scope, cost, and reform agenda of the investment program, and facilitate inter-
agency coordination. The PSC will be responsible for: (i) providing sanctions and approvals
under the investment program; (ii) making all important decisions on the investment program
implementation; and (iii) ensuring timely investment program implementation.
114. For water supply investments, MWSD will be the executing agency and NWSDB will be
the implementing agency. The PMU in the RSC WC has been established and headed by a full-
time project director. The PMU will be responsible for: (i) preparation and implementation of the
investment program; (ii) management of loan consultants; (iii) disbursement of funds and
recovery of loan repayments; and (iv) conducting overall investment program monitoring and
evaluation, including preparation of necessary investment program reports, with the help of loan
consultants.
115. The PMU will also be responsible for implementing and monitoring safeguards
compliance activities, public relations activities, gender mainstreaming activities, and community
participation activities. The PMU will have a social development and safeguards officer who will
be responsible for safeguards functions. The responsibilities of the PMU social development
and safeguards officer are to: (i) ensure that the EARF provisions are observed, such as
ensuring that works are selected according to the environmental criteria for project selection; (ii)
review and approve project IEEs and EMPs; (iii) confirm existing IEE and EMP are updated
based on detailed designs; (iv) confirm whether the EMP are included in bidding documents and
38
civil works contracts; (v) provide oversight on environmental management aspects of the project
and ensure EMP is implemented by contractors; (vi) establish a system to monitor
environmental safeguards of the project, including monitoring the indicators set out in the
monitoring plan of the EMP; (vii) facilitate and confirm overall compliance with all government
rules and regulations regarding site and environmental clearances, as well as any other
environmental requirements, as relevant; (viii) review, monitor, and evaluate the effectiveness
with which the EMP is implemented, and recommend necessary corrective actions to be taken
as necessary; (ix) consolidate monthly environmental monitoring reports from MASC and submit
semiannual monitoring reports to ADB; (x) ensure timely disclosure of final IEE/EMP in locations
and form accessible to the public; and (xi) address any grievances brought about through the
GRM in a timely manner. The monitoring report will focus on the progress of implementation of
the IEE and RP, issues encountered and measures adopted, follow-up actions required, if any,
as well as status of compliance with relevant loan covenants.
116. MASC. The MASC will be engaged to work closely with and advise the PMU, to build
capacity on NRW reduction, and to be involved in project supervision including construction.
The MASC will have an environment management specialist and a resettlement specialist. For
environmental related work, the MASC environment management specialist will (i) ensure
design and location of works are selected according to the environmental criteria for project
selection; (ii) prepare project IEEs and EMPs; (iii) conduct environmental compliance audit of
existing facilities as per Item F, Appendix 4 of ADB SPS, 2009; (iv) update the IEE/EMP during
detailed design stage; (v) include EMP in bidding documents and civil works contracts; (vi)
ensure all requisite government approvals are in place to allow implementation, and that these
are renewed in a timely fashion where required; (vii) oversee implementation of EMP during
construction, including environmental monitoring of contractors; (viii) take corrective actions
when necessary to ensure no environmental impacts; (ix) review monthly reports by contractors
and submit monthly environmental monitoring reports to the PMU; and (x) address any
grievances brought about through the GRM in a timely manner as per IEEs. The outline TOR for
the MASC environment management specialist is attached as Appendix 5.
117. Contractor. The contractor will have an environment supervisor to (i) coordinate with
MASC on updating the IEE/EMP based on detailed designs, and (ii) and ensure implementation
of EMP during civil works..
