SG6427-SY-CK0P-MTD-736-005 - Method Statement of Local Panel & Enclosure Installattion - Rev.B
SG6427-SY-CK0P-MTD-736-005 - Method Statement of Local Panel & Enclosure Installattion - Rev.B
C SAMSUNG GEC,
500 Sangil-dong, Gangdong-Gu, Seoul, Korea 05288
6600046420 (OOK),
ContractNo. : SECL Job No. : SG6427
O 6600045884 (IK)
: SG6427-SY-CK0P-MTD-736-
COMPANY : SAUDI ARAMCO Document No.
005
N .
T
METHOD STATEMENT
S OF
LOCAL PANEL AND ENCLOSURE INSTALLATION
B 26 Dec 2020 Issued for Review S.S.Byun Gi. Han Y.J.Choi S.H.Choi
A 05 Dec 2020 Issued for Review S.S.Byun Gi. Han Y.J.Choi S.H.Choi
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 2 of 12
1. PURPOSE................................ 3
3. SCOPE.......................................................................................................3
4. APPLICABLE DOCUMENT ..................................................................... 3
5. REFERENCES 3~6
6. RESPONSIBILITIES 6~7
8. METHODS/PROCEDURES 8~10
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 3 of 12
1. PURPOSE
This method statement will serve as a minimum guideline to carry out the Local Panel
and Enclosure for Hawiyah Unayzah Gas Reservoir Project to ensure that the work
is carried out in accordance with Project Drawings & Specification, Saudi Aramco
Engineering Standard, Materials and Procedure.
The following constitutes a list of terms, which have been used in this plan:
Client / Company : Saudi Aramco
Main Contractor : Samsung Engineering CO., LTD.(Hereafter, SECL)
Subcontractor : SAMYOUNG SAUDI ARABIA CO., LTD.(Hereafter, SY)
Project : Hawiyah Unayzah Gas Reservoir Storage Project
3. SCOPE
This method statement will cover the procedure to be followed for Local Panel and
Enclosure (Indoor/ Oudoor) installation including handling and receiving of materials,
inspection and safety for Hawiyah Unayzah Gas Reservoir Project, in accordance
with the scope of work, Approved Construction Drawing, SECL project specifications,
applicable Saudi Aramco Standards, National and International Engineering
Standards and specifications.
4. APPLICABLE DOCUMENTS
5. REFERENCES
5.1. Saudi Aramco Ebgineering Procedure (SAEP)
5.1.1. SAEP-302 Instruction for Obtaining a Waiver of a Mandatory
Saudi Aramco Engineering Requirements
5.1.2. SAEP-1634 Factory Acceptance Test
5.1.3. SAEP-1636 Installation and Checkout Plan
5.1.4. SAEP-1638 Site Acceptance Test Plan
5.2. Saudi Aramco Engineering Standards (SAES)
METHOD STATEMENT SG6427-SY-CK0P-MTD-736-005
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 4 of 12
5.2.1. SAES-B-006 Fireproofing for Plants
5.2.2. SAES-B-014 Safety Requirements for Plant and Operations Support Buildings
5.2.3. SAES-B-068 Electrical Area Classification
5.2.4. SAES-J-002 Technically Acceptable Instrument Manufacturers
5.2.5. SAES-J-003 Instrumentation - Basic Design Criteria
5.2.6. SAES-J-902 Electrical Systems for Instrumentation
5.2.7. SAES-J-903 Intrinsically Safe Systems
5.2.8. SAES-J-904 Foundation Fieldbus Systems
5.2.9. SAES-P-100 Basic Power System Design Criteria
5.2.10. SAES-P-104 Wiring Methods and Materials
5.2.11 SAES-P-111 Grounding
5.3. Saudi Aramco Material System Specofocation Standards (SAMSS)
5.3.1. 34-SAMSS-820 Instrument Control Cabinets – Indoor
5.3.2. 34-SAMSS-821 Instrument Control Cabinets - Outdoor
5.3.3. 34-SAMSS-830 Programmable Logic Controller
5.3.4. 34-SAMSS-831 Instrumentation for Packaged Units
5.3.5. 34-SAMSS-623 Programmable Controller Based ESD Systems
5.3.6. 34-SAMSS-621 ESD Systems - Hard-Wired - Solid-State(Nonprogrammable)
5.4. Industry Code and Standard
5.4.1. IEC 60529 Degrees of Protection Provided by Enclosures
5.4.2. NEMA ICS 6 Enclosures for Industrial Controls and Systems
5.4.3. NEMA 250 Enclosures for Electrical Equipment (1KV Volts Max)
5.4.4. NFPA 72 National Fire Alarm Code
