Approved by,

CONTRACTOR DAILY OVERTIME REPORT

DATE : 31-Oct-22 Arief Bayu Stefan A.


No : 31/20/10/SPKL/MEI/22
Photo
No NIK Full Name Dept Fajar PIC Clock In Clock Out Job Description
Before After

1 91100449 Saleh Fuat ETP Mr. Wagi 16:00 18:00

2 91100400 Tomo Setiawan ETP Mr. Wagi 16:00 18:00

3 91100378 Hariyanto ETP Mr. Wagi 16:00 18:00


Job fabrikasi support panel bellmer
Pulling kabel power bellmer 4 x 16mm dan 4x10mm

4 91100327 Aji Suprihatin ETP Mr. Wagi 16:00 18:00

5 91100380 Septa Irawan ETP Mr. Wagi 16:00 18:00

6 91100352 Toni Wibowo PM 1.2 Mr. Wandi 16:00 18:00 1. Daily check motor PM 1 2
2. Ambil kabel 4x70mm di gudang spare part untuk power
maruishi
3. Fabrikasi cover kopling motor
4. Fabrikasi frame filter panel Bruderhaus
5. Fabrikasi support limit switch conveyor Yue li.
7 91100322 Rasikun PM 1.2 Mr. Wandi 16:00 18:00 6. Bongkar panel PM 2
Photo
No NIK Full Name Dept Fajar PIC Clock In Clock Out Job Description
Before After
1. Daily check motor PM 1 2
2. Ambil kabel 4x70mm di gudang spare part untuk power
8 91100331 Hendra Sumitro PM 1.2 Mr. Wandi 16:00 18:00 maruishi
3. Fabrikasi cover kopling motor
4. Fabrikasi frame filter panel Bruderhaus

1. Daily cek motor dan panel drive Pm1/2 dan finishing


9 91100308 Jana Tri P PM 1.2 Mr. Eko 1:00 2:00 2. Input data AVS
3. Cek encoders motor unwinder yuili

10 91100257 Govinda Dimas PM 1.2 Mr. Wandi 16:00 18:00 1. Daily check motor PM 12
2. Ambil kabel 4x70mm di gudang spare part untuk power
maruishi
3. Fabrikasi cover kopling motor
4. Fabrikasi frame filter panel Bruderhaus
5. Fabrikasi support limit switch conveyor Yue li.
11 91100355 Pahri Husaeni PM 1.2 Mr. Wandi 16:00 18:00 6. Bongkar panel PM 2

12 91100342 Reza Pahlevi SP 1.2 Mr. Kukuh 16:00 18:00

12:00 13:00 1.bereskan material sp1.2


13 91100403 Nasrulloh SP 1.2 Mr. Kukuh 16:00 17:00 2. Dismantle mcc9 PM2

14 91100418 Ramdani SP 1.2 Mr. Kukuh 16:00 18:00

15 91100417 M. Dhiyauddin SP 1.2 Mr. Nanang 12:00 13:00 Review Daily Check Preventive Maintenance Panel Electric AC 1-
Photo
No NIK Full Name Dept Fajar PIC Clock In Clock Out Job Description
Before After

1.Layani pemadaman & pengaktifan modul-modul panel PM/SP3.


2.Cleaning motor dyer group 1,bongkar & Cek encoder , suara
16 91100351 Sigit Priyanto PM 3.7 Mr. Arif 12:00 13:00 masih ok
3. Monitoring temperature CPE & PAP PM7.

1. Catat eEnergy Scada JB207 & JB302 (Selasa).


2. General check AVS &Inspection electric PM37
17 91100438 Refli Hamdan PM 3.7 Mr. Arif 1:00 2:00
3. SP-29 V-belt putus, permintaan produksi dan mekanik untuk
amankan power module perbaikan ganti V-belt

1. Catat eEnergy Scada JB207 & JB302 (Selasa).


18 91100443 Aldino Eka PM 3.7 Mr. Sartika 18:00 19:00 2. General check AVS &Inspection electric PM37
3. SP-29 V-belt putus, permintaan produksi dan mekanik untuk
amankan power module perbaikan ganti V-belt

Mr.
19 91100404 AlfaDwi PM 5.8 16:00 18:00
Hariyanto
Ganti Bearing Depan dan Belakang
DE. : 6212
NDE : 6209
Motor AP 11 SP 8
- Test Putaran motor M36 PM 5
20 91100377 Galeh Rizki U PM 5.8 Mr. 16:00 18:00
Hariyanto