118. NGO. The project NGO, which will be responsible for formation of water user groups in
tenement gardens, will also help the PMU/MASC ensure poor and vulnerable APs in tenement
gardens are identified, and receive benefits of the project and any entitlements. The NGO will
collect and analyze data as required to help the MASC/PMU monitor impacts on the poor and
vulnerable. The NGO will (i) put forth grievances of APs/vulnerable groups in tenement gardens
to the PMU/MASC and GRC; (ii) generate awareness among APs and vulnerable groups about
opportunities for employment in project-related activities, rights, entitlements, and grievance
redress process, and help them make informed choices; (iii) assist the PMU in providing
assistance to APs in tenement gardens, if required/applicable; (iv) participate in public meetings
and consultations as and when required; (v) document lessons learned each year; (vi) identify
follow-up actions to ensure sustainability of water user groups formed; (vii) follow up on WASH
program 39; (viii) follow up on key messages of awareness campaign among tenement garden
communities; and (ix) analyze and report on gender impacts of project interventions. The
39
Water, Sanitation, and Hygiene Program
39
success of NGO inputs will largely depend on their liaison with APs and other concerned
government agencies.
40
Detailed measurement survey to be carried out during detailed design, to record and quantify resettlement impacts
and entitled persons.
40
B. Ca p a c ity Bu ild in g
120. A training program has been developed to build the capability of PMU. This will be
conducted by the MASC.
121. PMU and the MASC will organize an induction course for the training of contractors,
preparing them on: (i) EMP implementation, including environmental monitoring requirements
related to mitigation measures; and (ii) taking immediate actions to remedy unexpected adverse
impacts or ineffective mitigation measures found during the course of implementation. The
contractor will be required to conduct environmental awareness and orientation of workers prior
to deployment to work sites. The suggested outline of the training program is presented in Table
13.
C. En viro n m e n ta l Ma n a g em e n t Ac tio n P la n
122. The EMP will guide the environmentally sound construction of the project and ensure
efficient lines of communication between the PMU, MASC, and contractors. The EMP identifies
activities according to the following three phases: (i) site establishment and preliminary
activities, including finalizing IEE/EMP; (ii) construction stage; and (iii) post-
construction/operational stage. Table 14 outlines the mitigation measures and persons
responsible for implementation and monitoring. The EMP will be updated by MASC during the
detailed design stage. Note that the final IEE/EMP should be reviewed and cleared by NSWDB
and ADB at time of detailed design and prior to commencement of construction work.
123. Environmental monitoring program. Prior to commencement of any civil work, the
contractor will submit a compliance report41 to the MASC ensuring that all identified pre-
construction environmental impact mitigation measures as detailed in the EMP will be
undertaken. The MASC will review the report, and thereafter PMU will allow commencement of
civil works. PMU and the MASC will be responsible for monitoring.
41
This compliance report will include information on (i) barricades and warning signs; (ii) area for setting up of
construction camps; (iii) methodology for surveys; (iv) area for establishing lay-down and storage; (v) sources of
materials; (vi) records of environmental awareness, safety training, and orientation of workers prior to deployment
to work sites; (vii) contact information of the environmental and resettlement supervisors; and (viii) construction
method statement.
43
42
Traffic management plan and road safety plan for roadside excavation for trenching along road edges should be prepared as suggested in the construction
manual” of the Road Development Authority, Ministry of Transport and Highways.
43
Manual on Traffic Control Devices, Second Edition, 2007 by Ministry of Highways and Road Development and Road Development Authority, regulations
published in the Sri Lanka Government Gazette (Extraordinary) No. 444/19 dated 13 March 1987 under Section 237 along with Section 164 of the Motor Traffic
Act is the basis for providing traffic control devices.
44
44
Careful planning of the construction camp can ensure that time and costs associated with environmental management and rehabilitation are reduced.
45
Storage areas can be hazardous and unsightly and can cause environmental pollution if not designed and managed carefully.
46
Materials must be sourced in a legal and sustainable way to prevent offsite environmental degradation.
49
47
These points need to be made clear to all staff on-site before the project begins.
48
Layout of traffic control devices, number of traffic signs, traffic cones, barricade boards, and lighting requirement should follow the Manual on Traffic Control
Devices, Second Edition, 2007 by Ministry of Highways and Road Development and Road Development Authority.
50
Access - The contractor shall make available in his stock Contractor MASC Construction As work Construction
steel plates and wooden planks which will be environment method progresses method
deployed on top of trench excavation to provide management statement and
temporary access to building carport and specialist and inventory Detailed design
49
Included as Output 4 of the project.