5.4.5. NEMA 4X Electrical Enclosure
5.4.6. PIP PCCGN002 General Instrument Installation Criteria
5.4.7. ASTM A269 Standard Specification for Seamless and Welded Austenitic
Stainless Steel Tubing
5.4.8.ANSI BI.20.1 Pipe Threads, General Purpose (Inch)
5.5. Saudi Aramco Typical Inspection Plan (SATIP)
5.5.1. SATIP-J-902-06 Instrumentation Racks and Panels (open);
Terminal Boxes and Instrument Cabinets
5.5.2. SATIP-J-904-01 FOUNDATION Fieldbus Systems
5.5.3. SATIP-J-902-05 Inspection and Testing Requirements For
Elevating / Lifting Equipment
5.5.4. SATIP-B-014-01 Fire Detection and Alarm Systems
5.6. Saudi Aramco Inspection Checklist (SAIC)
METHOD STATEMENT SG6427-SY-CK0P-MTD-736-005
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 5 of 12
5.6.1.SAIC-B-6102 Fire Alarm System - Cable and Accessories - Material Receiving and
Installation
5.6.5.SAIC-P-3016 General Boxes & Enclosures - Class I, Div 1 or Zone 1, Haz. Location
5.6.6.SAIC-P-3017 General Boxes & Enclosures - Class I, Division 2 or Zone 2, Haz. Loc.
Material Receiving
and Pre-Commissioning
(Before Installation)
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 6 of 12
I11 Hand and Power Tools, I12 Material Handling, I13 Heat Stress
CSM II2 Scaffolding, II5 Fall Protection, II6 Concrete Construction
CSM III1 Machine Guarding, III2 Mechanical and HE, III3 Electrical Equipment,
III7 Crane and Lifting Equipment, III8 Slings and Rigging Hardware
G.I. 2.100 Work Permit System
GI 7.025 Heavy Equipment Operator and Rigger Testing and Certification
GI 7.028 Crane Lift: Types and Procedures
GI 8.001 Safety Requirements for Scaffold
6. RESPONSIBILITIES
6.1. Site Manager:
Site Manager is responsible for supporting and encouraging the related staffs
and workers, so as for them to participate actively as worksite. Site Manager is
responsible for implementation of HSE requirements.
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 7 of 12
Ensure relevant permits are raised and received prior to commencement of work,
with full compliance by associated Foreman and Instrument calibrator to the
requirements of this method statement, Quality Control Procedures, reference
drawings, and Customer’s Specifications.
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 8 of 12
7.1.1. Set of Instrument Hand Tools and Fittings
7.1.2. Bending and Cutting Machine
7.1.3. Threading machine with Tripod
7.1.4. Welding Machine
7.1.5. Chain Puller/ Chain block
7.1.6. Boom Truck
7.1.7. Hydraulic Pallet Jack
7.1.8. Common Hand Tools
7.1.9. Electric Power Tools (i.e. electric drill etc.)
7.1.10. Knock Out Puncher with Hydraulic Foot Pump
7.1.11. Set of Termination Tools
7.1.12. Absolute Pressure Gauge
7.1.13. Man lift
8. METHODS/ PROCEDURE
8.1. GENERAL PREPARATORY WORKS
8.1.1. All permanent materials, consumables, local panel and enclosure for installation
shall be prepared and checked prior to installation. Certificates shall always be
verified and counterchecked as per SECL and Saudi Aramco Engineering
Standard, Materials System Specification and Procedures.
8.1.2. Ensure that working areas are ready for installation to include availability of
scaffolding (by others) if needed, supports and access to avoid delays of the
activities.
8.1.3. Study and prepare all installation requirements and related references such as
approved for construction drawings, layout and Technical Scope of Work, work
permit requirements, and work procedures.
8.1.4. Erection procedure for the specific sensitive equipment prior to installation shall be
thoroughly studied to avoid physical damages and possible malfunctions to the
system and approved by SECL.
8.1.5. Equipment that has been shipped in sections and /or has loose components
shall be identified and checked with corresponding equipment package list.
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 9 of 12
8.2.3. Structure Mounted Panel installation shall be in accordance with the typical
installation drawing.
8.2.4. On concrete foundation (by others) for panel installation, chipping of concrete
foundation, levelling, setting of base plates, and setting of mechanical anchor bolts
prior to grouting, if required as per scope of work.
8.2.5. When miscellaneous foundation is needed, installation shall follow the typical
drawing and finishing mortar for concrete foundation with sunlight resistant coating
as per project specification.
8.2.6. All supports shall be installed as per the approved drawings. Welding shall be
done for supports wherever necessary.
8.2.7. All supports base plates, floor penetrations and cable entries shall be checked for
its location, measurements, level and overall measurements against the actual
dimension of the equipment.
8.2.8. Sufficient access and working space shall be provided and maintained about
enclosure housing electrical to permit ready and safe operation and maintenance
of such equipment, (NEC-110.26).
8.2.9. Sensitive equipment shall be handled with caution to avoid undue stress or
damage to the metal finished surfaces.
8.2.10. Moving of equipment to its designated position shall be done in safely manner
using Crane or boom truck, hydraulic pallet jack, and rollers or pipes.
8.2.11. Apply the concept of center of gravity for proper lifting of equipment to avoid
unbalance weight within the package unit.
8.2.12. Vendor’s installation instructions shall always be reviewed together with the
plans from time to time during the course of installation activities. Instruction shall
be coordinated and duly approved for construction by SECL
8.2.13. When equipment consists of number of panels or sections, the assembly shall
commence from the center section, while sections on either side shall be
alternated, levelled and shimmed as necessary.
8.2.14. The complete assembly shall be checked to ensure alignment and level after
tightening of bolts. Only the recommended bolting materials and torque values
should be used in assembling the equipment. Vendor shall always be available in
case query is necessary.
8.2.15. No welding works shall be made to the process equipment and steel structures.
Use necessary fixing materials such as uni-strut channel bolted to the equipment
using fabricated fittings as appropriate.
8.2.16. Local Panels and Enclosures shall be properly grounded in accordance with D-
000-1378-101, Instrument Grounding Philosophy.
8.2.17. Preservation Procedure After installation,
8.2.18. Panels shall be opened up and inspected for cleanliness to ensure no foreign
bodies are present.
8.2.19. Dust and dirt shall be removed by using appropriate vacuum cleaner or rags.
Protection cover shall be provided against damage during construction stage.
8.2.20. Maintain air conditioning at 21oC deg.
8.2.21. Door shall be closed every time.
METHOD STATEMENT SG6427-SY-CK0P-MTD-736-005
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 10 of 12
8.2.22. Working permit are require any work activities.
8.2.23. Person enter inside PIB (rack room) to be signed in log sheet.
8.2.24. Check the installed raceways and its access to suite the instrument panels,
enclosures and peripherals for the installation, ensuring a neat and proper
installation as per Saudi Aramco Standards.
8.2.25. Incoming and outgoing cables for the instrument panels and its peripherals shall
be sequentially arranging and identified to avoid confusions and minimize
unnecessary movements within the set point. Sealing of cable entry to panels shall
be in accordance with SECL project specification.
8.2.26. Touch up paint shall be carried out to every damaged metal surface and edges
caused by welding, grinding, drilling and cutting as per approved paint system and
materials by SECL.
8.2.27. QC inspection for the completed instrument panels, and peripherals installed and
its steel supports shall be requested while inspection reports shall be filed and
recorded in applicable forms as per approved SATIP and SAIC.
8.2.28. Approved “Site Query” shall be available for FCS (Field Change Sheet) shall be
issued for any IFC drawing changes.
8.2.29. Installation of nameplate and identification according to SAES-J-003, DD-950025
and PIP-PCCGN002 Sec. 3.3
8.2.30. Outdoor panel installation required sunlight protection or rain protection.
8.2.31. Enclosures shall be installed as per SAES-J-902 Sec. 7
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 11 of 12
Permit
Receiver
OF
Hawiyah Unayzah Gas REV.NO B
Reservoir Storage Project LOCAL PANEL & ENCLOSURE
INSTALLATION PAGE 12 of 12
ATTACHMENT:
Job Safety Analysis (JSA) for
Local Panel and Enclosure Installation