Comment matrix

# Comments Response References


1 Impact assessment for This has been included in Table 5.0 Page 10.
construction cost and Item 3.
resettlement cost
2 Revised the cost for This has been updated and shown in Table 5.0. Page 10
Option one to The cost has also increased due to the additional Item 3c
NGN169,000,000.00 works of pavement reconstruction.
3 Check the functionality This has been included in the report as Table 3b. Page 7
of enlarged attenuation
and the capacity of
existing opening of ID
565