51
50
Water quality is affected by the incorrect handling of substances and materials. Soil erosion and sediment are also detrimental to water quality. Mismanagement
of polluted runoff from vehicle and plant washing and wind dispersal of dry materials into rivers and watercourses are detrimental to water quality.
54
51
National Environmental (Noise Control) Regulations No. 1, 1996 defines a silent zone as area covered by a distance of 100 m from the boundary of a
courthouse, hospital, public library, school, zoo, sacred area, and areas set apart for recreation or environmental purposes.
52
Leq T means the equivalent continuous, A-weighted sound pressure determined over a time interval T (in decibels).
55
D. Re p o rtin g
124. The MASC will submit monthly monitoring reports to PMU, and the PMU will send
semiannual monitoring reports to ADB. ADB will post the environmental monitoring reports on
its website. The format of the monthly report is given in Appendix 6.
E. En viro n m e n ta l Co s ts
125. The contractor’s cost for site establishment, preliminary activities, construction, defect
liability activities, and environmental mitigation measures related to EMP implementation during
planning, design, and construction will be incorporated into the contractual agreements and
engineers costs, which will be binding on him for implementation. The survey will be conducted
by the contractor.
126. The operation phase mitigation measures are again of good operating practices, which
will be the responsibility of the implementing agency (NWSDB). All monitoring during the
operation and maintenance phase will be conducted by NWSDB; therefore, there are no
additional costs.
127. The activities identified in the EMP mainly include site inspections and informal
discussions with workers and local community, and this will be the responsibility of PMU with
the assistance of MASC, costs of which are part of project management.
Construction monitoring for Ongoing at two locations near pipe Portable noise Contractor’s Not applicable Covered under
noise replacement corridors meters liability engineering design
and cost – contractor
Surveys Ongoing before start of construction Lump sum Contractor’s $5,000 Covered under
work along pipe replacement corridors liability engineering design
and cost – contractor
Any unanticipated impact Mitigation of any unanticipated impact Lump sum Contractor’s As per insurance Covered under
due to project arising during construction phase and liability requirement engineering design
implementation defect liability period and cost – contractor’s
insurance
63
129. The process described in this document has assessed the environmental impacts of all
elements of the project in Colombo City. All potential impacts were identified in relation to pre-
construction, construction, and operation phases.
130. Planning principles and design considerations have been reviewed and incorporated into
the site planning process whenever possible; thus, environmental impacts as being due to the
project design or location were not significant. However, social impacts due to construction
activities are unavoidable, as the residential and commercial establishments exist along the
project corridor. A resettlement plan has been developed in accordance with ADB SPS 2009
and Sri Lankan laws and regulations.
131. Anticipated impacts during the construction period include (i) temporary disruption of
services during realignment of existing utilities along the corridor; (ii) temporary closure of roads
for laying of pipelines; (iii) interference with accesses to properties and businesses due to
construction works; (iv) risk of accidents associated with vehicular traffic and transport of
materials; (v) increased volume of construction vehicles on the roads that may lead to increased
wear and tear of roads in the vicinity of the project sites; and (vi) exposure to increased noise,
dust, vibrations, hazardous chemicals (oils and lubricants), and waste materials. The EMP will
assist the PMU, MASC, and contractors in mitigating the environmental impacts, and guide
them in the environmentally sound execution of the proposed project. The EMP will also ensure
efficient lines of communication between the implementing agency, project management unit,
and contractors.
132. Anticipated impacts during operation and maintenance will be related to detection and
repair of leaks and pipe bursts. These are, however, likely to be minimal, as proper design and
selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will
be similar to the pipe-laying work.
133. The public participation processes undertaken during project design ensured
stakeholders are engaged during the preparation of the IEE. The planned information disclosure
measures and process for carrying out consultation with affected people will facilitate their
participation during project implementation.
134. The project’s grievance redressal mechanism will provide the citizens with a platform for
redressal of their grievances, and describes the informal and formal channels, time frame, and
mechanisms for resolving complaints about environmental performance.
135. A copy of the EMP shall be kept on-site during the construction period at all times. The
EMP shall be made binding on all contractors operating on the site, and will be included in the
contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this
document shall constitute a failure in compliance.
136. The project will benefit the general public by contributing to the long-term improvement
of water supply system and community livability in Colombo City. The potential adverse
environmental impacts are mainly related to the construction period, which can be minimized by
the mitigating measures and environmentally sound engineering and construction practices.
137. Therefore the proposed project is unlikely to cause significant adverse impacts. The
potential impacts that are associated with design, construction and operation can be mitigated
64
to standard levels without difficulty through proper engineering design and the incorporation or
application of recommended mitigation measures and procedures. Based on the findings of the
IEE, there are no significant impacts and the classification of the subproject as Category “B” is
confirmed. No further special study or detailed environmental impact assessment (EIA) needs to
be undertaken to comply with ADB SPS, 2009 or Sri Lankan EIA National Environmental Act
and its amendments.
Appendix 1 65
Note: Tranche 1 = Project 1; Tranche 2 = Project 2; total length of pipes for rehabilitation and replacement
under Project 1 is 318 km of seriously degraded distribution network pipes, including 279 km of cast iron
pipes below 225 mm diameter and 39 km of spaghetti pipes in tenement gardens.
Appendix 3 69
No. of Specific
Participants Overall Concerns Of
Concerns People Who Suggestions Willingness to
Key Safeguard
GN Division Date Venue Expressed are Presently from People for Participate in
Issues Discussed
M F T Related to the Dependent on the Project Project
Project Non-NWSDB
Sources
1 Represented 20.Jan.2013 Sariputta 6 4 10 There will be no All the All the It is required a Participation in
several GNDs Viharaya, impact on participants had participants proper terms of labour
in Elvitigala Narahenpita community life. If the idea that were depended coordination is quite tricky
Flats and there are minor this project as a on the NWSDB between the but people will
Narahenpita temporary impacts, time need and water sources contactors and help in the
people are ready no objections the authorities community
to bear these for the project who belongs awareness
impacts. activities. the road, to activities
immediate and
There is no Some people proper damage
Resettlement and asked whether recovery.
land acquisition the water bill Otherwise the
due to this project. rates increases road system will
due to this damage
Obstruction of project and they severely due to
drainages and realized that the this project.
culvers might be water bill is not
occurred during increase due to Placing of
the project this project alternative
activities and other than water sources
proper mechanism government’s for emergency
for diverting the regular use (i.e: water
drainage water is increment of the bourses).
helpful. water charges.
Immediate
Since this area is damage
centrally located recovery for the
traffic impact due roads and
to the construction monitoring the
activities might be damage
severe than other recovery
areas, hence traffic process.
management plan
at the construction
period is required.
70 Appendix 3
No. of Specific
Participants Overall Concerns Of
Concerns People Who Suggestions Willingness to
Key Safeguard
GN Division Date Venue Expressed are Presently from People for Participate in
Issues Discussed
M F T Related to the Dependent on the Project Project
Project Non-NWSDB
Sources
Damaged roads
should be repaired
by NWSDB or
Appendix 3 71
No. of Specific
Participants Overall Concerns Of
Concerns People Who Suggestions Willingness to
Key Safeguard
GN Division Date Venue Expressed are Presently from People for Participate in
Issues Discussed
M F T Related to the Dependent on the Project Project
Project Non-NWSDB
Sources
CMC. If a property
damages due to
the construction
work that should
be replaced with
original manner.
A proper
constriction
mechanism should
be employ in order
to have a efficient
damage recovery
to the roads which
have recently
constructed with a
heavy investment
by the government.
3 Sarana 19.Jan.2013 At a 4 2 6 Damaged roads All the All the The Respondents
Mawatha, Participant’s should be repaired percipients participants respondents are willing to
Colobo 07 house, by NWSDB or agreed for the were depended have the participate for
Colombo 07 CMC. If a property project but they on the NWSDB concern about the project by
damages due to asked to carry water sources save the information
the construction out project drinkable water dissemination.
work that should activities with by having
be replaced with minimum industrial water
original manner. disturbance to supply for other
the community uses such as
All the meters and life. bathing and
water supply gardening.
systems should be No critical
rechecked for the issues
72 Appendix 3
No. of Specific
Participants Overall Concerns Of
Concerns People Who Suggestions Willingness to
Key Safeguard
GN Division Date Venue Expressed are Presently from People for Participate in
Issues Discussed
M F T Related to the Dependent on the Project Project
Project Non-NWSDB
Sources
leakages. regarding the
project were
A proper expressed.
constriction
mechanism should
be employ in order
to have a efficient
damage recovery
to the roads which
have recently
constructed with a
heavy investment
by the government.
4 Kirulapone 20.Jan.2013 At a 2 6 8 Other than No objection for All the Carry out major Respondents
Participant’s replacement of the project participants construction are willing to
house, existing steel pipe activities but the were depended works in night participate for
Colombo 05 network, other laid participants on the NWSDB time. the project by
pipes also required sought a water sources information
recheck for minimum dissemination
potential leakages. disturbance for with the local
the traffic and community.
A proper social life and
replacement of properties.
newly constructed
road is a prime
requirement along
with the project
activities.
5 Bambalapitiya 19.Jan.2013 Bambalapitiya 2 4 6 There will be At this moment The The There are
impact on day most of the participants respondents people who
today activities people don’t were willing to sought a soft willing to
during the project realize the have exclusive mechanism to participate as
implementation as necessity of this water supply have water daily paid
the community is project as most connection to supply workers at the
living closer to the of the people their houses connection to project
road network. not and they the houses. construction
(Flats type houses) experiencing cannot afford period.
Appendix 3 73
No. of Specific
Participants Overall Concerns Of
Concerns People Who Suggestions Willingness to
Key Safeguard
GN Division Date Venue Expressed are Presently from People for Participate in
Issues Discussed
M F T Related to the Dependent on the Project Project
Project Non-NWSDB
Sources
the problems for a large sum
There are about related to water of money to
500 houses supply and the pay initial
belongs to this quality aspects. instalment at
GND and more But, people are once.
than 99% people really keen if
have got toilet and they can get a
other sanitation good/efficient
facilities. There are supply of water.
few common stand
posts with meters It was a great
and few common concern
toilets. Hence they whether the
required an water bill will be
alternative water increased due
supply during the to project
project intervention.
construction works
since they do not
have water storing
facilities at their
premises.
Note: M = number of male participants; F = number of female participants; T = total number of participants
74 Appendix 3
Mode of communication:
Note/Letter
E-mail
Verbal/Telephonic
Reviewed by: (Names/Positions of Officials Reviewing Grievance)
Action Taken:
(i) organize an orientation workshop for the MWSD and NWSDB officials involved in
the project implementation on ADB Safeguards Policy Statement, Sri Lankan
environmental laws and regulations, and environmental assessment process;
(ii) organize an induction course for the training of contractors, preparing them on
EMP implementation, environmental monitoring requirements related to mitigation
measures, and taking immediate action to remedy unexpected adverse impacts or
ineffective mitigation measures found during the course of implementation;
(iii) ensure design and location of works are selected according to the environmental
criteria for project selection;
(iv) conduct rapid environmental assessment as per ADB REA checklist and submit
to PMU;
(viii) Include the EMP in bidding documents and civil works contracts;
(ix) comply with all government rules and regulations regarding site and
environmental clearances as well as any other environmental requirements (e.g., permit
from Coast Conservation Department, permit from Geological Survey and Mines Bureau,
excavation permit from Department of Archaeology, written consent from the Central
Environment Authority, tree-cutting permits, use of non-explosive/chemical blasting
agents for rock breaking, etc.), as relevant;
(xi) coordinate with the MASC resettlement specialist, NGO, and media contractors
on mitigation measures involving the community and affected persons;
(xiv) address any grievances through the grievance redress mechanism in a timely
manner as per the IEEs.
Appendix 6 81
Training
Construction phase
(mitigation measure 1)
(mitigation measure 2)
(mitigation measure …)
E. Grievance Redressal
Date of Grievance Details Nature of Grievance Action taken
82 Appendix 6
Prepared by: